CN114000718B - Construction post-pouring belt rubbish-preventing rainproof drainage device - Google Patents

Construction post-pouring belt rubbish-preventing rainproof drainage device Download PDF

Info

Publication number
CN114000718B
CN114000718B CN202111489125.1A CN202111489125A CN114000718B CN 114000718 B CN114000718 B CN 114000718B CN 202111489125 A CN202111489125 A CN 202111489125A CN 114000718 B CN114000718 B CN 114000718B
Authority
CN
China
Prior art keywords
cross rod
post
rubbish
construction
rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111489125.1A
Other languages
Chinese (zh)
Other versions
CN114000718A (en
Inventor
张志军
孔德忠
刘强
施磊
姚立铮
张志勇
刘青
吴彤
蔡建桢
樊建伟
刘长东
肖佳伟
张忠明
赵磊
李宇国
张福恺
宋淼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
City Construction Development Co Ltd of China Railway 16th Bureau Group Co Ltd
Original Assignee
City Construction Development Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by City Construction Development Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical City Construction Development Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority to CN202111489125.1A priority Critical patent/CN114000718B/en
Publication of CN114000718A publication Critical patent/CN114000718A/en
Application granted granted Critical
Publication of CN114000718B publication Critical patent/CN114000718B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/30Safety or protective measures preventing damage to building parts or finishing work during construction against mechanical damage or dirt, e.g. guard covers of stairs
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D29/00Filters with filtering elements stationary during filtration, e.g. pressure or suction filters, not covered by groups B01D24/00 - B01D27/00; Filtering elements therefor
    • B01D29/01Filters with filtering elements stationary during filtration, e.g. pressure or suction filters, not covered by groups B01D24/00 - B01D27/00; Filtering elements therefor with flat filtering elements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D29/00Filters with filtering elements stationary during filtration, e.g. pressure or suction filters, not covered by groups B01D24/00 - B01D27/00; Filtering elements therefor
    • B01D29/96Filters with filtering elements stationary during filtration, e.g. pressure or suction filters, not covered by groups B01D24/00 - B01D27/00; Filtering elements therefor in which the filtering elements are moved between filtering operations; Particular measures for removing or replacing the filtering elements; Transport systems for filters

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

The invention discloses a post-pouring belt rubbish-proof rainproof drainage device for construction, which relates to the technical field of building construction and comprises waterproof cloth, wherein one side of the top end of the waterproof cloth is provided with a first cross rod, the other side of the top end of the waterproof cloth is provided with a second cross rod, the bottom ends of the first cross rod and the second cross rod are respectively provided with a fixed rod, the top ends of the fixed rods and the bottom ends of the waterproof cloth are respectively provided with a sealing gasket, the top ends of the waterproof cloth are respectively provided with a filter screen, the two sides of the filter screens are respectively provided with a connecting plate, the top ends of the connecting plates are respectively provided with a first handle, one side of the first cross rod is provided with a sleeve, one end of the sleeve is sleeved with a first threaded rod, and the other end of the sleeve is sleeved with a second threaded rod. This kind of post-cast strip of construction prevents rubbish rain-proof drainage device, simple structure is reasonable, novel in design, and easy operation is convenient, can effectively realize preventing rubbish and rainwater entering construction post-cast strip in, and conveniently discharges the rainwater, has higher practical value.

Description

Construction post-pouring belt rubbish-preventing rainproof drainage device
Technical Field
The invention relates to the technical field of building construction, in particular to a post-pouring belt rubbish-preventing rainproof drainage device for construction.
Background
The construction post-pouring belt is used for preventing harmful cracks of a cast-in-situ reinforced concrete structure due to uneven temperature and shrinkage in construction, temporary construction joints are reserved at corresponding positions of a foundation slab, walls and beams according to design or construction specification requirements, the structure is temporarily divided into a plurality of parts, the construction joints are internally shrunk through members, concrete is poured and smashed after a plurality of times, the structure is connected into a whole, and the existing construction post-pouring belt is easily eroded by construction waste and rainwater when being temporarily reserved, so that the engineering post quality is influenced, the drainage is inconvenient, and the construction efficiency is influenced. Therefore, a post-pouring belt rubbish-proof, rain-proof and water draining device for construction is needed.
Disclosure of Invention
In order to solve the technical problems, the invention provides the post-pouring-belt rubbish-preventing rainproof drainage device for construction, which prevents the post-pouring-belt from being corroded by construction rubbish and rainwater so as to improve the engineering quality.
In order to achieve the above object, the present invention provides the following solutions:
the invention provides a post-pouring belt rubbish-proof rainproof drainage device for construction, which comprises waterproof cloth, a filter screen, a sealing gasket and an adjusting mechanism; waterproof layout arrange in the adjustment mechanism bottom, the filter screen set up in adjustment mechanism top, sealed pad set up in adjustment mechanism both ends, adjustment mechanism is used for adjusting the whole width of the waterproof drainage device of post-cast strip anti-rubbish of construction.
Optionally, the adjusting mechanism includes a first cross bar, a second cross bar, and an adjusting assembly; the adjusting component is arranged between the first cross rod and the second cross rod, and two ends of the waterproof cloth are respectively connected with the first cross rod and the second cross rod.
Optionally, the adjusting assembly includes a sleeve, a first threaded rod, and a second threaded rod; the first threaded rod one end with the second horizontal pole is connected, the other end of first threaded rod with telescopic one end cooperation is connected, second threaded rod one end with first horizontal pole is connected, the other end of second threaded rod with telescopic other end cooperation is connected.
Optionally, a second handle is arranged on the outer wall of the sleeve.
Optionally, the bottom of first horizontal pole with the second horizontal pole all is provided with the dead lever, the both ends of waterproof cloth are located respectively first horizontal pole with between the dead lever and the second horizontal pole with between the dead lever.
Optionally, sealing gaskets are arranged on the outer sides of the first cross rod and the second cross rod.
Optionally, the first cross bar and the second cross bar are respectively connected with the sealing gasket through bolts.
Optionally, a steel plate is disposed on a side, in contact with the first cross bar or the second cross bar, of the sealing pad, and the steel plate is connected with the bolt.
Optionally, connecting plates are arranged at two ends of the filter screen, and magnets are arranged in the connecting plates; the connecting plate is connected with the adjusting mechanism through magnetic attraction.
Optionally, a first handle is disposed on the connecting plate.
Compared with the prior art, the invention has the following technical effects:
1. according to the rubbish-preventing rainproof drainage device for the construction post-cast strip, the distance between the first cross rod and the second cross rod is conveniently adjusted through the first threaded rod and the second threaded rod, so that the construction post-cast strip with different sizes is convenient to install, and the supporting force of the second threaded rod and the first threaded rod is improved through the arrangement of the first installation seat and the second installation seat;
2. the post-pouring belt rubbish-preventing rainproof drainage device for construction has the advantages that the second handles are arranged on the two sides of the sleeve, so that constructors can conveniently install the post-pouring belt rubbish-preventing rainproof drainage device, the convenience in product use is improved, the magnets are arranged inside the connecting plates, the filter screen is convenient to detach, and the workers can conveniently clean rubbish of the filter screen;
3. according to the post-pouring-belt rubbish-preventing rainproof drainage device for construction, fine adjustment of the sealing gasket is achieved through the arrangement of the bolts, connection tightness of products and the post-pouring-belt for construction is improved, steel plates are arranged on the inner side of the sealing gasket, strength of the sealing gasket is improved, the sealing gasket is made of rubber materials, the sealing gasket has an antiskid function, product installation firmness is improved, double-sided film-covered color strip cloth is used for waterproof cloth, rainwater is conveniently collected on the waterproof cloth, and workers can conveniently drain water; the invention has simple and reasonable structure, novel design and simple and convenient operation, can effectively prevent garbage and rainwater from entering the post-pouring zone for construction, is convenient for discharging rainwater, and has higher practical value.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings that are needed in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
FIG. 1 is a perspective view of a post-construction casting belt anti-rubbish, rainproof and drainage device of the invention;
FIG. 2 is a perspective view of a sleeve of the post-construction casting belt anti-rubbish, rainproof drainage device of the invention;
fig. 3 is a perspective view of a filter screen of the post-pouring belt rubbish-proof rain-proof drainage device for construction.
In the figure: 1. waterproof cloth; 2. a first cross bar; 3. a fixed rod; 4. a sealing gasket; 5. a filter screen; 6. a connecting plate; 7. a first handle; 8. a sleeve; 9. a first threaded rod; 10. a second threaded rod; 11. a first mount; 12. a second handle; 13. a bolt; 14. a second cross bar; 15. and a second mounting seat.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
As shown in fig. 1 to 3, the present embodiment provides a post-pouring strip rubbish-proof, rain-proof and drainage device for construction, comprising a waterproof cloth 1, a filter screen 5, a sealing pad 4 and an adjusting mechanism; waterproof cloth 1 set up in adjustment mechanism bottom, filter screen 5 set up in adjustment mechanism top, sealed pad 4 set up in adjustment mechanism both ends, adjustment mechanism is used for the adjustment post-cast strip prevents rubbish rain-proof drainage device's whole width.
In this particular embodiment, the adjustment mechanism includes a first rail 2, a second rail 14, and an adjustment assembly; the adjusting component is arranged between the first cross bar 2 and the second cross bar 14, and two ends of the waterproof cloth 1 are respectively connected with the first cross bar 2 and the second cross bar 14.
The adjusting assembly comprises a sleeve 8, a first threaded rod 9 and a second threaded rod 10; one end of the first threaded rod 9 is connected with the second cross rod 14, the other end of the first threaded rod 9 is connected with one end of the sleeve 8 in a matched mode, one end of the second threaded rod 10 is connected with the first cross rod 2, and the other end of the second threaded rod 10 is connected with the other end of the sleeve 8 in a matched mode. More specifically, first mount pad 11 is equipped with to second threaded rod 10 one end cover, and first threaded rod 9 one end cover is equipped with second mount pad 15, through first threaded rod 9 and second threaded rod 10, conveniently adjusts the interval of first horizontal pole 2 and second horizontal pole 14 to the convenient not unidimensional construction post-cast strip installation.
A second handle 12 is arranged on the outer wall of the sleeve 8. The sleeve 8 is rotated through the second handle 12, so that constructors can conveniently install the product, and the use convenience of the product is improved.
The bottoms of the first cross rod 2 and the second cross rod 14 are respectively provided with a fixed rod 3, and two ends of the waterproof cloth 1 are respectively positioned between the first cross rod 2 and the fixed rod 3 and between the second cross rod 14 and the fixed rod 3.
And sealing gaskets 4 are arranged outside the first transverse rod 2 and the second transverse rod 14. The first cross bar 2 and the second cross bar 14 are respectively connected with the sealing gasket 4 through bolts 13. The side of the gasket 4 contacting the first cross bar 2 or the second cross bar 14 is provided with a steel plate, and the steel plate is connected with the bolt 13. The sealing gasket 4 is finely adjusted through the bolts 13, so that the connection tightness of the product and the construction post-pouring belt is improved. The sealing gasket 4 is made of rubber, a steel plate is arranged on the inner side of the sealing gasket 4, the strength of the sealing gasket 4 is improved, the sealing gasket 4 made of rubber has an anti-skid function, and the product installation firmness is improved.
Connecting plates 6 are arranged at two ends of the filter screen 5, and magnets are arranged in the connecting plates 6; the connecting plate 6 is connected with the adjusting mechanism through magnetic attraction. The connecting plate 6 is provided with a first handle 7. Through the inside magnet that is equipped with of connecting plate 6, make things convenient for filter screen 5 to dismantle, make things convenient for the staff to clear up the rubbish of filter screen 5.
The waterproof cloth 1 is double-sided film-covered color stripe cloth, the thickness of the waterproof cloth 1 is 0.2-0.3 mm, rainwater is convenient to collect, and rainwater is collected on the waterproof cloth 1, so that the water is convenient for workers to drain.
When using this kind of construction post-cast strip waterproof and rainproof drainage device, at first, detect whether this construction post-cast strip waterproof and rainproof drainage device's junction is fastened, after guaranteeing to be intact, install this construction post-cast strip waterproof and rainproof drainage device to appointed construction region again, the constructor only need rotate sleeve 8 through second handle 12, can adjust the interval of first horizontal pole 2 and second horizontal pole 14, thereby make things convenient for the installation of different sizes construction post-cast strip, through rotatory bolt 13, realize sealed fine setting of pad 4, improve the connection compactness of product and construction post-cast strip, through the setting of filter screen 5, realize building rubbish collection, avoid damaging below waterproof cloth 1, when filter screen 5 surface rubbish is too much, through constructor pulling connecting plate 6's first handle 7, dismantle filter screen 5, make things convenient for the rubbish of staff clearance filter screen 5, when rainy day, the rainwater can fall to waterproof cloth 1 surface, make the rainwater gather on waterproof cloth 1, make things convenient for the staff to carry out the drainage through the water pump, this kind of construction post-cast strip waterproof and rubbish drainage device, simple structure is reasonable, the realization is simple, easy to operate is novel, can effectively prevent to get into after the rainwater, and has high practical value to drain.
It should be noted that it will be apparent to those skilled in the art that the present invention is not limited to the details of the above-described exemplary embodiments, but may be embodied in other specific forms without departing from the spirit or essential characteristics thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein.
The principles and embodiments of the present invention have been described in this specification with reference to specific examples, the description of which is only for the purpose of aiding in understanding the method of the present invention and its core ideas; also, it is within the scope of the present invention to be modified by those of ordinary skill in the art in light of the present teachings. In view of the foregoing, this description should not be construed as limiting the invention.

Claims (4)

1. The rubbish-preventing rainproof drainage device for the construction post-pouring belt is characterized by comprising waterproof cloth, a filter screen, a sealing gasket and an adjusting mechanism; the waterproof layer is arranged at the bottom of the adjusting mechanism, the filter screen is arranged at the top of the adjusting mechanism, the sealing gaskets are arranged at two ends of the adjusting mechanism, and the adjusting mechanism is used for adjusting the integral width of the post-construction pouring belt anti-rubbish rainproof drainage device;
the adjusting mechanism comprises a first cross rod, a second cross rod and an adjusting assembly; the adjusting component is arranged between the first cross rod and the second cross rod, and two ends of the waterproof cloth are respectively connected with the first cross rod and the second cross rod;
the adjusting assembly comprises a sleeve, a first threaded rod and a second threaded rod; one end of the first threaded rod is connected with the second cross rod, the other end of the first threaded rod is connected with one end of the sleeve in a matched mode, one end of the second threaded rod is connected with the first cross rod, and the other end of the second threaded rod is connected with the other end of the sleeve in a matched mode;
the bottoms of the first cross rod and the second cross rod are respectively provided with a fixed rod, and two ends of the waterproof cloth are respectively positioned between the first cross rod and the fixed rods and between the second cross rod and the fixed rods;
the sealing gaskets are arranged on the outer sides of the first cross rod and the second cross rod;
the first cross rod and the second cross rod are connected with the sealing gasket through bolts respectively;
connecting plates are arranged at two ends of the filter screen, and magnets are arranged in the connecting plates; the connecting plate is connected with the adjusting mechanism through magnetic attraction;
install appointed construction area with this post-cast strip anti-rubbish rain-proof drainage device, through rotatory sleeve, adjust the interval of first horizontal pole and second horizontal pole, be fit for the post-cast strip of not unidimensional construction, through rotatory bolt, fine setting is sealed fills up, is closely with post-cast strip edge connection, when filter screen surface rubbish is too much, dismantles the filter screen, the rubbish of clearance filter screen, discharges the water on the waterproof cloth through the water pump.
2. The post-construction casting belt rubbish-proof, rain-proof and water-draining device according to claim 1, wherein a second handle is arranged on the outer wall of the sleeve.
3. The post-construction casting belt rubbish-preventing, rain-proof and water-draining device according to claim 1, wherein a steel plate is arranged on one side, which is in contact with the first cross rod or the second cross rod, of the sealing gasket, and the steel plate is connected with the bolt.
4. The post-construction casting belt rubbish-proof, rain-proof and water-draining device according to claim 1, wherein a first handle is arranged on the connecting plate.
CN202111489125.1A 2021-12-08 2021-12-08 Construction post-pouring belt rubbish-preventing rainproof drainage device Active CN114000718B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111489125.1A CN114000718B (en) 2021-12-08 2021-12-08 Construction post-pouring belt rubbish-preventing rainproof drainage device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111489125.1A CN114000718B (en) 2021-12-08 2021-12-08 Construction post-pouring belt rubbish-preventing rainproof drainage device

Publications (2)

Publication Number Publication Date
CN114000718A CN114000718A (en) 2022-02-01
CN114000718B true CN114000718B (en) 2023-04-28

Family

ID=79931524

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111489125.1A Active CN114000718B (en) 2021-12-08 2021-12-08 Construction post-pouring belt rubbish-preventing rainproof drainage device

Country Status (1)

Country Link
CN (1) CN114000718B (en)

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
IT1304092B1 (en) * 1998-12-10 2001-03-07 Sibelon Srl METHOD FOR WATERPROOFING JOINTS AND / OR CRACKS IN HYDRAULIC WORKS AND CONCRETE AND / OR MASONRY STRUCTURES
CN206941657U (en) * 2017-07-10 2018-01-30 深圳百勤建设工程有限公司 A kind of basement post-pouring zone water sealing structure
CN107986486A (en) * 2018-01-24 2018-05-04 洛阳高昌机电科技有限公司 A kind of sanitary sewage filtration apparatus
CN209891439U (en) * 2019-03-27 2020-01-03 江西中煤建设集团有限公司 Industrial and civil building expansion joint waterproof construction
CN210002585U (en) * 2019-05-28 2020-01-31 中铁建设集团有限公司 post-cast strip aluminum cover plate
CN211773935U (en) * 2020-02-27 2020-10-27 程宏光 Underground works post-cast strip waterproof construction
CN214994132U (en) * 2021-05-12 2021-12-03 中国机械工业第四建设工程有限公司 Garbage cleaning device for post-cast strip construction

Also Published As

Publication number Publication date
CN114000718A (en) 2022-02-01

Similar Documents

Publication Publication Date Title
CN203383121U (en) Prefabricated temporary pavement concrete slab convenient to assemble and disassemble
CN114000718B (en) Construction post-pouring belt rubbish-preventing rainproof drainage device
CN110747967A (en) Municipal rainwater and sewage inspection well and use method thereof
CN207739164U (en) A kind of road culvert structure
CN109520749A (en) A kind of Modular trial road surface
CN208328843U (en) It is a kind of based on concrete prefabricated aqueduct
CN115075188A (en) Rain-proof water pours into mechanism suitable for subway station entry
CN213328920U (en) Water measuring weir for gallery drainage ditch
CN211340484U (en) Road and bridge crack reinforced structure
CN203684293U (en) Antiseep structure of underground diaphragm wall
CN210507491U (en) Adjustable water cofferdam
CN209924095U (en) Prefabricated assembly type linear drainage ditch structure for overpass road section
CN208472902U (en) A kind of prefabrication type municipal drainage slot
CN216947868U (en) Bearing type highway bridge deck drainage trash barrier
CN215407414U (en) Pouring mold
CN211340869U (en) Divide storehouse water blocking formula post-cast strip structure
CN220747636U (en) Floor post-cast strip construction formwork structure
CN214738606U (en) Prevent highway engineering drainage canal of jam
CN220704787U (en) Sealing device for reserved holes of floor
CN219261807U (en) Turnover post-pouring belt cover plate system
CN213897576U (en) Advanced water stop structure of basement bottom plate
CN220813398U (en) Finalized detachable post-pouring strip bridge crossing device
CN209247369U (en) A kind of Modular trial road surface
CN216809447U (en) Road roller for road repair
CN217257053U (en) Steel mould is pour to opening curb

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant