CN114161106A - Unsettled jointing equipment of sewage drain pipe - Google Patents

Unsettled jointing equipment of sewage drain pipe Download PDF

Info

Publication number
CN114161106A
CN114161106A CN202111382383.XA CN202111382383A CN114161106A CN 114161106 A CN114161106 A CN 114161106A CN 202111382383 A CN202111382383 A CN 202111382383A CN 114161106 A CN114161106 A CN 114161106A
Authority
CN
China
Prior art keywords
fixing
rods
frame
rod
spring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111382383.XA
Other languages
Chinese (zh)
Inventor
陈敏睿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202111382383.XA priority Critical patent/CN114161106A/en
Publication of CN114161106A publication Critical patent/CN114161106A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P19/00Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P19/00Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes
    • B23P19/10Aligning parts to be fitted together

Abstract

The invention relates to a connecting device, in particular to a suspended connecting device for a sewage drain pipe. The invention provides a suspended connecting device for a sewage drain pipe, which can be used for quickly connecting a water pipe, improving the connection sealing performance and being simple to operate. The invention provides suspended connecting equipment for a sewage drain pipe, which comprises a base and a sliding frame, wherein the sliding frame is arranged at the top of the base; the middle part of the sliding frame is uniformly provided with first fixed rods, and the number of the first fixed rods is thirteen; the thirteen first fixing rods are respectively provided with a rotating ring in a rotating mode; the slide frame is provided with a calibration mechanism; the fixing mechanism and the calibration mechanism are provided with a fixing mechanism and a connecting mechanism, and the calibration mechanism is provided with a connecting mechanism. According to the invention, the calibration mechanism is arranged, so that people start the calibration mechanism, the calibration mechanism operates to complete the connection of the drain pipe, and the drain pipe is effectively, quickly and accurately connected.

Description

Unsettled jointing equipment of sewage drain pipe
Technical Field
The invention relates to a connecting device, in particular to a suspended connecting device for a sewage drain pipe.
Background
Water is a source of life and a basis for the development of civilized survival of human beings, the water crisis has become a key point of common attention of all the people all over the world at present, the increasingly serious water resource shortage and water environment pollution of China at present not only afflicts the nations of China, but also becomes an important factor restricting the sustainable development of social economy, the construction industry is the industry of pillars of China, the design, construction and maintenance of a building water supply and drainage system are well done, the concrete means for realizing water saving, energy saving and water quality pollution prevention and treatment are also the urgent requirements for energy saving, emission reduction and environmental protection, the drainage pipe mainly takes the drainage tasks of rainwater, sewage, farmland irrigation and drainage and the like, the drainage pipe is divided into a plastic drainage pipe, a concrete pipe and a reinforced concrete pipe, the connection among the water pipes is mostly ensured by the mode of fixing through gaskets, winding raw belts or hoops at present, but the modes are easy to fall off due to water pressure, the leakage phenomenon of water in the conveying process is caused, the installation mode is more complicated, and the installation position needs to be continuously adjusted to ensure the accuracy of butt joint of the water pipes, so that the prior art still has more defects.
In view of the above, it is desirable to design a suspended connection device for sewage drainage pipes, which can be used for quickly connecting water pipes, improving the connection tightness and being simple to operate.
Disclosure of Invention
In order to overcome the defects of poor sealing performance and complex operation of the connecting pipe in the prior art, the technical problems are as follows: the utility model provides a kind of sewage drain pipe unsettled jointing equipment of quick connection water pipe, improvement connection leakproofness and easy operation.
The technical scheme is as follows: a sewage drain pipe aerial junction device comprising:
the sliding frame is arranged at the top of the base;
the middle part of the sliding frame is uniformly provided with first fixed rods, and the number of the first fixed rods is thirteen;
the thirteen first fixing rods are respectively provided with a rotating ring in a rotating mode;
the slide frame is provided with a calibration mechanism;
the fixing mechanism is arranged on the calibration mechanism;
the connecting mechanism is arranged on the calibration mechanism.
Optionally, the calibration mechanism comprises:
the two sides of the sliding frame are uniformly provided with ten second fixed rods;
the first air cylinder is arranged between the upper parts of the ten second fixing rods;
the first cylinder telescopic rod is sleeved with the connecting pipe;
the connecting protection frame is detachably arranged on the connecting pipe and is connected with the telescopic rod of the first cylinder in a sliding manner;
the first fixing frame is detachably arranged on the connecting pipe;
the first cylinder telescopic rod is symmetrically provided with a first fixing rod;
the first sliding plate is arranged between the two third fixing rods in a sliding manner, and the first fixing frame and the first sliding plate are both connected with the connecting protection frame in a sliding manner;
the first springs are wound on the two third fixing rods, and two ends of each first spring are connected with the third fixing rods and the first sliding plate respectively.
Optionally, the securing mechanism comprises:
the connecting pipe is provided with a second fixed frame;
the second fixing frame and the first fixing frame are respectively provided with a fourth fixing rod at two sides, and the number of the fourth fixing rods is four;
the first limiting rods are arranged on the four fourth fixing rods in a sliding manner;
the second spring, the quantity of first gag lever post is four, all around having the second spring on four first gag lever posts, and the both ends of second spring are connected with first gag lever post and fourth dead lever respectively.
Optionally, the connection mechanism comprises:
the upper side and the lower side of the connecting protection frame are symmetrically provided with eight first fixed blocks;
the middle parts of the eight first fixing blocks are provided with second limiting rods in a sliding manner; the number of the second limiting rods is eight, the second limiting rods are connected with the connecting protection frame in a sliding mode, the second limiting rods are in contact fit with the connecting pipe, and the second limiting rods are in contact fit with the second fixing frame;
the second limiting rod is wound with a second spring, and two ends of the second spring are connected with the first fixing block and the second limiting rod respectively;
and the fourth spring is arranged on the second limiting rod, and two ends of the fourth spring are respectively connected with the first fixing block and the second limiting rod.
Optionally, still including screens mechanism, screens mechanism includes:
the upper side and the lower side of the first fixed frame are both provided with fifth fixed rods in a sliding manner, and the number of the fifth fixed rods is four;
the upper side and the lower side of the second fixed frame are both provided with a sixth fixed rod in a sliding manner;
the upper side and the lower side of the second fixing frame are symmetrically provided with four third limiting rods in a sliding manner, the third limiting rods are in contact fit with sixth fixing rods, and the sixth fixing rods are in contact fit with fifth fixing rods;
the fifth spring is wound on the sixth fixed rod, and two ends of the fifth spring are respectively connected with the second fixed frame and the third limiting rod;
and the sixth spring is wound on the sixth fixed rod, and two ends of the sixth spring are respectively connected with the second fixed frame and the third limiting rod.
Optionally, the lifting mechanism is further included, and the lifting mechanism includes:
the second cylinder is arranged in the base, and a telescopic rod of the second cylinder is connected with the sliding frame;
the two third fixed frames are connected with the second fixed rod in a sliding manner;
the lower parts of the first fixing rings and the ten second fixing rods are provided with the first fixing rings;
and the seventh springs are wound on the ten second fixing rods, and two ends of each seventh spring are respectively connected with the first fixing ring and the second fixing rod.
Optionally, a moving mechanism is further included, and the moving mechanism includes:
the bottom of the base is provided with a bidirectional motor;
the two sides of the bottom of the base are symmetrically provided with four second fixing rings, and the two second fixing rings are rotatably connected with the output shaft of the two-way motor;
the output shafts on two sides of the bidirectional motor are provided with first gears;
the first rotating shaft is rotatably arranged on two sides in the base;
two ends of the first rotating shaft are provided with four second gears, and the two second gears are meshed with the first gears;
the second rotating shaft is rotatably arranged between the two second fixing rings;
the two ends of the second rotating shaft are provided with third gears;
and the crawler wheels are connected between the output shafts on two sides of the bidirectional motor and the second rotating shaft.
Optionally, a push block is arranged at the top of the first fixing frame, and the push block is in contact fit with the first sliding plate.
The invention has the beneficial effects that:
1. according to the invention, the calibration mechanism is arranged, so that people start the calibration mechanism, the calibration mechanism operates to complete the connection of the drain pipe, and the drain pipe is effectively, quickly and accurately connected;
2. according to the invention, the fixing mechanism is arranged, and the calibration mechanism is matched with the fixing mechanism, so that the fixing mechanism fixes the drain pipe and prevents the calibration mechanism from falling off;
3. according to the invention, the connecting mechanism is arranged, and the calibrating mechanism is matched with the connecting mechanism, so that the calibrating mechanism is convenient to operate and connect with the drain pipe;
4. according to the invention, the clamping mechanism is arranged and matched with the connecting mechanism, so that the clamping mechanism automatically drives the connecting mechanism to operate, and manual operation is saved;
5. according to the invention, the lifting mechanism is arranged, so that people start the lifting mechanism, and the distance of the lifting mechanism can be adjusted according to the position of the drain pipe, so that the drain pipe connection at different heights can be effectively realized;
6. according to the invention, the moving mechanism is arranged, so that people can start the moving mechanism, and the moving mechanism operates to drive the connecting equipment to move, thereby facilitating the use of the connecting equipment by people.
Drawings
Fig. 1 is a schematic perspective view of the present invention.
Fig. 2 is a schematic perspective view of a first part of the alignment mechanism of the present invention.
Fig. 3 is a perspective view of a second part of the alignment mechanism of the present invention.
Fig. 4 is a perspective view of a third part of the alignment mechanism of the present invention.
Fig. 5 is a schematic perspective view of a first part of the fixing mechanism of the present invention.
Fig. 6 is a perspective view of a second part of the fixing mechanism of the present invention.
Fig. 7 is a perspective view of a first portion of the connection mechanism of the present invention.
Fig. 8 is a perspective view of a second portion of the connection mechanism of the present invention.
Fig. 9 is a schematic perspective view of a first part of the locking mechanism of the present invention.
Fig. 10 is a schematic perspective view of a second part of the locking mechanism of the present invention.
Fig. 11 is a schematic perspective view of the lifting mechanism of the present invention.
Fig. 12 is a perspective view of a first part of the moving mechanism of the present invention.
Fig. 13 is a perspective view of a second part of the moving mechanism of the present invention.
Description of reference numerals: 1: base, 2: slide frame, 3: first fixed link, 4: swivel, 5: calibration mechanism, 51: second fixing lever, 52: first cylinder, 53: connection protection frame, 54: connection pipe, 55: first fixed frame, 56: third fixing lever, 57: first spring, 58: first slide plate, 6: fixing mechanism, 61: second fixed frame, 62: fourth fixing lever, 63: first stopper rod, 64: second spring, 7: connection mechanism, 71: first fixing block, 72: second stopper rod, 73: third spring, 74: fourth spring, 8: screens mechanism, 81: fifth fixing lever, 82: sixth fixing lever, 83: third stopper rod, 84: fifth spring, 85: sixth spring, 9: lifting mechanism, 91: second cylinder, 92: third fixed frame, 93: first fixing ring, 94: seventh spring, 10: moving mechanism, 101: bidirectional motor, 102: second fixing ring, 103: first gear, 104: first rotating shaft, 105: second gear, 106: second rotating shaft, 107: third gear, 108: a track wheel.
Detailed Description
Embodiments of the present invention will be described below with reference to the drawings.
Example 1
The utility model provides a unsettled connecting device of sewage drain pipe, as shown in fig. 1-8, including base 1, sliding frame 2, first dead lever 3, change 4, aligning gear 5, fixed establishment 6 and coupling mechanism 7, sliding frame 2 is installed at base 1 top, sliding frame 2 middle part evenly is equipped with first dead lever 3, the quantity of first dead lever 3 is thirteen, equal rotary type is equipped with change 4 on thirteen first dead levers 3, be equipped with aligning gear 5 on the sliding frame 2, aligning gear 5 front side is equipped with fixed establishment 6, aligning gear 5 front side is equipped with coupling mechanism 7.
When people need connect to the drain pipe, people can use this kind of unsettled connecting device of sewage drain pipe, at first people put the drain pipe on swivel 4, promote the drain pipe afterwards, thereby drive swivel 4 and rotate, and then entangle the drain pipe through 5 calibration mechanisms, and then operate through 6 fixed establishment, make 6 fixed drain pipes of fixed establishment, people start 5 calibration mechanisms this moment, 5 functions of calibration mechanism correspond the drain pipe with the drain pipe on the wall, then operate through 7 connecting mechanisms, make drain pipe and the water piping connection on the wall, when people accomplish water piping connection, people close 5 calibration mechanisms can.
The calibration mechanism 5 comprises a second fixed rod 51, a first cylinder 52, a connecting protection frame 53, connecting pipes 54, a first fixed frame 55, third fixed rods 56, a first spring 57 and a first sliding plate 58, wherein the left side and the right side of the sliding frame 2 are uniformly provided with the second fixed rods 51, the number of the second fixed rods 51 is ten, the first cylinder 52 is arranged between the upper parts of the ten second fixed rods 51, the connecting pipe 54 is sleeved on the telescopic rod of the first cylinder 52, the front end of the connecting pipe 54 is detachably provided with the connecting protection frame 53, the connecting protection frame 53 is connected with the telescopic rod of the first cylinder 52 in a sliding way, the rear end of the connecting pipe 54 is detachably provided with the first fixed frame 55, the telescopic rods of the first cylinder 52 are symmetrically provided with the third fixed rods 56, the first sliding plate 58 is arranged between the two third fixed rods 56 in a sliding way, the first fixed frame 55 and the first sliding plate 58 are both connected with the connecting protection frame 53, the first spring 57 is wound on the two third fixed rods 56 in a sliding way, both ends of the first spring 57 are connected to the third fixing lever 56 and the first sliding plate 58, respectively.
Firstly, people push the connecting pipe 54, the connecting pipe 54 is sleeved on the first cylinder 52 and then is clamped with the connecting protection frame 53, people sleeve the first fixing frame 55 on the connecting pipe 54 on the wall, then people start the first cylinder 52, when the telescopic rod of the first cylinder 52 is extended, the telescopic rod of the first cylinder 52 drives the connecting pipe 54 and the connecting protection frame 53 to move forwards, so that the connecting protection frame 53 corresponds to the first fixing frame 55 on the wall, thereby driving the first sliding plate 58 to slide backwards, the first spring 57 is compressed, at the moment, the connecting protection frame 53 is not clamped with the first sliding plate 58, the first fixing frame 55 is clamped with the connecting protection frame 53, when the connecting pipe 54 is connected, the telescopic rod of the first cylinder 52 is shortened, so that the connecting pipe 54 and the connecting protection frame 53 are separated from the telescopic rod of the first cylinder 52, and then the next connecting pipe 54 is connected, when people do not need to connect the connecting pipe 54, one closes the first cylinder 52.
The fixing mechanism 6 comprises a second fixing frame 61, a fourth fixing rod 62, first limiting rods 63 and second springs 64, the second fixing frame 61 is installed on the front side of the connecting pipe 54, the fourth fixing rods 62 are arranged on the left side and the right side of the second fixing frame 61 and the left side of the first fixing frame 55, the number of the fourth fixing rods 62 is four, the first limiting rods 63 are arranged on the four fourth fixing rods 62 in a sliding mode, the number of the first limiting rods 63 is four, the second springs 64 are wound on the four first limiting rods 63, and two ends of each second spring 64 are connected with the first limiting rods 63 and the fourth fixing rods 62 respectively.
When people sleeve the connecting pipe 54 on the first cylinder 52 and the first fixing frame 55 is sleeved on the connecting pipe 54 on the wall, people pull the first limiting rod 63 outwards, the second spring 64 is compressed, people sleeve the second fixing frame 61 on the connecting pipe 54 with adaptability at the moment, the connecting pipe 54 moves forwards to drive the second fixing frame 61 to move forwards, so that the second fixing frame 61 controls the position of the first fixing frame 55 on the connecting pipe 54, the first fixing frame 55 is convenient to be connected with the connecting protection frame 53, people loosen the first limiting rod 63, because the second spring 64 resets, the first limiting rod 63 can be driven to move inwards to reset, the second fixing frame 61 and the first fixing frame 55 are clamped with the first limiting rod 63, the clamping effect is further realized, and the second fixing frame 61 and the first fixing frame 55 are prevented from falling off when being connected.
The connecting mechanism 7 comprises a first fixed block 71 and a second limiting rod 72, the connecting protection frame 53 is symmetrically provided with eight first fixing blocks 71 at the upper side, the lower side, the left side and the right side, the number of the first fixing blocks 71 is eight, the middle parts of the eight first fixing blocks 71 are provided with second limiting rods 72 in a sliding mode, the number of the second limiting rods 72 is eight, the second limiting rods 72 are connected with the connecting protection frame 53 in a sliding mode, the second limiting rods 72 at the rear side are in contact fit with the connecting pipe 54, the second limiting rods 72 at the front side are in contact fit with the second fixing frame 61, the second limiting rods 72 at the front side are wound with third springs 73, two ends of the third springs 73 are respectively connected with the first fixing blocks 71 and the second limiting rods 72, the second limiting rods 72 at the rear side are provided with fourth springs 74, and two ends of the fourth springs 74 are respectively connected with the first fixing blocks 71 and the second limiting rods 72.
When one engages the connection protection frame 53 with the connection pipe 54, one pulls the second stopper rod 72 at the rear side outward, the fourth spring 74 is compressed, when the connection pipe 54 is fitted over the connection protection frame 53, one releases the second stopper 72 at the rear side, and, due to the fourth spring 74, so as to drive the second limiting rod 72 at the rear side to move inwards, the second limiting rod 72 at the rear side is engaged with the connecting pipe 54, so that the connecting pipe 54 and the connecting protection frame 53 are more fixed, when the connection protection frame 53 moves forward, a person pulls the second stopper rod 72 at the front side outward, the third spring 73 is compressed, and when the connection protection frame 53 corresponds to the first fixing frame 55 at this time, the person releases the second stopper rod 72, and since the third spring 73 is restored, the second limiting rod 72 at the front side is driven to move inwardly, so that the connection protection frame 53 is clamped to the first fixing frame 55, thereby completing the connection pipe 54.
Example 2
On the basis of embodiment 1, as shown in fig. 9 to 13, the present invention further comprises a locking mechanism 8, the locking mechanism 8 comprises a fifth fixing rod 81, a sixth fixing rod 82, a third limiting rod 83, a fifth spring 84 and a sixth spring 85, the first fixing frame 55 is slidably provided with the fifth fixing rod 81 at the upper, lower, left and right sides, the number of the fifth fixing rods 81 is four, the second fixing frame 61 is slidably provided with the sixth fixing rod 82 at the upper, lower, left and right sides, the second fixing frame 61 is symmetrically slidably provided with the third limiting rod 83 at the upper, lower, left and right sides, the number of the third limiting rods 83 is four, the third limiting rod 83 at the rear side is in contact fit with the sixth fixing rod 82, the sixth fixing rod 82 at the front side is in contact fit with the fifth fixing rod 81, the sixth fixing rod 82 at the rear side is wound with the fifth spring 84, two ends of the fifth spring 84 are respectively connected with the second fixing frame 61 and the third limiting rod 83, a sixth spring 85 is wound on the front sixth fixing rod 82, and both ends of the sixth spring 85 are respectively connected with the second fixing frame 61 and the third limiting rod 83.
When a person puts the second fixing frame 61 on the connecting pipe 54, the second fixing frame 61 moves forward to drive the sixth fixing rod 82 to move forward, the sixth fixing rod 82 contacts with the third limiting rod 83 at the rear side to drive the third limiting rod 83 at the rear side to move upward, the fifth spring 84 is compressed to release the second limiting rod 72 at the rear side, so that the second limiting rod 72 automatically clamps the connecting pipe 54, meanwhile, when the connecting protection frame 53 corresponds to the first fixing frame 55, the fifth fixing rod 81 contacts with the third limiting rod 83 at the front side to drive the third limiting rod 83 to move upward, the sixth spring 85 is compressed to automatically release the second limiting rod 72 at the front side, so that the second limiting rod 72 is clamped with the first fixing frame 55, thereby saving manual operation, when the person needs to replace the second fixing frame 61 and the first fixing frame 55, the person pushes the second fixing frame 61 and the first fixing frame 55 backward, thereby drive the fixed frame 61 of second backward movement and drive sixth dead lever 82 backward movement, sixth dead lever 82 and fifth dead lever 81 all do not all with the contact of third gag lever post 83, because fifth spring 84 and sixth spring 85 all reset, so can drive third gag lever post 83 downstream and reset, and then block second gag lever post 72, people can take out the fixed frame 61 of second and first fixed frame 55 then.
Still including rising mechanism 9, rising mechanism 9 is including second cylinder 91, the fixed frame 92 of third, first solid fixed ring 93 and seventh spring 94, 1 internally mounted of base has second cylinder 91, the telescopic link of second cylinder 91 is connected with smooth frame 2, the fixed frame 92 of third all is equipped with to the 1 upper portion left and right sides of base, two fixed frames 92 of third all with second dead lever 51 sliding type connection, ten second dead lever 51 lower parts all are equipped with first solid fixed ring 93, all around having seventh spring 94 on ten second dead levers 51, the both ends of seventh spring 94 are connected with first solid fixed ring 93 and second dead lever 51 respectively.
People can start second cylinder 91, the flexible smooth frame 2 up-and-down motion that drives of second cylinder 91 telescopic link, when second cylinder 91 telescopic link extension, second cylinder 91 telescopic link drives smooth frame 2 upward movement, and then drive second dead lever 51 upward movement, seventh spring 94 is tensile, when second cylinder 91 telescopic link shortens, second cylinder 91 telescopic link drives smooth frame 2 downward movement, and then drive second dead lever 51 downward movement, seventh spring 94 resets, seventh spring 94 plays the cushioning effect, and then can adjust the distance of smooth frame 2 according to the height distance of connecting pipe 54 on the wall, and then make things convenient for people to connect the connecting pipe 54 of co-altitude.
The automatic transmission mechanism further comprises a moving mechanism 10, the moving mechanism 10 comprises a two-way motor 101, second fixing rings 102, a first gear 103, a first rotating shaft 104, second gears 105, a second rotating shaft 106, a third gear 107 and crawler wheels 108, the two-way motor 101 is installed at the bottom of the front side of the base 1, the second fixing rings 102 are symmetrically arranged on the front side and the rear side of the bottom of the base 1, the number of the second fixing rings 102 is four, the two second fixing rings 102 on the front side are rotatably connected with an output shaft of the two-way motor 101, the first gears 103 are respectively arranged on output shafts on the left side and the right side of the two-way motor 101, the first rotating shaft 104 is rotatably arranged on the left side and the right side of the inside of the base 1, the second gears 105 are respectively arranged on the left end and the right end of the first rotating shaft 104, the number of the second gears 105 on the front side is four, the two second gears 105 on the front side are respectively meshed with the first gear 103, the second rotating shaft 106 is rotatably arranged between the two second fixing rings 102 on the rear side, third gears 107 are arranged at the left end and the right end of the second rotating shaft 106, the third gears 107 are meshed with the second gears 105, and crawler wheels 108 are connected between output shafts on the left side and the right side of the bidirectional motor 101 and the second rotating shaft 106.
People can start two-way motor 101, two-way motor 101 output shaft rotates and drives first gear 103 and rotate, because first gear 103 and the meshing of second gear 105, so can drive and rotate first pivot 104 and rotate, because second gear 105 meshes with third gear 107 again, so can drive third gear 107 and rotate, thereby drive second pivot 106 and rotate, and then drive the transmission of athey wheel 108, then drive the jointing equipment motion, make things convenient for people to use jointing equipment, when people need stop the use, people close two-way motor 101 can.
Although embodiments of the present invention have been shown and described, it would be appreciated by those skilled in the art that changes may be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the claims and their equivalents.

Claims (8)

1. The utility model provides a unsettled jointing equipment of sewage drain pipe which characterized in that includes:
the device comprises a base (1) and a sliding frame (2), wherein the sliding frame (2) is installed at the top of the base (1);
the middle part of the sliding frame (2) is uniformly provided with the first fixed rods (3), and the number of the first fixed rods (3) is thirteen;
the rotating rings (4) are rotatably arranged on the thirteen first fixing rods (3);
the calibration mechanism (5) is arranged on the sliding frame (2);
the fixing mechanism (6) is arranged on the calibration mechanism (5);
the connecting mechanism (7) is arranged on the calibration mechanism (5).
2. Sewage drain pipe aerial connection device according to claim 1, characterized in that the calibration mechanism (5) comprises:
the two sides of the sliding frame (2) are uniformly provided with the second fixing rods (51), and the number of the second fixing rods (51) is ten;
the first air cylinder (52) is installed between the upper parts of the ten second fixing rods (51);
the connecting pipe (54) is sleeved on the telescopic rod of the first cylinder (52);
the connecting protection frame (53) is detachably arranged on the connecting pipe (54), and the connecting protection frame (53) is in sliding connection with the telescopic rod of the first cylinder (52);
the first fixing frame (55) is detachably arranged on the connecting pipe (54);
the telescopic rods of the first cylinder (52) are symmetrically provided with third fixing rods (56);
the first sliding plate (58) is arranged between the two third fixing rods (56) in a sliding manner, and the first fixing frame (55) and the first sliding plate (58) are both connected with the connecting protection frame (53) in a sliding manner;
the first springs (57) are wound on the two third fixing rods (56), and two ends of each first spring (57) are connected with the third fixing rods (56) and the first sliding plate (58) respectively.
3. A sewage drain pipe suspended connection apparatus according to claim 2, characterised in that the securing mechanism (6) comprises:
a second fixed frame (61), wherein the second fixed frame (61) is installed on the connecting pipe (54);
the fourth fixing rods (62) are arranged on two sides of the second fixing frame (61) and the first fixing frame (55), and the number of the fourth fixing rods (62) is four;
the first limiting rods (63) and the four fourth fixing rods (62) are respectively provided with the first limiting rods (63) in a sliding manner;
the number of the first limiting rods (63) is four, the second springs (64) are wound on the four first limiting rods (63), and two ends of each second spring (64) are connected with the first limiting rods (63) and the fourth fixing rods (62) respectively.
4. A sewage drain pipe aerial connection device according to claim 3, characterised in that the connection mechanism (7) comprises:
the upper side and the lower side of the connecting protection frame (53) are symmetrically provided with the first fixed blocks (71), and the number of the first fixed blocks (71) is eight;
the middle parts of the second limiting rods (72) and the eight first fixing blocks (71) are respectively provided with the second limiting rods (72) in a sliding manner; the number of the second limiting rods (72) is eight, the second limiting rods (72) are connected with the connecting protection frame (53) in a sliding mode, the second limiting rods (72) are in contact fit with the connecting pipe (54), and the second limiting rods (72) are in contact fit with the second fixing frame (61);
the third spring (73) is wound on the second limiting rod (72), and two ends of the third spring (73) are respectively connected with the first fixing block (71) and the second limiting rod (72);
the fourth spring (74) is arranged on the second limiting rod (72), and two ends of the fourth spring (74) are connected with the first fixing block (71) and the second limiting rod (72) respectively.
5. The sewage drain pipe suspended connection device according to claim 4, further comprising a clamping mechanism (8), wherein the clamping mechanism (8) comprises:
the upper side and the lower side of the first fixed frame (55) are both provided with fifth fixed rods (81) in a sliding manner, and the number of the fifth fixed rods (81) is four;
the upper side and the lower side of the second fixed frame (61) are both provided with a sixth fixed rod (82) in a sliding way;
the upper side and the lower side of the second fixing frame (61) are symmetrically provided with three limiting rods (83) in a sliding manner, the number of the third limiting rods (83) is four, the third limiting rods (83) are in contact fit with a sixth fixing rod (82), and the sixth fixing rod (82) is in contact fit with a fifth fixing rod (81);
the fifth spring (84) is wound on the sixth fixing rod (82), and two ends of the fifth spring (84) are respectively connected with the second fixing frame (61) and the third limiting rod (83);
and the sixth spring (85) is wound on the sixth fixing rod (82), and two ends of the sixth spring (85) are respectively connected with the second fixing frame (61) and the third limiting rod (83).
6. The sewage drain pipe suspended connecting device according to claim 5, further comprising a lifting mechanism (9), wherein the lifting mechanism (9) comprises:
the second cylinder (91) is installed in the base (1), and a telescopic rod of the second cylinder (91) is connected with the sliding frame (2);
the two sides of the upper part of the base (1) are respectively provided with a third fixed frame (92), and the two third fixed frames (92) are both connected with the second fixed rod (51) in a sliding manner;
the lower parts of the first fixing rings (93) and the ten second fixing rods (51) are provided with the first fixing rings (93);
the seventh springs (94) are wound on the ten second fixing rods (51), and two ends of each seventh spring (94) are respectively connected with the first fixing ring (93) and the second fixing rods (51).
7. The sewage drain pipe suspended connecting device according to claim 6, further comprising a moving mechanism (10), wherein the moving mechanism (10) comprises:
the bidirectional motor (101) is installed at the bottom of the base (1);
the two sides of the bottom of the base (1) are symmetrically provided with the second fixing rings (102), the number of the second fixing rings (102) is four, and the two second fixing rings (102) are rotatably connected with an output shaft of the bidirectional motor (101);
the output shafts on two sides of the bidirectional motor (101) are provided with the first gear (103);
the first rotating shaft (104) is rotatably arranged on two sides in the base (1);
the two ends of the first rotating shaft (104) are provided with the second gears (105), the number of the second gears (105) is four, and the two second gears (105) are meshed with the first gear (103);
the second rotating shaft (106) is rotatably arranged between the two second fixing rings (102);
the third gear (107) is arranged at both ends of the second rotating shaft (106);
and the third gear (107) is meshed with the second gear (105), and the crawler wheels (108) are connected between the output shafts on the two sides of the bidirectional motor (101) and the second rotating shaft (106).
8. The sewage drain pipe suspended connecting device is characterized in that a push block is arranged at the top of the first fixing frame (55), and the push block is in contact fit with the first sliding plate (58).
CN202111382383.XA 2021-11-22 2021-11-22 Unsettled jointing equipment of sewage drain pipe Pending CN114161106A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111382383.XA CN114161106A (en) 2021-11-22 2021-11-22 Unsettled jointing equipment of sewage drain pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111382383.XA CN114161106A (en) 2021-11-22 2021-11-22 Unsettled jointing equipment of sewage drain pipe

Publications (1)

Publication Number Publication Date
CN114161106A true CN114161106A (en) 2022-03-11

Family

ID=80479825

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111382383.XA Pending CN114161106A (en) 2021-11-22 2021-11-22 Unsettled jointing equipment of sewage drain pipe

Country Status (1)

Country Link
CN (1) CN114161106A (en)

Citations (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0473541A (en) * 1990-07-11 1992-03-09 Matsushita Seiko Co Ltd Ventilation fan duct connector device
DE9307825U1 (en) * 1993-05-24 1994-04-28 Wang Shiow Duan Device for connecting pipes
US20040000788A1 (en) * 2002-06-27 2004-01-01 Gerald Cronley Quick-connecting coupler for hoses, pipes and faucets
US20100201116A1 (en) * 2009-02-06 2010-08-12 Kipker Eric E Flexible duct seal
US20110259441A1 (en) * 2008-11-27 2011-10-27 Caterpillar Work Tools B.V. Extendable Pressurized Fluid Coupler
US20130031775A1 (en) * 2011-08-03 2013-02-07 Omar Cueto Apparatus For Connecting A Fuel Injector To A Test Machine
GB202014718D0 (en) * 2020-09-18 2020-11-04 Edwards Ltd Clamp assembly
CN212044399U (en) * 2020-04-16 2020-12-01 中建四局安装工程有限公司 Quick mounting structure for sewer line connection
CN112228641A (en) * 2020-11-04 2021-01-15 魏志峰 Drainage pipeline connecting component capable of being positioned quickly and accurately
CN112268149A (en) * 2020-10-26 2021-01-26 张燕 Pipeline connecting device for sewage treatment with prevent stifled function
JP6831146B1 (en) * 2019-08-29 2021-02-17 東莞理工学院 Piping automatic connection tightening device and tubular member automatic connection tightening device
CN113028182A (en) * 2021-03-04 2021-06-25 吉林建筑大学 Pipeline connecting structure for basin pollution control and connecting method thereof
CN213778119U (en) * 2020-12-22 2021-07-23 汇鑫环境科技有限公司 Pipeline docking mechanism for installation of central air conditioner
CN113251165A (en) * 2021-06-11 2021-08-13 胜利油田海胜石油机械制造有限公司 Well head gate valve with automatic mechanism of changing of sleeve pipe is pressed in area
CN113330169A (en) * 2019-01-09 2021-08-31 菲择克林有限公司 Drain connector system
CN214425334U (en) * 2020-12-21 2021-10-19 西安裕雅隆贸易有限公司 Y type pipe connection head fixed establishment
CN214425335U (en) * 2020-12-22 2021-10-19 粤海滚塑科技(中山)有限公司 Pipe fitting connecting mechanism with good fastening effect
CN113650305A (en) * 2021-07-21 2021-11-16 江西林基环保新科技有限公司 Pipe orifice molding device for mounting drain pipe

Patent Citations (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0473541A (en) * 1990-07-11 1992-03-09 Matsushita Seiko Co Ltd Ventilation fan duct connector device
DE9307825U1 (en) * 1993-05-24 1994-04-28 Wang Shiow Duan Device for connecting pipes
US20040000788A1 (en) * 2002-06-27 2004-01-01 Gerald Cronley Quick-connecting coupler for hoses, pipes and faucets
US20110259441A1 (en) * 2008-11-27 2011-10-27 Caterpillar Work Tools B.V. Extendable Pressurized Fluid Coupler
US20100201116A1 (en) * 2009-02-06 2010-08-12 Kipker Eric E Flexible duct seal
US20130031775A1 (en) * 2011-08-03 2013-02-07 Omar Cueto Apparatus For Connecting A Fuel Injector To A Test Machine
CN113330169A (en) * 2019-01-09 2021-08-31 菲择克林有限公司 Drain connector system
JP6831146B1 (en) * 2019-08-29 2021-02-17 東莞理工学院 Piping automatic connection tightening device and tubular member automatic connection tightening device
CN212044399U (en) * 2020-04-16 2020-12-01 中建四局安装工程有限公司 Quick mounting structure for sewer line connection
GB202014718D0 (en) * 2020-09-18 2020-11-04 Edwards Ltd Clamp assembly
CN112268149A (en) * 2020-10-26 2021-01-26 张燕 Pipeline connecting device for sewage treatment with prevent stifled function
CN112228641A (en) * 2020-11-04 2021-01-15 魏志峰 Drainage pipeline connecting component capable of being positioned quickly and accurately
CN214425334U (en) * 2020-12-21 2021-10-19 西安裕雅隆贸易有限公司 Y type pipe connection head fixed establishment
CN213778119U (en) * 2020-12-22 2021-07-23 汇鑫环境科技有限公司 Pipeline docking mechanism for installation of central air conditioner
CN214425335U (en) * 2020-12-22 2021-10-19 粤海滚塑科技(中山)有限公司 Pipe fitting connecting mechanism with good fastening effect
CN113028182A (en) * 2021-03-04 2021-06-25 吉林建筑大学 Pipeline connecting structure for basin pollution control and connecting method thereof
CN113251165A (en) * 2021-06-11 2021-08-13 胜利油田海胜石油机械制造有限公司 Well head gate valve with automatic mechanism of changing of sleeve pipe is pressed in area
CN113650305A (en) * 2021-07-21 2021-11-16 江西林基环保新科技有限公司 Pipe orifice molding device for mounting drain pipe

Similar Documents

Publication Publication Date Title
CN113047639A (en) Installation and construction method for reinforced light steel keel partition wall
CN114161106A (en) Unsettled jointing equipment of sewage drain pipe
CN105565064A (en) Three-crawler-type intelligent flexible automatic tractor for large-size flexible pipe
CN211581008U (en) Be used for pipeline for irrigation
CN112809337B (en) Movable type assists pipeline installation device
CN215060432U (en) Trenchless pipeline repairing system
CN216076204U (en) Outer wall construction platform for civil engineering
CN207527133U (en) Municipal pipeline embedded underground device
CN215522352U (en) Drainage pipe of hydraulic engineering antiseep
CN214405161U (en) Ultraviolet light repairing air bag device for pipeline
CN214271859U (en) A quick cleaning device of step for municipal works
CN212984111U (en) Water supply and drainage pipeline convenient to dredge
CN113202067A (en) Water-blocking steel plug for water intake of hydraulic tunnel and use method thereof
CN209960049U (en) Steel band pipe convenient to link up
CN217272580U (en) Anti-seepage device for exhaust valve well of long-distance water delivery pipeline
CN219413724U (en) Municipal pipeline auxiliary laying device
CN214360031U (en) Movable type assists pipeline installation device
CN220434763U (en) Tunnel auxiliary tunnel ditch rapid construction integrated die carrier
CN214783053U (en) Drainage device for plastic track
CN217168792U (en) Perforating device of HDPE double-walled bellows
CN215879117U (en) A light belt cleaning device that makes a video recording for pipeline desilting robot
CN211288988U (en) Pipe conveying device for municipal water supply and drainage
CN213745299U (en) Closed ring reinforced plastic structure wall pipe
CN213452350U (en) Hinge type hanging pipe clamp for building water supply and drainage
CN217379788U (en) Concrete spreader telescoping device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination