CN114325114A - 一种免拆接地线的双端接地回路电阻测试方法 - Google Patents

一种免拆接地线的双端接地回路电阻测试方法 Download PDF

Info

Publication number
CN114325114A
CN114325114A CN202111433259.1A CN202111433259A CN114325114A CN 114325114 A CN114325114 A CN 114325114A CN 202111433259 A CN202111433259 A CN 202111433259A CN 114325114 A CN114325114 A CN 114325114A
Authority
CN
China
Prior art keywords
resistance
grounding
circuit breaker
loop
test
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111433259.1A
Other languages
English (en)
Inventor
李蓉
杨敏
张庆
浦云飞
杨超
白添凯
周帆
浦通
鲁强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Power Grid Co Ltd
Original Assignee
Yunnan Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Power Grid Co Ltd filed Critical Yunnan Power Grid Co Ltd
Priority to CN202111433259.1A priority Critical patent/CN114325114A/zh
Publication of CN114325114A publication Critical patent/CN114325114A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Measurement Of Resistance Or Impedance (AREA)

Abstract

本发明涉及免拆接地线的双端接地回路电阻测试方法。包括:采用恒流源控制模块用于确保恒定大电流电源输出;采用电桥测量法用于排除接触电阻对测量的影响;使用“4+1”端子接线法,“4”即为I、I、U、U四根测试引出线,测试时需要采用电压线内置的接线方式;“1”即增加钳形电流表支路进行电流屏蔽,测试并联支路分流的电流值,将其反馈回计算模块,计算出被测断路器主回路电阻的实际值。本发明有效排除寄生回路及测试线电阻的影响,实现无需拆除接地排就能够完成回路电阻试验。新型测试方法消除因拆除接地排造成感应电伤人的风险,创新了GIS回路电阻试验的操作流程,可显著提高现场的工作效率。

Description

一种免拆接地线的双端接地回路电阻测试方法
技术领域
本发明涉及一种免拆接地线的双端接地回路电阻测试方法,属于断路器回路电阻试验技术领域。
背景技术
目前进行断路器回路电阻试验时,需要进行安全措施变更,将断路器一侧的接地点解开,一方面,需要汇报调度,批准后运行人员配合拆除工作地点一侧安全措施,工作结束前再进行恢复,增加工作量的同时,延长工作时间及设备停电时间;另一方面,安全措施变更后,断路器一侧接地点解除,存在安全风险,尤其是对GIS内部断路器来说,断口距离极近,拆开一侧接地点安全风险极大。对于500kV断路器回路电阻试验,一次设备高度高,接线复杂,回路电阻试验需要用到高架车进行一次引流线接线,安全措施变更后,设备附件感应电更强,极大增加了人身风险。
断路器回路电阻试验可以检测其通流能力,发现主回路中有无接触不良的缺陷,检查设备安装、检修质量和运行中的健康水平。回路电阻试验是在断路器合闸状态下,通过两侧接地刀闸施加试验电流进行测量,由于接地刀闸会形成并联支路产生分流影响测量结果,所以传统测试方法需要拆除其中一侧接地点,消除并联回路后,进行准确测量。
发明内容
本发明提供了一种免拆接地线的双端接地回路电阻测试方法,以用于实现无需拆除接地排就能够完成回路电阻试验,可显著提高现场的工作效率。
本发明的技术方案是:一种免拆接地线的双端接地回路电阻测试方法,所述方法的具体步骤如下:
Step1、停电布置安全措施:断开断路器,拉开断路器两侧隔离开关,合上断路器两侧接地刀闸;
Step2、安全措施布置完毕,履行现场安全手续后,合上断路器;
Step3、断路器在合闸位置时,进行测试线布置;
Step4、完成接线后,输出选择100A以上,按照以下测试方法运行,进行测试;
测试方法包括:
Step4.1、采用恒流源控制模块用于确保恒定大电流电源输出;
Step4.2、采用电桥测量法用于排除接触电阻对测量的影响;
Step4.3、使用“4+1”端子接线法,“4”即为I、I、U、U四根测试引出线,由于断路器回路电阻通常为微欧级,属于小电阻测量,测试时需要采用电压线内置的接线方式;“1”即增加钳形电流表支路进行电流屏蔽,测试并联支路分流的电流值ΔI,将其反馈回计算模块,计算出被测断路器主回路电阻的实际值。
作为本发明的进一步方案,所述步骤Step4.3中,“4+1”端子接线法包括:
I、I、U、U四根线分布在断路器触头两侧,I、U位于一侧,I、U位于另一侧,此时需注意,电压线始终位于电流线内侧;钳形电流表布置于一侧接地刀闸回路。
本发明的有益效果是:
1、本发明的方法免拆接地线,因为进行回路电阻试验再也不需要拆除安全措施,试验人员始终处于双侧接地线的保护范围内,消除因拆除接地线造成感应电伤人的风险,可以极大提升试验人员的安全水平,创新了GIS回路电阻试验的操作流程,可显著提高现场的工作效率;
2、其次,本发明运行人员可以省去变更安全措施及试验结束后的恢复工作,极大节约时间成本,减少试验人员及运行人员在变电站风险暴露时间;本发明可以在减少工作量的前提下,获取到更准确的试验数据。
附图说明
图1为本发明中的原理图;
图2为本发明中屏蔽电流测试接线图;
图3为本发明中屏蔽电流测试接线图等效电路示意图。
具体实施方式
实施例1:如图1-图3所示,一种免拆接地线的双端接地回路电阻测试方法,所述方法的具体步骤如下:
Step1、停电布置安全措施:断开断路器,拉开断路器两侧隔离开关,合上断路器两侧接地刀闸;
Step2、安全措施布置完毕,履行现场安全手续后,合上断路器;
Step3、断路器在合闸位置时,进行测试线布置;
Step4、完成接线后,输出选择100A以上,按照以下测试方法运行,进行测试;
测试方法包括:
Step4.1、本发明采用先进大功率开关电源技术和电力电子技术相结合,采用恒流源控制模块用于确保恒定大电流电源输出,可以有效提高测试准确性;
Step4.2、采用电桥测量法用于排除接触电阻对测量的影响;
Step4.3、使用“4+1”端子接线法,“4”即为I、I、U、U四根测试引出线,由于断路器回路电阻通常为微欧级,属于小电阻测量,测试时需要采用电压线内置的接线方式;“1”即增加钳形电流表支路进行电流屏蔽,测试并联支路分流的电流值ΔI,将其反馈回计算模块,计算出被测断路器主回路电阻的实际值,有效排除寄生回路及测试线电阻的影响,实现无需拆除接地排就能够完成回路电阻试验。新型测试方法消除因拆除接地排造成感应电伤人的风险,创新了GIS回路电阻试验的操作流程,可显著提高现场的工作效率。其中,“4+1”端子接线法包括:I、I、U、U四根线分布在断路器触头两侧,I、U位于一侧,I、U位于另一侧,此时需注意,电压线始终位于电流线内侧;钳形电流表布置于一侧接地刀闸回路。
本发明革新旧的试验接线方式,在测量断路器回路电阻时,无需变更安全措施,消除因拆除接地线造成感应电伤人的风险;无需变更安全措施,也节省了大量人力、时间成本,减少试验人员及运行人员在变电站风险暴露时间。专利成果应用后,首先因为进行回路电阻试验再也不需要拆除安全措施,可以极大提升试验人员的安全水平;某供电局35-220kV变电站共218座,220kV及以上的电气设备一般需要3年进行一次试验,而110kV及以下设备需要6年,若试验班组均采用项目研发的双端接地回路电阻测试装置及方法,那么需求量和带来的改善效益将是极为巨大的。
上面结合附图对本发明的具体实施方式作了详细说明,但是本发明并不限于上述实施方式,在本领域普通技术人员所具备的知识范围内,还可以在不脱离本发明宗旨的前提下作出各种变化。

Claims (2)

1.一种免拆接地线的双端接地回路电阻测试方法,其特征在于:所述方法的具体步骤如下:
Step1、停电布置安全措施:断开断路器,拉开断路器两侧隔离开关,合上断路器两侧接地刀闸;
Step2、安全措施布置完毕,履行现场安全手续后,合上断路器;
Step3、断路器在合闸位置时,进行测试线布置;
Step4、完成接线后,输出选择100A以上,按照以下测试方法运行,进行测试;
测试方法包括:
Step4.1、采用恒流源控制模块用于确保恒定大电流电源输出;
Step4.2、采用电桥测量法用于排除接触电阻对测量的影响;
Step4.3、使用“4+1”端子接线法,“4”即为I、I、U、U四根测试引出线,由于断路器回路电阻通常为微欧级,属于小电阻测量,测试时需要采用电压线内置的接线方式;“1”即增加钳形电流表支路进行电流屏蔽,测试并联支路分流的电流值ΔI,将其反馈回计算模块,计算出被测断路器主回路电阻的实际值。
2.根据权利要求1所述的免拆接地线的双端接地回路电阻测试方法,其特征在于:所述步骤Step4.3中,“4+1”端子接线法包括:
I、I、U、U四根线分布在断路器触头两侧,I、U位于一侧,I、U位于另一侧,此时需注意,电压线始终位于电流线内侧;钳形电流表布置于一侧接地刀闸回路。
CN202111433259.1A 2021-11-29 2021-11-29 一种免拆接地线的双端接地回路电阻测试方法 Pending CN114325114A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111433259.1A CN114325114A (zh) 2021-11-29 2021-11-29 一种免拆接地线的双端接地回路电阻测试方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111433259.1A CN114325114A (zh) 2021-11-29 2021-11-29 一种免拆接地线的双端接地回路电阻测试方法

Publications (1)

Publication Number Publication Date
CN114325114A true CN114325114A (zh) 2022-04-12

Family

ID=81047295

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111433259.1A Pending CN114325114A (zh) 2021-11-29 2021-11-29 一种免拆接地线的双端接地回路电阻测试方法

Country Status (1)

Country Link
CN (1) CN114325114A (zh)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101968524A (zh) * 2010-09-30 2011-02-09 王道龙 公共回路多点接地分流测试法及测试仪
CN103604998A (zh) * 2013-10-22 2014-02-26 河南省电力公司商丘供电公司 测量断路器导电回路电阻的方法
CN103969576A (zh) * 2014-04-24 2014-08-06 国家电网公司 双接地断路器动特性分析仪
CN104459529A (zh) * 2014-12-21 2015-03-25 国家电网公司 变电站高压断路器机械特性试验的双环流测试方法
CN204422686U (zh) * 2014-12-01 2015-06-24 广东电网有限责任公司佛山供电局 Tv二次回路多点接地检测装置
CN108169568A (zh) * 2018-01-31 2018-06-15 淮安信息职业技术学院 毫欧级电阻测量电路
CN108594019A (zh) * 2018-03-19 2018-09-28 广东电网有限责任公司中山供电局 一种不拆接地排的gis回路电阻测试装置及方法
CN109116119A (zh) * 2018-09-19 2019-01-01 中国南方电网有限责任公司超高压输电公司柳州局 一种双接地状态下的回路电阻测试系统
US20190339305A1 (en) * 2018-05-03 2019-11-07 Keithley Instruments, Llc Non-linear active shunt ammeter

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101968524A (zh) * 2010-09-30 2011-02-09 王道龙 公共回路多点接地分流测试法及测试仪
CN103604998A (zh) * 2013-10-22 2014-02-26 河南省电力公司商丘供电公司 测量断路器导电回路电阻的方法
CN103969576A (zh) * 2014-04-24 2014-08-06 国家电网公司 双接地断路器动特性分析仪
CN204422686U (zh) * 2014-12-01 2015-06-24 广东电网有限责任公司佛山供电局 Tv二次回路多点接地检测装置
CN104459529A (zh) * 2014-12-21 2015-03-25 国家电网公司 变电站高压断路器机械特性试验的双环流测试方法
CN108169568A (zh) * 2018-01-31 2018-06-15 淮安信息职业技术学院 毫欧级电阻测量电路
CN108594019A (zh) * 2018-03-19 2018-09-28 广东电网有限责任公司中山供电局 一种不拆接地排的gis回路电阻测试装置及方法
US20190339305A1 (en) * 2018-05-03 2019-11-07 Keithley Instruments, Llc Non-linear active shunt ammeter
CN109116119A (zh) * 2018-09-19 2019-01-01 中国南方电网有限责任公司超高压输电公司柳州局 一种双接地状态下的回路电阻测试系统

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘平安等: "电桥法测电阻", 普通物理实验, pages 179 *
范志国: "《电业安全工作规程》的修改和补充建议", 电力安全技术, no. 06 *
魏力强;齐锦涛;张学伟;谷丽娜;李雪松;: "电力电缆试验方法及检测技术分析", 河北电力技术, no. 04 *

Similar Documents

Publication Publication Date Title
CN108169567A (zh) 一种断路器的回路电阻测试仪
CN201656454U (zh) 直流牵引供电开关柜线路测试装置
CN202230150U (zh) 一种光纤供电的电力避雷器在线监测智能终端
CN105259488A (zh) 500kV高压并联电抗器匝间绝缘性能测试平台
CN106707030B (zh) 配电变压器接地阻抗、功率损耗的测量方法和装置
CN112485717A (zh) 配电真型试验负载模拟装置及方法
CN204190234U (zh) 高压开关柜接地及试验一体化小车
CN214174589U (zh) 配电真型试验负载模拟装置
CN109116119A (zh) 一种双接地状态下的回路电阻测试系统
CN102968668A (zh) 城市配电网评估系统及方法
CN205139307U (zh) 500kV高压并联电抗器匝间绝缘性能测试装置
CN111707887A (zh) 一种电力变压器例行试验最优方案
CN114325114A (zh) 一种免拆接地线的双端接地回路电阻测试方法
CN204479654U (zh) 一种交流线路交流避雷器带电检测系统
CN113138333A (zh) 基于双端接地的高压断路器回路电阻测量方法
CN109142873A (zh) 一种轨道交通直流供电系统全回路直流电阻测试方法
CN209070019U (zh) 一种双接地状态下的回路电阻测试系统
CN113866526A (zh) 一种智能变电站的一次模拟带电试验系统及方法
CN108279345B (zh) 一种变电所送电检验装置
CN102636683B (zh) 基于小电流突变电力直流电源系统短路电流测试装置及方法
CN215768950U (zh) 一种变电设备接地引下线导通状态在线检测装置
CN221572755U (zh) 一种飞机电传系统电源性能原位检查仪
CN114942358B (zh) 一种地铁供电系统多电气量同步测试方法
CN216285604U (zh) 地铁gis高压开关柜系统检测装置
CN110596489B (zh) 一种新型轨道交通的配电系统辅助调试方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20220412