Prior art keywords
curtain wall
shaped
rod
vertical
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111617299.1A
Other languages
Chinese (zh)
Other versions
CN114182969A (en
Inventor
魏新亚
周展
孙建平
王淼
李庆辉
郭威威
魏俊伟
许连军
袁森
张华强
唐大龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Konita Decoration Co ltd
Original Assignee
Konita Decoration Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Konita Decoration Co ltd filed Critical Konita Decoration Co ltd
Priority to CN202111617299.1A priority Critical patent/CN114182969B/en
Publication of CN114182969A publication Critical patent/CN114182969A/en
Application granted granted Critical
Publication of CN114182969B publication Critical patent/CN114182969B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates
    • E04G21/1841Means for positioning building parts or elements
    • E04G21/185Means for positioning building parts or elements for anchoring elements or elements to be incorporated in the structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/18Implements for finishing work on buildings for setting wall or ceiling slabs or plates
    • E04F21/1838Implements for finishing work on buildings for setting wall or ceiling slabs or plates for setting a plurality of similar elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

The invention relates to the technical field of curtain wall installation, in particular to a construction method of a cambered surface building curtain wall, wherein a positioning connecting device is arranged and can be detachably connected with the curtain wall, the position of the curtain wall is convenient to adjust, the curtain wall is attractive in installation, the initial positioning of the curtain wall can be realized through the matching of a U-shaped rod on the curtain wall and a U-shaped groove in the positioning connecting device, the U-shaped rod has a certain transverse moving space relative to the U-shaped groove on a sliding block, the sliding block is driven to move along a sliding groove by rotating a lead screw, a threaded hole on the sliding block corresponds to a vertical groove on the U-shaped rod of the vertical groove, the curtain wall is positioned at a proper position so as to be matched with the curtain wall adjacent to the left side and the right side of the curtain wall, the joint is attractive in appearance, then the fixing is completed through a bolt, the curtain wall is fixed on the positioning connecting device, the curtain wall is attractive in installation, and the position of the positioning connecting device relative to the vertical rod can be changed through a screw rod, so that the joint of the curtain wall adjacent to the upper side and the lower side is attractive in appearance.

Description

Construction method of cambered surface building curtain wall
Technical Field
The invention relates to the technical field of curtain wall installation, in particular to a construction method of a cambered surface building curtain wall.
Background
Along with the development of modern building technology and scientific technology and the improvement of the living standard of people, the use of the building curtain wall is gradually popularized. According to different manufacturing materials of the building curtain wall, the building curtain wall has different characteristics such as light adjustment, heat preservation and insulation, safety (bulletproof, anti-theft, fireproof, radiation-proof and electromagnetic wave interference-proof), artistic decoration and the like.
In some steel structure's venue class building, its building structure is often non-planar arc structure, and the used decoration curtain wall of its structure for matching is the arc structure equally, however at present in the curtain installation, the curtain installation is not well fixed to the curtain is also convenient for change its position once more after fixed, when the curtain need do the fine setting so that the seam is pleasing to the eye, is very inconvenient to adjust.
Disclosure of Invention
Aiming at the situation and overcoming the defects of the prior art, the invention provides a construction method of a cambered surface building curtain wall, which effectively solves the problems that the positioning is not good when the curtain wall is installed in the prior art and the position of the curtain wall is not convenient to adjust so as to influence the aesthetic measure of a seam;
the positioning and connecting device comprises square sleeves which are vertically sleeved on each vertical rod in a sliding manner, the front end of each vertical rod is fixedly connected with two supporting plates which are vertically arranged at intervals, the two supporting plates are rotatably connected with screws which are vertically arranged and used for driving the square sleeves to slide, the rear end of each square sleeve is fixedly connected with a transverse plate, transversely arranged sliding grooves are formed in the transverse plate, the middle part of the transverse plate is fixedly connected with an L-shaped plate, the left end and the right end of the L-shaped plate are respectively rotatably connected with transversely arranged lead screws, the two lead screws are respectively in threaded connection with sliding blocks in sliding fit with the sliding grooves, U-shaped grooves capable of being inserted into the U-shaped rods are formed in each sliding block, longitudinally arranged threaded holes are formed in each sliding block, and bolts which are longitudinally arranged and can be inserted into and matched with vertical grooves in the U-shaped rods are detachably connected with the threaded holes; the construction method comprises an installation method and a disassembly method, wherein the installation method comprises the following steps:
welding a framework, fixing the framework on the arc-shaped wall body through expansion bolts, and welding reinforcing ribs which are arranged in a crossed mode in each grid for increasing the strength of the framework;
the two U-shaped rods on the inner arc surface of the curtain wall are in one-to-one inserting fit with the two U-shaped grooves, and the vertical grooves are ensured to be in one-to-one correspondence with the threaded holes, so that the curtain wall can be fixed through bolts. In order to enable the vertical groove to correspond to the threaded hole of the bolt, the sliding block can be driven to move along the sliding groove by rotating the lead screw, so that the threaded hole in the sliding block corresponds to the vertical groove in the U-shaped rod, and then the bolt penetrates through the threaded hole and the vertical groove to complete the fixed connection of the curtain wall and the positioning connecting device;
vertical elongated grooves are formed in the left end and the right end of each vertical rod, and a convex block in sliding fit with the corresponding side elongated groove is fixedly connected to the inner wall of each square sleeve on each vertical rod;
when the left curtain wall and the right curtain wall are installed and adjacent to each other, the U-shaped rod has a certain transverse moving space relative to the U-shaped groove, when the left curtain wall and the right curtain wall are installed and the curtain walls are matched and fixed through the U-shaped rod and the U-shaped groove, the relative positions of the U-shaped rod and the U-shaped groove are adjusted, the installation positions of the left curtain wall and the right curtain wall are matched, and the joint is attractive;
when two curtain walls which are adjacent up and down are installed, in order to enable the joint of the two curtain walls to be attractive, the screw rod on the supporting plate can be rotated to drive the square sleeve to vertically move along the long groove on the vertical rod, and the positions of the two curtain walls which are adjacent up and down are adjusted to enable the joint to be attractive;
the disassembling method comprises the following steps: unscrewing the bolt causes the U-bar to be unrestrained.
Preferably, each lead screw is coaxially and fixedly connected with a fixed sleeve, and each fixed sleeve is fixedly connected with a plurality of shifting levers in an annular array.
Preferably, the cross bar is of an arc-shaped structure.
The invention has the beneficial effects that:
the locating and connecting device that is equipped with can be connected and be convenient for adjust the curtain position with the curtain dismantlement, make the curtain installation pleasing to the eye, cooperate through U type groove in U type pole on the curtain and the locating and connecting device, can realize the preliminary location of curtain, U type pole has certain horizontal activity space for U type groove on the slider, it removes along the spout to drive the slider through rotating the lead screw, make screw hole on the slider correspond with the vertical groove on the vertical groove U type pole, fix the curtain in suitable position, so that match rather than controlling adjacent curtain, make the seam pleasing to the eye, later accomplish fixedly through the bolt, the curtain is fixed on locating and connecting device this moment, later for the pleasing to the eye of curtain installation, can also change the position of locating and connecting device for the montant through the screw rod, make upper and lower adjacent curtain seam department pleasing to the eye.
Drawings
FIG. 1 is a perspective view of the present invention.
Fig. 2 is an enlarged view of region a in a perspective view of the present invention.
FIG. 3 is a first perspective view of the positioning connection device of the present invention.
FIG. 4 is a perspective view of a second perspective view of the positioning connection device of the present invention.
FIG. 5 is a perspective view of the curtain wall of the present invention.
Reference numerals
1. The curtain wall comprises a curtain wall body, 2 horizontal rods, 3 vertical rods, 4.U type rods, 5 vertical grooves, 6 square sleeves, 7 supporting plates, 8 screw rods, 9 transverse plates, 10 sliding grooves, 11L type plates, 12 screw rods, 13 sliding blocks, 14U type grooves, 15 threaded holes, 16 bolts, 17 reinforcing ribs, 18 fixing sleeves, 19 deflector rods, 20 elongated grooves and 21 protruding blocks.
Detailed Description
The following description of the embodiments of the present invention will be made in detail with reference to the accompanying drawings 1 to 5.
The locating and connecting device can be detachably connected with the curtain wall 1 and is convenient to adjust the position of the curtain wall 1, the curtain wall 1 is attractive in installation, the U-shaped rod 4 on the curtain wall 1 is matched with the U-shaped groove 14 in the locating and connecting device, the primary locating of the curtain wall 1 can be realized, the U-shaped rod 4 has a certain transverse moving space relative to the U-shaped groove 14 on the sliding block 13, the sliding block 13 is driven to move along the sliding groove 10 by rotating the screw rod, a threaded hole 15 on the sliding block 13 corresponds to the vertical groove 5 on the U-shaped rod 4 of the vertical groove 5, the curtain wall 1 is located at a proper position, so that the curtain wall 1 adjacent to the left side and the right side is matched, the joint is attractive, then the fixing is completed through the bolt 16, at the moment, the curtain wall 1 is fixed on the locating and connecting device, the position of the locating and connecting device relative to the vertical rod 3 can be changed through the screw rod 8, and the joint of the curtain wall 1 adjacent to the top and the bottom is attractive.
Further in order to increase the aesthetic property, the cross rod 2 is of an arc-shaped structure, the optimal radian of the cross rod 2 and the optimal radian of the curtain wall 1 are matched with the radian of the appearance of a building, and the aesthetic property can be further increased. After the curtain wall 1 is in plug-in fit with the U-shaped groove 14 on the sliding block 13 through the U-shaped rod 4, the curtain wall 1 is supported by the sliding block 13, and at the moment, the labor for supporting the curtain wall 1 can be released under the condition of ensuring the construction safety, so that the labor intensity is reduced. Then, the position of the sliding block 13 is adjusted through the lead screw, so that the threaded hole 15 corresponds to the vertical slot 5, and then the bolt 16 passes through the threaded hole 15 and the vertical slot 5 to complete the fixed connection of the curtain wall 1 and the positioning connecting device. The length of the vertical slot 5 is larger than the diameter of the threaded hole 15, so that the bolt 16 can smoothly pass through the vertical slot 5 after being matched with the threaded hole 15. After a curtain wall 1 is installed, when the curtain walls 1 adjacent to the left and right of the curtain wall 1 are installed, the relative positions of the curtain walls 1 and the sliding blocks 13 and the relative positions of the two curtain walls 1 are adjusted, so that the joint is attractive. Two screw rods 12 on one L-shaped plate 11 independently control corresponding slide blocks 13, so that the adjustment is convenient. The U-shaped rod 4 has a certain transverse moving space relative to the U-shaped groove 14, so that the flexibility of adjustment is further increased; after installing a curtain 1, when installation and its upper and lower adjacent curtain 1, for the convenience of adjusting the distance of two-phase adjacent curtain 1 under the mountain makes the seam pleasing to the eye, can carry out vertical slip along montant 3 through rotating screw 8 drive square sleeve 6 for location connecting device reciprocates together rather than fixed connection's curtain 1.
In order to facilitate the rotation of the screw rod 12, a fixed sleeve 18 is fixedly connected on the screw rod, and a plurality of deflector rods 19 in an annular array are fixedly connected on the fixed sleeve 18, so that the screw rod 12 can be conveniently rotated through the deflector rods 19; in order to limit the square sleeve 6 to slide vertically along the vertical rod 3, the left end and the right end of the vertical rod 3 are provided with elongated slots 20, and the inner wall of the square sleeve 6 on each vertical rod 3 is fixedly connected with a convex block 21 in sliding fit with the corresponding elongated slot 20, so that the square sleeve 6 is driven to move vertically by a screw 8 rotationally connected with the supporting plate 7. When the curtain wall 1 needs to be disassembled, the bolts 16 only need to be screwed out, and then the curtain wall 1 can be enabled to be out of the limit of the U-shaped groove 14.

Claims (3)

1. A construction method of a cambered surface building curtain wall comprises a curtain wall (1), and is characterized in that a device used in the construction method of the cambered surface building curtain wall comprises a framework formed by a plurality of grids, each grid comprises a cross rod (2) and a vertical rod (3), U-shaped rods (4) are symmetrically arranged on the left side and the right side of the inner cambered surface of the curtain wall (1), a vertical groove (5) is formed in the rear end of each U-shaped rod (4), and a positioning connecting device used for positioning and connecting the curtain wall (1) is arranged on each vertical rod (3);
the positioning and connecting device comprises square sleeves (6) which are vertically slidably sleeved on each vertical rod (3), the front end of each vertical rod (3) is fixedly connected with two supporting plates (7) which are vertically arranged at intervals, the two supporting plates (7) are rotatably connected with screws (8) which are vertically arranged and are used for driving the square sleeves (6) to slide, the rear end of each square sleeve (6) is fixedly connected with a transverse plate (9), sliding grooves (10) which are transversely arranged are formed in the transverse plate (9), an L-shaped plate (11) is fixedly connected to the middle part of each transverse plate (9), transversely arranged screw rods (12) are respectively rotatably connected to the left end and the right end of each L-shaped plate (11), the two screw rods (12) are respectively in threaded connection with sliding blocks (13) which are in sliding fit with the sliding grooves (10), U-shaped grooves (14) which can be inserted into the U-shaped rods (4) are formed in each sliding block (13), longitudinally arranged threaded holes (15) are formed in each sliding block (13), and bolts (16) which are longitudinally arranged and can be inserted into and matched with vertical grooves (5) in the U-shaped rods (4) are detachably connected to each threaded hole (15); the construction method comprises an installation method and a disassembly method, wherein the installation method comprises the following steps:
welding a framework, fixing the framework on the arc-shaped wall body through expansion bolts (16), and welding reinforcing ribs (17) which are arranged in a crossed manner in each grid for increasing the strength of the framework;
the two U-shaped rods (4) on the inner arc surface of the curtain wall (1) are correspondingly matched with the two U-shaped grooves (14) in a one-to-one inserting mode, and the vertical grooves (5) are ensured to be correspondingly matched with the threaded holes (15) one by one, so that the curtain wall (1) can be fixed through bolts (16);
in order to enable the vertical groove (5) to correspond to a threaded hole (15) of a bolt (16), a lead screw is rotated to drive a sliding block (13) to transversely move along a sliding groove (10) on a transverse plate (9), so that the threaded hole (15) on the sliding block (13) corresponds to the vertical groove (5) on the U-shaped rod (4), and then the bolt (16) penetrates through the threaded hole (15) and the vertical groove (5) to complete the fixed connection of the curtain wall (1) and the positioning connecting device;
vertical elongated grooves (20) are formed in the left end and the right end of each vertical rod (3), and a convex block (21) in sliding fit with the corresponding side elongated groove (20) is fixedly connected to the inner wall of each square sleeve (6) on each vertical rod (3);
when the left curtain wall and the right curtain wall (1) are installed, the U-shaped rod (4) has a certain transverse moving space relative to the U-shaped groove (14), when the left curtain wall and the right curtain wall (1) are installed, and the curtain walls (1) are matched and fixed with the U-shaped groove (14) through the U-shaped rod (4), the relative positions of the U-shaped rod (4) and the U-shaped groove (14) are adjusted, so that the installation positions of the left curtain wall and the right curtain wall (1) are matched, and the joint is attractive;
when two vertically adjacent curtain walls (1) are installed, in order to enable the joint of the upper and lower curtain walls (1) to be attractive, the screw rod (8) on the rotating supporting plate (7) can be used for driving the square sleeve (6) to vertically move along the long groove (20) on the vertical rod (3), and the positions of the vertically adjacent curtain walls (1) are adjusted to enable the joint to be attractive;
the disassembling method comprises the following steps: the bolt (16) is unscrewed to cause the U-shaped rod (4) to be out of the limit.
2. The construction method of building curtain wall with cambered surface as claimed in claim 1, wherein each screw is coaxially and fixedly connected with a fixed sleeve (18), and each fixed sleeve (18) is fixedly connected with a plurality of deflector rods (19) in annular array.
3. The construction method of the cambered surface building curtain wall as claimed in claim 1, wherein the cross bar (2) is of an arc-shaped structure.
CN202111617299.1A 2021-12-28 2021-12-28 Construction method of cambered surface building curtain wall Active CN114182969B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111617299.1A CN114182969B (en) 2021-12-28 2021-12-28 Construction method of cambered surface building curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111617299.1A CN114182969B (en) 2021-12-28 2021-12-28 Construction method of cambered surface building curtain wall

Publications (2)

Publication Number Publication Date
CN114182969A CN114182969A (en) 2022-03-15
CN114182969B true CN114182969B (en) 2023-04-07

Family

ID=80545069

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111617299.1A Active CN114182969B (en) 2021-12-28 2021-12-28 Construction method of cambered surface building curtain wall

Country Status (1)

Country Link
CN (1) CN114182969B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115142687A (en) * 2022-07-27 2022-10-04 康利达装饰股份有限公司 Installation method of hardcover house wood veneer

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN213572539U (en) * 2020-10-14 2021-06-29 邵泽浩 Building curtain anti-drop device that adaptability is high
CN215054373U (en) * 2021-08-02 2021-12-07 广东爱得威建设(集团)股份有限公司 Multifunctional building curtain wall

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08165728A (en) * 1994-12-12 1996-06-25 Higaki Manitetsuku:Kk Fastener for curtain wall
JP2003343088A (en) * 2002-05-30 2003-12-03 Kyowa Rope:Kk Jack for adjusting verticality of steel-framed column
CN204098298U (en) * 2014-08-19 2015-01-14 苏州金螳螂幕墙有限公司 A kind of metal energy-saving curtain wall
CN211472997U (en) * 2019-11-30 2020-09-11 杨靖 Mounting bracket for curtain wall
CN212200934U (en) * 2020-04-28 2020-12-22 山东天元装饰工程有限公司 Assembled building curtain
CN214402334U (en) * 2020-11-02 2021-10-15 张先炎 Stable mounting structure of stone building curtain wall
CN112343226A (en) * 2020-11-05 2021-02-09 谢志福 Unit type solar photovoltaic building component unit and photovoltaic curtain wall thereof
CN214575828U (en) * 2020-12-29 2021-11-02 中哲国际工程设计有限公司 Building wall decoration curtain wall installation positioner

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN213572539U (en) * 2020-10-14 2021-06-29 邵泽浩 Building curtain anti-drop device that adaptability is high
CN215054373U (en) * 2021-08-02 2021-12-07 广东爱得威建设(集团)股份有限公司 Multifunctional building curtain wall

Also Published As

Publication number Publication date
CN114182969A (en) 2022-03-15

Similar Documents

Publication Publication Date Title
CN114182969B (en) Construction method of cambered surface building curtain wall
CN211817332U (en) Mounting structure of subway station furred ceiling
CN210659080U (en) Decorative panel keel connecting structure
CN112922198B (en) Flame-retardant heat-insulation polycarbonate plate curtain wall
CN212104916U (en) GRC decorative concrete external wall panel
CN211499361U (en) Curtain wall mounting structure
CN111188448B (en) Unit type adjustable suspended ceiling structure
CN111677179A (en) Construction method of open type folding suspended ceiling
CN109403535A (en) A kind of hanging structure of open type folding face furred ceiling
CN206625432U (en) Adjustable type lightgage steel joist
CN209261021U (en) A kind of hanging structure of open type folding face furred ceiling
CN215630887U (en) Panel adjusting seat for special-shaped curtain wall and special-shaped curtain wall
CN110725619B (en) Fender is enclosed in construction convenient to dismantle
CN219753661U (en) Quick assembly's grid smallpox
CN112160483A (en) Assembled furred ceiling with steel framed aerial layer locking structure
CN112227737A (en) Wallboard fixing bracket with splicing structure for constructional engineering
CN217352945U (en) High-quality connecting structure of double P plates and laminated floor slab of prefabricated building
CN220565713U (en) Aluminum alloy template wallboard bottom regulator
CN219690826U (en) Airport curtain wall mounting structure
CN216197186U (en) Civil engineering is with enclosing fender
CN204206842U (en) The greenhouse of adjustable shade structures
CN219451254U (en) Novel energy-saving heat-insulation sandwich board
CN214958459U (en) Cable testing bridge support that stability is high
CN217233023U (en) Envelope for construction of assembly type building curtain wall
CN218029084U (en) Reserved steel bar positioning structure of window-grid-shaped outer facade decorative wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant