CN114077767A - BIM-based project progress monitoring system and method - Google Patents
BIM-based project progress monitoring system and method Download PDFInfo
- Publication number
- CN114077767A CN114077767A CN202111418003.3A CN202111418003A CN114077767A CN 114077767 A CN114077767 A CN 114077767A CN 202111418003 A CN202111418003 A CN 202111418003A CN 114077767 A CN114077767 A CN 114077767A
- Authority
- CN
- China
- Prior art keywords
- construction
- progress
- bim
- module
- task
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 22
- 238000012544 monitoring process Methods 0.000 title claims abstract description 16
- 238000010276 construction Methods 0.000 claims abstract description 194
- 238000010586 diagram Methods 0.000 claims abstract description 6
- 238000007726 management method Methods 0.000 claims description 11
- 230000004075 alteration Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Physics & Mathematics (AREA)
- Human Resources & Organizations (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Geometry (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- General Business, Economics & Management (AREA)
- Tourism & Hospitality (AREA)
- Computer Hardware Design (AREA)
- Marketing (AREA)
- Architecture (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Development Economics (AREA)
- Civil Engineering (AREA)
- Primary Health Care (AREA)
- Educational Administration (AREA)
- Structural Engineering (AREA)
- Computational Mathematics (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a project progress monitoring system based on BIM and a monitoring method thereof, which comprises the steps of obtaining a project prototype diagram to generate the BIM; the BIM acquires a construction plan of each time period and an actual construction project progress; judging whether the difference of the project schedules of the construction plan of each time period exceeds a threshold value or not based on the construction schedule of each time period in the BIM and the project schedule of the actual construction; if so, acquiring the deviation reason, the information of the related responsible personnel and a construction progress adjusting scheme, and redistributing and updating the construction progress; if not, continuing to execute task allocation in the construction plan and counting the completion condition of the construction task. The project progress monitoring system can intuitively embody the construction progress of the building, simultaneously realize the comparison of the actual construction progress and the construction plan, and find the reasons of the construction deviation in time, thereby realizing the high-efficiency management of the construction progress of the building.
Description
Technical Field
The invention belongs to the technical field of BIM, and particularly relates to a BIM-based engineering progress supervision system and a supervision method thereof.
Background
Most of the existing engineering progress supervision methods adopt manpower supervision and management, a large amount of labor cost is required to be invested, no rationalization standard exists for the control of the engineering progress, people in charge are difficult to be traced, and the management efficiency is low.
The Building Information Model (BIM) can visually present the whole project and the progress of the project, but the reason for slow construction progress and related persons in charge can not be traced.
Disclosure of Invention
In view of the above, the invention provides a BIM-based project progress monitoring system and a monitoring method thereof, which can realize efficient management of building construction progress
In order to achieve the above purpose, the invention is realized by the following technical scheme, which specifically comprises the following steps:
step 1: acquiring an engineering prototype diagram to generate BIM;
step 2: the BIM acquires a construction plan of each time period and an actual construction project progress;
and step 3: judging whether the difference of the project schedules of the construction plan of each time period exceeds a threshold value or not based on the construction schedule of each time period in the BIM and the project schedule of the actual construction;
if so, acquiring the deviation reason, the information of the related responsible personnel and a construction progress adjusting scheme, and redistributing and updating the construction progress;
if not, continuing to execute task allocation during construction planning and counting the completion condition of the construction task.
Further, the construction plan of each time period of the BIM is used for generating a BIM construction plan module, and the BIM construction plan module is used for acquiring the engineering progress information of the construction plan in each time period on the BIM;
and further, the project progress of the BIM actual construction is used for generating a BIM actual progress module, and the BIM actual progress module is used for acquiring the project progress information of the actual construction in each time period on the BIM.
Further, the task allocation during execution of the construction plan and the construction task completion condition are counted to generate a construction plan management module, and the construction plan management module is used for construction task allocation and construction progress statistics;
the construction task allocation module is used for allocating individual construction tasks according to the project construction plan progress or adjusting the individual construction tasks according to construction progress adjustment measures; the construction task completion condition acquisition module is used for acquiring the completion condition of the personal construction task.
Further, the BIM acquires the deviation reason, the information of the related responsible personnel and a construction progress adjusting scheme, redistributes and updates the construction progress to generate a construction progress early warning module,
the construction progress early warning module is used for outputting a numerical deviation value corresponding to each coordinate point in the difference value curve chart, and outputting a corresponding deviation reason and related responsible personnel information based on the LSSVM;
the construction progress early warning module is provided with a construction task supervision and allocation module, and the construction task supervision and allocation module is used for supervising the completion condition of an individual construction task and allocating the construction task when the individual construction task deviates from a construction plan;
furthermore, the construction task supervision and allocation module is connected with the construction task allocation module, and after the construction task is allocated, the construction task supervision and allocation module feeds back the allocation result to the construction task allocation module.
Further, the BIM construction planning module and the BIM actual progress module are based on BIM, the BIM takes 3DMX as modeling software, the coordinates of the engineering construction line are led into the CATIA, a space curve is generated, and a building three-dimensional graph corresponding to construction in each time period is drawn according to the space curve and a construction drawing.
In another aspect, the present invention provides a BIM-based project progress monitoring system, including:
an acquisition module: the construction schedule and the actual construction schedule information of the BIM are obtained;
a comparison module: the system is used for comparing the project progress information of the construction plan with the project progress information of the actual construction to generate a comparison curve graph and a difference curve graph;
adjusting the distribution module: the method is used for acquiring deviation reasons, information of related responsible personnel and a construction progress adjusting scheme, and reallocating and updating the construction progress.
Compared with the prior art, the invention has the following beneficial effects:
the invention discloses a project progress monitoring system based on BIM and a monitoring method thereof, which comprises the steps of obtaining a project prototype diagram to generate the BIM; the BIM acquires a construction plan of each time period and an actual construction project progress; judging whether the difference of the project schedules of the construction plan of each time period exceeds a threshold value or not based on the construction schedule of each time period in the BIM and the project schedule of the actual construction; if so, acquiring the deviation reason, the information of the related responsible personnel and a construction progress adjusting scheme, and redistributing and updating the construction progress; if not, continuing to execute task allocation in the construction plan and counting the completion condition of the construction task. The project progress monitoring system can intuitively embody the construction progress of the building, simultaneously realize the comparison of the actual construction progress and the construction plan, and find the reasons of the construction deviation in time, thereby realizing the high-efficiency management of the construction progress of the building.
Drawings
Fig. 1 is a structural framework diagram of a BIM-based project progress monitoring system according to an embodiment of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The invention provides a BIM-based project progress monitoring system and a monitoring method thereof, comprising
Step 1: acquiring an engineering prototype diagram to generate BIM;
step 2: the BIM acquires a construction plan of each time period and an actual construction project progress;
and step 3: judging whether the difference of the project schedules of the construction plan of each time period exceeds a threshold value or not based on the construction schedule of each time period in the BIM and the project schedule of the actual construction;
if so, acquiring the deviation reason, the information of the related responsible personnel and a construction progress adjusting scheme, and redistributing and updating the construction progress;
if not, continuing to execute task allocation during construction planning and counting the completion condition of the construction task.
Further, the construction plan of each time period of the BIM is used for generating a BIM construction plan module, and the BIM construction plan module is used for acquiring the engineering progress information of the construction plan in each time period on the BIM;
and further, the project progress of the BIM actual construction is used for generating a BIM actual progress module, and the BIM actual progress module is used for acquiring the project progress information of the actual construction in each time period on the BIM.
Further, the task allocation during execution of the construction plan and the construction task completion condition are counted to generate a construction plan management module, and the construction plan management module is used for construction task allocation and construction progress statistics;
the construction task allocation module is used for allocating individual construction tasks according to the project construction plan progress or adjusting the individual construction tasks according to construction progress adjustment measures; the construction task completion condition acquisition module is used for acquiring the completion condition of the personal construction task.
Further, the BIM acquires the deviation reason, the information of the related responsible personnel and a construction progress adjusting scheme, redistributes and updates the construction progress to generate a construction progress early warning module,
the construction progress early warning module is used for outputting a numerical deviation value corresponding to each coordinate point in the difference value curve chart, and outputting a corresponding deviation reason and related responsible personnel information based on the LSSVM;
the construction progress early warning module is provided with a construction task supervision and allocation module, and the construction task supervision and allocation module is used for supervising the completion condition of an individual construction task and allocating the construction task when the individual construction task deviates from a construction plan;
furthermore, the construction task supervision and allocation module is connected with the construction task allocation module, and after the construction task is allocated, the construction task supervision and allocation module feeds back the allocation result to the construction task allocation module.
Further, the BIM construction planning module and the BIM actual progress module are based on BIM, the BIM takes 3DMX as modeling software, the coordinates of the engineering construction line are led into the CATIA, a space curve is generated, and a building three-dimensional graph corresponding to construction in each time period is drawn according to the space curve and a construction drawing.
In another aspect, the present invention provides a BIM-based project progress monitoring system, including:
an acquisition module: the construction schedule and the actual construction schedule information of the BIM are obtained;
a comparison module: the system comprises a data processing unit, a data processing unit and a data processing unit, wherein the data processing unit is used for comparing the project progress information of a construction plan with the project progress information of actual construction to generate a comparison curve graph and a difference curve graph, and comparing the numerical deviation value corresponding to each coordinate point in the difference curve graph with a threshold value;
adjusting the distribution module: the method is used for acquiring deviation reasons, information of related responsible personnel and a construction progress adjusting scheme, and reallocating and updating the construction progress.
The supervision method of the project progress supervision system of the invention supervises and allocates the construction task by comparing the construction plan with the actual construction project progress, thereby determining responsible personnel and the reason of slow progress, realizing high-efficiency management and reducing the labor cost.
It should be noted that, in this document, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (7)
1. A BIM-based project progress monitoring system method is characterized by specifically comprising the following steps:
step 1: acquiring an engineering prototype diagram to generate BIM;
step 2: the BIM acquires a construction plan of each time period and an actual construction project progress;
and step 3: judging whether the difference of the project schedules of the construction plan of each time period exceeds a threshold value or not based on the construction schedule of each time period in the BIM and the project schedule of the actual construction;
if so, acquiring the deviation reason, the information of the related responsible personnel and a construction progress adjusting scheme, and redistributing and updating the construction progress;
if not, continuing to execute task allocation in the construction plan and counting the completion condition of the construction task.
2. The method of claim 1, wherein the BIM obtains a construction plan for each time period to generate a BIM construction plan module,
and the BIM construction plan module is used for acquiring the project progress information of the construction plan in each time period on the BIM.
3. The method of claim 1, wherein the BIM obtains the engineering progress of the actual construction in each time period to generate a BIM actual progress module, and the BIM actual progress module is used to obtain the engineering progress information of the actual construction in each time period on the BIM.
4. The method of claim 1, wherein the task assignment and the statistics of the completion of the construction tasks in executing the construction plan are performed to generate a construction plan management module,
the construction plan management module comprises a construction task distribution module and a construction task completion condition acquisition module;
the construction task allocation module is used for allocating individual construction tasks according to the project construction plan progress or adjusting the individual construction tasks according to construction progress adjustment measures;
the construction task completion condition acquisition module is used for acquiring the completion condition of the personal construction task.
5. The method of claim 1, wherein the BIM obtains deviation reasons and related responsible personnel information and a construction progress adjustment scheme, redistributes and updates construction progress to generate a construction progress pre-warning module,
the construction progress early warning module is used for outputting a numerical deviation value corresponding to each coordinate point in the difference value curve chart, and outputting a corresponding deviation reason and related responsible personnel information based on the LSSVM;
the construction progress early warning module is provided with a construction task supervision and allocation module, and the construction task supervision and allocation module is used for supervising the completion condition of an individual construction task and allocating the construction task when the individual construction task deviates from a construction plan;
the construction task supervision and allocation module is connected with the construction task allocation module, and after the construction task is allocated, the construction task supervision and allocation module feeds back the allocation result to the construction task allocation module.
6. The method according to claims 2-3, wherein the BIM construction planning module and the BIM actual progress module are based on BIM, the BIM takes 3DMX as modeling software, the coordinates of the engineering construction line are imported into CATIA, a space curve is generated, and a building three-dimensional drawing corresponding to construction in each time period is drawn according to the space curve and a construction drawing.
7. A BIM-based project progress supervision system is characterized in that,
an acquisition module: the construction schedule and the actual construction schedule information of the BIM are obtained;
a comparison module: the system is used for comparing the project progress information of the construction plan with the project progress information of the actual construction to generate a comparison curve graph and a difference curve graph;
adjusting the distribution module: the method is used for acquiring deviation reasons, information of related responsible personnel and a construction progress adjusting scheme, and reallocating and updating the construction progress.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111418003.3A CN114077767A (en) | 2021-11-26 | 2021-11-26 | BIM-based project progress monitoring system and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111418003.3A CN114077767A (en) | 2021-11-26 | 2021-11-26 | BIM-based project progress monitoring system and method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114077767A true CN114077767A (en) | 2022-02-22 |
Family
ID=80284204
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111418003.3A Pending CN114077767A (en) | 2021-11-26 | 2021-11-26 | BIM-based project progress monitoring system and method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114077767A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117350684A (en) * | 2023-12-04 | 2024-01-05 | 山东九巨龙建设集团有限公司 | Management method of steel structure engineering management system |
CN117557065A (en) * | 2024-01-05 | 2024-02-13 | 广州市嘉品电子科技有限公司 | Building engineering construction progress supervisory systems based on BIM technique |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111369226A (en) * | 2020-03-27 | 2020-07-03 | 陕西工业职业技术学院 | BIM-based project progress supervision system |
CN112329117A (en) * | 2020-11-25 | 2021-02-05 | 陕西铁路工程职业技术学院 | Building construction supervision method based on BIM |
WO2021056791A1 (en) * | 2019-09-23 | 2021-04-01 | 济南轨道交通集团有限公司 | Smart management platform for integrated construction and maintenance of rail transport engineering, and method |
-
2021
- 2021-11-26 CN CN202111418003.3A patent/CN114077767A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2021056791A1 (en) * | 2019-09-23 | 2021-04-01 | 济南轨道交通集团有限公司 | Smart management platform for integrated construction and maintenance of rail transport engineering, and method |
CN111369226A (en) * | 2020-03-27 | 2020-07-03 | 陕西工业职业技术学院 | BIM-based project progress supervision system |
CN112329117A (en) * | 2020-11-25 | 2021-02-05 | 陕西铁路工程职业技术学院 | Building construction supervision method based on BIM |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117350684A (en) * | 2023-12-04 | 2024-01-05 | 山东九巨龙建设集团有限公司 | Management method of steel structure engineering management system |
CN117557065A (en) * | 2024-01-05 | 2024-02-13 | 广州市嘉品电子科技有限公司 | Building engineering construction progress supervisory systems based on BIM technique |
CN117557065B (en) * | 2024-01-05 | 2024-04-23 | 广州市嘉品电子科技有限公司 | Building engineering construction progress supervisory systems based on BIM technique |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN114077767A (en) | BIM-based project progress monitoring system and method | |
CN103077482B (en) | Power operation risk control method and system thereof | |
CN110322147A (en) | A kind of Project Supervision approaches to IM and system | |
CN111369226A (en) | BIM-based project progress supervision system | |
CN112734284B (en) | Flow industrial energy consumption optimization decision system and method for improving accuracy of evaluation result | |
CN110889626A (en) | Intelligent shift planning method, device, equipment and storage medium | |
CN108897969A (en) | A method of the facility maintenance Automatic dispatching based on BIM | |
CN103500375A (en) | EM-Plant-based MES (Manufacturing Execution Systems) dispatching control method | |
CN110895832B (en) | Engineering management and control method and device | |
CN113988804B (en) | Digital management method, device, equipment and storage medium for whole engineering construction process | |
CN116029682A (en) | Construction progress management method and system based on BIM technology | |
CN115049201A (en) | Job scheduling method and device, electronic equipment and storage medium | |
CN112288180B (en) | Comprehensive dispatching method and system for distribution network maintenance work orders | |
CN111695883B (en) | Automatic checking method for consistency of line live working worksheet and master station listing operation | |
CN110378670B (en) | Space network technology model and construction method and application thereof | |
CN111080247A (en) | Staff training schedule adjusting method and device | |
CN115310366A (en) | Method for evaluating airport publishing capacity based on random optimization model | |
CN114896677B (en) | BIM (building information modeling) -based construction simulation method and system | |
CN111105050A (en) | Method, device and equipment for generating fan maintenance plan and storage medium | |
CN116128270A (en) | Power grid operation plan management method and device for multi-source data fusion | |
US9460240B2 (en) | Method for determining a partial-load condition of a system | |
CN115674198A (en) | Method, device, equipment and storage medium for deploying robot | |
CN115194910A (en) | Plate processing control system for customized furniture | |
CN110262891B (en) | Automatic multifunctional resource recycling system across virtualization platforms | |
CN114792230A (en) | Intelligent community comprehensive command center scheduling system and method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |