CN113988509A - Capital construction site system material regulation and control management system and method - Google Patents

Capital construction site system material regulation and control management system and method Download PDF

Info

Publication number
CN113988509A
CN113988509A CN202111121181.XA CN202111121181A CN113988509A CN 113988509 A CN113988509 A CN 113988509A CN 202111121181 A CN202111121181 A CN 202111121181A CN 113988509 A CN113988509 A CN 113988509A
Authority
CN
China
Prior art keywords
data
control
capital construction
regulation
construction site
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111121181.XA
Other languages
Chinese (zh)
Inventor
毛水强
蒋征毅
马新华
刘新
周昀飞
陈益坪
周汪平
赵凯美
吴良建
金博韬
都威
姜宇翔
方琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority to CN202111121181.XA priority Critical patent/CN113988509A/en
Publication of CN113988509A publication Critical patent/CN113988509A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063114Status monitoring or status determination for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06315Needs-based resource requirements planning or analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/087Inventory or stock management, e.g. order filling, procurement or balancing against orders
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply

Abstract

The invention provides a capital construction site system material regulation and control management system and a method thereof. The management method specifically comprises the steps that a capital construction site manager initiates a material regulation and control request, a data acquisition module acquires engineering construction data and transmits the engineering construction data to a data processing module, the data processing module acquires capital construction site material consumption data and corresponding capital construction site numbers through the engineering construction data, the data processing module extracts corresponding material drawings through the capital construction site numbers and acquires material spare data, and a control module formulates a capital construction site material regulation and control scheme according to the capital construction site material consumption data and the material spare data. According to the invention, the material consumption condition can be obtained through the engineering construction data of the capital construction site, and the accuracy of subsequent material regulation and control is improved.

Description

Capital construction site system material regulation and control management system and method
Technical Field
The invention relates to the technical field of capital construction site material management, in particular to a capital construction site system material regulation and control management system and method.
Background
In recent years, with the continuous improvement of the economic and social level of China, the speed of building, upgrading and reconstructing the power grid of China is increased, and the demand for power materials is increased. However, with the continuous expansion of the electric power infrastructure site, the management and control difficulty of electric power materials also rises continuously. Because the task process of the infrastructure site is influenced by factors such as constructors and construction environment, the consumption degree of materials in the infrastructure site is difficult to predict. If the material consumption statistics is carried out manually, the accuracy of the material consumption statistics is difficult to ensure. And careless mistakes are easy to occur in the mode of manually making a goods and materials regulation and control scheme, goods and materials waste is easy to be caused due to too much goods and materials regulation and control quantity, and project progress delay is easy to be caused due to too little goods and materials regulation and control quantity. And because the personnel of the capital construction site are numerous, the difficulty of material management is higher, and if the material utilization is abnormal, the subsequent execution of the capital construction project task can be influenced, thereby causing the efficiency reduction of the project construction.
Disclosure of Invention
The invention aims to overcome the defects in the prior art and provides a capital construction site system material regulation and control management system and method.
The purpose of the invention is realized by the following technical scheme:
a capital construction site system material regulation and control management method comprises the following steps:
firstly, a capital construction site manager initiates a material regulation and control request, a data acquisition module acquires engineering construction data, and the data acquisition module transmits the engineering construction data to a data processing module through a wireless communication network;
the data processing module acquires capital construction site material consumption data and corresponding capital construction site numbers through the engineering construction data, extracts corresponding material drawings through the capital construction site numbers, acquires corresponding material spare data of the capital construction site according to the material drawings, and transmits the material spare data and the capital construction site material consumption data to the control module through the wireless communication network;
and step three, the control module formulates a capital construction site material regulation and control scheme according to capital construction site material consumption data and material preparation data, wherein the capital construction site material regulation and control scheme comprises material regulation and control types and material regulation and control quantity.
Further, when at least two infrastructure sites initiate material regulation and control requests and corresponding infrastructure site material regulation and control schemes are formulated, the priority coefficient of each infrastructure site material regulation and control scheme is calculated according to the engineering task progress, the engineering task duration and the material use condition of each infrastructure site, the execution sequence of the infrastructure site material regulation and control schemes is determined according to the priority coefficient, and the infrastructure site material regulation and control scheme with the highest priority coefficient is preferentially executed.
Furthermore, after a capital construction site material regulation and control scheme is implemented, the storage data of a storage material library is also collected, the stock value of each type of material is determined according to the storage data of the storage material library, the stock value of the material, the material demand of the capital construction site material regulation and control scheme and the weight of the priority coefficient corresponding to the previous sequencing capital construction site material regulation and control scheme are set, the priority coefficients of the remaining capital construction site material regulation and control schemes are recalculated according to the stock value of the material, the material demand of the capital construction site material regulation and control scheme and the priority coefficient corresponding to the previous sequencing capital construction site material regulation and control scheme, the material regulation and control scheme with the largest execution priority coefficient is selected, and the priority coefficients of the remaining capital construction site material regulation and control schemes are recalculated after one capital construction site material regulation and control scheme is implemented each time.
Furthermore, after the control module formulates a infrastructure field material regulation and control scheme, the control module collects the storage access control data in real time through the storage monitoring module, the storage monitoring module determines material receiving information according to the storage material inventory data, the control module compares the material receiving information with the infrastructure field material regulation and control scheme, judges an execution result of the infrastructure field material regulation and control scheme according to the comparison result, gives an alarm when the material receiving information is inconsistent with the infrastructure field material regulation and control scheme, and determines corresponding personnel information when the material receiving information is inconsistent through the storage access control data.
The utility model provides a capital construction on-site system material regulation and control management system, includes data acquisition module, data analysis module and control module, the data acquisition module is connected with the data analysis module, the data acquisition module is used for gathering the on-site engineering construction data of capital construction, the data analysis module is connected with control module, the data analysis module is used for acquireing material preparation data and the on-site material consumption data of capital construction, control module is used for formulating the on-site material regulation and control scheme of capital construction.
Further, capital construction on-site system material regulation and control management system still includes storage monitoring module, storage monitoring module is connected with control module, storage monitoring module is used for monitoring storage material inventory and changes, storage monitoring module still is used for gathering storage entrance guard's data in real time, acquires material personnel's personnel information.
Further, the data acquisition module includes terminal equipment and the sensor of configuration on terminal equipment, terminal equipment includes camera, cloth accuse ball, law enforcement appearance, floodgate machine, weather station, tower crane and lift.
The invention has the beneficial effects that:
the material consumption of the capital construction site is obtained through the engineering construction data of the capital construction site, the material regulation and control can be carried out according to the specific conditions of the capital construction site, and the accuracy of the material regulation and control is improved. And the priority coefficient of the infrastructure site material regulation and control scheme is calculated, and the execution sequence of the infrastructure site material regulation and control scheme is carried out according to the priority coefficient, so that the material regulation and control can be more reasonable, and the material shortage condition is prevented. And the material receiving condition is monitored in real time, the material is prevented from being received by the user in a fake manner or leaked, and the material storage safety is ensured, so that the efficiency of capital construction engineering construction is ensured.
Drawings
FIG. 1 is a schematic diagram of an embodiment of the present invention;
FIG. 2 is a schematic flow diagram of the present invention;
wherein: 1. the system comprises a data acquisition module 2, a data analysis module 3, a control module 4 and a storage monitoring module.
Detailed Description
The invention is further described below with reference to the figures and examples.
Example (b):
the utility model provides a capital construction on-site system material regulation and control management system, as shown in figure 1, including data acquisition module 1, data analysis module 2, control module 3 and storage monitoring module 4, data acquisition module 1 is connected with data analysis module 2, data acquisition module 1 is used for gathering the on-the-spot engineering construction data of capital construction, data analysis module 2 is connected with control module 3, data analysis module 2 is used for acquireing material spare data and the on-the-spot material consumption data of capital construction, control module 3 is used for formulating the on-the-spot material regulation and control scheme of capital construction.
Storage monitoring module 4 is connected with control module 3, storage monitoring module 4 is used for monitoring storage material inventory and changes, storage monitoring module 4 still is used for gathering storage entrance guard's data in real time, acquires material personnel's personnel information.
Data acquisition module 1 includes terminal equipment and the sensor of configuration on terminal equipment, terminal equipment includes camera, cloth accuse ball, law enforcement appearance, floodgate machine, meteorological station, tower crane and lift.
Through obtaining the engineering construction data to terminal equipment and the sensor of configuration on terminal equipment, every type of terminal equipment all corresponds concrete kind of goods and materials, for example through the detection to tower crane operating condition, can effectively judge the in service behavior of steel. The terminal device and the sensor can acquire the process of the capital construction field engineering construction, so that the material use condition in the process of the capital construction field engineering construction is determined, the statistical efficiency can be effectively improved compared with the manual material consumption statistics, and the accuracy of the subsequent material regulation and control scheme can also be improved.
A material regulation and control management method for a capital construction field system is shown in figure 2 and comprises the following steps:
firstly, a capital construction site manager initiates a material regulation and control request, a data acquisition module 1 acquires engineering construction data, and the data acquisition module 1 transmits the engineering construction data to a data processing module through a wireless communication network;
step two, the data processing module acquires capital construction field material consumption data and corresponding capital construction field numbers through engineering construction data, the data processing module extracts corresponding material drawings through the capital construction field numbers, the data processing module acquires corresponding material spare data of the capital construction field according to the material drawings, and the data processing module transmits the material spare data and the capital construction field material consumption data to the control module 3 through a wireless communication network;
and step three, the control module 3 formulates a capital construction site material regulation and control scheme according to capital construction site material consumption data and material preparation data, wherein the capital construction site material regulation and control scheme comprises material regulation and control types and material regulation and control quantity.
The material consumption of the capital construction site is obtained through the engineering construction data of the capital construction site, the material regulation and control can be carried out according to the specific conditions of the capital construction site, and the accuracy of the material regulation and control is improved. Because every capital construction scene all needs to carry out the goods and materials preparation according to the goods and materials drawing before the engineering task is carried out, and every capital construction scene is because the engineering task is different, and the goods and materials preparation is also different, when carrying out goods and materials regulation and control, need carry out goods and materials regulation and control according to the goods and materials preparation, can satisfy the engineering operation demand of capital construction scene after guaranteeing the goods and materials regulation and control. Therefore, a specific material regulation and control scheme is carried out according to material preparation data and capital construction site material consumption data, and the material regulation and control of the capital construction site can be safely and effectively carried out.
The wireless communication network is a 5G network, engineering construction data are transmitted through the 5G network, the acquisition density can be effectively improved, the data acquisition amount is increased, and the detection efficiency of the material service condition can be improved.
When at least two infrastructure sites initiate material regulation and control requests and corresponding infrastructure site material regulation and control schemes are formulated, the priority coefficient of each infrastructure site material regulation and control scheme is calculated according to the engineering task progress, the engineering task duration and the material use condition of each infrastructure site, the execution sequence of the infrastructure site material regulation and control schemes is determined according to the priority coefficient, and the infrastructure site material regulation and control scheme with the highest priority coefficient is preferentially executed.
After a capital construction site material regulation and control scheme is implemented, warehouse material database data is collected, the stock value of each type of material is determined according to the warehouse material database data, the stock value of the material, the material demand of the capital construction site material regulation and control scheme and the weight of the priority coefficient corresponding to the previous sequencing capital construction site material regulation and control scheme are set, the priority coefficients of the rest of the capital construction site material regulation and control schemes are recalculated according to the stock value of the material, the material demand of the capital construction site material regulation and control scheme and the priority coefficient corresponding to the previous sequencing capital construction site material regulation and control scheme, the material regulation and control scheme with the largest execution priority coefficient is selected, and the priority coefficients of the rest of the capital construction site material regulation and control schemes are recalculated after one capital construction site material regulation and control scheme is implemented each time.
The project task progress and the project task time limit of the infrastructure site can reflect the degree of demand of the infrastructure site for material regulation, and the urgent degree of material regulation of the infrastructure site can be judged according to the material consumption condition, so that the priority coefficient of each infrastructure site material regulation scheme is calculated according to the project task progress, the project task time limit and the material use condition of each infrastructure site, the demand of the infrastructure site with higher priority coefficient for material regulation is more urgent, and the overall material management can be performed more orderly and in a planned way by establishing the execution sequence of the infrastructure site material regulation scheme.
Because the whole storage inventory of the materials can be changed after the material regulation and control scheme of one infrastructure site is executed, the priority coefficients of the rest regulation and control schemes of the infrastructure site need to be recalculated, the material regulation and control can be carried out on the premise that the whole storage inventory of the materials meets the requirement, and if the storage inventory of the material storage is not enough to meet the requirement of the material regulation and control, the engineering construction process of the infrastructure site can be slowed down, and the waste of manpower and material resources is caused.
After the control module 3 formulates a infrastructure field material regulation and control scheme, the storage access control data are collected in real time through the storage monitoring module 4, the storage monitoring module 4 determines material receiving information according to the storage material inventory data, the control module 3 compares the material receiving information with the infrastructure field material regulation and control scheme, the execution result of the infrastructure field material regulation and control scheme is judged according to the comparison result, an alarm is sent out when the material receiving information is inconsistent with the infrastructure field material regulation and control scheme, and corresponding personnel information when the material receiving information is inconsistent is determined through the storage access control data.
The material receiving information includes types of material receiving and receiving amount of each material type.
Storage entrance guard data can take notes and carry out the personnel information that the goods and materials received, storage inventory data around receiving through the goods and materials can acquire goods and materials information of receiving, receive information through the goods and materials and can carry out real-time monitoring to the goods and materials condition of receiving, if the goods and materials condition of receiving or leaking appears, in time report to the police, guarantee goods and materials safety, acquire the personnel information that the goods and materials received through storage entrance guard data, when the goods and materials abnormal conditions such as receiving or leaking appear, also can trace to the source according to the personnel information that the goods and materials received, reduce goods and materials loss risk, improve the accuracy of goods and materials management.
The above-described embodiments are only preferred embodiments of the present invention, and are not intended to limit the present invention in any way, and other variations and modifications may be made without departing from the spirit of the invention as set forth in the claims.

Claims (7)

1. A capital construction site system material regulation and control management method is characterized by comprising the following steps:
firstly, a capital construction site manager initiates a material regulation and control request, a data acquisition module acquires engineering construction data, and the data acquisition module transmits the engineering construction data to a data processing module through a wireless communication network;
the data processing module acquires capital construction site material consumption data and corresponding capital construction site numbers through the engineering construction data, extracts corresponding material drawings through the capital construction site numbers, acquires corresponding material spare data of the capital construction site according to the material drawings, and transmits the material spare data and the capital construction site material consumption data to the control module through the wireless communication network;
and step three, the control module formulates a capital construction site material regulation and control scheme according to capital construction site material consumption data and material preparation data, wherein the capital construction site material regulation and control scheme comprises material regulation and control types and material regulation and control quantity.
2. The material regulation and control management method of the infrastructure site system according to claim 1, wherein when at least two infrastructure sites initiate material regulation and control requests and corresponding infrastructure site material regulation and control schemes are formulated, the priority coefficient of each infrastructure site material regulation and control scheme is further calculated according to the engineering task progress, the engineering task duration and the material use condition of each infrastructure site, the execution sequence of the infrastructure site material regulation and control schemes is determined according to the priority coefficient, and the infrastructure site material regulation and control scheme with the highest priority coefficient is preferentially executed.
3. The method as claimed in claim 2, wherein the capital construction site material regulation and control scheme is implemented to collect data of warehouse material, determining the stock value of each type of materials according to the stock data of the stored materials, setting the stock value of the materials, the material demand of the capital construction site material regulation and control scheme and the weight of the priority coefficient corresponding to the previous sequencing capital construction site material regulation and control scheme, recalculating the priority coefficient of the remaining capital construction site material regulation and control scheme according to the stock value of the materials, the material demand of the capital construction site material regulation and control scheme and the priority coefficient corresponding to the previous sequencing capital construction site material regulation and control scheme, and selecting the material regulation and control scheme with the maximum execution priority coefficient, and recalculating the priority coefficients of the material regulation and control schemes of the rest infrastructure sites after implementing one infrastructure site material regulation and control scheme each time.
4. The method for regulating and managing the materials of the capital construction site system according to claim 1, wherein after the control module sets a capital construction site material regulation and control scheme, the control module collects warehousing entrance guard data in real time through the warehousing monitoring module, the warehousing monitoring module determines material receiving information according to the warehousing material inventory data, the control module compares the material receiving information with the capital construction site material regulation and control scheme, judges an execution result of the capital construction site material regulation and control scheme according to the comparison result, gives an alarm when the material receiving information is inconsistent with the capital construction site material regulation and control scheme, and determines corresponding personnel information when the material receiving information is inconsistent through the warehousing entrance guard data.
5. The utility model provides a capital construction on-site system material regulation and control management system, its characterized in that includes data acquisition module, data analysis module and control module, data acquisition module is connected with data analysis module, data acquisition module is used for gathering the on-site engineering construction data of capital construction, data analysis module is connected with control module, data analysis module is used for acquireing material spare data and capital construction on-site material consumption data, control module is used for formulating capital construction on-site material regulation and control scheme.
6. The capital construction site system material regulation and control management system according to claim 5, characterized by further comprising a storage monitoring module, wherein the storage monitoring module is connected with the control module, the storage monitoring module is used for monitoring storage material inventory changes, and the storage monitoring module is further used for acquiring storage access control data in real time and acquiring personnel information of material requisitors.
7. The capital construction field system material regulation and control management system of claim 5, wherein the data acquisition module comprises a terminal device and a sensor configured on the terminal device, and the terminal device comprises a camera, a distribution control ball, a law enforcement instrument, a gate, a meteorological station, a tower crane and a lifter.
CN202111121181.XA 2021-09-24 2021-09-24 Capital construction site system material regulation and control management system and method Pending CN113988509A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111121181.XA CN113988509A (en) 2021-09-24 2021-09-24 Capital construction site system material regulation and control management system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111121181.XA CN113988509A (en) 2021-09-24 2021-09-24 Capital construction site system material regulation and control management system and method

Publications (1)

Publication Number Publication Date
CN113988509A true CN113988509A (en) 2022-01-28

Family

ID=79736543

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111121181.XA Pending CN113988509A (en) 2021-09-24 2021-09-24 Capital construction site system material regulation and control management system and method

Country Status (1)

Country Link
CN (1) CN113988509A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115546677A (en) * 2022-07-11 2022-12-30 北京国电通网络技术有限公司 Capital construction site information processing method, device, equipment and computer readable medium

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115546677A (en) * 2022-07-11 2022-12-30 北京国电通网络技术有限公司 Capital construction site information processing method, device, equipment and computer readable medium
CN115546677B (en) * 2022-07-11 2023-10-24 北京国电通网络技术有限公司 Method, apparatus, device and computer readable medium for processing information of construction site

Similar Documents

Publication Publication Date Title
WO2023040575A1 (en) Internet-of-things-based abnormality early warning analysis system and method for special operation site
CN111307823B (en) System and method for detecting typical visual defects of power transformation equipment based on edge cloud cooperation
CN115296422B (en) Power cable running state monitoring and control system and method based on big data
CN110796847B (en) Block chain-based environment monitoring station operation and maintenance system and method
CN111062504A (en) AR technology-based intelligent power distribution station operation and maintenance system and method
CN106570567A (en) Main network maintenance multi-constraint multi-target evaluation expert system and optimization method
CN109905406A (en) A kind of drainage pipeline networks monitoring system based on big data
CN115270974B (en) Intelligent electricity larceny detection system based on big data analysis
CN107832946A (en) A kind of power energy monitoring and controlling for workshop and management method and system
CN106817708A (en) One kind patrols and examines cluster construction method and device
CN113988509A (en) Capital construction site system material regulation and control management system and method
CN115345568A (en) Monitoring and early warning method and system based on drainage pipe network GIS
CN115002166B (en) Intelligent battery monitoring and leasing management system and method based on Internet of things
CN111668925A (en) Transformer inspection tour inspection device based on intelligent vision
CN105005235A (en) On-line icing monitoring system for power transmission line
CN117614487A (en) Beidou system-based transmission line communication method and system
CN205787141U (en) The terminal unit of supervision substation operation person works's state
CN113487157B (en) Cloud technology-based prestress construction quality unmanned supervision platform and method
CN111126825A (en) Intelligent charge-discharge energy-saving management system for visual battery and control method thereof
CN113473261B (en) Prestress engineering construction monitoring system and method based on Internet of things
CN107871177B (en) Implementation method of new energy power prediction centralized framework
CN210515359U (en) Transformer substation secondary equipment fault monitoring system based on edge calculation
CN107633091A (en) A kind of automatic power supervisory systems
CN114069843A (en) Alarm method for misoperation of transformer substation
CN111932097A (en) Data quality monitoring method and device based on electric vehicle service platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination