CN113789425B - Method for smelting return high silicon steel water by converter - Google Patents

Method for smelting return high silicon steel water by converter Download PDF

Info

Publication number
CN113789425B
CN113789425B CN202111076513.7A CN202111076513A CN113789425B CN 113789425 B CN113789425 B CN 113789425B CN 202111076513 A CN202111076513 A CN 202111076513A CN 113789425 B CN113789425 B CN 113789425B
Authority
CN
China
Prior art keywords
converter
blowing
steel
high silicon
slag
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111076513.7A
Other languages
Chinese (zh)
Other versions
CN113789425A (en
Inventor
尚德义
陈晨
王富亮
马宁
赵自鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Angang Steel Co Ltd
Original Assignee
Angang Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Angang Steel Co Ltd filed Critical Angang Steel Co Ltd
Priority to CN202111076513.7A priority Critical patent/CN113789425B/en
Publication of CN113789425A publication Critical patent/CN113789425A/en
Application granted granted Critical
Publication of CN113789425B publication Critical patent/CN113789425B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21CPROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
    • C21C5/00Manufacture of carbon-steel, e.g. plain mild steel, medium carbon steel or cast steel or stainless steel
    • C21C5/28Manufacture of steel in the converter
    • C21C5/36Processes yielding slags of special composition
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21CPROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
    • C21C5/00Manufacture of carbon-steel, e.g. plain mild steel, medium carbon steel or cast steel or stainless steel
    • C21C5/28Manufacture of steel in the converter
    • C21C5/30Regulating or controlling the blowing
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P10/00Technologies related to metal processing
    • Y02P10/20Recycling

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Carbon Steel Or Casting Steel Manufacturing (AREA)

Abstract

The invention relates to a method for smelting return high-silicon molten steel by a converter, which comprises the steps of adding the return high-silicon molten steel into the converter, and adding molten iron to a preset loading amount so that the silicon content of the molten steel in the converter is less than or equal to 1.0%; the converter adopts a double slag smelting method, and the added slag forming materials comprise active lime, dolomite, light burned dolomite and sinter; when oxygen accumulation reaches 83% -85% during blowing, measuring TSC by using a sublance, blowing to reach the target composition and target temperature of molten steel according to TSC measurement data, lifting the sublance, and tapping. The invention realizes the stable control of the high silicon steel water in the converter smelting return. Reduces the economic loss of steel factories and reduces the accident rate of steelmaking production. Improves the steel-making production operation rate.

Description

Method for smelting return high silicon steel water by converter
Technical Field
The invention relates to the technical field of ferrous metallurgy, in particular to a method for smelting return high-silicon steel water by a converter.
Background
When the high-silicon molten steel is produced, faults of a continuous casting machine can be encountered, the accident that the high-silicon molten steel does not have castability due to the fact that components are not mixed and the like is found before casting, in order to avoid larger economic loss, the high-silicon molten steel must be returned to a converter again, conventional raw materials smelted by the converter are molten iron and scrap steel, and the silicon content of the molten iron is generally about 0.3% -0.6%. The silicon content of common molten steel returned from furnace is about 0.02% -0.5%. However, the silicon content of the high silicon steel water is high and can reach between 1.5 and 3.5 percent, so that great difficulty is caused to converter smelting.
The high-silicon molten steel with ultrahigh silicon content can obviously increase the consumption of slag charge, is extremely easy to cause splashing, has extremely low metal yield, and can further aggravate corrosion to a furnace lining due to excessive SiO2 in slag, influence the melting speed of active lime and obviously prolong blowing time.
Disclosure of Invention
The technical problem to be solved by the invention is to provide a method for smelting the return high silicon steel water by the converter, so that the purposes of normal smelting of the converter, no splash, qualified temperature and qualified components are achieved.
In order to achieve the above purpose, the invention adopts the following technical scheme:
a method for smelting return high-silicon molten steel by a converter comprises the following steps: the method comprises the following specific steps of returning high silicon steel water, a converter, an argon station, refining and a casting machine:
1) Load control
Adding returned high silicon molten steel into the converter, adding molten iron to a preset loading amount to ensure that the silicon content of the molten steel in the converter is less than or equal to 1.0 percent, and according to the silicon content of the returned high silicon molten steel, adding the following components into the converter:
adding 1/2 of the furnace return high silicon steel into the converter, wherein the silicon content of the return high silicon steel is less than or equal to 2%;
2 percent is less than 3 percent of the water silicon content of the return high silicon steel, and the return high silicon steel water is added into the converter in a proportion of less than or equal to 1/3 of the converter;
the silicon content of the return high silicon steel water is more than or equal to 3 percent, and the return high silicon steel water of less than or equal to 1/4 of the furnace is added into the converter;
2) Slag formation control
The converter adopts a double slag smelting method, and the added slag forming materials comprise active lime, dolomite, light burned dolomite and sinter; the total addition amount of the sintering ore is = [ (molten iron temperature-1300) + (molten steel silicon content/n-0.3) ×200+180]/20; units: t is; n is the number of times of molten steel blending;
a. slag control before slag discharge: the addition amount of the active lime is as follows: 15+/-0.5 kg/t; the addition amount of dolomite and light burned dolomite is as follows: 15+/-0.5 kg/t; the addition amount of the sintering ore is as follows: adding 1+/-0.5 t of the total amount of the sintering ore; after opening and blowing for 30s, adding in two batches;
b. slag discharge control: the addition amount of the active lime is as follows: 25+ -0.5 kg/t; the addition amount of dolomite and light burned dolomite is as follows: 5+/-0.5 kg/t; sinter added = total sinter added-amount of sinter added before deslagging;
3) Gun position control
a. Blowing gun position: 2600mm-2700mm, oxygen pressure is opened: 0.9MPa-1.05MPa, oxygen blowing flow 53700 + -50 Nm 3 /h; reducing the gun position to 2400+/-10 mm in 1 min+/-30 s of blowing, reducing the gun position to 2200+/-10 mm in 2 min+/-30 s of blowing, reducing the gun position to 2600+/-10 mm in3 min+/-30 s of blowing, reducing the gun position to 3000+/-10 mm in 4 min+/-30 s of blowing, and waiting for 5 min+/-30 s of lifting gun to discharge slag;
b. blowing again after slag discharge, and opening a blowing gun position: 2600+ -10 mm, oxygen flow 48000+ -50 Nm 3 After successful ignition, the gun position is lifted to 2800+/-10 mm, and the oxygen blowing flow is regulated to 53700 +/-50 Nm 3 /h;
4) Endpoint control
When the oxygen is accumulated to 83% -85%, measuring TSC by using a sublance, blowing according to TSC measurement data to reach the target composition and target temperature of molten steel, lifting the sublance, and tapping.
The re-melted high silicon steel water comprises FJACT, FJACT-1, FJACT-2, 50AW470, 50AW800, 50AW1300, 50AW600 and AW800R, DY015-03K.
Compared with the prior art, the invention has the beneficial effects that:
the invention discloses a method for realizing converter smelting return high silicon steel water through converter loading control, slag formation control, gun position control and end point control. The purpose of normal smelting of the converter is achieved, and stable control of the high silicon steel water returned from the converter smelting is realized. Reduces the economic loss of steel factories and reduces the accident rate of steelmaking production. Improves the steel-making production operation rate.
Detailed Description
The invention is further illustrated by the following examples:
the following examples illustrate the invention in detail. These examples are merely illustrative of the best embodiments of the invention and do not limit the scope of the invention.
Examples
The method for smelting the back-smelting high-silicon molten steel by the converter comprises the following process steps: the method comprises the steps of returning high silicon steel water, a converter, an argon station, refining, a casting machine, smelting steel SPHC, and 270 tons of converter loading, and comprises the following steps:
1) A new D-level ladle is used during tapping, and the turnover time is less than or equal to 100min;
2) Adding molten iron except for the recycled high silicon steel water, wherein the temperature of the molten iron is 1284 ℃ and the silicon content is 0.32%;
3) The target tapping temperature of the converter is 1665 ℃, and the product requirement P is less than or equal to 0.020%;
4) The water silicon content of the high silicon steel is 2.9%, the water amount of the high silicon steel added into the converter is 90 tons, and the water amount of the added iron is 180 tons;
5) After the high silicon molten steel and molten iron are added, blowing oxygen by a lance, and opening the lance position: 2600mm-2700mm, oxygen pressure is opened: 0.9Mpa-1.05Mpa, oxygen blowing flow 53700Nm 3 Adding 3000kg of active lime, 3000kg of dolomite and 500kg of light burned dolomite after successful ignition, blowing for 1min until the gun position is reduced to 2400mm, and adding 3000 of sinterkg, blowing for 2min until the gun position is reduced to 2200mm, simultaneously adding 1000kg of second batch of active lime, 500kg of light burned dolomite, lifting the gun position to 2600mm, blowing for 3min until the gun position is lifted to 3000mm, adding 1000kg of sinter during 4min, and waiting for 5min for 30s of gun lifting and slag discharging;
6) Blowing again after slag discharge, and opening a blowing gun position: 2600mm, oxygen flow 48000Nm 3 After successful ignition, the gun position is lifted to 2800mm, and the oxygen blowing flow is regulated to 53700Nm 3 Adding 7000kg of active lime, 1000kg of dolomite, 500kg of light burned dolomite and 13800kg of residual sinter, and obtaining 9500Nm of oxygen accumulation according to automatic calculation 3 When the gun is used, TSC test is carried out through the sublance, the gun is lifted through the TSC measurement data to be blown to the end point; the end point temperature is 1663 ℃, the oxygen value is 503ppm, the end point P=0.0163% and tapping is carried out;
7) Refining after steel is discharged, and pouring the steel on a machine after the refining treatment is qualified;
8) And (3) continuously adding the residual furnace returning high silicon steel water into different two furnace times for 2 times, and repeating the steps 4) -7) to carry out blowing and casting.

Claims (2)

1. A method for smelting return high-silicon molten steel by a converter comprises the following steps: the method is characterized by comprising the following specific steps of:
1) Load control
Adding high silicon molten steel returned from the converter, and adding molten iron to a preset loading amount to ensure that the silicon content of the molten steel in the converter is less than or equal to 1.0 percent; according to the silicon content of the returned high silicon steel water, the converter is added with the returned high silicon steel water according to the following weight:
adding 1/2 of the furnace return high silicon steel into the converter, wherein the silicon content of the return high silicon steel is less than or equal to 2%;
2 percent is less than 3 percent of the water silicon content of the return high silicon steel, and the return high silicon steel water is added into the converter in a proportion of less than or equal to 1/3 of the converter;
the silicon content of the return high silicon steel water is more than or equal to 3 percent, and the return high silicon steel water of less than or equal to 1/4 of the furnace is added into the converter;
2) Slag formation control
The converter adopts a double slag smelting method, and the added slag forming materials comprise active lime, dolomite, light burned dolomite and sinter; the total addition amount of the sintering ore is = [ (molten iron temperature-1300) + (molten steel silicon content/n-0.3) ×200+180]/20; units: t is; n is the number of times of molten steel blending;
a. slag control before slag discharge: the addition amount of the active lime is as follows: 15+/-0.5 kg/t; the addition amount of dolomite and light burned dolomite is as follows: 15+/-0.5 kg/t; adding 1+/-0.5 t of the total amount of the sintering ore;
b. slag discharge control: the addition amount of the active lime is as follows: 25+ -0.5 kg/t; the addition amount of dolomite and light burned dolomite is as follows: 5+/-0.5 kg/t; sinter added = total sinter added-amount of sinter added before deslagging;
3) Gun position control
a. Blowing gun position: 2600mm-2700mm, oxygen pressure is opened: 0.9MPa-1.05MPa, oxygen blowing flow 53700 + -50 Nm 3 /h; reducing the gun position to 2400+/-10 mm in 1 min+/-30 s of blowing, reducing the gun position to 2200+/-10 mm in 2 min+/-30 s of blowing, reducing the gun position to 2600+/-10 mm in3 min+/-30 s of blowing, reducing the gun position to 3000+/-10 mm in 4 min+/-30 s of blowing, and waiting for 5 min+/-30 s of lifting gun to discharge slag;
b. blowing again after slag discharge, and opening a blowing gun position: 2600+ -10 mm, oxygen flow 48000+ -50 Nm 3 After successful ignition, the gun position is lifted to 2800+/-10 mm, and the oxygen blowing flow is regulated to 53700 +/-50 Nm 3 /h;
4) Endpoint control
When the oxygen is accumulated to 83% -85%, measuring TSC by using a sublance, blowing according to TSC measurement data to reach the target composition and target temperature of molten steel, lifting the sublance, and tapping.
2. The method for smelting back-to-furnace high silicon steel water in a converter according to claim 1, wherein in the step 2) a, slag is added in two batches after being blown for 30 seconds.
CN202111076513.7A 2021-09-14 2021-09-14 Method for smelting return high silicon steel water by converter Active CN113789425B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111076513.7A CN113789425B (en) 2021-09-14 2021-09-14 Method for smelting return high silicon steel water by converter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111076513.7A CN113789425B (en) 2021-09-14 2021-09-14 Method for smelting return high silicon steel water by converter

Publications (2)

Publication Number Publication Date
CN113789425A CN113789425A (en) 2021-12-14
CN113789425B true CN113789425B (en) 2023-05-12

Family

ID=78880320

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111076513.7A Active CN113789425B (en) 2021-09-14 2021-09-14 Method for smelting return high silicon steel water by converter

Country Status (1)

Country Link
CN (1) CN113789425B (en)

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102952915B (en) * 2011-08-20 2014-06-04 鞍钢股份有限公司 Phosphorus-containing steel converter smelting method
CN105714012A (en) * 2014-12-01 2016-06-29 鞍钢股份有限公司 Converter little slag smelting method for high silicon molten iron
CN105950815A (en) * 2016-06-22 2016-09-21 山东钢铁股份有限公司 Recycled steel converter blowing method
CN106834592B (en) * 2017-01-03 2019-02-12 山东钢铁股份有限公司 A kind of method that steel treatment is melted down in converter
CN112210638B (en) * 2019-07-10 2022-03-11 山东钢铁股份有限公司 Converter smelting method for medium and high silicon molten iron

Also Published As

Publication number Publication date
CN113789425A (en) 2021-12-14

Similar Documents

Publication Publication Date Title
CN111411300B (en) Method for producing nickel-based steel by using high-phosphorus molten iron
CN105861775A (en) Smelting process for ultra-low phosphorus steel with high nickel content
CN114606357A (en) Method for removing phosphorus and leaving carbon in medium-high carbon steel by converter
CN111286577A (en) Smelting method of ultra-low titanium steel
CN112981032B (en) Method for smelting low-titanium high-carbon chromium bearing steel by high-titanium molten iron
CN113604631B (en) Method for inhibiting refining and resulfurization of low-sulfur steel in LF (ladle furnace)
CN113444855B (en) Smelting method utilizing residual steel and residual slag in steel ladle
CN113789425B (en) Method for smelting return high silicon steel water by converter
CN114645108B (en) Method for treating residual iron
CN111635973B (en) Method for removing titanium from molten iron of converter
CN114892066A (en) Production method of steel for low-carbon electrode
CN114908217A (en) Low-cost structural steel smelting process
CN113088616A (en) Method for efficiently controlling manganese content of molten steel during steel making of return steel
CN106498116A (en) A kind of production technology of circle chain of mine steel
CN111705178A (en) Method for controlling oxygen content in molten steel RH vacuum refining furnace
CN111206138A (en) Method for efficiently producing high-quality steel billets
CN1441066A (en) Slagging aluminium ball and its making process
CN114854927B (en) Method for opening large converter
CN113234887B (en) Slag regulating agent for washing furnace bottom and use method thereof
CN115074490B (en) Converter steelmaking decarburization method
CN115323108B (en) Method for shortening Gao Tieshui ratio smelting period of electric furnace
CN117845143B (en) High-quality free-cutting die steel casting blank and preparation method thereof
CN115404300B (en) Control method for converter bottom thickness
CN114657309B (en) Furnace protection method with low iron loss
CN117265206A (en) Smelting process for thermal compensation and deep desulfurization of semi-steel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant