CN113802773B - Construction method of large-diameter slow-bonding prestressed tendon in large-span member - Google Patents

Construction method of large-diameter slow-bonding prestressed tendon in large-span member Download PDF

Info

Publication number
CN113802773B
CN113802773B CN202111069697.4A CN202111069697A CN113802773B CN 113802773 B CN113802773 B CN 113802773B CN 202111069697 A CN202111069697 A CN 202111069697A CN 113802773 B CN113802773 B CN 113802773B
Authority
CN
China
Prior art keywords
prestressed
concrete
fixing
reinforcement
tendon
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111069697.4A
Other languages
Chinese (zh)
Other versions
CN113802773A (en
Inventor
张桂军
郭志国
白尧尧
丁国权
陈健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN202111069697.4A priority Critical patent/CN113802773B/en
Publication of CN113802773A publication Critical patent/CN113802773A/en
Application granted granted Critical
Publication of CN113802773B publication Critical patent/CN113802773B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions
    • E04C5/12Anchoring devices
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/162Connectors or means for connecting parts for reinforcements
    • E04C5/163Connectors or means for connecting parts for reinforcements the reinforcements running in one single direction
    • E04C5/165Coaxial connection by means of sleeves
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

The invention relates to a construction method of a large-diameter slow-bonding prestressed tendon in a large-span component. According to the invention, the fixed sleeve and the bar penetrating rod are matched with the bar penetrating mode, so that the correct position of the prestressed bar is ensured, and the bar penetrating construction efficiency is higher. In the invention, the prestressed tendon is restrained by the fixed sleeve so as to ensure that the prestressed tendon is firmly positioned in the construction of the subsequent steps.

Description

Construction method of large-diameter slow-bonding prestressed tendon in large-span member
Technical Field
The invention relates to the technical field of building construction, in particular to a construction method of a large-diameter slow-bonding prestressed tendon in a large-span member.
Background
As a new post-tensioning process, the principle of the slow bonding construction process is that pre-assembled slow bonding prestressed bars (namely steel strand bundles, wherein the strand bundles are coated with a slow-setting adhesive, and the steel strand bundles are wrapped by a corrosion-resistant protective layer) and the non-adhesion property of concrete are utilized to lay the pre-assembled slow bonding prestressed bars in a template together with the non-prestressed bars according to the designed positions, then the concrete is poured, and after the concrete reaches the strength required by the design, the tension and anchor sealing are carried out by utilizing the longitudinal sliding property of the slow bonding prestressed bars in the structure, so that the anchor applies external pressure to the concrete under the action of the internal pressure stress of the prestressed bars, thereby improving the structural performance, prolonging the service life of the structure and reducing the temperature deformation and crack resistance of the whole structure.
When the on-site reinforcing mesh binding operation is carried out in the slow bonding construction process, the HRB type conventional reinforcing mesh is usually bound and formed (the section height of the reinforcing mesh is usually 16-30cm, namely the distance between the thickness of a member plate and a reinforcing protective layer), and then the installation and the laying of the prestressed tendons are started. Different from the conventional steel bar with high rigidity and small deformation in the steel bar penetrating process, the prestressed steel bar processed by the steel strand has certain flexibility, the angle of the end part of the prestressed steel bar is easy to change in the steel bar penetrating process to a preset position, and particularly in a large-span plate component, so that the position of the end part of the prestressed steel bar is often required to be adjusted manually during installation and laying of the prestressed steel bar, the position of the prestressed steel bar is kept correct, and the construction efficiency of the conventional slow bonding construction process is lower.
Disclosure of Invention
Aiming at the problems, the construction method of the large-diameter slow-bonding prestressed tendon in the large-span member is provided, and aims to effectively solve the problems of the prior art.
The invention has the beneficial effects that:
1) According to the invention, the fixed sleeve and the bar penetrating rod are matched with the bar penetrating mode, so that the correct position of the prestressed bar is ensured, and the bar penetrating construction efficiency is higher.
Drawings
Fig. 1 is a schematic structural view of a tendon-threading assisting device provided in an embodiment of the present invention;
fig. 2 is a schematic structural diagram of a fixing device provided in an embodiment of the present invention.
In the drawings: 1. a bar penetrating auxiliary device; 2. fixing the sleeve; 3. a bar penetrating rod; 4. a spring marble; 5. a fixing device; 6. a lower connecting ring; 7. an adjustment sleeve; 8. an upper connecting ring.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be obtained by a person skilled in the art without inventive efforts based on the embodiments of the present invention, shall fall within the scope of protection of the present invention.
It should be noted that the embodiments and features of the embodiments may be combined with each other without conflict.
The invention is further described with reference to the following drawings and specific examples, which are not intended to be limiting.
As shown in fig. 1 and 2, a construction method provided in an embodiment of the present invention includes the steps of:
1) Binding common steel bars after supporting the beam or the plate bottom mold;
2) Spot welding the fixed sleeves 2 in the tendon-penetrating auxiliary device 1 on the common steel bars at intervals at the prestressed tendon laying position according to a design drawing, then penetrating and fixing one end of each prestressed tendon on a tendon-penetrating rod 3, spot-welding spring marbles 4 on the tendon-penetrating rod, and then sequentially penetrating and fixing the tendon-penetrating rods in the fixed sleeves 2 by the spring marbles 4 according to the design drawing so as to finish the laying of the prestressed tendons according to the design drawing;
3) Pressing the spring marble 4 to release the bar penetrating rod 3, then taking down the bar penetrating rod 3, and fixing the tensioning end of the prestressed bar on the common steel bar by using a binding wire;
4) Clamping a lower connecting ring 6 in a fixing device 5 on a common steel bar, then rotating an adjusting sleeve 7 to clamp an upper connecting ring 8 (the upper connecting ring 8 is spirally connected to the adjusting sleeve 7, and the upper end of the lower connecting ring 6 is embedded on the adjusting sleeve 7, so that the upper connecting ring 8 can be extended/retracted when the adjusting sleeve 7 is rotated) in the fixing device 5 on a prestressed bar, rotating the adjusting sleeve 7 and jacking the prestressed bar among all the fixing sleeves 2 to a designed height (the thickness of a steel bar or a prestressed reinforced concrete protective layer in a concrete member needs to be accurate, and the fixing device 5 can adjust the position of the prestressed bar according to the thickness of the protective layer required by design, thereby ensuring that the position of the prestressed bar does not change in the concrete pouring process of the protective layer and further ensuring the thickness of the protective layer to be accurate), and then fixing a hole mold or foam, a spiral bar and a pressure bearing plate on the common steel bar by using binding wires;
5) Pouring concrete;
6) After the strength of the concrete reaches 85% of the design strength, removing the hole molds, cleaning Zhang Lakong, calibrating prestress tensioning equipment, and then installing an anchorage device at a tensioning end for tensioning;
7) Cutting off redundant prestressed tendons after tensioning is finished, performing anticorrosion treatment on the anchorage device, removing loose concrete and floating sand in Zhang Lacao, then washing the concrete and floating sand completely with water, removing redundant water in Zhang Lacao, filling and plugging the tensioning groove with fine stone concrete with the same strength grade as the structure or fine stone concrete with a high grade, and finally polishing and flattening the concrete which exceeds the concrete surface of the original structure during plugging with a polishing machine.
According to the invention, the fixed sleeve and the bar penetrating rod are matched with the bar penetrating mode, so that the correct position of the prestressed bar is ensured, and the bar penetrating construction efficiency is higher.
In the invention, the prestressed tendon is restrained by the fixed sleeve 2 so as to ensure the position of the prestressed tendon to be firm in the subsequent step of construction.
It should be noted that when the prestressed reinforcement is laid in the step 1), positioning points are drawn in advance according to a drawing and design requirements, then positioning devices are installed in advance, and then the prestressed steel strands which are well blanked are laid uniformly according to the positioning points; and (3) when the prestressed tendons are penetrated in the step 1), the horizontal deflection of the prestressed tendons is required to be not more than 50mm, and the vertical deviation is not more than 15mm.
While the invention has been described with reference to a preferred embodiment, it will be understood by those skilled in the art that various changes in form and detail may be made without departing from the spirit and scope of the invention.

Claims (3)

1. A construction method of a large-diameter slow-bonding prestressed tendon in a large-span member is characterized by comprising the following steps:
1) Binding common steel bars after supporting the beam or the plate bottom mold;
2) Spot welding fixing sleeves in the reinforcement penetrating auxiliary device on common steel bars at intervals at the position where the prestressed reinforcement is laid according to a design drawing, then penetrating and fixing one end of the prestressed reinforcement on a reinforcement penetrating rod, spot welding spring marbles on the reinforcement penetrating rod, and then sequentially penetrating and fixing the reinforcement penetrating rod in each fixing sleeve by using the spring marbles according to the design drawing so as to finish the laying of the prestressed reinforcement;
3) Pressing the spring marble to release the bar penetrating rod, then taking down the bar penetrating rod, and fixing the tensioning end of the prestressed tendon on the common steel bar by using a binding wire;
4) Clamping a lower connecting ring in a fixing device on a common steel bar, then rotating an adjusting sleeve to clamp an upper connecting ring in the fixing device on a prestressed tendon, rotating the adjusting sleeve and jacking the prestressed tendon among all the fixing sleeves to a designed height, and then fixing a hole die or foam, a spiral tendon and a pressure-bearing plate on the common steel bar by using a binding wire;
5) Pouring concrete;
6) After the strength of the concrete reaches 85% of the design strength, removing the hole molds, cleaning Zhang Lakong, calibrating prestress tensioning equipment, and then installing an anchorage device at a tensioning end for tensioning;
7) Cutting off redundant prestressed tendons after tensioning is finished, performing anticorrosion treatment on the anchorage device, removing loose concrete and floating sand in Zhang Lacao, then washing the concrete and floating sand completely with water, removing redundant water in Zhang Lacao, filling and plugging the tensioning groove with fine stone concrete with the same strength grade as the structure or fine stone concrete with a high grade, and finally polishing and flattening the concrete which exceeds the concrete surface of the original structure during plugging with a polishing machine;
the upper connecting ring is spirally connected to the adjusting sleeve, and the upper end of the lower connecting ring is embedded in the adjusting sleeve.
2. The construction method according to claim 1, wherein when the prestressed reinforcement is laid in the step 1), positioning points are drawn in advance according to drawings and design requirements, then positioning devices are installed in advance, and then the blanked prestressed steel strands are uniformly laid according to the positioning points.
3. The construction method according to claim 1, wherein the prestressed tendon is required to horizontally deflect by no more than 50mm and vertically deflect by no more than 15mm when the prestressed tendon is penetrated in the step 1).
CN202111069697.4A 2021-09-13 2021-09-13 Construction method of large-diameter slow-bonding prestressed tendon in large-span member Active CN113802773B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111069697.4A CN113802773B (en) 2021-09-13 2021-09-13 Construction method of large-diameter slow-bonding prestressed tendon in large-span member

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111069697.4A CN113802773B (en) 2021-09-13 2021-09-13 Construction method of large-diameter slow-bonding prestressed tendon in large-span member

Publications (2)

Publication Number Publication Date
CN113802773A CN113802773A (en) 2021-12-17
CN113802773B true CN113802773B (en) 2023-04-14

Family

ID=78940998

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111069697.4A Active CN113802773B (en) 2021-09-13 2021-09-13 Construction method of large-diameter slow-bonding prestressed tendon in large-span member

Country Status (1)

Country Link
CN (1) CN113802773B (en)

Family Cites Families (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0592342U (en) * 1992-05-21 1993-12-17 大成建設株式会社 PC strand guide cap
JP3762717B2 (en) * 2002-04-30 2006-04-05 住友電工スチールワイヤー株式会社 PC steel fixed structure
CN2799743Y (en) * 2005-06-21 2006-07-26 杨清晨 Cast-in-place concrete precise regulator and controller
CN101289890B (en) * 2008-05-27 2010-08-11 东南大学 Steel stranded line rapid traction joint
CN102852092B (en) * 2012-10-10 2015-07-15 中铁上海工程局集团有限公司 Hanging cable guiding device and method
CN203403362U (en) * 2013-06-14 2014-01-22 中交二航局第四工程有限公司安徽分公司 Pretensioned prestressed pedestal
US9638353B2 (en) * 2014-11-03 2017-05-02 A.L. Patterson, Inc. Clip for supporting a prestressed cable along a dovetail slot in a cement casting
CN204252399U (en) * 2014-12-01 2015-04-08 中石化胜利建设工程有限公司 The fastening devices of posttension soap-free emulsion polymeization, retarded adhesive prestressed steel bar sleeve pipe
CN207130972U (en) * 2017-07-07 2018-03-23 中冶建工集团有限公司 The cushion block of concrete bar protective layer poured applied to concrete wall column
CN210104728U (en) * 2019-03-15 2020-02-21 江苏泰林建设有限公司 Can splice formula tubular pile skeleton
CN112411884B (en) * 2020-10-10 2021-09-24 陕西建工第九建设集团有限公司 Fixing device for slow-bonding prestressed tendon
CN213683254U (en) * 2020-10-23 2021-07-13 陕西建工第九建设集团有限公司 Tendon distributing device for slow-bonding prestressed tendons
CN112832512B (en) * 2021-01-07 2022-05-27 中铁三局集团建筑安装工程有限公司 Large-span slow-bonding prestressed reinforced concrete beam and construction method

Also Published As

Publication number Publication date
CN113802773A (en) 2021-12-17

Similar Documents

Publication Publication Date Title
US10640977B2 (en) Concrete structure using reinforcing panel including embedded reinforcing grid and method of repairing and reinforcing the same
CN110847044B (en) Semi-prefabricated assembled bent cap construction method
CN110206143B (en) Construction method of post-tensioning prestressed assembly concrete frame structure
CN112832512B (en) Large-span slow-bonding prestressed reinforced concrete beam and construction method
CN109853981B (en) Concrete floor reinforcing construction method
CN110468727B (en) Temporary prestress tensioning pedestal and lifting point integrated structure of segmental beam and construction method
CN211396286U (en) Unbonded prestressed steel strand positioning bracket
CN211312247U (en) Prestressed steel strand reinforcing device additionally arranged in hollow plate hinge joint space
CN102808414A (en) Bonded post-tensioned prestressed anchoring construction method for cast-in-place concrete structure
CN215888972U (en) Large-span slow-bonding prestressed beam
CN108858740B (en) Construction method of hogging moment tensioning groove of precast beam
CN113802773B (en) Construction method of large-diameter slow-bonding prestressed tendon in large-span member
CN113152535A (en) Rear-inserted unbonded steel strand pressure-bearing type uplift pile construction method and assembly used in same
CN110107019B (en) Composite prefabricated floor slab for prefabricated building
CN108843024B (en) Construction method for pretensioning and binding longitudinal distribution ribs of prefabricated small box girder steel reinforcement framework
CN217780474U (en) Large-scale prefabricated case roof beam hoist and mount crack control device
CN213268016U (en) Prestressed anti-corrosion anti-floating anchor rod
CN216884551U (en) High-strength built-in post-tensioned reinforced concrete pole
CN114458018A (en) Prestress construction method
CN109914800B (en) Accurate pre-installation structure and construction method for civil building line-connecting and line-arranging pipes
CN220768569U (en) Large building roof prestress structure
CN105386555A (en) Anti-crack construction method for pre-buried pipeline part in concrete floor slab and anti-crack structure adopted
CN111101708A (en) Precise control construction process for prestress of wild goose-shaped plate
CN111305435A (en) One-way stress post-tensioning type connecting method for connecting prefabricated column joints
CN221778817U (en) Adjustable device of reinforcement protection layer thickness

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant