CN113585355B - Construction process for preventing basement exterior wall waterproof layer protection plate from being pasted and toppled - Google Patents

Construction process for preventing basement exterior wall waterproof layer protection plate from being pasted and toppled Download PDF

Info

Publication number
CN113585355B
CN113585355B CN202110981048.5A CN202110981048A CN113585355B CN 113585355 B CN113585355 B CN 113585355B CN 202110981048 A CN202110981048 A CN 202110981048A CN 113585355 B CN113585355 B CN 113585355B
Authority
CN
China
Prior art keywords
waterproof
wall
waist
waterproof layer
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110981048.5A
Other languages
Chinese (zh)
Other versions
CN113585355A (en
Inventor
郭瑞东
黄建逵
秦锦帅
汤鑫
孟俭杰
李心意
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Nantong Sanjian Construction Group Co ltd
Original Assignee
Jiangsu Nantong Sanjian Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Nantong Sanjian Construction Group Co ltd filed Critical Jiangsu Nantong Sanjian Construction Group Co ltd
Priority to CN202110981048.5A priority Critical patent/CN113585355B/en
Publication of CN113585355A publication Critical patent/CN113585355A/en
Application granted granted Critical
Publication of CN113585355B publication Critical patent/CN113585355B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/12Back-filling of foundation trenches or ditches
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/06Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against corrosion by soil or water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a construction process for preventing a waterproof layer protection plate of an external wall of a basement from being stuck and toppled, wherein a pressure rod body consisting of a steel pipe for hands and a special waist-shaped hoop for iron is lifted by arranging a hemp or nylon soft rope with the diameter of 5-6 mm, and then the pressure rod body is put down to the position below 200 mm along the waterproof protection plate, and the force for extruding the protection plate is generated by utilizing the weight of the pressure rod body. The method not only solves the problem of righting and restoring safety after falling and toppling due to the fact that the waterproof protection plate is adhered to the basement and is easy to be affected by external force, but also reduces labor and materials, and solves the problem that backfill filler possibly damages a waterproof layer, so that the whole waterproof effect of the basement is guaranteed.

Description

Construction process for preventing basement exterior wall waterproof layer protection plate from being pasted and toppled
Technical Field
The invention relates to the field of waterproof layer construction of an outer wall, in particular to a construction process for preventing a protective plate of a waterproof layer of an outer wall of a basement from being stuck and toppled.
Background
With the development of building construction technology, the technology of the space required underground becomes more mature, and underground buildings become larger. The realization of underground building functions requires that the structure body has good waterproof and anti-permeability performances. The structure can ensure good waterproof and anti-permeability performance of the underground building under the combined action of the waterproof layer and the waterproof layer.
When the underground structure uses the external water-proof structure of the building, the backfilling of the fertilizer groove earthwork can be completed in time by proper protection measures and a reasonable construction method, and the water-proof layer can be well protected from being damaged.
In the environment of energy conservation and emission reduction, the waterproof protective layer is usually made of a polystyrene board with certain elasticity and heat insulation performance. Before earth backfilling of the fertilizer groove, a worker at the project part fixes the polystyrene board on the waterproof layer by adopting a point bonding method, but whatever materials are used for point bonding, but the time after point bonding is prolonged, and the polystyrene board and the waterproof layer can be loosened and toppled; meanwhile, when the earthwork slides down along the pit slope, the loosening and the toppling of the polystyrene board are accelerated by wind power generated in the process of sliding down the soil material. If the polystyrene board is not supported in time and is attached again, the backfilled soil and the waterproof layer are easy to be impacted to cause damage to the waterproof layer. And unnecessary injury can be caused to personnel holding the polystyrene board on the working surface in the process of the soil material sliding downwards. The problem that the safety of workers for supporting the polystyrene board on the working surface cannot be avoided is guaranteed while the waterproof protection board is in a good state in the backfilling process.
In the application of patent publication No. CN 111005443A, a construction method for punching and pasting a heat insulation board of a waterproof protection layer of an outer wall of a basement is disclosed, wherein the heat insulation board is punched and pasted, the position of the heat insulation board is fixed, construction is carried out, but through the pasting mode, the subsequent construction time is prolonged, accidents such as falling and toppling of a waterproof layer can possibly occur, and the convenient and practical effect cannot be achieved.
Disclosure of Invention
The invention aims to provide a construction method which is convenient and practical and can ensure the perfect working condition of a waterproof protection plate in the backfilling process.
The technical scheme adopted by the invention is as follows:
the utility model provides a prevent that basement outer wall waterproof layer protection shield from pasting construction process who emptys which characterized in that: the method comprises the following steps:
step 1: organizing foundation pit earthwork excavation according to a conventional method to construct a structural body;
step 2: after the reinforced concrete column wall and the beam slab structure of the underground structure are qualified, immediately organizing waterproof layers on the outer sides of the wall columns, the upper plane of the convex outer wall surface of the raft plate and the outer side surface of the raft plate for construction;
and step 3: a waterproof protection plate is attached outside the raft plate;
and 4, step 4: one end of a soft rope made of hemp or nylon and with the phi of 5-6 mm is connected with the waist-shaped hoop, and the other end of the soft rope is connected with a lower horizontal rod of a protective railing on the top cover of the underground structure; a scaffold steel pipe of 6000 mm penetrates through the two special iron waist-shaped hoops to form a compression rod body; when a first-stage waterproof protective plate is adhered along the waterproof layer surface of the outer wall column and vertically arranged in the longitudinal direction, a pressing rod body consisting of a scaffold steel pipe and two iron special waist-shaped hoops is put down to 200 mm below the top of the first-stage protective plate; backfilling earthwork in the area, layering and paving the earthwork for 300 mm, and mechanically compacting the earthwork;
and 5: after the backfilled soil surface touches the pressure roller body consisting of the steel scaffold tube and the special iron waist-shaped hoop, the soft rope is tensioned, and the pressure roller body consisting of the steel scaffold tube and the special iron waist-shaped hoop is withdrawn for standby;
and 6: then sticking an upper-level waterproof protective plate along the waterproof layer surface of the column wall, vertically arranging in the length direction, lowering a pressing stick body consisting of a scaffold steel pipe and an iron special waist-shaped hoop until the distance is 150-250 mm below the top of the protective plate, backfilling earthwork in the area, layering and spreading for 250-300 mm, and mechanically compacting;
and 7: after the backfilled soil surface touches the pressure stick body consisting of the scaffold steel pipe and the iron special waist-shaped hoop, the soft rope is tensioned, and the pressure stick body consisting of the scaffold steel pipe and the iron special waist-shaped hoop is withdrawn for standby;
and step 8: if the height of the basement is larger, the step 6 and the step 7 are circulated;
and step 9: and finally, adhering a last-stage waterproof protective plate along the waterproof layer surface outside the column wall, vertically arranging in the length direction, backfilling earthwork in the area, spreading in layers for 250-300 mm, and mechanically compacting.
The step 1 of organizing foundation pit earthwork excavation according to a conventional method, and the construction of the structural body comprises the following steps: the foundation pit foundation is formed with the elevation lines at the bottom of the foundation pit, the slope lines of the foundation pit and the elevation lines of original soil, and after the foundation pit foundation is accepted, the plain concrete cushion layer, the reinforced concrete leveling waterproof layer, the reinforced concrete raft, the reinforced concrete guide wall, the water stop steel plate, the reinforced concrete wall column and the reinforced concrete beam slab are embedded at the joint face of the guide wall in sequence, and the protective railing is erected on the top cover of the structure body and comprises a lower horizontal rod, an upper horizontal rod and a vertical rod.
In step 3, the raft plate is externally pasted with a waterproof protection plate, which comprises: pumping accumulated water in a foundation pit fertilizer groove, cleaning sundries, attaching a waterproof protective plate and a raft outer convex outer wall waterproof protective plate to the side surface of the reinforced concrete raft, placing a heavy object on the waterproof protective plate on the upper plane of the raft outer convex outer wall waterproof protective plate, backfilling earthwork in the area, spreading in layers for 250-300 mm, and mechanically compacting.
The scaffold steel pipe is sleeved at a fixed position in the waist-shaped hoop.
The invention has the advantages that: the pressing rod body consisting of the scaffold steel pipe and the special iron waist-shaped hoop is lifted by arranging a hemp or nylon soft rope with the phi of 5-6 mm, and then is put down to the waterproof protective plate along the line below 200 mm, and the force for extruding the protective plate is generated by utilizing the weight of the pressing rod body. The method not only solves the problem of righting and restoring safety after falling and toppling due to the fact that the waterproof protection plate is adhered to the basement and is easy to be affected by external force, but also reduces labor and materials, and solves the problem that backfill filler possibly damages a waterproof layer, so that the whole waterproof effect of the basement is guaranteed.
Drawings
The present invention will be described in further detail with reference to the accompanying drawings and specific embodiments.
FIG. 1 is a schematic view of the present invention for completing excavation of foundation pit earthwork and construction of an underground structure;
FIG. 2 is a schematic diagram illustrating the completion of the waterproof construction of the outer side surface of the underground structure column wall according to the present invention;
fig. 3 is a schematic view of the side edge and upper plane protection plate of the raft plate of the invention;
fig. 4 is a schematic diagram of layered backfilling of earthwork of a fertilizer groove at the side edge of a raft plate;
FIG. 5 is a schematic view illustrating the installation of a first outer wall pillar protective plate according to the present invention;
fig. 6 is a schematic diagram of the trough earth backfilling to 200 mm elevation (with a pressure bar) below the first external wall column protective plate according to the invention;
fig. 7 is a schematic diagram of the trough earth backfilling to 200 mm elevation (no-pressure rod) under the first external wall column protective plate according to the invention;
FIG. 8 is a schematic diagram of the backfilling of the earth of the fertilizer trough to the first external wall pillar protection plate according to the present invention;
fig. 9 is a schematic diagram of the trough earth backfilling to 200 mm elevation (with a pressure bar) under the second external wall pillar protection plate according to the invention;
fig. 10 is a schematic diagram of the trough earth backfilling to 200 mm elevation (no-pressure rod) backfilling below the protective plate of the second external wall column according to the invention;
FIG. 11 is a schematic diagram of the backfilling of the earth space of the fertilizer groove to the second external wall pillar protection plate according to the present invention;
FIG. 12 is a schematic view of the last outer wall pillar protection plate of the present invention;
FIG. 13 is a schematic diagram of the backfilling of the earth of the fertilizer trench to the top level of the structure according to the present invention;
figure 14 is a schematic representation of the position of the waist hoop and scaffold steel tube of the present invention in use.
Wherein: 1. marking a high line at the bottom of the foundation pit; 2. a foundation pit side slope line; 3. marking a height line by undisturbed soil; 4. a plain concrete cushion; 5. leveling the waterproof layer by reinforced concrete; 6. reinforced concrete raft, 7, reinforced concrete guide wall; 8. a reinforced concrete column wall; 9. reinforced concrete beam slabs; 10. a water stop steel plate; 11. a lower horizontal bar; 12. an upper horizontal rod; 13. erecting a rod; 14. a waterproof layer; 15. a raft plate outer convex outer wall waterproof protection plate; 16. waterproof protection plates are arranged on the lateral sides of the raft plates; 17. pressing into blocks; 18. a waterproof protection plate; 19. a waist-shaped hoop; 20. a scaffold steel tube; 21. a soft rope.
Detailed Description
As shown in fig. 1 to 14, a construction process for preventing a basement exterior wall waterproof layer protective board from being stuck and toppled comprises the following steps:
step 1: organizing foundation pit earthwork excavation according to a conventional method to form a foundation pit bottom elevation line 1, a foundation pit side slope line 2 and an original state soil elevation line 3, after a foundation pit foundation is checked and accepted, sequentially completing a plain concrete cushion layer 4, a reinforced concrete leveling and waterproof layer 5, a reinforced concrete raft 6, a reinforced concrete guide wall 7, a water stop steel plate 10, a reinforced concrete wall column 8 and a reinforced concrete beam plate 9 which are embedded at the joint face of the guide wall, and erecting a protective railing on the top cover of a structure body, wherein the protective railing comprises a lower horizontal rod 11, an upper horizontal rod 12 and a vertical rod 13;
step 2: after the reinforced concrete column wall and the beam slab structure of the underground structure are qualified, immediately organizing waterproof layers 14 on the outer sides of the wall columns, the upper plane of the outer wall surface protruded by the reinforced concrete raft 6 and the outer side surfaces of the upper plane and the outer side surfaces according to the design waterproof layer standard;
and 3, step 3: draining accumulated water and cleaning sundries in a foundation pit fertilizer groove, attaching a waterproof protective plate 16 and a raft outer convex outer wall waterproof protective plate 15 on the side surface of a reinforced concrete raft 6 according to a design standard, placing a pressing block 17 on the waterproof protective plate on the upper plane of the raft outer convex outer wall waterproof protective plate 15, backfilling earthwork in the area, spreading in layers for 250-300 mm, and mechanically compacting;
and 4, step 4: one end of a soft rope 21 made of hemp or nylon and with the phi of 5-6 mm is connected with the special waist-shaped hoop 19 for the iron, and the other end is connected with a lower horizontal rod 11 of the protective railing on the top cover of the underground structure; a scaffold steel pipe 20 of 6000 mm (or other lengths) penetrates through the two special iron waist-shaped hoop rings 19 to form a rod pressing body; when a first-stage waterproof protective plate 18 is adhered along the waterproof layer surface of the outer wall column and vertically arranged in the longitudinal direction, a pressing rod body consisting of a scaffold steel pipe 20 and two iron special waist-shaped hoops 19 is put down to 200 mm below the top of the first-stage protective plate; backfilling earthwork in the area, layering and spreading for 250-300 mm, and mechanically compacting; one end of the special waist-shaped hoop 19 is 500 mm away from the 6000 mm (or other lengths) of the scaffold steel pipe 20, so that for a 6000 mm long steel pipe, the distance between the two special waist-shaped hoops 19 is 5000 mm, and the distance between the two special waist-shaped hoops 19 of other lengths is correspondingly decreased progressively;
and 5: after the backfilled soil surface touches a stick body consisting of the scaffold steel pipe 20 and the iron special waist-shaped hoop 19, tensioning a hemp or nylon soft rope 21 with the diameter of 5-6 mm, and withdrawing the stick body consisting of the scaffold steel pipe 20 and the iron special waist-shaped hoop 19 for later use;
step 6: then, after an upper-level waterproof protection plate 18 is pasted along the waterproof layer 14 surface of the column wall (vertically arranged in the longitudinal direction), a press rod body consisting of a scaffold steel pipe 20 and an iron special waist-shaped hoop 19 is put down to 200 mm below the top of the first-level protection plate, the earth in the area is backfilled, and the waterproof protection plate is paved for 300 mm in layers and mechanically compacted;
and 7: after the backfilled soil surface touches the pressing roller body consisting of the steel scaffold tube 20 and the special iron waist-shaped hoop 19, the soft rope 21 is tensioned, and the pressing roller body consisting of the steel scaffold tube 20 and the special iron waist-shaped hoop 19 is withdrawn for standby;
and 8: if the height of the basement is larger, the step 6 and the step 7 are circulated;
and step 9: and finally, sticking a last-stage waterproof protective plate 18 along the waterproof layer surface of the outer wall column, vertically arranging in the longitudinal direction, backfilling earthwork in the area, spreading in layers for 250-300 mm, and mechanically compacting.
According to the invention, the flexible rope made of hemp or nylon and with the phi of 5-6 mm is arranged to lift the pressing rod body consisting of the scaffold steel pipe and the special iron waist-shaped hoop, and then the pressing rod body is placed on the waterproof protective plate and is positioned below 200 mm along the line, and the force for extruding the protective plate is generated by utilizing the weight of the pressing rod body. The method not only solves the problem of righting and recovering safety after falling and toppling due to the fact that the waterproof protection plate is easily affected by external force after being pasted, but also reduces labor and materials, and solves the problem that backfill filler can damage a waterproof layer, so that the whole waterproof effect of the basement is guaranteed.
The above-mentioned embodiments are merely illustrative of the preferred embodiments of the present invention, and do not limit the scope of the present invention, and various modifications and improvements made to the technical solution of the present invention by those skilled in the art without departing from the spirit of the present invention should be included in the protection scope defined by the claims of the present invention.

Claims (3)

1. The utility model provides a prevent that basement outer wall waterproof layer protection shield from pasting construction technology of empting which characterized in that: the method comprises the following steps:
step 1: organizing foundation pit earth excavation according to a conventional method to construct a structural body;
step 2: after the reinforced concrete column wall and the beam slab structure of the underground structure are qualified, immediately organizing waterproof layers on the outer sides of the wall columns, the upper plane of the convex outer wall surface of the raft plate and the outer side surface of the raft plate for construction;
and 3, step 3: a waterproof protection plate is attached outside the raft plate;
and 4, step 4: one end of a soft rope made of hemp or nylon and having the diameter of 5 to 6 mm is connected with the waist-shaped hoop, and the other end of the soft rope is connected with a lower horizontal rod of a protective railing on the top cover of the underground structure; a scaffold steel pipe of 6000 mm penetrates through the two special iron waist-shaped hoop to form a rod pressing body; when a first-stage waterproof protective plate is adhered along the waterproof layer surface of the outer wall column and vertically arranged in the longitudinal direction, a pressing rod body consisting of a scaffold steel pipe and two iron special waist-shaped hoop rings is placed downwards until the top of the first-stage waterproof protective plate is 200 mm; backfilling earthwork in the area, layering and paving the earthwork for 300 mm, and mechanically compacting the earthwork;
and 5: after the backfilled soil surface touches the pressing roller body consisting of the scaffold steel pipe and the special iron waist-shaped hoop, the flexible rope is tensioned, and the pressing roller body consisting of the scaffold steel pipe and the special iron waist-shaped hoop is withdrawn for later use;
and 6: then sticking an upper-level waterproof protective plate along the waterproof layer surface of the column wall, vertically arranging in the longitudinal direction, then putting down a pressing rod body consisting of a scaffold steel pipe and the special iron waist-shaped hoop until the thickness is 150-250 mm below the top of the waterproof protective plate, then backfilling earthwork in the area, layering and spreading for 250-300 mm, and mechanically compacting;
and 7: after the backfilled soil surface touches the pressure stick body consisting of the scaffold steel pipe and the iron special waist-shaped hoop, the flexible rope is tensioned, and the pressure stick body consisting of the scaffold steel pipe and the iron special waist-shaped hoop is withdrawn for standby;
and 8: if the height of the basement is larger, the step 6 and the step 7 are circulated;
and step 9: finally, adhering a last-stage waterproof protective plate along the waterproof layer surface outside the column wall, vertically arranging in the length direction, backfilling earthwork in the area, spreading in layers for 250-300 mm, and mechanically compacting; the scaffold steel pipe is sleeved at a fixed position in the waist-shaped hoop.
2. The construction process for preventing the basement exterior wall waterproof layer protection board from being stuck and toppled over as claimed in claim 1, wherein: organizing foundation pit earthwork excavation according to a conventional method in the step 1, and constructing a structural body comprises the following steps: the foundation pit foundation is formed with the elevation lines at the bottom of the foundation pit, the slope lines of the foundation pit and the elevation lines of original soil, and after the foundation pit foundation is accepted, the plain concrete cushion layer, the reinforced concrete leveling waterproof layer, the reinforced concrete raft, the reinforced concrete guide wall, the water stop steel plate, the reinforced concrete wall column and the reinforced concrete beam slab are embedded at the joint face of the guide wall in sequence, and the protective railing is erected on the top cover of the structure body and comprises a lower horizontal rod, an upper horizontal rod and a vertical rod.
3. The construction process for preventing the basement exterior wall waterproof layer protective board from being stuck and toppled over as claimed in claim 1, wherein the construction process comprises the following steps: in step 3, the raft plate is externally pasted with a waterproof protection plate, which comprises: pumping accumulated water in a foundation pit fertilizer groove, cleaning sundries, attaching a waterproof protective plate and a raft outer convex outer wall waterproof protective plate to the side surface of the reinforced concrete raft, placing a heavy object on the waterproof protective plate on the upper plane of the raft outer convex outer wall waterproof protective plate, backfilling earthwork in the area, spreading in layers for 250-300 mm, and mechanically compacting.
CN202110981048.5A 2021-08-25 2021-08-25 Construction process for preventing basement exterior wall waterproof layer protection plate from being pasted and toppled Active CN113585355B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110981048.5A CN113585355B (en) 2021-08-25 2021-08-25 Construction process for preventing basement exterior wall waterproof layer protection plate from being pasted and toppled

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110981048.5A CN113585355B (en) 2021-08-25 2021-08-25 Construction process for preventing basement exterior wall waterproof layer protection plate from being pasted and toppled

Publications (2)

Publication Number Publication Date
CN113585355A CN113585355A (en) 2021-11-02
CN113585355B true CN113585355B (en) 2023-03-10

Family

ID=78239743

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110981048.5A Active CN113585355B (en) 2021-08-25 2021-08-25 Construction process for preventing basement exterior wall waterproof layer protection plate from being pasted and toppled

Country Status (1)

Country Link
CN (1) CN113585355B (en)

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08269984A (en) * 1995-03-28 1996-10-15 Toa Kensetsu Kk Construction of basement in outside waterproofing construction method
CN111173166A (en) * 2020-02-25 2020-05-19 华川建设集团有限公司 Basement outer wall waterproof protection structure and construction method
CN212336112U (en) * 2020-05-09 2021-01-12 中北华宇建筑工程公司 Fixing device of polyphenyl board on underground outdoor wall

Also Published As

Publication number Publication date
CN113585355A (en) 2021-11-02

Similar Documents

Publication Publication Date Title
CN101725258B (en) Integral jacking method of heritage buildings
CN100455731C (en) Guide pit type manual pot holing pile reinforing and underpinning method for building foundation and composite supporting pile
CN101092850A (en) Method and installation for rising building or historical building / cluster of historical building integrally
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN108612110B (en) Combined type supporting construction method for deep foundation pit of subway station
CN105804007B (en) A kind of reinforced earth quaywall structure based on the soft base of beach
CN109898520A (en) A kind of heavy wall construction method
CN107542115A (en) Underground project waterproof structure and its construction method
CN110004991B (en) Underground structure anti-floating system based on convex wing foot plate and construction method
CN102116030A (en) Combined bracing structure for foundation pit and construction method thereof
CN111456032B (en) Foundation pit supporting system and construction method thereof
CN107119695A (en) A kind of operation support body and construction method for cancelling outer wall of basement backfill
CN101418575B (en) L-shaped retaining wall, construction method and detection method thereof
CN105421477A (en) Construction method for tower crane foundation
CN111622234B (en) Unloading type thin-wall box-type retaining wall supported by obliquely and vertically combined steel pipe pile and construction process
CN113585355B (en) Construction process for preventing basement exterior wall waterproof layer protection plate from being pasted and toppled
CN205382942U (en) Multilayer underground space curtain posture subsurface excavated construction's supporting construction under existing facility
CN106400814A (en) Foundation pit supporting method
CN217150275U (en) High water level weak foundation pit supporting device
CN110820756A (en) Shield well and vertical shaft deep foundation pit excavation safety construction method
CN101148889B (en) Compressed-air caisson anchor pile supporting device
CN216713040U (en) Full-prefabricated pier type portal inclined support pile structure system
CN212026271U (en) Supporting construction of weak soil foundation ditch
CN215715515U (en) Municipal pipe network construction supporting integrated structure under unfavorable geological conditions
CN115198806A (en) Underground wall post-cast strip template reinforcing and installing construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant