CN213778119U - A pipeline docking mechanism for central air-conditioning installation - Google Patents

A pipeline docking mechanism for central air-conditioning installation Download PDF

Info

Publication number
CN213778119U
CN213778119U CN202023100404.8U CN202023100404U CN213778119U CN 213778119 U CN213778119 U CN 213778119U CN 202023100404 U CN202023100404 U CN 202023100404U CN 213778119 U CN213778119 U CN 213778119U
Authority
CN
China
Prior art keywords
fixedly installed
fixing plate
connecting mechanism
central air
fixing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202023100404.8U
Other languages
Chinese (zh)
Inventor
郜银锋
李朝锋
申响亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Qinhexin Energy Technology Co.,Ltd.
Original Assignee
Huixin Environmental Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huixin Environmental Technology Co Ltd filed Critical Huixin Environmental Technology Co Ltd
Priority to CN202023100404.8U priority Critical patent/CN213778119U/en
Application granted granted Critical
Publication of CN213778119U publication Critical patent/CN213778119U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Air Filters, Heat-Exchange Apparatuses, And Housings Of Air-Conditioning Units (AREA)

Abstract

本实用新型属于管道对接领域,具体为一种中央空调安装用管道对接机构,包括有通风管道、连接机构,所述通风管道的一端固定安装有连接环,所述连接机构的侧面固定安装有侧支架,所述侧支架的顶部螺纹套接有调节螺栓,所述调节螺栓的底端活动连接有固定板,所述固定板的两端固定安装有卡位板。通过设置一个连接机构在两个通风管道连接端之间,通过连接机构侧面的侧支架将调节螺栓和固定板的位置限定住,并且可以通过调节螺栓的旋转将固定板的位置向下按压,直至固定板顶部的卡位板卡接在连接环的中部,完成定位,再利用固定螺栓将固定板与连接环固定起来,即可将结构之间的连接完全固定住,提高了结构的固定牢固性。

Figure 202023100404

The utility model belongs to the field of pipeline docking, in particular to a pipeline docking mechanism for central air conditioning installation, comprising a ventilation duct and a connecting mechanism, one end of the ventilation duct is fixedly installed with a connecting ring, and a side surface of the connecting mechanism is fixedly installed A bracket, the top of the side bracket is threadedly sleeved with an adjustment bolt, the bottom end of the adjustment bolt is movably connected with a fixing plate, and the two ends of the fixing plate are fixedly installed with a clamping plate. By arranging a connecting mechanism between the connecting ends of the two ventilation ducts, the position of the adjusting bolt and the fixing plate is limited by the side brackets on the side of the connecting mechanism, and the position of the fixing plate can be pressed down by the rotation of the adjusting bolt until The clamping plate on the top of the fixing plate is clamped in the middle of the connecting ring to complete the positioning, and then the fixing plate and the connecting ring are fixed with the fixing bolts, so that the connection between the structures can be completely fixed, and the fixing firmness of the structure can be improved. .

Figure 202023100404

Description

Pipeline docking mechanism for installation of central air conditioner
Technical Field
The utility model relates to a pipeline butt joint field especially relates to a pipeline docking mechanism is used in central air conditioning installation.
Background
The central air conditioning system is composed of one or more cold and heat source systems and a plurality of air conditioning systems, and the system is different from the traditional refrigerant type air conditioner and intensively processes air to meet the comfort requirement. The principle of liquid gasification refrigeration is adopted to provide the required cold energy for the air conditioning system so as to offset the heat load of the indoor environment; the heating system provides the air conditioning system with the required heat to offset the indoor environment cooling and heating load.
When the central air conditioner is installed, the wind power transmission pipelines of the central air conditioner need to be butted, the existing butting mechanisms are all in threaded sleeve joint, although the butting is simple, the situation of air leakage and water leakage is easy to occur after the butting is usually, the connection is not stable enough, and the existing pipelines are not provided with a filtering function, so that dust contained in the wind power of the device is discharged indoors along with the pipelines, and the cleanliness of the environment is influenced.
In order to solve the above problems, the present application provides a pipe docking mechanism for installing a central air conditioner.
SUMMERY OF THE UTILITY MODEL
Objects of the invention
For solving the technical problem who exists among the background art, the utility model provides a pipeline docking mechanism is used in central air conditioning installation has to connect firmly, filters the characteristics that remove dust.
(II) technical scheme
For solving the technical problem, the utility model provides a pipeline docking mechanism is used in central air conditioning installation, including air pipe, coupling mechanism, air pipe's one end fixed mounting has the go-between, coupling mechanism's side fixed mounting has the collateral branch frame, adjusting bolt has been cup jointed to the top screw thread of collateral branch frame, adjusting bolt's bottom swing joint has the fixed plate, the both ends fixed mounting of fixed plate has the screens board, and the both sides screw thread of fixed plate has cup jointed fixing bolt, coupling mechanism's inside fixed mounting has the filter.
Preferably, the connecting mechanism is fixedly installed at a position between the two connecting rings, and rubber rings are fixedly sleeved at positions where two sides of the connecting mechanism are connected with the connecting rings.
Preferably, the middle part of the fixed plate is movably sleeved with a limiting rod, the bottom end of the limiting rod is fixedly installed on the outer side of the connecting mechanism, and the top of the limiting rod is fixedly provided with a reinforcing pressure spring.
Preferably, the bottom of the clamping plate is clamped in the middle of the connecting ring, and the bottom end of the fixing bolt penetrates through the fixing plate and is in threaded sleeve connection with the side face of the connecting ring.
Preferably, the number of the filter plates is two, and the two filter plates are respectively and symmetrically arranged on the inner side of the connecting mechanism.
The above technical scheme of the utility model has following profitable technological effect:
1. through setting up a coupling mechanism between two air pipe link, the position of adjusting bolt and fixed plate is injectd to the collateral branch frame through the coupling mechanism side to can press the position of fixed plate downwards through adjusting bolt's rotation, the screens board joint at the fixed plate top is at the middle part of go-between, accomplishes the location, recycle fixing bolt and fix fixed plate and go-between, can fix the connection between the structure completely, improved the fixed fastness of structure.
2. Two-layer filter is arranged in the connecting mechanism, so that wind power in the pipeline is used for filtering air by the filter when being transmitted, dust in the pipeline is filtered, the dust is prevented from entering the room, the cleanliness of the indoor air is influenced, the reliability of the device is improved, and when the filtering effect of the filter is damaged, only a new connecting mechanism needs to be replaced.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is a schematic view of the connection mechanism of the present invention.
Reference numerals:
1. a ventilation duct; 2. a connecting ring; 3. a connecting mechanism; 4. a side bracket; 5. adjusting the bolt; 6. a fixing plate; 7. a limiting rod; 8. a clamping plate; 9. fixing the bolt; 10. a filter plate.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention will be described in detail with reference to the accompanying drawings. It should be understood that the description is intended to be illustrative only and is not intended to limit the scope of the present invention. Moreover, in the following description, descriptions of well-known structures and techniques are omitted so as to not unnecessarily obscure the concepts of the present invention.
As shown in fig. 1-2, a pipeline docking mechanism for installing a central air conditioner is provided, which comprises an air duct 1 and a connecting mechanism 3, wherein a connecting ring 2 is fixedly installed at one end of the air duct 1, a side bracket 4 is fixedly installed at the side surface of the connecting mechanism 3, an adjusting bolt 5 is sleeved on the top thread of the side bracket 4, a fixing plate 6 is movably connected to the bottom end of the adjusting bolt 5, clamping plates 8 are fixedly installed at the two ends of the fixing plate 6, fixing bolts 9 are sleeved on the threads at the two sides of the fixing plate 6, and a filter plate 10 is fixedly installed inside the connecting mechanism 3.
As shown in fig. 2, the connecting mechanism 3 is fixedly installed at a position between the two connecting rings 2, the rubber rings are fixedly sleeved at positions where the two sides of the connecting mechanism 3 are connected with the connecting rings 2, and the rubber rings are arranged at the two sides of the connecting mechanism 3, so that the connection between the connecting mechanism 3 and the connecting rings 2 is tighter, the situations of air leakage and water leakage are avoided, and the reliability of the device is improved.
In this embodiment, gag lever post 7 has been cup jointed in the middle part activity of fixed plate 6, the bottom fixed mounting of gag lever post 7 is in coupling mechanism 3's the outside, and the top fixed mounting of gag lever post 7 has the reinforcement pressure spring, through set up gag lever post 7 at the middle part of fixed plate 6, and set up the bottom of gag lever post 7 in coupling mechanism 3's the outside, thereby it is spacing to utilize gag lever post 7 to carry out, make the position of fixed plate 6 firm more, set up the reinforcement pressure spring simultaneously at the top of gag lever post 7, thereby at the fastness that promotes fixed plate 6 positions, the practicality of device has been improved.
It should be noted that, the bottom joint of screens board 8 is at the middle part of go-between 2, fixing bolt 9's bottom runs through fixed plate 6 and cup joints with the side screw thread of go-between 2, through the middle part with the joint of screens board 8 at go-between 2, make and utilize screens board 8 to accomplish the location and install in advance, the portability of device installation has been promoted, run through the side threaded connection of fixed plate 6 with go-between 2 with fixing bolt 9's bottom simultaneously, can install the structure completely, the steadiness of structure has been improved.
It should be understood that, the quantity of filter 10 is two, and two filters 10 are respectively the symmetry and install in coupling mechanism 3's inboard, through setting up two filters 10 for when filtering, utilize double-deck filter 10 to promote the filter effect, make the device use more comfortable, avoided external dust to enter into indoorly, influence indoor cleanliness factor.
The utility model discloses a theory of operation and use flow: at first, place coupling mechanism 3 between two go-between 2, then utilize two go-between 2 to grasp coupling mechanism 3's position, rotatory adjusting bolt 5 pushes down the position of fixed plate 6 simultaneously to make the screens board 8 joint at fixed plate 6 both ends at the middle part of go-between 2, thereby make the position of go-between 2 tentatively fixed, finally, through rotatory fixing bolt 9 with fixed plate 6 completely fixed with the position of go-between 2, can.
It is to be understood that the above-described embodiments of the present invention are merely illustrative of or explaining the principles of the invention and are not to be construed as limiting the invention. Therefore, any modification, equivalent replacement, improvement and the like made without departing from the spirit and scope of the present invention should be included in the protection scope of the present invention. Further, it is intended that the appended claims cover all such variations and modifications as fall within the scope and boundaries of the appended claims or the equivalents of such scope and boundaries.

Claims (5)

1.一种中央空调安装用管道对接机构,包括有通风管道(1)、连接机构(3),其特征在于,所述通风管道(1)的一端固定安装有连接环(2),所述连接机构(3)的侧面固定安装有侧支架(4),所述侧支架(4)的顶部螺纹套接有调节螺栓(5),所述调节螺栓(5)的底端活动连接有固定板(6),所述固定板(6)的两端固定安装有卡位板(8),且固定板(6)的两侧螺纹套接有固定螺栓(9),所述连接机构(3)的内部固定安装有过滤板(10)。1. A duct docking mechanism for central air-conditioning installation, comprising a ventilation duct (1) and a connecting mechanism (3), characterized in that a connecting ring (2) is fixedly installed at one end of the ventilation duct (1), and the A side bracket (4) is fixedly installed on the side of the connecting mechanism (3), an adjustment bolt (5) is threadedly sleeved on the top of the side bracket (4), and a fixing plate is movably connected to the bottom end of the adjustment bolt (5). (6), the two ends of the fixing plate (6) are fixedly installed with the clamping plate (8), and the two sides of the fixing plate (6) are threadedly sleeved with fixing bolts (9), and the connecting mechanism (3) A filter plate (10) is fixedly installed inside. 2.根据权利要求1所述的一种中央空调安装用管道对接机构,其特征在于,所述连接机构(3)固定安装在两个所述连接环(2)之间的位置,且连接机构(3)的两侧与连接环(2)连接的位置固定套接有橡胶圈。2 . The pipe docking mechanism for central air conditioner installation according to claim 1 , wherein the connecting mechanism ( 3 ) is fixedly installed at a position between the two connecting rings ( 2 ), and the connecting mechanism The position where both sides of (3) are connected with the connecting ring (2) is fixedly sleeved with a rubber ring. 3.根据权利要求1所述的一种中央空调安装用管道对接机构,其特征在于,所述固定板(6)的中部活动套接有限位杆(7),所述限位杆(7)的底端固定安装在所述连接机构(3)的外侧,且限位杆(7)的顶部固定安装有加固压簧。3. A pipeline docking mechanism for central air-conditioning installation according to claim 1, characterized in that a limit rod (7) is movably sleeved in the middle of the fixing plate (6), and the limit rod (7) The bottom end of the connecting mechanism (3) is fixedly installed on the outside of the connecting mechanism (3), and the top of the limiting rod (7) is fixedly installed with a reinforced compression spring. 4.根据权利要求1所述的一种中央空调安装用管道对接机构,其特征在于,所述卡位板(8)的底部卡接在所述连接环(2)的中部,所述固定螺栓(9)的底端贯穿固定板(6)并与连接环(2)的侧面螺纹套接。4. A pipeline docking mechanism for central air-conditioning installation according to claim 1, characterized in that the bottom of the clamping plate (8) is clamped in the middle of the connecting ring (2), and the fixing bolts The bottom end of (9) penetrates the fixing plate (6) and is threadedly sleeved with the side surface of the connecting ring (2). 5.根据权利要求1所述的一种中央空调安装用管道对接机构,其特征在于,所述过滤板(10)的数量为两个,两个所述过滤板(10)分别对称安装在所述连接机构(3)的内侧。5 . The pipe docking mechanism for central air conditioner installation according to claim 1 , wherein the number of the filter plates ( 10 ) is two, and the two filter plates ( 10 ) are respectively symmetrically installed on the the inner side of the connecting mechanism (3).
CN202023100404.8U 2020-12-22 2020-12-22 A pipeline docking mechanism for central air-conditioning installation Active CN213778119U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023100404.8U CN213778119U (en) 2020-12-22 2020-12-22 A pipeline docking mechanism for central air-conditioning installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023100404.8U CN213778119U (en) 2020-12-22 2020-12-22 A pipeline docking mechanism for central air-conditioning installation

Publications (1)

Publication Number Publication Date
CN213778119U true CN213778119U (en) 2021-07-23

Family

ID=76899785

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023100404.8U Active CN213778119U (en) 2020-12-22 2020-12-22 A pipeline docking mechanism for central air-conditioning installation

Country Status (1)

Country Link
CN (1) CN213778119U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114161106A (en) * 2021-11-22 2022-03-11 陈敏睿 Unsettled jointing equipment of sewage drain pipe
CN115126943A (en) * 2022-07-06 2022-09-30 无锡市公用水务投资有限公司 Pipeline connector convenient to adjust and use for urban sewage discharge

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114161106A (en) * 2021-11-22 2022-03-11 陈敏睿 Unsettled jointing equipment of sewage drain pipe
CN114161106B (en) * 2021-11-22 2024-06-04 陈敏睿 Suspended connection equipment for sewage drain pipe
CN115126943A (en) * 2022-07-06 2022-09-30 无锡市公用水务投资有限公司 Pipeline connector convenient to adjust and use for urban sewage discharge
CN115126943B (en) * 2022-07-06 2023-12-01 无锡市公用水务投资有限公司 Urban sewage discharges with pipe connector who is convenient for adjust use

Similar Documents

Publication Publication Date Title
CN213778119U (en) A pipeline docking mechanism for central air-conditioning installation
CN110530173B (en) Heat exchanger
CN204830249U (en) Air conditioner system
CN111156573A (en) Indoor electric heating system with dust removal function
CN104864574B (en) A kind of central air conditioner system
CN210106818U (en) Air conditioner pipe assembly
CN213900238U (en) An easy-to-install central air-conditioning ventilation duct
CN222993100U (en) Energy-saving ventilation device for building engineering design
CN214172614U (en) Differential pressure device of air source heat pump system
CN219300972U (en) Two pipe pipeline connection structures of fan coil
CN209309668U (en) A kind of sulfur dioxide gas auxiliary cooling device
CN220566776U (en) Safe air conditioner cold pipe
CN223050179U (en) A quick disassembly and assembly air conditioning pipeline structure
CN221144497U (en) Anti-crack ventilation pipe for tunnel
CN223363987U (en) Cooling device of excitation system of hydraulic generator
CN219283583U (en) Air conditioner pipe arrangement profiling tool
CN221237964U (en) Assembled heating and ventilation pipeline for air purification
CN222086792U (en) A kind of collecting pipe capable of preventing clogging
CN217153454U (en) Pipeline connecting device for building heating and ventilation construction
CN221780872U (en) A smoke exhaust duct structure that is easy to install
CN214949599U (en) Novel warm idle call filter that leads to
CN222658077U (en) Circulating filter applied to air conditioner pipeline system
CN217567234U (en) Simple to operate's fire control pipeline connector
CN223120974U (en) Assembled silent ventilation duct
CN219954651U (en) A heating and ventilation duct regulating device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20250524

Address after: 725500 Group 4, Jiangjiaping Village, Laoxian Town, Pingli County, Ankang City, Shaanxi Province

Patentee after: Luo Wen

Country or region after: China

Patentee after: Luo Jiao

Address before: No.28 Jinshui Road, Jinshui District, Zhengzhou City, Henan Province

Patentee before: Huixin Environmental Technology Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20250822

Address after: 050000 Hebei Province, Shijiazhuang City, Yuhua District, Jianhua South Street, Zhongmei Business Building, A Building, Room 2101

Patentee after: Hebei Qinhexin Energy Technology Co.,Ltd.

Country or region after: China

Address before: 725500 Group 4, Jiangjiaping Village, Laoxian Town, Pingli County, Ankang City, Shaanxi Province

Patentee before: Luo Wen

Country or region before: China

Patentee before: Luo Jiao

TR01 Transfer of patent right