CN114150656A - Zero-slope-cutting tunnel entering method for tunnel under condition of surrounding rock breaking - Google Patents

Zero-slope-cutting tunnel entering method for tunnel under condition of surrounding rock breaking Download PDF

Info

Publication number
CN114150656A
CN114150656A CN202111359490.0A CN202111359490A CN114150656A CN 114150656 A CN114150656 A CN 114150656A CN 202111359490 A CN202111359490 A CN 202111359490A CN 114150656 A CN114150656 A CN 114150656A
Authority
CN
China
Prior art keywords
tunnel
slope
cast
pipe shed
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111359490.0A
Other languages
Chinese (zh)
Inventor
魏立恒
倪修能
许健
邹伟平
徐柯锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN202111359490.0A priority Critical patent/CN114150656A/en
Publication of CN114150656A publication Critical patent/CN114150656A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries

Abstract

The invention relates to a zero-slope-cutting tunnel entering method for a tunnel under the condition of surrounding rock crushing; the method comprises the following steps of 1, carrying out cast-in-place pile row construction outside an excavation boundary along the tunnel line direction; step 2, constructing a top beam system at the upper part of the cast-in-place pile row pile; step 3, constructing the long pipe shed; step 4, tunnel excavation, primary tunnel lining, waterproof system and secondary lining construction are carried out; and 5, performing other pavement structure constructions such as tunnel inverted arch backfilling and the like. The method adopts the construction of cast-in-place piles at two sides of the excavation boundary along the tunnel line direction; constructing an integrated crown beam along a slope toe of an upward slope above the tunnel and the top of the cast-in-place pile; and pipe shed holes are reserved along the peripheral crown beams of the tunnel, a long pipe shed is constructed, and the long pipe shed, the cast-in-place piles and the crown beams form a whole, so that the stability of the upward slope in the excavation process is ensured, the problem of difficult tunnel entry which puzzles the tunnel engineering for a long time is innovatively solved, and the zero-slope-cutting tunnel entry of the tunnel engineering is realized.

Description

Zero-slope-cutting tunnel entering method for tunnel under condition of surrounding rock breaking
Technical Field
The invention relates to the technical field of tunnel construction, in particular to a zero-slope-cutting tunnel entering method for a tunnel under a surrounding rock crushing condition.
Background
The stability control of the side slope and the heading slope is a serious difficulty in mountain tunnel construction, and the problem of difficult entry always troubles the smooth development of mountain tunnel engineering construction. The tunnel entering of the mountain tunnel is excavation construction aiming at the original stable mountain side slope body, and the excavation of the wall foot of the stable side slope inevitably influences the original stable side and upward slopes on the upper part of the tunnel. In broken country rock advances the hole work progress, because the country rock stability of excavation face top is relatively poor, easily produces the collapse, for guaranteeing that excavation face top country rock is stable, often adopt the pipe shed to carry out the reinforcement of the peripheral country rock of excavation face, nevertheless to the stability consideration of pipe shed not enough, the stratum is gone into to pipe shed one end anchor, and the tip of the end of exposing supports not enough, though the pipe shed has been under construction often appeared, still produces the adverse slope unstability in the work progress.
Disclosure of Invention
The invention aims to overcome the defects and provides a zero-slope-cutting tunnel entering method for a tunnel under a broken surrounding rock condition by using a cast-in-place pile, which has the characteristics of high construction safety and small construction disturbance.
In order to achieve the above object, the present invention is realized by:
a zero-slope-cutting tunnel entering method for a tunnel under a surrounding rock crushing condition comprises the following steps
Step 1, excavating bored concrete pile row piles outside a boundary along the tunnel line direction to construct, and ensuring the stability of broken surrounding rocks on two sides of a tunnel;
step 2, constructing a top beam system at the upper part of the cast-in-place pile row pile, and excavating boundary top beams along the cross section of the tunnel to reserve a pipe shed construction hole;
the cast-in-place piles and the crown beams are integrally constructed on two sides of the excavation boundary along the tunnel line direction, and effective support is formed for the broken surrounding rock bodies on two sides of the tunnel;
step 3, long pipe shed construction is carried out, the long pipe shed, the cast-in-place piles and the crown beams form a whole, stability of the upward slope in the excavation process is guaranteed, meanwhile, the rock mass is anchored at the rock inlet end of the long pipe shed, the exposed end of the long pipe shed is anchored into the crown beams to form a beam structure, and therefore effective support is provided for crushing the surrounding rocks of the upward slope at the upper part in the excavation process;
step 4, tunnel excavation, primary tunnel lining, waterproof system and secondary lining construction are carried out;
and 5, performing other pavement structure constructions such as tunnel inverted arch backfilling and the like.
The invention adopts the construction filling pile on both sides of the excavation boundary along the tunnel line direction; constructing an integrated crown beam along a slope toe of an upward slope above the tunnel and the top of the cast-in-place pile; the method has the advantages that pipe shed holes are reserved along the peripheral crown beams of the tunnel, the long pipe shed is constructed, the long pipe shed, the cast-in-place piles and the crown beams form a whole, stability of the upward slope in the excavation process is guaranteed, the problem of 'difficult hole entry' which puzzles the tunnel engineering for a long time is innovatively solved, zero slope cutting hole entry of the tunnel engineering is achieved, and the method has the advantages of being high in construction safety, small in construction disturbance, friendly to the environment and the like.
Drawings
FIG. 1 is a front view of the hole entry method of the present invention.
FIG. 2 is a cross-sectional view of a hole-drilling method according to the present invention.
Detailed Description
The invention is further illustrated by the following specific examples.
As shown in figures 1 and 2, the zero-cutting slope tunnel entering method for the tunnel under the condition of surrounding rock crushing comprises the steps of
Step 1, excavating bored concrete pile row piles outside a boundary along the tunnel line direction to construct, and ensuring the stability of broken surrounding rocks on two sides of a tunnel;
step 2, constructing a top beam system at the upper part of the cast-in-place pile row pile, and excavating boundary top beams along the cross section of the tunnel to reserve a pipe shed construction hole;
the cast-in-place piles and the crown beams are integrally constructed on two sides of the excavation boundary along the tunnel line direction, and effective support is formed for the broken surrounding rock bodies on two sides of the tunnel;
step 3, long pipe shed construction is carried out, the long pipe shed, the cast-in-place piles and the crown beams form a whole, stability of the upward slope in the excavation process is guaranteed, meanwhile, the rock mass is anchored at the rock inlet end of the long pipe shed, the exposed end of the long pipe shed is anchored into the crown beams to form a beam structure, and therefore effective support is provided for crushing the surrounding rocks of the upward slope at the upper part in the excavation process;
step 4, tunnel excavation, primary tunnel lining, waterproof system and secondary lining construction are carried out;
and 5, performing other pavement structure constructions such as tunnel inverted arch backfilling and the like.
The invention adopts the construction filling pile on both sides of the excavation boundary along the tunnel line direction; constructing an integrated crown beam along a slope toe of an upward slope above the tunnel and the top of the cast-in-place pile; the method has the advantages that pipe shed holes are reserved along the peripheral crown beams of the tunnel, the long pipe shed is constructed, the long pipe shed, the cast-in-place piles and the crown beams form a whole, stability of the upward slope in the excavation process is guaranteed, the problem of 'difficult hole entry' which puzzles the tunnel engineering for a long time is innovatively solved, zero slope cutting hole entry of the tunnel engineering is achieved, and the method has the advantages of being high in construction safety, small in construction disturbance, friendly to the environment and the like.

Claims (1)

1. A zero-slope-cutting tunnel entering method for a tunnel under a surrounding rock crushing condition is characterized by comprising the following steps: comprises that
Step 1, excavating bored concrete pile row piles outside a boundary along the tunnel line direction to construct, and ensuring the stability of broken surrounding rocks on two sides of a tunnel;
step 2, constructing a top beam system at the upper part of the cast-in-place pile row pile, and excavating boundary top beams along the cross section of the tunnel to reserve a pipe shed construction hole;
the cast-in-place piles and the crown beams are integrally constructed on two sides of the excavation boundary along the tunnel line direction, and effective support is formed for the broken surrounding rock bodies on two sides of the tunnel;
step 3, long pipe shed construction is carried out, the long pipe shed, the cast-in-place piles and the crown beams form a whole, stability of the upward slope in the excavation process is guaranteed, meanwhile, the rock mass is anchored at the rock inlet end of the long pipe shed, the exposed end of the long pipe shed is anchored into the crown beams to form a beam structure, and therefore effective support is provided for crushing the surrounding rocks of the upward slope at the upper part in the excavation process;
step 4, tunnel excavation, primary tunnel lining, waterproof system and secondary lining construction are carried out;
and 5, performing other pavement structure constructions such as tunnel inverted arch backfilling and the like.
CN202111359490.0A 2021-11-17 2021-11-17 Zero-slope-cutting tunnel entering method for tunnel under condition of surrounding rock breaking Pending CN114150656A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111359490.0A CN114150656A (en) 2021-11-17 2021-11-17 Zero-slope-cutting tunnel entering method for tunnel under condition of surrounding rock breaking

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111359490.0A CN114150656A (en) 2021-11-17 2021-11-17 Zero-slope-cutting tunnel entering method for tunnel under condition of surrounding rock breaking

Publications (1)

Publication Number Publication Date
CN114150656A true CN114150656A (en) 2022-03-08

Family

ID=80456347

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111359490.0A Pending CN114150656A (en) 2021-11-17 2021-11-17 Zero-slope-cutting tunnel entering method for tunnel under condition of surrounding rock breaking

Country Status (1)

Country Link
CN (1) CN114150656A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204783044U (en) * 2015-06-25 2015-11-18 贵州省公路工程集团有限公司 Coombe topography loose slope body bevel tunnel in mountain area advances supporting construction in hole
CN110374633A (en) * 2019-07-19 2019-10-25 中铁隧道集团二处有限公司 The Portal Section Construction method of Tunnel Passing loose media

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204783044U (en) * 2015-06-25 2015-11-18 贵州省公路工程集团有限公司 Coombe topography loose slope body bevel tunnel in mountain area advances supporting construction in hole
CN110374633A (en) * 2019-07-19 2019-10-25 中铁隧道集团二处有限公司 The Portal Section Construction method of Tunnel Passing loose media

Similar Documents

Publication Publication Date Title
CN108533272B (en) Exit construction method for tunnel with extremely small clear distance
CN105839643B (en) A kind of tunnel construction method of use pattern foundation pit supporting structure
CN102134998B (en) Construction method for wind-blown sand tunnel
CN108412503B (en) Bias shallow tunnel entrance construction safeguard structure and its construction method
CN101324072A (en) Construction method of pervious rib type arch beam tunnel
CN103775093A (en) Construction method for right-angle skew tunnel-entering cover arch of unsymmetrical-loaded and shallow-buried tunnel
CN110043264A (en) A kind of construction method of jacking prefabricated rectangle shaft structure pattern
CN102758458B (en) Underground continuous wall repairing method
CN109853399B (en) Large-section inclined tunnel type arch support structure for arch bridge and construction method thereof
CN110424971A (en) The method for handling jacked piles with small section landslide
CN111593734B (en) Shallow tunnel foundation pit enclosure construction method in upper-soft lower-hard stratum
KR20130058193A (en) Method for constructing largesection tunnel and largesection tunnel
CN114150656A (en) Zero-slope-cutting tunnel entering method for tunnel under condition of surrounding rock breaking
WO2023138033A1 (en) Short-bench construction method for weak surrounding rock section of super-large-section tunnel
JPH03202599A (en) Reinforced structure of twin tunnels
JP2868651B2 (en) Earth retaining method above existing underground structure
CN209799979U (en) Tunnel portal protective structure suitable for water-rich clay stratum
CN113668554A (en) Construction method of foundation pit supporting structure adjacent to building
CN113863285B (en) Inclination stopping method for high-rise building with foundation side large-diameter pile and external box type structure
CN110258587A (en) The branch mark structure and construction method of side slope
CN109268030A (en) A kind of multistage set arch structure, pipe canopy set arch structure and its construction method for tunnel portal supporting
CN108868780A (en) A kind of method of mud-rock flow stratum tunnel excavation
JP2002021491A (en) Reinforcing method for leg portion of tunnel
CN108979645A (en) The corridor tunneling of composite curve bilayer pipe gallery traffic ring and adverse construction method technique under bridge
CN212272228U (en) Dense-net type advanced support system of underground excavation tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220308