CN113917234B - Automatic calibration method for cage wiring of target controller - Google Patents

Automatic calibration method for cage wiring of target controller Download PDF

Info

Publication number
CN113917234B
CN113917234B CN202111527308.8A CN202111527308A CN113917234B CN 113917234 B CN113917234 B CN 113917234B CN 202111527308 A CN202111527308 A CN 202111527308A CN 113917234 B CN113917234 B CN 113917234B
Authority
CN
China
Prior art keywords
test
terminal
interface
insulation
resistance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111527308.8A
Other languages
Chinese (zh)
Other versions
CN113917234A (en
Inventor
陈小猛
韦启盟
陈帝尧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Casco Signal Beijing Ltd
Original Assignee
Casco Signal Beijing Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Casco Signal Beijing Ltd filed Critical Casco Signal Beijing Ltd
Priority to CN202111527308.8A priority Critical patent/CN113917234B/en
Publication of CN113917234A publication Critical patent/CN113917234A/en
Application granted granted Critical
Publication of CN113917234B publication Critical patent/CN113917234B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R27/00Arrangements for measuring resistance, reactance, impedance, or electric characteristics derived therefrom
    • G01R27/02Measuring real or complex resistance, reactance, impedance, or other two-pole characteristics derived therefrom, e.g. time constant
    • G01R27/025Measuring very high resistances, e.g. isolation resistances, i.e. megohm-meters
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R27/00Arrangements for measuring resistance, reactance, impedance, or electric characteristics derived therefrom
    • G01R27/02Measuring real or complex resistance, reactance, impedance, or other two-pole characteristics derived therefrom, e.g. time constant

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)

Abstract

The invention discloses an automatic calibration method for the wiring of a cage of a target controller, relates to the technical field of railway equipment production, and aims to automatically calibrate the wiring, reduce the error risk caused by manual intervention, and realize simple and efficient operation. The main technical scheme of the invention is as follows: a target controller cage wiring calibration tool is set up in advance, and the structural design of the calibration tool at least comprises the following steps: the system comprises a display screen, a central processing unit, an insulation tester, a resistance tester, a switching circuit, a first terminal test interface, a second terminal test interface, a network port test interface and a third terminal test interface, wherein the first terminal test interface is in butt joint with an output terminal of a cage of a target controller, the second terminal test interface is in butt joint with a power supply terminal of the cage of the target controller, and the third terminal test interface is in butt joint with an internal terminal of the cage of the target controller; the checking tool is used for completing the line-to-line insulation test and the contact resistance test, and a feedback test result is output to the display screen through the central processing unit.

Description

Automatic calibration method for cage wiring of target controller
Technical Field
The invention relates to the technical field of railway equipment production, in particular to an automatic calibration method for the distribution of a cage of a target controller.
Background
With the continuously strengthened demand of informatization and networking of the railway system, the application and popularization speed of the target controller is continuously accelerated. The target controller may be divided into: switch machine controller, signal machine controller, track circuit controller, coding equipment controller, zero-dispersion equipment controller and the like. The insulation performance of the internal wiring of the target controller is directly related to the station operation safety and the equipment stable operation.
At present, a target controller has the characteristics of more internal wiring, high risk of wiring errors and the like, and once wiring errors occur, engineering implementation and operation safety are greatly influenced, so that wiring verification work is very important. However, the existing wiring verification work not only involves a large amount of work, but also needs more manual debugging work, so that the risk of manual error is difficult to avoid, and the wiring verification work involving more manual interventions is complicated in steps and low in efficiency, and the work difficulty of installation and debugging personnel is indirectly increased.
Disclosure of Invention
In view of the above, the invention provides an automatic calibration method for target controller cage wiring, and mainly aims to automatically complete target controller cage wiring calibration work in a factory production stage by using a built target controller cage wiring calibration tool, so that wiring calibration is automated, error risks caused by manual intervention are reduced, and the operation is simple and efficient.
In order to achieve the above purpose, the present invention mainly provides the following technical solutions:
the application provides an automatic verification method for the wiring of a cage of a target controller, which comprises the following steps:
set up target controller cage wiring check tool, the structural design of check tool includes at least: the testing device comprises a display screen, a central processing unit, an insulation tester, a resistance tester, a switching circuit, a first terminal testing interface, a second terminal testing interface, a network port testing interface and a third terminal testing interface; the first terminal test interface is in butt joint with an output terminal of a target controller cage, the second terminal test interface is in butt joint with a power supply terminal of the target controller cage, and the third terminal test interface is in butt joint with an internal terminal of the target controller cage;
after the display screen receives an operation instruction for operating and selecting the type corresponding to the target controller, responding to the operation instruction, and determining the target type correspondingly selected by the target controller;
when the central processing unit is controlled to send an insulation test instruction to the switching circuit, the switching circuit automatically accesses the insulation tester into a test loop, the first terminal test interface, the second terminal test interface, the network port test interface and the third terminal test interface are utilized to complete inter-line insulation test, and test data corresponding to the insulation test instruction are output;
when the central processing unit is controlled to send a resistance test instruction to the switching circuit, the switching circuit automatically accesses the resistance tester into a test loop, completes a contact resistance test by using the first terminal test interface, the second terminal test interface, the network port test interface and the third terminal test interface, and outputs test data corresponding to the resistance test instruction;
the central processing unit outputs a first test result and feeds back and displays the first test result on the display screen according to a preset criterion corresponding to the target type and test data corresponding to the insulation test instruction;
and the central processing unit outputs a second test result and feeds back and displays the second test result on the display screen according to the preset criterion corresponding to the target type and the test data corresponding to the resistance test instruction.
In some modified embodiments of the present application, the outputting test data corresponding to the insulation test instruction by using the first terminal test interface, the second terminal test interface, the network interface test interface, and the third terminal test interface to complete the inter-line insulation test includes:
the insulation tester receives the insulation test instruction and respectively sends a first insulation test signal to the first terminal test interface, the second terminal test interface and the network port test interface;
and the insulation tester samples a second insulation test signal fed back by a cage of a target controller through a switching circuit interface, and takes the first insulation test signal and the second insulation test signal as test data.
In some modified embodiments of the present application, the outputting test data corresponding to the resistance test instruction by using the first terminal test interface, the second terminal test interface, the network interface test interface, and the third terminal test interface to complete a contact resistance test includes:
the resistance tester receives the resistance test instruction and respectively sends first resistance test signals to the first terminal test interface, the second terminal test interface and the network port test interface;
and the resistance tester samples a second resistance test signal fed back by the cage of the target controller through a switching circuit interface, and takes the first resistance test signal and the second resistance test signal as test data.
In some variations of the present application, the central processor comprises a master processor and a slave processor;
the control the central processing unit sends the insulation test instruction to the switching circuit, including: controlling the master processor and the slave processor to respectively send insulation test instructions to the switching circuit;
the control the central processing unit sends resistance test instruction to the switching circuit, including: and controlling the master processor and the slave processor to respectively send resistance test instructions to the switching circuit.
In some variations of the present application,
the insulation tester passes through the reduce BUS to the test data that central processing unit sent, include: test data corresponding to the insulation test instruction triggered by the master processor and test data corresponding to the insulation test instruction triggered by the slave processor;
the resistance tester passes through the reduce BUS to the test data that central processing unit sent, include: the test data corresponding to the resistance test instruction triggered by the master processor and the test data corresponding to the resistance test instruction triggered by the slave processor.
In some modified embodiments of the present application, the outputting, by the central processing unit, a first test result and displaying the first test result on the display screen in a feedback manner according to the preset criterion corresponding to the target type and the test data corresponding to the insulation test instruction includes:
the central processing unit compares whether the test data corresponding to the insulation test instruction triggered by the main processor is consistent with the test data corresponding to the insulation test instruction triggered by the auxiliary processor;
if so, outputting a first test result and feeding back and displaying the first test result on the display screen according to test data corresponding to the insulation test instruction triggered by the main processor and a preset criterion corresponding to the target type;
if not, judging that the test is abnormal and outputting the abnormal test to the display screen.
In some modified embodiments of the present application, the outputting, by the central processing unit, a second test result and displaying the second test result on the display screen in a feedback manner according to the preset criterion corresponding to the target type and the test data corresponding to the resistance test instruction includes:
the central processing unit compares whether the test data corresponding to the resistance test instruction triggered by the main processor is consistent with the test data corresponding to the resistance test instruction triggered by the auxiliary processor;
if yes, outputting a second test result and feeding back and displaying the second test result on the display screen according to test data corresponding to the resistance test instruction triggered by the main processor and a preset criterion corresponding to the target type;
if not, judging that the test is abnormal and outputting the abnormal test to the display screen.
In some variations of the present application, the structural design of the verification tool further comprises: a USB interface for providing a connection to copy the first test result or the second test result.
In some modified embodiments of the present application, the central processing unit is connected to the display screen through a serial bus, the main processor and the slave processor in the central processing unit work in parallel, and the test data obtained from the slave processor is used for checking the test data obtained from the main processor.
In some variations of the present application, the target controller is at least one of:
a point switch controller, a signal machine controller, a track circuit controller, a coding equipment controller and a zero-dispersion equipment controller.
By the technical scheme, the technical scheme provided by the invention at least has the following advantages:
the invention provides an automatic calibration method of a target controller cage wiring, which is characterized in that a calibration tool of the target controller cage wiring is set up in advance, and the structural design of the calibration tool at least comprises the following steps: the display screen, central processing unit, insulation tester, resistance tester, switching circuit, first terminal test interface, second terminal test interface, net gape test interface and third terminal test interface, this first terminal test interface be with the output terminal butt joint of target controller cage, this second terminal test interface be with the power supply terminal butt joint of target controller cage, this third terminal test interface be with the inside terminal butt joint of target controller cage. Therefore, the target type of the target controller can be selected by operating the display screen, the central processing unit can search the preset criterion corresponding to the target type, and after the central processing unit sends out the insulation test instruction or the resistance test instruction, the switching circuit is switched to connect the insulation tester or the resistance tester into the test loop, so that the insulation test and the contact resistance test between the lines can be completed by utilizing different test loops. For both tests, a test signal is sent to a target controller cage through the first terminal test interface, the second terminal test interface and the network port test interface, and a test signal fed back by the target controller cage is obtained through the third terminal test interface to form test data, and the test data is transmitted to the central processing unit, so that the central processing unit outputs a final test result and feeds back the final test result to the display screen according to the test data and a preset criterion corresponding to a target type obtained before. Compared with the prior art, the method and the device solve the problems of low efficiency and easy error caused by large workload of wiring verification and excessive manual debugging work, automatically complete the wiring verification work of the cage of the target controller in the production stage of a factory by using the built wiring verification tool of the cage of the target controller, automatically verify the wiring, reduce the error risk caused by manual intervention, and have simple and efficient operation.
The foregoing description is only an overview of the technical solutions of the present invention, and the embodiments of the present invention are described below in order to make the technical means of the present invention more clearly understood and to make the above and other objects, features, and advantages of the present invention more clearly understandable.
Drawings
Various other advantages and benefits will become apparent to those of ordinary skill in the art upon reading the following detailed description of the preferred embodiments. The drawings are only for purposes of illustrating the preferred embodiments and are not to be construed as limiting the invention. Also, like reference numerals are used to refer to like parts throughout the drawings. In the drawings:
fig. 1 is a flowchart of an automatic verification method for a cage wiring of a target controller according to an embodiment of the present invention;
FIG. 2 is a schematic diagram of a system architecture of a calibration tool according to an embodiment of the present invention;
FIG. 3 is a schematic view illustrating a D terminal structure according to an embodiment of the present invention;
FIG. 4 is a schematic view of an exemplary inside A terminal of a target controller according to an embodiment of the present invention;
FIG. 5 is a schematic diagram of an exemplary P terminal, D terminal and net port of a target controller according to an embodiment of the present invention;
FIG. 6 is a schematic diagram illustrating a P-terminal test interface according to an embodiment of the present invention;
fig. 7 is a schematic structural diagram illustrating a socket test interface according to an embodiment of the present invention.
Detailed Description
Exemplary embodiments of the present invention will be described in more detail below with reference to the accompanying drawings. While exemplary embodiments of the invention are shown in the drawings, it should be understood that the invention can be embodied in various forms and should not be limited to the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the invention to those skilled in the art.
The embodiment of the invention provides an automatic checking method for target controller cage wiring, as shown in fig. 1, the embodiment of the invention is provided with an automatic checking tool for target controller cage wiring in advance, and the built trackside equipment simulation measurement testing tool is utilized to assist in completing wiring work of a tested target controller cage, such as problems of wrong wiring, mixed wiring, missing wiring, poor insulation, overlarge contact resistance and the like of the tested target controller cage, and the embodiment of the invention is provided with the following specific steps:
101. and (5) building a target controller cage wiring calibration tool.
Wherein, the structural design of check-up instrument includes at least: the testing device comprises a display screen, a central processing unit, an insulation tester, a resistance tester, a switching circuit, a first terminal testing interface, a second terminal testing interface, a network port testing interface and a third terminal testing interface. The first terminal test interface is in butt joint with an output terminal of a target controller cage, the second terminal test interface is in butt joint with a power supply terminal of the target controller cage, and the third terminal test interface is in butt joint with an internal terminal of the target controller cage.
It should be noted that the words "first", "second", and "third" are only used to identify the terminal test interface for different purposes, and different english letters may be used to replace the identification for identification, and the embodiment of the present invention is not limited.
Illustratively, a schematic diagram of a system structure of the verification tool shown in fig. 2 is illustrated, wherein the first terminal test interface is alternatively identified as a D terminal test interface, the second terminal test interface is alternatively identified as a P terminal test interface, and the third terminal test interface is alternatively identified as an a terminal test interface. A large number of internal wirings are arranged between the terminal a on the inner side of the cage of the target controller and the terminal D, the terminal P and the net port of the target controller, as shown in fig. 4, which illustrates a schematic diagram of the terminal a on the inner side of the target controller. It should be noted that the terminal identifier exemplified by the embodiment of the present invention may include, but is not limited to A, D, P.
In fig. 2, the D terminal of the target controller is an output terminal, the P terminal is a power supply terminal, the network port is a network interface, and the types of the terminals can be modified according to the requirements of the project. The D terminal is an output terminal of the target controller cage, is communicated with the target controller board card and is used for controlling the filling of trackside equipment and acquisition trackside equipment; the P terminal is a power supply of the cage of the target controller, is communicated with each board card of the target controller and is used for providing an action power supply or an expression power supply for each board card of the cage of the target controller; the network port is communicated with a communication board of the target controller equipment and is a network channel for the external communication of the target controller equipment; the terminal a on the inner side of the cage is a terminal inside the cage of the target controller, various board cards can be plugged on the terminal, and the terminal a is communicated with the terminal D, the terminal P and the net opening through a large number of internal wirings of the target controller, for example, a schematic diagram of the terminal P, the terminal D and the net opening of the target controller is illustrated in fig. 5.
To further illustrate, in fig. 2, the calibration tool introduces the test signal into the target controller cage through the D terminal test interface, the P terminal test interface, and the network port test interface, and receives the test signal fed back by the target controller cage through the a terminal test interface.
102. And after the display screen receives an operation instruction for operating and selecting the type corresponding to the target controller, responding to the operation instruction, and determining the target type correspondingly selected by the target controller.
In the embodiment of the invention, the display screen provides a human-computer interaction interface, an operator can select the type of the tested target controller in the interface, and various target controllers of different types and corresponding preset judgment bases can be stored in the central processing unit, one preset judgment base is suitable for the specified target controller, and the preset judgment base is mainly used for judging whether a large number of wires in the specified target controller are abnormal (such as the problems of wire missing, wire mixing, wire leakage, poor insulation, overlarge contact resistance and the like).
It should be noted that, because the judgment bases corresponding to different types of target controllers are different, the target type needs to be selected by operating on the display screen at this point, so as to perform subsequent verification on a large number of wiring operations inside the cage of the target controller of the specified target type.
103a, when the central processing unit is controlled to send an insulation test instruction to the switching circuit, the switching circuit automatically accesses the insulation tester into the test loop, the first terminal test interface, the second terminal test interface, the network port test interface and the third terminal test interface are utilized to complete the insulation test between lines, and test data corresponding to the insulation test instruction are output.
In the embodiment of the present invention, explained with reference to fig. 1, after the target type of the target controller is selected by operation on the display screen, the central processing unit is triggered to issue a test instruction, where the test includes: line-to-line insulation test and contact resistance test. When the control central processing unit sends an insulation test instruction to the switching circuit, the switching circuit automatically accesses the insulation tester into the test loop, and the first terminal test interface, the second terminal test interface, the network port test interface and the third terminal test interface are utilized to complete the insulation test between lines, specifically, the test process of the insulation test between the lines can include the following steps:
firstly, the insulation tester receives an insulation test instruction and respectively sends insulation test signals to the D terminal test interface, the P terminal test interface and the network port test interface. Then, the insulation test signal enters the cage of the target controller through the D terminal corresponding to the D terminal test interface, the P terminal corresponding to the P terminal test interface and the network port corresponding to the network port test interface.
In the embodiment of the invention, the inside of the absolute limit tester comprises: the device comprises a strong current controller, a signal collector and a test signal generator, wherein the strong current controller is used for converting an input 220V alternating current power supply into a test power supply, namely a direct current strong current power supply, such as a DC500V power supply, and sending the strong current to the test signal generator; the test signal generator sends a negative polarity test strong current to the core wire to be tested after receiving the insulation test command: negative DC500V, sending a positive polarity test strong current to the remaining core wires as: a positive DC 500V; the signal collector is used for collecting current values between the core wire to be tested and other core wires, the resistance tester sends the sampled current values to the CPU, and the CPU judges whether the insulation performance between the cable wires meets the requirements or not by combining with criteria.
And secondly, the insulation tester samples the insulation test signal fed back by the cage of the target controller through the switching circuit interface, and takes the insulation test strong current sent to the target controller and the insulation test signal fed back by the target controller as test data.
103b, when the central processing unit is controlled to send a resistance test instruction to the switching circuit, the switching circuit automatically accesses the resistance tester into the test loop, the first terminal test interface, the second terminal test interface, the network port test interface and the third terminal test interface are utilized to complete the contact resistance test, and test data corresponding to the resistance test instruction are output.
In the embodiment of the present invention, explained in conjunction with fig. 1, after the target type of the target controller is selected by operation on the display screen, the central processing unit is triggered to issue a test command. When the control central processing unit sends the resistance test instruction to the switching circuit, the switching circuit automatically accesses the resistance tester into the test loop, and the first terminal test interface, the second terminal test interface, the network port test interface and the third terminal test interface are utilized to complete the contact resistance test, and specifically, the test process of the contact resistance test can include the following steps:
firstly, the resistance tester receives a resistance test instruction and respectively sends resistance test signals to the D terminal test interface, the P terminal test interface and the network port test interface. Then, the resistance test signal enters the cage of the target controller through the D terminal corresponding to the D terminal test interface, the P terminal corresponding to the P terminal test interface, and the net port corresponding to the net port test interface.
In the embodiment of the invention, the resistance tester internally comprises: the weak current controller is used for connecting weak current of the weak current input port and sending the weak current to the test signal generator; after receiving the test command, the test signal generator sends a test signal to the core wire to be tested of the D terminal, the P terminal and the network port test terminal; the signal collector receives a test signal through the A terminal. The resistance tester sends a test signal sampled by the signal collector to the CPU, and the CPU judges that the OC cage has the problems of wrong lines, mixed lines, leakage lines, overlarge contact resistance and the like by combining with the criterion.
And secondly, the resistance tester receives a resistance test signal fed back by the cage of the target controller through the A terminal test interface, and the resistance test signal sent to the target controller before and the resistance test signal fed back by the target controller are used as test data.
Furthermore, in the embodiment of the invention, the checking tool can adopt a redundancy structure design, so that two-way comparison checking and data transmission are realized, and the accuracy of the test data can be greatly improved. The specific statement is as follows:
as shown in fig. 1, the display screen performs data communication with the central processing unit through a Serial Bus (Serial Bus), the central processing unit includes a main processor and a sub-processor, and then correspondingly controls the central processing unit to send a test instruction to the switching circuit, the main processor and the sub-processor will respectively send a test instruction to the switching circuit, it should be noted that the related control operation executed by the sub-processor is equivalent to a checking operation executed as the main processor to execute the related control operation, and therefore the sub-processor needs to execute the same operation as the main processor to achieve the checking purpose. For example: for the inter-line insulation test, the master processor and the slave processor are controlled to respectively send insulation test instructions to the switching circuit, the switching circuit automatically accesses the insulation tester into the test loop according to each insulation test instruction, then the inter-line insulation test corresponding to the insulation test command sent by the master processor is respectively completed, and meanwhile the inter-line insulation test corresponding to the insulation test command sent by the slave processor is also needed to be completed.
For another example: for the contact resistance test, the master processor and the slave processor are controlled to respectively send resistance test instructions to the switching circuit, the switching circuit automatically connects the resistance tester to the test loop according to each resistance test instruction, and then the line-to-line resistance test corresponding to the resistance test instruction sent by the master processor is respectively completed, and meanwhile the line-to-line resistance test corresponding to the resistance test instruction sent by the slave processor is also required to be completed.
104a, the central processing unit outputs a first test result according to the preset criterion corresponding to the target type and the test data corresponding to the insulation test instruction, and feeds back and displays the first test result on the display screen.
In the embodiment of the invention, the checking tool adopts a redundant structure design, namely the central processing unit comprises a main processing unit and a secondary processing unit, and the main processing unit and the secondary processing unit are controlled to respectively send the insulation test instruction to the switching circuit. The test data sent by the insulation tester to the cpu via the heavy BUS should include: the test data corresponding to the insulation test command triggered by the master processor and the test data corresponding to the insulation test command triggered by the slave processor.
Accordingly, the central processing unit compares whether the test data corresponding to the insulation test instruction triggered by the main processor is consistent with the test data corresponding to the insulation test instruction triggered by the auxiliary processor; if so, outputting a test result and feeding back and displaying the test result on a display screen according to test data corresponding to the insulation test instruction triggered by the main processor and a preset criterion corresponding to the target type; if not, judging that the test is abnormal and outputting the abnormal test to a display screen.
104b, the central processing unit outputs a second test result according to the preset criterion corresponding to the target type and the test data corresponding to the resistance test instruction, and feeds back and displays the second test result on the display screen.
In the embodiment of the present invention, as the Redundant structure design given by the verification tool in fig. 2, the test data sent by the resistance tester to the central processing unit through the Redundant BUS should include: the test data corresponding to the resistance test instruction triggered by the master processor and the test data corresponding to the resistance test instruction triggered by the slave processor.
Accordingly, the central processing unit compares whether the test data corresponding to the resistance test instruction triggered by the main processor is consistent with the test data corresponding to the resistance test instruction triggered by the auxiliary processor; if yes, outputting a test result and feeding back and displaying the test result on a display screen according to test data corresponding to the resistance test instruction triggered by the main processor and a preset criterion corresponding to the target type; if not, judging that the test is abnormal and outputting the abnormal test to a display screen.
Further, the structural design of the verification tool provided by the embodiment of the present invention further includes: and the USB interface is used for providing connection to copy a test result corresponding to the inter-wire insulation test or a test result corresponding to the contact resistance test. In the embodiment of the invention, the display screen receives the test result fed back by the central processing unit, the test report can be generated by using the preset template, and the test report can be conveniently led out at any time by using the USB interface.
In an embodiment of the present invention, the target controller is at least one of: a point switch controller, a signal machine controller, a track circuit controller, a coding equipment controller and a zero-dispersion equipment controller. Specifically, in the embodiment of the present invention, the specific implementation process of automatically verifying the cage wiring of the target controller as shown in fig. 2 is elaborated by exemplifying different types of target controllers, where the adopted preset judgment basis is also different for the different types of target controllers:
example 1, if the target controller is an ac switch machine controller, the specific implementation of automatically verifying the ac switch machine controller cage wiring is as follows:
in the embodiment of the present invention, a schematic diagram of a D terminal structure is illustrated, as shown in fig. 3, the D terminal is divided into three rows a, b, and c, each row is wired in a full-scale manner, and row a is illustrated in fig. 3.
As shown in fig. 3, of the D terminal: a1, a5 (corresponding to X1 of a switch control circuit), a7, a11 (corresponding to X2 of the switch control circuit), a13, a17 (corresponding to X3 of the switch control circuit), c1, c5 (corresponding to X4 of the switch control circuit), c7, c11 (corresponding to X5 of the switch control circuit), and a24, e24, a26, e26, a28, e28, a30, e30, a32, e32 of An A system \ B system 5 block controller in the cage as shown in FIG. 4, which correspond to the connector of the A system \ B system 5 block controller in the cage, which is a, c, e3 column in sequence, when sending test signals to the D terminal, the corresponding interfaces in the double-system cage should be able to receive test signals at the same time, X1, X2, X3, X4, X5 are AC interfaces for controlling the switch and outputting three-phase communication signals to the switch;
as shown in fig. 5, of the PA \ PB terminal: the 1-2 ports correspond to a2 and e4 of an A-1-A-5 \ B1-B5 (A1-A5 \ B1-B5 corresponds to a connector of an A system \ B system 5 block controller in the cage) on the inner side of the cage in sequence, a2 and e4 of A1-A5 can receive test signals when sending test signals to the PA 1-2 ports, a2 and e4 of B1-B5 can receive the test signals when sending the test signals to the PB 1-2 ports, and a2 and e4 switch controllers represent electric input ports;
as shown in fig. 5, of the PA \ PB terminal: the 3 ports are respectively communicated with a18 and e18 of cages A1-A5 \ B1-B5, the 4 ports are respectively communicated with a16 and e16 of cages A1-A5 \ B1-B5, the 5 ports are respectively communicated with a14 and e14 of cages A1-A5 \ B1-B5, and the 6 ports are respectively communicated with e12 of cages A1-A5 \ B1-B5.
Example 2, if the target controller is a dc switch machine controller, the specific implementation process of automatically verifying the cage wiring of the dc switch machine controller is as follows:
as shown in fig. 3, of the D terminal: c1, C3, C5, C7, C9 and C11 (respectively corresponding to X1 to X6 of a switch machine control circuit and used for actuating a switch machine and communicating with a switch machine representation circuit) correspond to D22, D14, D6, D26, D18 and D10 (connected with a direct current switch machine controller and used for outputting switch machine actuation electricity and communicating with a switch machine representation circuit) of An/Bn (An/Bn corresponds to a connector of An a system/B system 5 block controller in the cage, and a, C and e3 columns) at the inner side of the cage as shown in fig. 4 in sequence, and when a test signal is sent to a D terminal, the inner side interface of the dual-system cage should simultaneously receive the test signal;
as shown in FIG. 5, the PBA \ PBB terminals have: the ports 1-10 correspond to z4 and z8 of A1-A5 \ B1-B5 on the inner side of the cage in sequence, z4 and z8 of A1-A5 can receive test signals when sending test signals to PBA 1-10 ports, z4 and z8 of B1-B5 can receive test signals when sending test signals to PBB 1-10 ports, and PBA \ PBB is used for providing a representation power supply for an A-system direct-current switch controller and a B-system direct-current switch controller;
PDA \ PDB terminal: 1. the 3 ports are respectively communicated with z32 and d30 of cages A1-A5 \ B1-B5, wherein 1 is communicated with z32, and 3 is communicated with d30, when the test signals are sent to the 1 port and the 3 port of the PDA, the z32 and the d30 of the A1-A5 can receive the test signals, when the test signals are sent to the 1 port and the 3 port of the PDB, the z32 and the d30 of the B1-B5 can receive the test signals, and the DPA \ PDB is used for providing an action power supply for the A-series and B-series direct-current switch controllers.
Example 3, if the target controller is a semaphore controller, the specific implementation process for automatically verifying the wiring of the cage of the semaphore controller is as follows:
as shown in fig. 3, of the D terminal: a1, c1, a3, c3, a5, c5, a7, c7, a9, c9, a11, c11 (a 1, c1 are used for controlling the first street lamp, a3, c3 are used for controlling the second street lamp, a5, c5 are used for controlling the third street lamp, a7, c7 are used for controlling the fourth street lamp, a9, c9 are used for controlling the fifth street lamp, a11, c11 are used for controlling the sixth street lamp) and the inner side of the cage as shown in fig. 4, e \ Bn (An \ Bn corresponds to the connector of the a system \ B system 5 in the cage, and the columns a, c, e3 are shared, e10, and e10, and a test signal corresponding to the inner side of the cage;
as shown in fig. 5, of the PA \ PB terminal: the ports 1-2 correspond to a2 and c2 of cages A1-A5 \ B1-B5 in sequence, a2 and c2 of the ports A1-A5 can receive test signals when the test signals are sent to the ports PA 1-2, and a2 and c2 of the ports B1-B5 can receive the test signals when the test signals are sent to the ports PB 1-2. The ports 1 and 2 of the PA \ PB are used for providing a lighting power supply for the A system \ B system annunciator controller;
of the D terminal: c1, a1, c3, a3, c5, a5, c7, a7, c9, a9, c11, a11, c13, a13, c15 and a15 correspond to c1, a1, c3, a3, c5, a5, c7, a7, c9, a9, c11, a11, c13, a13, c15 and a15 of the cage An \ Bn in sequence, and when a test signal is sent to the D terminal, the internal interface of the dual-system cage can receive the test signal at the same time;
of PA \ PB terminal: the 1-2 ports correspond to c2 and a2 of cages A1-A5 \ B1-B5 in sequence, c2 and a2 of A1-A5 can receive test signals when the test signals are sent to the 1-2 ports of the PA, and c2 and a2 of B1-B5 can receive the test signals when the test signals are sent to the PB 1-2 ports;
of PA \ PB terminal: the 3-4 ports correspond to e2 and e4 of cages A1-A5 \ B1-B5 in sequence, e2 and e4 of A1-A5 can receive test signals when the test signals are sent to the 1-2 ports of the PA, and e2 and e4 of B1-B5 can receive the test signals when the test signals are sent to the PB 1-2 ports;
example 4, if the target controller is a coded controller, the specific implementation process for automatically verifying the cage wiring of the coded controller is as follows:
as shown in fig. 3, of the D terminal: a1, a2, a3, a4, a5, a6, a7, a8, a11, a12, a13, a14, a15, a16, a17, a18, c1, c2, c3, c4, c5, c6, B6 (a 6, B72, B6, B72, B72, B6, B72, B6, B6, B72, B6, B6, B3, B72, B72, B3, B72, B3, B72, B3, B3, B6, B3, B6, B3, B3, B3, B3, B6, B3, B3, B, a, c, e, a, c, e, a, c, a) of the columns a, c and e) correspond to each other in sequence, and when a test signal is sent to the D terminal, the inner interface of the dual-system cage can receive the test signal at the same time;
as shown in fig. 5, of the PA \ PB terminal: the ports 1-20 correspond to c2, e2, c4 and e4 of cages A1-A5 \ B1-B5 in sequence, c2, e2, c4 and e4 of A1 can receive test signals in sequence when the test signals are sent to the ports 1-4 of PA in sequence, and c2, e2, c4 and e4 of B1 can receive the test signals in sequence when the test signals are sent to the ports PB 1-4 in sequence; when the test signals are sequentially sent to the 5-8 ports of the PA, c2, e2, c4 and e4 of A2 should be capable of sequentially receiving the test signals, and when the test signals are sequentially sent to the PB 5-8 ports, c2, e2, c4 and e4 of B2 should be capable of sequentially receiving the test signals; when the test signals are sequentially sent to the ports 9-12 of the PA, c2, e2, c4 and e4 of the A3 should be capable of sequentially receiving the test signals, and when the test signals are sequentially sent to the ports PB 9-12, c2, e2, c4 and e4 of the B3 should be capable of sequentially receiving the test signals; when the test signals are sequentially sent to the ports 13-16 of the PA, c2, e2, c4 and e4 of A4 should be capable of sequentially receiving the test signals, and when the test signals are sequentially sent to the ports PB 13-16, c2, e2, c4 and e4 of B4 should be capable of sequentially receiving the test signals; when the test signals are sequentially sent to the ports 17-20 of the PA, the test signals should be sequentially received by c2, e2, c4 and e4 of the A5, and when the test signals are sequentially sent to the ports PB 17-20, the test signals should be sequentially received by c2, e2, c4 and e4 of the B5. The PA/PB is used for providing a coding power supply for the coding controller
Example 5, if the target controller is a null device controller, the specific implementation process for automatically verifying the null device controller cage wiring is as follows:
as shown in fig. 3, of the D terminal: c1, c3, c5, c7, c9 and c11 (c 1 and c3 complete the first path 1 collection or drive, c5 and c7 complete the second path 1 collection or drive, and c9 and c11 complete the third path 1 collection or drive) correspond to a10, a12, a14, a16, a18 and a20 of An/Bn (An/Bn corresponds to the connector of the cage internal A system/B system 5 controller, and the a, c and e3 columns are shared) in sequence as shown in fig. 4, when the test signal is sent to the D terminal, the dual-system cage internal interface can receive the test signal at the same time;
as shown in fig. 5, of the PA \ PB terminal: the ports 1-30 correspond to a22, a24, a26, a28, a30 and a32 of cages A1-A5 \ B1-B5 in sequence, a22, a24, a26, a28, a30 and a32 of A1 can receive test signals when the test signals are sent to the ports 1-6 of PA, and a22, a24, a26, a28, a30 and a32 of B1 can receive the test signals when the test signals are sent to the ports PB 1-6; the method comprises the steps that a22, a24, a26, a28, a30 and a32 of A2 should be capable of receiving test signals when the test signals are sent to ports 7-12 of a PA, and a22, a24, a26, a28, a30 and a32 of B2 should be capable of receiving the test signals when the test signals are sent to ports PB 7-12; the method comprises the steps that a22, a24, a26, a28, a30 and a32 of A3 should be capable of receiving test signals when the test signals are sent to ports 13-18 of a PA, and a22, a24, a26, a28, a30 and a32 of B3 should be capable of receiving the test signals when the test signals are sent to ports PB 13-18; the method comprises the steps that a22, a24, a26, a28, a30 and a32 of A4 should be capable of receiving test signals when the test signals are sent to ports 19-24 of a PA, and a22, a24, a26, a28, a30 and a32 of B4 should be capable of receiving the test signals when the test signals are sent to ports PB 19-24; a22, a24, a26, a28, a30 and a32 of A5 should be capable of receiving test signals when the test signals are transmitted to ports 19-24 of PA, and a22, a24, a26, a28, a30 and a32 of B5 should be capable of receiving test signals when the test signals are transmitted to ports PB 19-24. And the PA \ PB is used for providing a driving power supply for the zero dispersion equipment controller.
Exemplary 6, target controller line to line insulation Performance test
The insulation resistance between the cable wires in the cage of the target controller is not less than 25M omega, and a user can modify the resistance value of the insulation resistance in the criterion according to actual requirements.
When the line-to-line insulation resistance test is carried out, the insulation tester sends negative polarity strong current to the core wire to be tested of the OC cage through the D terminal test interface, the P terminal test interface and the net port test interface, positive polarity strong current is sent to other core wires in sequence, the insulation tester automatically tests the current value between the core wire to be tested and other core wires, the parallel current value sends CPUA and CPUB, the CPU carries out the calculation of the insulation resistance, when the resistance value is smaller than 25M omega 5, the poor insulation is judged, and an alarm prompt is given.
It should be noted that, in the embodiment of the present invention, for the line-to-line insulation test or the contact resistance test, as for the test of the target controller, the principle on which the criterion is adopted in the embodiment of the present invention is as follows:
for insulation test, the insulation tester sends DC500V test power supply to the core wire to be tested and other cables in sequence, when the insulation between the cage wires of the target controller is good, the signal collector should not collect current signals, or the current signals are smaller than the threshold set by the user (the tool judges according to the expected resistance set by the user and combining the sampling signals).
For the resistance test, the resistance value of the core wires with the corresponding relationship in examples 1 to 5 should be smaller than the resistance value set by the user, and when the resistance value is too large (the test signal received by the resistance tester is too small), the contact resistance is determined to be not in accordance with the requirement; when the resistance value is infinite (the resistance tester cannot receive the test signal), the problem of wire breakage is judged to exist; and when the core wire receiving end without the corresponding relation receives the test signal, judging that mixed wires exist.
During the insulation resistance test, as shown in fig. 2, the test interface (D terminal test interface, P terminal test interface, net port test interface) of the insulation tester is connected with the P terminal, D terminal, net port of the target controller cage; the P terminal, D terminal, and net port of the target controller cage are communicated with the a terminal (fig. 4) inside the cage through the internal wiring (part to be measured) of the target controller cage. Taking the core wire corresponding to a1 in fig. 3 as an example, it is required to measure whether the core wire meets the requirement of the insulation resistance between the core wire and any other wire in the target empty controller cage, during the test, the CPU sends a1 core wire test command to the insulation tester, the test signal generator of the insulation tester sends negative polarity test strong current to the D terminal a1 through the switching circuit, and simultaneously sends positive polarity test strong current to other core wires of the target controller cage in sequence, the signal collector samples the a1 terminal at any moment, when the insulation performance is poor, the signal collector can collect current signals, the signal collector sends sampling values to the CPU in real time, and the CPU determines the insulation resistance between the wires by combining the voltage and the sampled current values. And other core wires need to finish the test in turn according to the CPU instruction.
In the embodiment of the invention, the insulation resistance between the cables in the cage of the target controller is not less than 25 MOmega, a user can modify the resistance value of the insulation resistance in the criterion according to actual requirements, the resistance value of the cables in the cage of the target controller is less than 0.1 ohm, and the user can modify the resistance value of the resistance in the criterion according to the actual cable model.
Take the line-to-line insulation test as an example: when the strong current test signal is U, the signal collector of the insulation tester samples a signal A, and the CPU calculates the insulation resistance by combining the test signal and the sampling result.
Taking the contact resistance test as an example: the resistance tester self-resistance R, the contact resistance R, the test signal voltage U, the signal collector sampling signal A, and the CPU combines R, R, U, A to complete the calculation of the contact resistance.
In addition, the embodiment of the present invention further exemplifies a schematic structural diagram of a P-terminal test interface, as shown in fig. 6, the P-terminal is wired in a full-scale manner, and a user of the P-terminal model can freely select. The embodiment of the present invention also illustrates a schematic structural diagram of a socket test interface, as shown in fig. 7, in which an M12 interface is taken as an example, and a crystal head or other interfaces may also be used.
Finally, with reference to the verification tool shown in fig. 2, the embodiment of the present invention further exemplifies a test operation flow, which includes the following steps:
step 1, connecting a D terminal test interface, a P terminal test interface and a network port test interface of a checking tool with a P terminal, a D terminal and a network port of a target controller cage respectively;
step 2, connecting a terminal A test interface of the checking tool to the inner side of a cage of the target controller;
step 3, connecting the high-voltage external power and the low-voltage external power to the verification tool;
step 4, starting the system, operating the display screen to select the type of the target controller, clicking to start testing, and selecting manual testing or automatic traversal testing by an operator;
and 5, automatically giving a test result by the verification tool after the test is finished, storing the test result in a test report form, and copying and storing the test result by an operator.
In summary, an embodiment of the present invention provides an automatic calibration method for target controller cage wiring, where a calibration tool for target controller cage wiring is pre-established in the embodiment of the present invention, and a structural design of the calibration tool at least includes: the display screen, central processing unit, insulation tester, resistance tester, switching circuit, first terminal test interface, second terminal test interface, net gape test interface and third terminal test interface, this first terminal test interface be with the output terminal butt joint of target controller cage, this second terminal test interface be with the power supply terminal butt joint of target controller cage, this third terminal test interface be with the inside terminal butt joint of target controller cage. Therefore, the target type of the target controller can be selected by operating the display screen, the central processing unit can search the preset criterion corresponding to the target type, and after the central processing unit sends out the insulation test instruction or the resistance test instruction, the switching circuit is switched to connect the insulation tester or the resistance tester into the test loop, so that the insulation test and the contact resistance test between the lines can be completed by utilizing different test loops. For both tests, a test signal is sent to a target controller cage through the first terminal test interface, the second terminal test interface and the network port test interface, and a test signal fed back by the target controller cage is obtained through the third terminal test interface to form test data, and the test data is transmitted to the central processing unit, so that the central processing unit outputs a final test result and feeds back the final test result to the display screen according to the test data and a preset criterion corresponding to a target type obtained before. Compared with the prior art, the method and the device solve the problems of low efficiency and high possibility of errors caused by large workload of wiring verification and excessive manual debugging work, automatically complete the wiring verification work of the cage of the target controller in the production stage of a factory by using the built wiring verification tool of the cage of the target controller, automatically verify the wiring, reduce the error risk caused by manual intervention, and are simple and efficient to operate.
The present application is described with reference to flowchart illustrations and/or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the application. It will be understood that each flow and/or block of the flow diagrams and/or block diagrams, and combinations of flows and/or blocks in the flow diagrams and/or block diagrams, can be implemented by computer program instructions. These computer program instructions may be provided to a processor of a general purpose computer, special purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, create means for implementing the functions specified in the flowchart flow or flows and/or block diagram block or blocks.
In a typical configuration, a device includes one or more processors (CPUs), memory, and a bus. The device may also include input/output interfaces, network interfaces, and the like.
The memory may include volatile memory in a computer readable medium, Random Access Memory (RAM) and/or nonvolatile memory such as Read Only Memory (ROM) or flash memory (flash RAM), and the memory includes at least one memory chip. The memory is an example of a computer-readable medium.
Computer-readable media, including both non-transitory and non-transitory, removable and non-removable media, may implement information storage by any method or technology. The information may be computer readable instructions, data structures, modules of a program, or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), Static Random Access Memory (SRAM), Dynamic Random Access Memory (DRAM), other types of Random Access Memory (RAM), Read Only Memory (ROM), Electrically Erasable Programmable Read Only Memory (EEPROM), flash memory or other memory technology, compact disc read only memory (CD-ROM), Digital Versatile Discs (DVD) or other optical storage, magnetic cassettes, magnetic tape magnetic disk storage or other magnetic storage devices, or any other non-transmission medium that can be used to store information that can be accessed by a computing device. As defined herein, a computer readable medium does not include a transitory computer readable medium such as a modulated data signal and a carrier wave.
It should also be noted that the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising an … …" does not exclude the presence of other identical elements in the process, method, article, or apparatus that comprises the element.
As will be appreciated by one skilled in the art, embodiments of the present application may be provided as a method, system, or computer program product. Accordingly, the present application may take the form of an entirely hardware embodiment, an entirely software embodiment or an embodiment combining software and hardware aspects. Furthermore, the present application may take the form of a computer program product embodied on one or more computer-usable storage media (including, but not limited to, disk storage, CD-ROM, optical storage, and the like) having computer-usable program code embodied therein.
The above are merely examples of the present application and are not intended to limit the present application. Various modifications and changes may occur to those skilled in the art. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included in the scope of the claims of the present application.

Claims (8)

1. An automatic verification method for a target controller cage wiring, the method comprising:
set up target controller cage wiring check tool, the structural design of check tool includes at least: the testing device comprises a display screen, a central processing unit, an insulation tester, a resistance tester, a switching circuit, a first terminal testing interface, a second terminal testing interface, a network port testing interface and a third terminal testing interface; the first terminal test interface is in butt joint with an output terminal of a target controller cage, the second terminal test interface is in butt joint with a power supply terminal of the target controller cage, and the third terminal test interface is in butt joint with an internal terminal of the target controller cage;
after the display screen receives an operation instruction for operating and selecting the type corresponding to the target controller, responding to the operation instruction, and determining the target type correspondingly selected by the target controller;
controlling the central processing unit to send an insulation test instruction to the switching circuit, wherein the switching circuit automatically accesses the insulation tester into a test loop, completes an inter-line insulation test by using the first terminal test interface, the second terminal test interface, the network port test interface and the third terminal test interface, and outputs test data corresponding to the insulation test instruction, and the method further comprises the following steps: the insulation tester receives the insulation test instruction and respectively sends a first insulation test signal to the first terminal test interface, the second terminal test interface and the network port test interface; the insulation tester samples a second insulation test signal fed back by a cage of a target controller through a switching circuit interface, and the first insulation test signal and the second insulation test signal are used as test data;
controlling the central processing unit to send a resistance test instruction to the switching circuit, wherein the switching circuit automatically accesses the resistance tester into a test loop, and outputs test data corresponding to the resistance test instruction by using the first terminal test interface, the second terminal test interface, the network port test interface and the third terminal test interface to complete a contact resistance test, and further comprises: the resistance tester receives the resistance test instruction and respectively sends first resistance test signals to the first terminal test interface, the second terminal test interface and the network port test interface; the resistance tester samples a second resistance test signal fed back by a cage of a target controller through a switching circuit interface, and takes the first resistance test signal and the second resistance test signal as test data;
the central processing unit outputs a first test result and feeds back and displays the first test result on the display screen according to a preset criterion corresponding to the target type and test data corresponding to the insulation test instruction;
and the central processing unit outputs a second test result and feeds back and displays the second test result on the display screen according to the preset criterion corresponding to the target type and the test data corresponding to the resistance test instruction.
2. The method of claim 1, wherein the central processor comprises a master processor and a slave processor;
the control the central processing unit sends the insulation test instruction to the switching circuit, including: controlling the master processor and the slave processor to respectively send insulation test instructions to the switching circuit;
the control the central processing unit sends resistance test instruction to the switching circuit, including: and controlling the master processor and the slave processor to respectively send resistance test instructions to the switching circuit.
3. The method of claim 2,
the insulation tester passes through the reduce BUS to the test data that central processing unit sent, include: test data corresponding to the insulation test instruction triggered by the master processor and test data corresponding to the insulation test instruction triggered by the slave processor;
the resistance tester passes through the reduce BUS to the test data that central processing unit sent, include: the test data corresponding to the resistance test instruction triggered by the master processor and the test data corresponding to the resistance test instruction triggered by the slave processor.
4. The method of claim 3, wherein the step of outputting a first test result and displaying the first test result on the display screen in a feedback manner by the central processing unit according to the preset criterion corresponding to the target type and the test data corresponding to the insulation test instruction comprises:
the central processing unit compares whether the test data corresponding to the insulation test instruction triggered by the main processor is consistent with the test data corresponding to the insulation test instruction triggered by the auxiliary processor;
if so, outputting a first test result and feeding back and displaying the first test result on the display screen according to test data corresponding to the insulation test instruction triggered by the main processor and a preset criterion corresponding to the target type;
if not, judging that the test is abnormal and outputting the abnormal test to the display screen.
5. The method of claim 3, wherein the step of outputting a second test result and displaying the second test result on the display screen in a feedback manner by the central processing unit according to the preset criterion corresponding to the target type and the test data corresponding to the resistance test instruction comprises:
the central processing unit compares whether the test data corresponding to the resistance test instruction triggered by the main processor is consistent with the test data corresponding to the resistance test instruction triggered by the auxiliary processor;
if yes, outputting a second test result and feeding back and displaying the second test result on the display screen according to test data corresponding to the resistance test instruction triggered by the main processor and a preset criterion corresponding to the target type;
if not, judging that the test is abnormal and outputting the abnormal test to the display screen.
6. The method of claim 1, wherein the structural design of the verification tool further comprises: a USB interface for providing a connection to copy the first test result or the second test result.
7. The method of claim 2, wherein the central processor is connected to the display screen via a serial bus, the master processor and the slave processors in the central processor operate in parallel, and the test data from the slave processors is used to check the test data from the master processor.
8. The method of any of claims 1 to 7, wherein the target controller is at least one of:
a point switch controller, a signal machine controller, a track circuit controller, a coding equipment controller and a zero-dispersion equipment controller.
CN202111527308.8A 2021-12-15 2021-12-15 Automatic calibration method for cage wiring of target controller Active CN113917234B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111527308.8A CN113917234B (en) 2021-12-15 2021-12-15 Automatic calibration method for cage wiring of target controller

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111527308.8A CN113917234B (en) 2021-12-15 2021-12-15 Automatic calibration method for cage wiring of target controller

Publications (2)

Publication Number Publication Date
CN113917234A CN113917234A (en) 2022-01-11
CN113917234B true CN113917234B (en) 2022-03-15

Family

ID=79249073

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111527308.8A Active CN113917234B (en) 2021-12-15 2021-12-15 Automatic calibration method for cage wiring of target controller

Country Status (1)

Country Link
CN (1) CN113917234B (en)

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01202624A (en) * 1988-02-09 1989-08-15 Mitsubishi Electric Corp Judgement of trouble in measuring controller
CN206431226U (en) * 2016-11-16 2017-08-22 北京铁路信号有限公司 A kind of distribution test device of train control on board equipment
CN109765453A (en) * 2019-03-29 2019-05-17 广东电网有限责任公司 A kind of Protection secondary circuit wiring automatic tester
CN110196381A (en) * 2019-06-26 2019-09-03 北京航天新风机械设备有限责任公司 A kind of cable general purpose automatic test system based on cpci bus
CN112398220A (en) * 2020-10-30 2021-02-23 无锡中科电气设备有限公司 Integrated intelligent testing device for medium-voltage switch of nuclear power station
CN113254291B (en) * 2021-07-15 2022-03-15 卡斯柯信号(北京)有限公司 Trackside equipment simulation quantity testing method

Also Published As

Publication number Publication date
CN113917234A (en) 2022-01-11

Similar Documents

Publication Publication Date Title
CN102854432B (en) Automotive wiring harness detection device
CN104569730B (en) A kind of Cable Testing System applied to moonlet
CN101937038B (en) Intelligent multi-core cable harness detection device
CN101241162B (en) Cable tester
CN104297623A (en) Automatic test system for onboard cable integrity
CN104698326A (en) Intelligent multi-core cable detection device and detection method thereof
CN107292769B (en) Substation reconstruction and extension configuration consistency comparison and verification method based on RCD
CN106443311A (en) Conduction and insulation test system and method of large aircraft automatic system
CN104280648A (en) Automatic adapting cable test device and method
CN103778589A (en) Monitoring method and system of railway signal system
CN104020376A (en) Three-remote automatic testing method for power distribution terminal
CN112034388A (en) Automatic wire harness detection system and detection method
JP2021533719A (en) Devices and methods for testing the contents of switch cabinets after installation according to plan
CN108983019A (en) Cable continuity test method, apparatus and test equipment
CN106602549B (en) Electrical main wiring analysis system, analysis method and operation method
CN101793937B (en) Wire automatic control system for electric control cabinet and detection method thereof
CN103633936A (en) Photovoltaic header box automatic test system
CN113917234B (en) Automatic calibration method for cage wiring of target controller
CN107271854B (en) Dual-redundancy equipotential cable network mixed wire testing device and testing method
CN112578197B (en) Automatic testing system and method for secondary circuit of transformer substation
CN103995207A (en) Three-remote automatic test device for power distribution terminal
CN109634849B (en) Visual signal interaction intelligent substation reconstruction and extension virtual testing device and method
CN112666429B (en) Satellite power supply interface measurement method
CN108226691A (en) A kind of Beam Detector based on wireless communication
KR20180116792A (en) Method for marking area of short current analysis

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant