CN113668542A - Anti-cracking construction method for concrete dam overwintering interlayer in severe cold region - Google Patents

Anti-cracking construction method for concrete dam overwintering interlayer in severe cold region Download PDF

Info

Publication number
CN113668542A
CN113668542A CN202111132637.2A CN202111132637A CN113668542A CN 113668542 A CN113668542 A CN 113668542A CN 202111132637 A CN202111132637 A CN 202111132637A CN 113668542 A CN113668542 A CN 113668542A
Authority
CN
China
Prior art keywords
layer
concrete
overwintering
lower layer
geocell
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111132637.2A
Other languages
Chinese (zh)
Inventor
王立成
董承山
岳丽丽
顾小兵
刘艳红
谢绍红
白琳
常媛
王阳
王澍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Water Resources Beifang Investigation Design and Research Co Ltd
Original Assignee
China Water Resources Beifang Investigation Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Water Resources Beifang Investigation Design and Research Co Ltd filed Critical China Water Resources Beifang Investigation Design and Research Co Ltd
Priority to CN202111132637.2A priority Critical patent/CN113668542A/en
Publication of CN113668542A publication Critical patent/CN113668542A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • E02B7/08Wall dams
    • E02B7/10Gravity dams, i.e. those in which the weight of the structure prevents overturning

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses an anti-cracking construction method for an overwintering interlayer of a concrete dam in a severe cold region, which comprises the steps of firstly pouring concrete on a lower layer, pouring concrete on an upper layer poured by the upper part of the lower layer and the upper layer poured by the upper part of the lower layer, arranging horizontal copper water stop and a high-strength geocell on an overwintering intermittent layer between the first poured concrete on the lower layer and the upper layer poured concrete poured on the upper part, performing roughening treatment on the overwintering intermittent layer, and then continuously pouring concrete on the upper layer in the next construction period, wherein the whole construction process is finished. The construction method effectively prevents horizontal cracking and vertical cracks of upper post-cast concrete by arranging the copper water stop and the high-strength geocell on the overwintering intermittent layer, and has the advantages of convenient construction, small investment and good effect.

Description

Anti-cracking construction method for concrete dam overwintering interlayer in severe cold region
Technical Field
The invention relates to a concrete dam construction method, in particular to an anti-cracking construction method for an overwintering interlayer of a concrete dam in a severe cold region.
Background
When a roller compacted concrete gravity dam is built in a severe cold area, cracks are generated due to severe weather conditions, namely cold, hot, wind and dry. The cold is that the average temperature per year in a severe cold area is very low, the average temperature per month in winter is below-10 ℃, the cold tide is frequent all the year round, and the temperature difference between day and night is large; "Hot" means that the temperature is high in summer, and the average temperature is about 20 ℃ in summer; wind refers to severe cold areas with strong wind power, strong wind speed and easy evaporation of water; the term "dry" refers to the climate dryness in spring and autumn in alpine regions, and these climate characteristics are extremely unfavorable for the temperature control and crack prevention of roller compacted concrete. The stable temperature of the dam body is low due to low annual average temperature, and the highest temperature of concrete poured in summer is high, so that the temperature difference of the dam foundation is large (often exceeding the specification), and foundation penetrating cracks are often generated due to large temperature difference of the foundation; the cold tide is frequent all the year round, the temperature difference between day and night is large, and the concrete on the upper layer and the lower layer of the pre-cast concrete and the post-cast concrete form a large temperature difference due to the existence of the intermission period, so that horizontal cracks appear, and the concrete on the upper layer of the post-cast concrete generates vertical cracks, thereby causing the water leakage of the dam body. Research shows that the tensile strength between horizontal layers is only 41-86% of that of the original concrete, so that the horizontal cracking phenomenon is easy to form. In engineering practice, the overwintering layer and the long intermittent layer are horizontally cracked and the vertical head-wrapping seam is formed in the upper static dam, the Japanese Yuchuan dam, the Liaoning kwan-yin pavilion dam, the Songyue dam, the Mancheng platform dam, the Hebei peach forest mouth dam, the Iris river mouth dam, the Xinjiang Chong Duan dam and the like of the United states in sequence, so that the water leakage of the dam body is caused, and the problems are urgently solved.
Disclosure of Invention
The invention aims to solve the technical problem of providing an anti-cracking construction method for the overwintering layer of a concrete dam in a severe cold region.
In order to solve the problems, the technical scheme adopted by the invention is as follows: an anti-cracking construction method for an overwintering interlayer of a concrete dam in a severe cold region comprises the following steps:
(1) after the lower layer of the pre-cast concrete which is about to enter the wintering period is poured, laying a horizontal copper water stop layer and a geocell on the lower layer of the pre-cast concrete wintering intermittent layer, inserting the lower part of the geocell into the lower layer of the pre-cast concrete, exposing the surface of the lower layer of the pre-cast concrete on the upper part of the geocell, and roughening the wintering intermittent layer before final setting of the lower layer of the pre-cast concrete;
(2) and (5) continuously pouring the upper-layer post-cast concrete in the construction of the next year, and finishing the whole construction process.
The size height of the geocell is more than or equal to 30cm, the size of the geocell is 30cm multiplied by 30cm, and the width is more than or equal to 3 m.
The geocell is buried in the lower layer of the precast concrete and is more than or equal to 15 cm.
The invention has the beneficial effects that: the construction method of the invention effectively prevents horizontal cracking and vertical cracks of upper post-cast concrete by arranging the copper water stop and the geocell on the overwintering intermittent layer, and has convenient construction, small investment and good effect.
Detailed Description
The present invention will be described in further detail with reference to specific embodiments below:
the invention discloses an anti-cracking construction method for an overwintering interlayer of a concrete dam in a severe cold region, which comprises the following steps of:
(1) after the lower layer of the pre-cast concrete which is about to enter the wintering period is poured, laying a horizontal copper water stop layer and a geocell on the lower layer of the pre-cast concrete wintering intermittent layer, wherein the geocell is arranged on the whole wintering layer surface, the lower part of the geocell is inserted into the lower layer of the pre-cast concrete, the upper part of the geocell exposes the surface of the lower layer of the pre-cast concrete, and the lower layer of the pre-cast concrete is roughened before final setting;
(2) and (5) continuously pouring the upper-layer post-cast concrete in the construction of the next year, and finishing the whole construction process.
The size height of the geocell is more than or equal to 30cm, the size of the geocell is 30cm multiplied by 30cm, and the width is more than or equal to 3 m.
The geocell is buried in the lower layer of the precast concrete and is more than or equal to 15 cm.
Specifically, after an upper layer of later-poured concrete is poured on the lower layer of earlier-poured concrete which is intermittently poured in winter, an overwintering intermittent layer which exists between the lower layer of earlier-poured concrete and the upper layer of later-poured concrete is arranged, horizontal copper water stop and a geocell are arranged on the overwintering intermittent layer which is between the lower layer of earlier-poured concrete and the upper layer of later-poured concrete which is poured on the upper layer, the overwintering intermittent layer is subjected to roughening treatment, then the upper layer of later-poured concrete is continuously poured in the next construction period, and the whole construction process is finished.
The intermittence is not limited to the overwintering intermittence, and the intermittence for a period of time comprises the condition that the intermittence time of pouring the upper layer after pouring the concrete on the upper part of the lower layer of the first poured concrete is more than or equal to 15 days.
In the present embodiment, the construction is performed according to the following steps: laying horizontal copper water stop and high-strength geocells on the lower layer of the first-cast concrete overwintering intermittent layer, scouring the overwintering intermittent layer before final setting of the lower layer of the first-cast concrete, pouring concrete after the upper layer of the second-year construction is poured, and finishing the whole construction process. The horizontal copper water stop is used for preventing water leakage between layers when horizontal cracking occurs, after the high-strength geocell arranged on the lower layer of the early-poured concrete overwintering intermittent layer is poured with the later-poured concrete on the upper layer, when the later-poured concrete on the upper layer is in a temperature rise expansion stage, the volume expansion of the later-poured concrete on the upper layer is limited due to the side limiting effect, the expansion deformation of the later-poured concrete on the upper layer in the plane direction is also limited, so that when the later-poured concrete on the upper layer shrinks due to temperature reduction, the shrinkage deformation is coordinated with the deformation of the earlier-poured concrete on the lower layer, the strong constraint effect of the earlier-poured concrete on the upper layer of the later-poured concrete on the lower layer is reduced, the temperature stress is greatly reduced, and the horizontal cracking of the overwintering layer and the long intermittent layer and the vertical head-on seam are effectively prevented.
In a certain project of Xinjiang, a scheme of laying geocells, laying horizontal copper water stop and then pouring upper-layer concrete is adopted on the overwintering layer surface and the long intermittent warehouse surface which is more than 15 days, the existing dam is poured to the top, the combination of the upper layer and the lower layer of the concrete dam body is good through field observation, horizontal cracks of the overwintering layer are basically eliminated, and the horizontal cracks and the vertical split-end cracks of the overwintering layer and the long intermittent layer are effectively prevented.
The above examples are only for illustrating the technical ideas and features of the present invention, and the purpose thereof is to enable those skilled in the art to understand the contents of the present invention and to implement the same, and the scope of the present invention is not limited by the examples, i.e., the equivalent changes or modifications made in the spirit of the present invention disclosed are still within the scope of the present invention.

Claims (3)

1. An anti-cracking construction method for an overwintering interlayer of a concrete dam in a severe cold area is characterized by comprising the following steps:
(1) after the lower layer of the pre-cast concrete which is about to enter the wintering period is poured, laying a horizontal copper water stop layer and a geocell on the lower layer of the pre-cast concrete wintering intermittent layer, inserting the lower part of the geocell into the lower layer of the pre-cast concrete, exposing the surface of the lower layer of the pre-cast concrete on the upper part of the geocell, and roughening the wintering intermittent layer before final setting of the lower layer of the pre-cast concrete;
(2) and (5) continuously pouring the upper-layer post-cast concrete in the construction of the next year, and finishing the whole construction process.
2. The overwintering interlaminar anti-cracking construction method for the concrete dam in the severe cold region as claimed in claim 1, wherein the size height of the geocell is more than or equal to 30cm, the size of the geocell is 30cm x 30cm, and the width of the geocell is more than or equal to 3 m.
3. The anti-cracking construction method for the overwintering interlayer of the concrete dam in the severe cold region as claimed in claim 2, wherein the geocell is buried in the lower layer of the pre-cast concrete for more than or equal to 15 cm.
CN202111132637.2A 2021-09-26 2021-09-26 Anti-cracking construction method for concrete dam overwintering interlayer in severe cold region Pending CN113668542A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111132637.2A CN113668542A (en) 2021-09-26 2021-09-26 Anti-cracking construction method for concrete dam overwintering interlayer in severe cold region

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111132637.2A CN113668542A (en) 2021-09-26 2021-09-26 Anti-cracking construction method for concrete dam overwintering interlayer in severe cold region

Publications (1)

Publication Number Publication Date
CN113668542A true CN113668542A (en) 2021-11-19

Family

ID=78550267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111132637.2A Pending CN113668542A (en) 2021-09-26 2021-09-26 Anti-cracking construction method for concrete dam overwintering interlayer in severe cold region

Country Status (1)

Country Link
CN (1) CN113668542A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2378003A1 (en) * 2010-04-19 2011-10-19 Dywidag-Systems International GmbH Assembly for connecting a geoplastic to a stable base
CN107542059A (en) * 2017-09-14 2018-01-05 张传河 A kind of method repaired base soil and be lost in buttress
CN110593209A (en) * 2019-09-24 2019-12-20 中水北方勘测设计研究有限责任公司 Method for preventing horizontal cracks of overwintering layer of roller compacted concrete dam in severe cold area
CN110616618A (en) * 2019-11-08 2019-12-27 南通大学 Reinforced asphalt-based concrete three-dimensional rectangular grid structure and preparation method thereof
CN111074717A (en) * 2020-01-20 2020-04-28 湖南科技学院 Perennial frozen soil area airport runway structure and construction method thereof
CN112211161A (en) * 2020-10-27 2021-01-12 中水北方勘测设计研究有限责任公司 Method for plugging diversion bottom hole of concrete dam in severe cold area

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2378003A1 (en) * 2010-04-19 2011-10-19 Dywidag-Systems International GmbH Assembly for connecting a geoplastic to a stable base
CN107542059A (en) * 2017-09-14 2018-01-05 张传河 A kind of method repaired base soil and be lost in buttress
CN110593209A (en) * 2019-09-24 2019-12-20 中水北方勘测设计研究有限责任公司 Method for preventing horizontal cracks of overwintering layer of roller compacted concrete dam in severe cold area
CN110616618A (en) * 2019-11-08 2019-12-27 南通大学 Reinforced asphalt-based concrete three-dimensional rectangular grid structure and preparation method thereof
CN111074717A (en) * 2020-01-20 2020-04-28 湖南科技学院 Perennial frozen soil area airport runway structure and construction method thereof
CN112211161A (en) * 2020-10-27 2021-01-12 中水北方勘测设计研究有限责任公司 Method for plugging diversion bottom hole of concrete dam in severe cold area

Similar Documents

Publication Publication Date Title
CN104018673B (en) Ultra-large volume concrete one-time continuous pours into a mould multi cycle real-time temperature control construction technology
CN102900067B (en) Processing method for reinforcing soft clay ground through vacuum preloading in combination with electro-osmosis method
CN103806437B (en) Double-layer vacuum preloading and hydraulic reclamation soft foundation processing method
CN105418008B (en) A kind of root resistance water-proof concrete and green roof structure
CN205134283U (en) Base concrete panel rock-fill dam
CN203546678U (en) Asphalt concrete core-wall rockfill dam structure
CN107310022A (en) Foundation pile for Frozen Ground Area photovoltaic bracket and preparation method thereof
CN108536978A (en) A method of prevent High Concrete Dam gallery crown from cracking
CN205636683U (en) Quick block structure of diversion tunnel
CN113668542A (en) Anti-cracking construction method for concrete dam overwintering interlayer in severe cold region
CN111549725A (en) Waterproof horizontal water leakage structure for roller compacted concrete dam intermittent layer in severe cold area
CN209384447U (en) A kind of dark skeleton rubble wall building structure
CN113106931A (en) Core wall dam that can be under construction fast
CN212248090U (en) Waterproof horizontal water leakage structure for roller compacted concrete dam intermittent layer in severe cold area
CN103046534A (en) Method for improving bearing capacity of foundation
CN212388473U (en) Temperature control structure system for dam body in severe cold region
CN209369026U (en) Assembly concrete beam column dry type connector
CN207189941U (en) Foundation pile for Frozen Ground Area photovoltaic bracket
CN115492057A (en) Concrete core rock-fill dam structure body and construction method
CN215406639U (en) Prefabricated steel plate structure of post-cast strip pretreatment for advance construction of top plate backfill
CN207828910U (en) Novel double-layer geomembrane seepage-proofing structure
CN112211161A (en) Method for plugging diversion bottom hole of concrete dam in severe cold area
CN216075134U (en) Rich water district faces lake sandy soil deep basal pit hillside top construction road structure
CN211774800U (en) Tibetan rubble wall body
CN209620426U (en) A kind of Asia rigid roofing structure plate structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211119

RJ01 Rejection of invention patent application after publication