CN113833020B - Construction method of large fish belly type inclined column structure in underground space - Google Patents

Construction method of large fish belly type inclined column structure in underground space Download PDF

Info

Publication number
CN113833020B
CN113833020B CN202111160389.2A CN202111160389A CN113833020B CN 113833020 B CN113833020 B CN 113833020B CN 202111160389 A CN202111160389 A CN 202111160389A CN 113833020 B CN113833020 B CN 113833020B
Authority
CN
China
Prior art keywords
inclined column
construction
reserved
layer
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111160389.2A
Other languages
Chinese (zh)
Other versions
CN113833020A (en
Inventor
王圣涛
章新生
艾鹏鹏
王明刚
李然
黄永虎
耿大新
朱雄涛
王宁
祝俊华
陈航
唐谟宁
陈俊
李康宁
何元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East China Jiaotong University
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Fifth Engineering Co Ltd of CTCE Group
Original Assignee
East China Jiaotong University
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Fifth Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East China Jiaotong University, China Tiesiju Civil Engineering Group Co Ltd CTCE Group, Fifth Engineering Co Ltd of CTCE Group filed Critical East China Jiaotong University
Priority to CN202111160389.2A priority Critical patent/CN113833020B/en
Publication of CN113833020A publication Critical patent/CN113833020A/en
Application granted granted Critical
Publication of CN113833020B publication Critical patent/CN113833020B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars
    • E04B1/0015Cellars constructed from prefabricated units
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Sustainable Development (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention provides a construction method of a large fish belly type inclined column structure in an underground space. The invention abandons the traditional beam and column system, adopts a fish belly type multi-layer subsection batter post structure, and comprises reserved joints of each layer of batter post and splicing sections of each layer of batter post. The multilayer segmented batter post structure adopts a construction method of combining cover-excavation reverse construction with cover-excavation forward construction, and during construction, reserved joints of each layer of batter post are firstly reversely constructed, and then spliced sections of each layer of batter post are sequentially constructed; the fish belly type inclined columns are symmetrically arranged, so that natural lighting of an underground structure is improved, and the using area of an underground space is increased. The construction method overcomes the defects of narrow construction site, various buildings on the ground at the periphery, complex ground traffic composition and the like, not only facilitates construction, improves the safety of engineering construction, but also shortens the construction period.

Description

Construction method of large fish belly type inclined column structure in underground space
Technical Field
The invention relates to the technical field of building construction, in particular to a construction method of a large fish belly type inclined column structure in an underground space.
Background
Nowadays, as competition between cities and even countries gradually upgrades, competition between the inner regions thereof and the cities becomes more intense, thereby causing urban traffic congestion problems to be increasingly prominent. The traditional transportation hub is lack of characteristics, only meets the requirements of people due to the reasons of monotonous function and structural form and the like, and one of the means for solving the problem is to establish a three-dimensional transportation system, construct an underground comprehensive transportation hub and fully develop and utilize urban underground space resources. However, the underground comprehensive hub development project performed in the busy downtown area of the large city generally has the problems of narrow site, various buildings on the ground around, complex ground traffic composition and the like.
For a large underground transportation junction, how to improve the limited ventilation and lighting and fully utilize the underground use space is often a design focus, but the traditional beam-column structure stress system cannot well meet the design requirements of functionality and attractiveness of the underground transportation junction. The complex pavement untwining conditions, the restriction of the harsh surrounding environment, and the conflict between the unique structure of the underground structure and the reverse construction method in the construction process of adopting the cover-excavation reverse construction method, further present great challenges to the construction method of the underground structure.
Disclosure of Invention
In order to meet the design requirements of limited underground space conditions of underground transportation hubs in modern building design, such as openness, space effect and the like, and improve the ventilation and lighting conditions, the traditional beam and column system is abandoned.
The core technology of the invention is that when the cover-and-dig reverse construction method is adopted, the reserved joints of the inclined columns at each layer are reversely constructed, then the splicing sections of the inclined columns at each layer are sequentially constructed, and the reserved joints of the inclined columns at each layer and the splicing sections of the inclined columns form the fish belly type multi-layer segmented inclined column. The inclination angle of the multilayer subsection batter post is determined before the construction of the batter post splicing section, the construction is greatly simplified, and meanwhile, the fish-bellied batter post symmetrical arrangement mode is more beneficial to natural lighting of an underground structure.
The invention is realized by the following technical scheme:
a construction method of a large fish belly type inclined column structure in underground space comprises the following steps:
1) Construction preparation: processing the section steel beam and the inclined column reserved joint according to the designed size in a processing plant, and connecting the inclined column reserved joint and the main structure beam into a whole;
2) Constructing a cushion layer and an embedded part: performing earth excavation in the cover plate area, and immediately pouring cushion concrete after the foundation pit of the cover plate is excavated and the bottom is cleared; constructing and excavating a foundation serving as an erection support below the inclined column, then paying off and installing a pre-embedded steel plate in the foundation serving as the erection support, connecting the bottoms of the steel plates by using reinforcing steel bars, and pouring concrete;
3) Measuring and lofting: modeling the reserved joints of the section steel beams and the inclined columns, calculating the coordinates of the installation joints according to the design coordinates and the elevation of the installation positions, and taking the calculated coordinates of the installation joints as the basis for measuring and paying off after the calculated coordinates of the installation joints are consistent with the coordinates called out by modeling; welding a positioning steel plate at the installation side line of the measurement popup, then installing each layer of inclined column reserved joint, measuring the upper and lower end control points of the inclined column reserved joint after the installation is finished, and manufacturing each layer of inclined column splicing section according to the control points;
4) Hoisting reserved joints of the section steel beams and the inclined columns: installing the inclined column reserved joint to a design position according to the lofting position in the step 3), and processing and installing the section steel beam according to the actual length on site after the inclined column reserved joint is installed;
5) Positioning and reinforcing the reserved joints of the section steel beams and the inclined columns: rechecking and finely adjusting the elevation of the top of the section steel beam and the axis, the verticality and the angle of the reserved joint of the inclined column, and performing reinforcement measures after the positioning is completed; after positioning and reinforcing, rechecking the axes and elevations of the reserved joints of the section steel beams and the inclined columns, and entering the next step after no errors exist;
6) Construction of the inclined column splicing section: after the main structure is constructed, constructing the splicing sections of the inclined columns by adopting a cover-excavation method; and hoisting the inclined column splicing section to the splicing section position, adjusting the inclined column splicing section to be completely aligned with the inclined column reserved joint by using the reserved limiting clamp plate, and performing full penetration welding after accurate positioning.
As a further improvement of the technical scheme, the reserved joints of the inclined columns and the splicing sections of the inclined columns form a fish belly type multi-layer subsection inclined column.
As a further improvement of the technical scheme, the fish belly type symmetrical arrangement formed by the multilayer subsection batter posts ensures the natural lighting of the underground space to the maximum extent.
As a further improvement of the technical scheme, the multi-layer subsection batter post adopts a construction method combining cover-excavation reverse construction and cover-excavation forward construction: during construction, the reserved joints of the inclined columns of each layer are firstly reversely constructed, and then the splicing sections of the inclined columns of each layer are sequentially constructed.
Considering that the fish belly type batter posts are large in quantity and weight, and loads are applied to each layer of plate, so that the stress of the temporary posts is overlarge; the reserved joints of the inclined columns of each layer are reversely made, and then the splicing sections of the inclined columns of each layer are covered and dug, so that the cross operation in the inclined column splicing process can be reduced, the operation interference between an upper layer and a lower layer in the multilayer splicing process can be reduced, the construction operation surface can be effectively increased, and the engineering quality can be obviously improved.
As a further improvement of the technical scheme, temporary stand columns are arranged between the layers of plates, and temporary support is provided for the main structure before the construction of the inclined column splicing section.
As a further improvement of the technical scheme, a skylight made of transparent materials is arranged between the fish-bellied inclined columns at the top plate, and the purpose is to improve the natural lighting of the underground structure.
As a further improvement of the technical scheme, the earth excavation of the construction cover plate area in the step 2) is carried out for 4m until the earth excavation reaches 2.2m below the top plate, and the rest layers are excavated to 2m below the layer plate; and excavating the cover plate foundation pit to a position close to the substrate by 200 mm.
As a further improvement of the technical scheme, the 'foundation' used as the erection support in the step 2) is 3000mm × 3000mm, the depth is 400mm, and phi 14@200 steel bar meshes are distributed inside; pre-embedding 4 steel plates with the size of 1000mm 600mm 16mm at the top of the foundation in advance; simultaneously, the support steel plates with the thickness of 600mm 16mm are embedded in the oblique direction of the oblique columns and the direction of the section steel beams respectively.
As the further improvement of the technical scheme, the step 5) after fine adjustment, the deviation of the top elevation of the steel beam is required to be ensured within +/-2 mm, the deviation of the axis of the reserved joint of the inclined column is less than 3mm, and the verticality of the reserved joint of the inclined column is less than 1mm.
As a further improvement of the above technical solution, the specific operation of hoisting and moving the spliced section of the batter post to the spliced section position in step 6) is to horizontally pull the upper end and the lower end of the spliced section of the batter post respectively by using two hoisting points arranged on the steel beam, slowly unload the lifting hook after moving to the spliced section position, and tighten the horizontal pull ropes at the upper end and the lower end to position the spliced section of the batter post.
As a further improvement of the technical scheme, in the step 6), before the inclined column splicing section is welded, an operation frame needs to be erected according to construction requirements, so that the inclined column splicing section is convenient to install and weld.
As a further improvement of the technical scheme, the section steel beam is fixed by the limiting blocks when the section steel beam and the inclined column reserved joint are welded, the side lines of the steel column and the steel beam are positioned firstly during installation, the bottom of the steel column is positioned by the limiting plates, and finally elevation rechecking is required to be carried out, so that the accuracy of the elevation and the plane position is ensured.
Compared with the prior art, the invention has the beneficial effects that:
1. according to the invention, a coordinate system is established by utilizing CAD (computer-aided design) and the position coordinates of each control point at the top and the bottom of the reserved joint of the batter post are obtained by measuring through a total station, so that the batter post is accurately positioned and lofted, and the projection of each control point at the top of the batter post on the floor is guided onto the template support frame by adopting an optical plummet or a plumb bob to determine the position of the side line of the template, so that the positioning and mounting efficiency of the batter post is improved.
2. The invention adopts a construction method combining cover-excavation reverse-construction and cover-excavation forward-construction, overcomes the defects of narrow construction site, various buildings on the ground at the periphery, complex ground traffic composition and the like, and shortens the construction period.
3. According to the invention, the batter post is designed into a multi-layer sectional form, so that the construction is greatly facilitated, and the safety of engineering construction is improved. Meanwhile, the fish belly type inclined columns are symmetrically arranged, so that sufficient upper space is provided for the underground structure, the using area of the underground space is increased, and natural lighting is increased.
Drawings
FIG. 1 is a flow diagram of the construction method of the large fish belly type inclined column structure in the underground space.
FIG. 2 is a three-dimensional view of the large fish belly type inclined column structure of the underground space.
FIG. 3 is a cross section view of the large fish belly type inclined column structure of the underground space.
FIG. 4 is a three-dimensional schematic diagram of a splicing section of the large fish belly type batter post structure of the underground space without installing the batter post.
FIG. 5 is a cross section view of a section of the large fish belly type batter post structure of the underground space without installing batter posts.
In the figure: 2. a section steel beam; 3. a temporary upright post; 4. a transparent material; 11. an oblique column splicing section; 12. the inclined column is provided with a joint.
Detailed Description
The technical solutions in the embodiments of the present application will be described clearly and completely with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are only some embodiments of the present application, and not all embodiments. The following description of at least one exemplary embodiment is merely illustrative in nature and is in no way intended to limit the application, its application, or uses. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
The relative arrangement of the components and steps, the numerical expressions, and numerical values set forth in these embodiments do not limit the scope of the present application unless specifically stated otherwise. Meanwhile, it should be understood that the sizes of the respective portions shown in the drawings are not drawn in an actual proportional relationship for the convenience of description. Techniques, methods, and apparatus known to those of ordinary skill in the relevant art may not be discussed in detail but are intended to be part of the specification where appropriate. In all examples shown and discussed herein, any particular value should be construed as merely illustrative, and not limiting. Thus, other examples of the exemplary embodiments may have different values. It should be noted that: like reference numbers and letters refer to like items in the following figures, and thus, once an item is defined in one figure, further discussion thereof is not required in subsequent figures.
In the description of the present application, it should be understood that the terms "first", "second", etc. are used to define the components, and are used only for the convenience of distinguishing the corresponding components, and if not otherwise stated, the terms have no special meaning, and thus, should not be construed as limiting the scope of the present application.
In the description of the present application, it is to be understood that the orientation or positional relationship indicated by the directional terms such as "front, rear, upper, lower, left, right", "lateral, vertical, horizontal" and "top, bottom", etc., are generally based on the orientation or positional relationship shown in the drawings, and are used for convenience of description and simplicity of description only, and in the case of not making a reverse description, these directional terms do not indicate and imply that the device or element being referred to must have a particular orientation or be constructed and operated in a particular orientation, and therefore, should not be considered as limiting the scope of the present application; the terms "inner and outer" refer to the inner and outer relative to the profile of the respective component itself.
The present application is described in detail below with reference to fig. 2.
Fig. 2 is a three-dimensional view of the large fish belly type inclined column structure of the underground space of the invention, which comprises structural steel beams 2 of each layer, temporary upright columns 3, inclined column splicing sections 11 of each layer and reserved joints 12 of inclined columns of each layer besides a main body top plate, a bottom plate and laminated plates of each layer, wherein:
the section steel beam 2: each layer of section steel beam 2 is connected with the top plate, the bottom plate and each layer of layer plate;
the temporary upright post 3: the temporary upright posts 3 are arranged among the top plate, the bottom plate and each layer of laminate;
transparent material 4: the skylight of the transparent material 4 is arranged between the fish belly type inclined columns at the top plate;
inclined column reserved joint 12: welding reserved joints 12 of the inclined columns of each layer with the section steel beams 2 of each layer;
inclined column splicing section 11: and the splicing sections 11 of the inclined columns of each layer and the reserved joints 12 of the inclined columns of each layer are welded to form the fish belly type multi-layer subsection inclined column.
Examples
A construction method of a large fish belly type inclined column structure in underground space comprises the following steps:
the method comprises the following steps:
construction preparation: the construction drawing and the design files thereof are familiar and examined, the construction organization design is well finished, the section steel beam 2 and the inclined column reserved joint 12 are processed in a professional steel structure processing field, and the inclined column reserved joint 12 and the main structure beam are connected into a whole.
Step two:
constructing a cushion layer and an embedded part:
1. earth excavation: the earth excavation above the main structure cover plate is constructed from west to east by adopting an open excavation method; excavating earth in the construction cover plate area for about 4m until 2.2m below the top plate, and excavating the rest layers to 2m below the layer plate;
2. cushion layer construction: when the excavation of the cover plate foundation pit is close to the foundation by 200mm, manually matching with an excavator to clear the bottom, immediately constructing cushion concrete after clearing the bottom, and pouring C20 concrete into the cushion with the pouring thickness of 150mm;
3. constructing an inclined column foundation: during construction, an enlarged foundation is constructed below the inclined column, wherein the foundation is 3000mm × 3000mm, the depth is 400mm, a phi 14@200 steel bar mesh is arranged inside the foundation, 4 foundation steel plates are pre-embedded at the top of the foundation in advance, and the size of each steel plate is 1000mm × 600mm × 16mm; simultaneously, embedding 600mm 16mm supporting steel plates in the oblique direction of the oblique columns and the 2 direction of the section steel beams respectively to serve as foundations for erection and support;
4. positioning construction of the embedded steel plate: after foundation excavation is finished, firstly paying off and drawing the position of an embedded steel plate in a foundation by a measuring group, then driving 4 phi 22 steel bars with the length not less than 1m into a soil layer at 4 corner points of the steel plate, then installing the embedded steel plate, measuring and adjusting the whole process of the measuring group in the installation process, connecting the bottom of the steel plate into a whole by adopting the steel bars after the installation of 4 embedded steel plates is finished, and then pouring foundation concrete.
Step three:
measuring and lofting:
1. and (3) coordinate calculation: the method comprises the steps of modeling the section steel beam 2 and the inclined column reserved joint 12, calling any position of the inclined column reserved joint 12, calculating the position of any elevation and the coordinates of the position of the inclined column reserved joint 12 manually, and calculating the coordinates of four point positions at the upper end and the lower end of each mounting joint according to the design coordinates and the mounting position elevation. After the calculated coordinates are completely consistent with the coordinates called out by modeling, the coordinates are used as the basis for measuring and paying off;
2. marking the corner points of the section steel beam 2 or the inclined column reserved joint 12 to be constructed on the cushion layer by a measuring group, measuring the actual cushion layer elevation to determine the temporary supporting height, popping out the mounting side line of the inclined column reserved joint 12 by construction operators according to the axis released by the measuring group by a ruler amount, and welding a positioning steel plate at the mounting side line. After the installation of each layer of inclined column reserved joint 12 is finished, 4 control points are measured at the upper end and the lower end of each layer of inclined column reserved joint 12 respectively, and the inclined column splicing section 11 is manufactured through blanking of a manufacturer according to the actual measurement condition.
Step four:
hoisting each layer of section steel beam 2 and the inclined column reserved joint 12: the batter post is reserved and is connected 12 and adopt 50t truck crane to hoist, reserves the batter post and connects 12 hoist to take horizontal rotation function's ground tank removal instrument on, power adopts 5t hoist engine to pull, and ground tank removal instrument adopts the channel-section steel to do the track, moves according to lofting position, reserves the batter post and connects 12 fortune to the design position and install. And after the inclined column reserved joint 12 is installed, machining the section steel beam 2 according to the actual length on site, and installing by using a crane after machining.
Step five:
and (3) positioning and reinforcing the joints 12 of the section steel beams 2 and the inclined columns: after the inclined column reserved joint 12 is in place, on-site measuring personnel recheck the elevation and the axis of the beam top and the perpendicularity and the angle of the inclined column reserved joint 12 by using a total station, fine adjustment is carried out on the axis of the inclined column reserved joint 12 by adopting a method of matching a crane with manual left-right moving, the axis deviation is ensured to be less than 3mm, fine adjustment is carried out on the elevation of the beam top by adopting a temporary support, the design elevation is finally reached, the deviation of the elevation of the beam top is ensured to be +/-2 mm, and the perpendicularity of the inclined column reserved joint 12 is less than 1mm. After the inclined column reserved joint 12 is positioned and finished, the inclined column reserved joint 12 needs to be reinforced, an H-shaped steel support column is adopted at the end of the section steel beam 2 to support, and the section steel beam is ensured to be stable and does not shake.
Step six:
and (3) measurement and rechecking: and after the section steel beam 2 and the inclined column reserved joint 12 are reinforced, rechecking the axes and the elevations of the section steel beam 2 and the inclined column reserved joint 12 again by using a total station, and entering the next procedure after the situation that the axes and the elevations are correct is determined.
Step seven:
and (3) constructing an inclined column splicing section 11: after the construction of all the main structures in the underground space is completed, the inclined column splicing sections 11 are sequentially operated.
1. The inclined column splicing section 11 is vertically hoisted by utilizing a preset lifting hook of the upper steel beam;
2. respectively horizontally pulling the upper end and the lower end of the inclined column splicing section 11 by utilizing two lifting points arranged on the upper steel beam, and gradually shifting to the splicing section; the vertical hook portion unloads slowly.
3. The upper end and the lower end of the horizontal pulling rope are tightened, the inclined column splicing section 11 is slowly put in place, the inclined column splicing section 11 is adjusted by means of reserved limiting clamping plates and the like and is completely aligned with the inclined column reserved joint 12, the inclined column reserved joint 12 and the inclined column splicing section 11 are welded by full penetration welding after being accurately positioned, welding quality is guaranteed to be qualified, and a welding seam is 100% detected.
In the seventh step of the present embodiment, an operation frame is set up according to the construction requirements before the welding of the inclined column splicing section 11, which is convenient for the installation and welding of the inclined column splicing section 11. The shaped steel beam 2 is fixed by a limiting block when the shaped steel beam 2 and the inclined column reserved joint 12 are welded, the welded shaped steel beam is transported to the site to be installed, the side lines of the steel column and the shaped steel beam 2 are positioned firstly during installation, the bottom of the steel column is positioned by a limiting plate, and finally elevation rechecking is carried out to ensure that the elevation and the plane position are accurate and correct. Temporary columns 3 are installed between the laminates to provide temporary support for the structure before the construction of the batter post splicing section 12. A skylight made of transparent materials 4 is arranged between the fish belly type inclined columns at the top plate, and the purpose is to naturally collect light of an underground structure.
The construction method of the large fish belly type inclined column structure in the underground space overcomes the defects of narrow construction site, multiple surrounding buildings, complex ground traffic composition and the like, has the advantages of high safety, short construction period, high construction efficiency, low influence on the surrounding environment and the like, and is suitable for engineering development of the current downtown areas of large cities with fierce competition and traffic jam. According to the invention, the reserved joints of the inclined columns of each layer are firstly reversely made, so that the horizontal deformation of the enclosure structure in the construction process is reduced, the engineering quantity of temporary facilities is reduced, and the influence on the surrounding environment is reduced; then, the inclined column splicing sections of each layer are sequentially fabricated, so that the operation interference in the splicing process is reduced, the operation surface is increased, and the construction efficiency is improved; the reserved joints of the inclined columns of all layers and the splicing sections of the inclined columns of all layers form the fish-bellied multi-layer subsection inclined column, and the multi-layer subsection form of the inclined columns facilitates construction and also improves construction safety. The large fish belly type inclined column structure in the underground space constructed by the construction method has the advantages of large underground use space, good natural lighting and good application prospect.
The above-described embodiments are only preferred embodiments of the present invention and are not intended to limit the present invention. Various changes and modifications may be effected therein by one skilled in the art without departing from the spirit and scope of the invention, and any such changes, substitutions, improvements and the like are intended to be included within the scope of the invention.

Claims (7)

1. A construction method of a large fish belly type inclined column structure in an underground space is characterized by comprising the following steps:
1) Construction preparation: processing the section steel beam and the inclined column reserved joint in a processing plant according to the design size, and connecting the inclined column reserved joint and the section steel beam into a whole;
2) Constructing a cushion layer and an embedded part: performing earth excavation in the cover plate area, and immediately pouring cushion concrete after the foundation pit of the cover plate is excavated and the bottom is cleared; constructing and excavating a foundation serving as an erection support below the inclined column, then paying off and installing a pre-embedded steel plate in the foundation serving as the erection support, connecting the bottoms of the steel plates by using reinforcing steel bars, and pouring concrete;
3) Measuring and lofting: modeling the section steel beam and the inclined column reserved joint, calculating the coordinates of the inclined column reserved joint according to the design coordinates and the mounting position elevation, and taking the calculated coordinates of the inclined column reserved joint as the basis of measurement and paying-off when the coordinates of the inclined column reserved joint are consistent with the coordinates set out by modeling; welding a positioning steel plate at the installation sideline where the inclined columns pop out in the measuring process, then installing reserved joints of the inclined columns at all layers, measuring control points at the upper end and the lower end of the reserved joints of the inclined columns after the installation is finished, and manufacturing splicing sections of the inclined columns at all layers according to the control points;
4) Hoisting the reserved joints of the section steel beams and the inclined columns: installing the inclined column reserved joint to a design position according to the lofting position in the step 3), and processing and installing the section steel beam according to the actual length on site after the inclined column reserved joint is installed;
5) Positioning and reinforcing the reserved joints of the section steel beams and the inclined columns: rechecking and finely adjusting the top elevation of the section steel beam and the axis, the verticality and the angle of the reserved joint of the inclined column, and performing reinforcement measures after the positioning is finished; after positioning and reinforcing, rechecking the axes and the elevations of the reserved joints of the section steel beams and the inclined columns, and entering the next step after no errors exist;
6) Construction of the inclined column splicing section: after the main structure is constructed, constructing the splicing sections of the inclined columns by adopting a cover-excavation method; hoisting the inclined column splicing section to the splicing section, adjusting the inclined column splicing section to be completely aligned with the inclined column reserved joint by using the reserved limiting clamping plate, and performing full penetration welding after accurate positioning;
each layer batter post reserve joint and each layer batter post concatenation section constitute multilayer segmentation batter post, and multilayer segmentation batter post adopts the lid to dig contrary to do and cover digs the construction method who makes the combination in the same direction as: during construction, connectors are reserved on each layer of batter post in the reverse direction, and then splicing sections of each layer of batter post are sequentially constructed; the multilayer subsection batter posts form fish belly type symmetrical arrangement, and natural lighting of underground space is guaranteed to the greatest extent.
2. The method for constructing the large fish belly type inclined column structure in the underground space according to claim 1, wherein temporary columns are installed between the floors, and temporary supports are provided for the main body structure before the construction of the splicing sections of the inclined columns.
3. The construction method of the large fish belly type inclined column structure in the underground space according to claim 1, wherein the earth excavation of the construction cover plate area in the step 2) is carried out for 4m until the earth excavation reaches 2.2m below the top plate, and the rest layers are excavated until the bottom of the layer plate reaches 2 m; and excavating the cover plate foundation pit to a position close to the substrate by 200 mm.
4. The construction method of the large fish belly type inclined column structure in the underground space according to claim 1, wherein the 'foundation' used as the erection support in the step 2) is 3000mm x 3000mm, the depth is 400mm, and a phi 14@200 steel mesh is arranged inside; pre-embedding 4 steel plates with the size of 1000mm 600mm 16mm at the top of the foundation in advance; simultaneously, the support steel plates with the thickness of 600mm 16mm are embedded in the oblique direction of the oblique columns and the direction of the section steel beams respectively.
5. The construction method of the large fish belly type inclined column structure in the underground space according to claim 1, wherein after the fine adjustment in the step 5), the deviation of the elevation of the steel beam top is within +/-2 mm, the deviation of the axis of the reserved joint of the inclined column is less than 3mm, and the verticality of the reserved joint of the inclined column is less than 1mm.
6. The construction method of the large fish belly type inclined column structure in the underground space according to claim 1, wherein the specific operation of hoisting and moving the inclined column splicing section to the splicing section position in the step 6) is to horizontally pull the upper end and the lower end of the inclined column splicing section by using two hoisting points arranged on the section steel beams, move the section steel beams to the splicing section position, unload the lifting hooks slowly, and tighten the horizontal pulling ropes at the upper end and the lower end to position the inclined column splicing section.
7. The construction method of the large fish belly type inclined column structure in the underground space according to claim 1, wherein the shaped steel beam is fixed by a limiting block when being welded with the inclined column reserved joint, the inclined column reserved joint and the side line of the shaped steel beam are positioned when being installed, the bottom of the inclined column reserved joint is positioned by a limiting plate, and finally elevation rechecking is carried out to ensure that the elevation and the plane position are accurate.
CN202111160389.2A 2021-09-30 2021-09-30 Construction method of large fish belly type inclined column structure in underground space Active CN113833020B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111160389.2A CN113833020B (en) 2021-09-30 2021-09-30 Construction method of large fish belly type inclined column structure in underground space

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111160389.2A CN113833020B (en) 2021-09-30 2021-09-30 Construction method of large fish belly type inclined column structure in underground space

Publications (2)

Publication Number Publication Date
CN113833020A CN113833020A (en) 2021-12-24
CN113833020B true CN113833020B (en) 2022-11-01

Family

ID=78967775

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111160389.2A Active CN113833020B (en) 2021-09-30 2021-09-30 Construction method of large fish belly type inclined column structure in underground space

Country Status (1)

Country Link
CN (1) CN113833020B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114232786A (en) * 2021-12-30 2022-03-25 中铁四局集团第五工程有限公司 Underground structure type steel concrete inclined column construction method
CN114673169A (en) * 2022-05-13 2022-06-28 华东交通大学 Multi-layer large-span deep foundation pit cover-excavation forward-backward combined construction method for urban core area
CN115748984B (en) * 2022-11-28 2024-04-26 中铁建设集团有限公司 Reverse operation construction method for large-section fusiform double-inclined column
CN115637872B (en) * 2022-12-01 2023-03-21 北京市第三建筑工程有限公司 Construction method for installing cross-floor inclined column in existing floor

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101687495B1 (en) * 2015-10-01 2016-12-16 박광호 Partial top-down construction method for building underground structures
CN106284665A (en) * 2016-08-04 2017-01-04 中建钢构有限公司 A kind of tiltedly steel column Double helix space structure and construction method thereof
CN106436760A (en) * 2016-08-12 2017-02-22 武汉志和岩土工程有限公司 Top-down construction method
CN107542268A (en) * 2017-09-30 2018-01-05 中建五洲工程装备有限公司 The reverse construction method of installation of stage steel construction in a kind of grand theater room
CN109025286A (en) * 2018-07-20 2018-12-18 中建三局第三建设工程有限责任公司 A kind of construction method of large span high-altitude three-dimensional canopy of the heavens steel construction
CN112031406A (en) * 2020-08-31 2020-12-04 上海宝冶集团有限公司 Construction method for 360-degree rotary bending of snowmobile ski-racing track

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105298143B (en) * 2015-05-12 2019-06-21 江苏南通六建建设集团有限公司 Polygon hyperboloid open type titanium composite plate curtain wall construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101687495B1 (en) * 2015-10-01 2016-12-16 박광호 Partial top-down construction method for building underground structures
CN106284665A (en) * 2016-08-04 2017-01-04 中建钢构有限公司 A kind of tiltedly steel column Double helix space structure and construction method thereof
CN106436760A (en) * 2016-08-12 2017-02-22 武汉志和岩土工程有限公司 Top-down construction method
CN107542268A (en) * 2017-09-30 2018-01-05 中建五洲工程装备有限公司 The reverse construction method of installation of stage steel construction in a kind of grand theater room
CN109025286A (en) * 2018-07-20 2018-12-18 中建三局第三建设工程有限责任公司 A kind of construction method of large span high-altitude three-dimensional canopy of the heavens steel construction
CN112031406A (en) * 2020-08-31 2020-12-04 上海宝冶集团有限公司 Construction method for 360-degree rotary bending of snowmobile ski-racing track

Also Published As

Publication number Publication date
CN113833020A (en) 2021-12-24

Similar Documents

Publication Publication Date Title
CN113833020B (en) Construction method of large fish belly type inclined column structure in underground space
CN106894639B (en) The hanging reverse construction method of installation of steel construction under a kind of
CN103485549B (en) Based on the localization method to large-scale built-in fitting
CN112900692B (en) Large-span special-shaped steel structure building, supporting device thereof and construction method
CN112627434B (en) Cross construction method for complex V-shaped stiff columns and irregular ring beams of large stadium
CN114232805B (en) Construction method of ultrahigh-height large-span steel concrete beam hanging structure
CN1978838A (en) Construction method for combined V-shape steel pipe concrete pile
CN105863042A (en) All-steel structure building and construction method thereof
CN110344335B (en) Method for constructing steel trestle, initial platform and cofferdam in bridge construction process
CN110303265B (en) Low-temperature storage tank inner tank top plate construction process and low-temperature storage tank construction process
CN114033051A (en) Large-span hyperbolic truss construction process based on steel structure spherical curtain cinema engineering
CN105672314A (en) Method for constructing steel pipe upright pile through semi-reversed-construction method
CN114134928B (en) Construction method of steel pipe column tower crane foundation
CN111119332A (en) Novel electromechanical wire pipe prefabricating and mounting connection construction method for fabricated building
CN215760673U (en) Temporary supporting structure for shuttle-shaped column
CN112012197A (en) Manual hole digging pile and construction method thereof
CN105201107A (en) Construction method for stacked plate type shear wall of underground garage
CN106638645A (en) Layering prefabricated structure and building method of basement bottom board water collection pit reinforcing mesh
CN113338333A (en) Quick mounting method for steel beam plate under cover-excavation top-down condition
CN115341653B (en) Steep gentle slope radian abrupt change multi-curved-surface steel reticulated shell building structure and construction process thereof
US20080006003A1 (en) Method of Constructing Strip Foundations with Longitudinal Socket
CN114411761B (en) Advanced pre-supporting system and method for subway tunnel to be built in new building construction
CN115387207A (en) Shallow covering layer steel-concrete composite pile pier structure and construction method
CN114016518A (en) Underground foundation pit V-shaped column and construction method thereof
CN110258890B (en) Construction method of concrete structure with connected broken line type outer wall and roof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant