CN113622585A - Assembly type suspended ceiling connecting structure and mounting method thereof - Google Patents

Assembly type suspended ceiling connecting structure and mounting method thereof Download PDF

Info

Publication number
CN113622585A
CN113622585A CN202110958539.8A CN202110958539A CN113622585A CN 113622585 A CN113622585 A CN 113622585A CN 202110958539 A CN202110958539 A CN 202110958539A CN 113622585 A CN113622585 A CN 113622585A
Authority
CN
China
Prior art keywords
hanging
hanging piece
buckle
suspended ceiling
wall surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110958539.8A
Other languages
Chinese (zh)
Inventor
丁欣欣
王文广
周东珊
姜凯庭
余广
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Yasha Decoration Co Ltd
Original Assignee
Zhejiang Yasha Decoration Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Yasha Decoration Co Ltd filed Critical Zhejiang Yasha Decoration Co Ltd
Priority to CN202110958539.8A priority Critical patent/CN113622585A/en
Publication of CN113622585A publication Critical patent/CN113622585A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/22Connection of slabs, panels, sheets or the like to the supporting construction
    • E04B9/28Connection of slabs, panels, sheets or the like to the supporting construction with the slabs, panels, sheets or the like having grooves engaging with horizontal flanges of the supporting construction or accessory means connected thereto
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/06Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
    • E04B9/065Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members comprising supporting beams having a folded cross-section
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/18Means for suspending the supporting construction
    • E04B9/20Means for suspending the supporting construction adjustable
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to an assembly type suspended ceiling connecting structure, which comprises hanging pieces, a hanging rod for fixing the hanging pieces, a plurality of hanging pieces, a buckle line and a top plate, wherein the hanging pieces are movably fixed on the hanging pieces, a first clamping part is arranged on each hanging piece, a second clamping part mutually clamped with the first clamping part is arranged on each buckle line, a long straight groove for enabling the second clamping part to move in each hanging piece is also arranged on each hanging piece, the first clamping part is mutually communicated with the long straight groove, a first sliding groove is arranged on the top plate, a plug board matched with the first sliding groove is arranged at the bottom end of each buckle line, and a second sliding groove is arranged on each hanging piece. The leveling is only needed once in the process of installing the top plate, and the leveling is not needed twice, so that the installation efficiency is increased, and the second step is as follows: there is not the gap, three between the roof after convenient quick installation roof and installation: each roof is conveniently dismantled.

Description

Assembly type suspended ceiling connecting structure and mounting method thereof
Technical Field
The invention relates to the technical field of ceiling installation, in particular to an assembly type suspended ceiling connecting structure and an installation method thereof.
Background
The existing ceiling installation mode mostly adopts the installation mode of light steel keels, the base layer construction generally adopts the installation mode of main keels and auxiliary keels double-layer keels or single-layer keels, the keels are connected through gypsum board openings, a large number of screws are usually needed for installation and fixation when the method is adopted for connection, and the installation panel is usually needed to be pasted on the gypsum panel in the later period, so that the aim of hiding the screws is achieved, and the technical problem is solved later,
chinese patents such as cn202010319872.x have appeared which disclose a mounting structure for a fabricated ceiling of a narrow toilet, comprising: the wall board is arranged on an original wall body, and a plurality of connecting pieces are arranged at the top of the wall board; the furred ceiling, the edge of furred ceiling is provided with the connecting hole, and the connecting piece passes the connecting hole to be connected through the retaining member. Compared with the prior art, the invention has the following advantages: the problem that nailing cannot be performed in a narrow installation space is solved, and the installation work can be performed smoothly without nailing, so that the installation efficiency is improved, and the installation quality is improved;
although the technical problem of screw-free installation is solved, once the installation of the top plate is completed, the top plate cannot be detached, and secondly, the installation is only limited to indoor decoration of a narrow toilet, when large-area decoration areas such as a living room and the like need to be decorated, the adoption of the installation structure can enable the selected materials of the suspended ceiling to be installed by a whole suspended ceiling with the length equal to that of the suspended ceiling to be decorated, and due to the adoption of the mode, due to the fact that the span of the suspended ceiling is too large, the middle of the suspended ceiling is concave, the attractiveness is affected, and when the suspended ceiling is serious, the suspended ceiling collapses due to the self weight;
therefore, the problems of the prior art are urgently needed to be solved.
Disclosure of Invention
In order to solve the technical problems, the invention aims to provide an assembly type suspended ceiling connecting structure and an installation method thereof, and the purpose of efficient installation and disassembly without nailing is achieved.
In order to achieve the purpose, the invention discloses an assembly type suspended ceiling connecting structure, which comprises a hanging piece, a hanging rod for fixing the hanging piece, a plurality of hanging pieces, a buckle line and a top plate, wherein the hanging pieces are movably fixed on the hanging piece;
first joint portion has been seted up on the pendant, be equipped with on the buckle lines with the second joint portion of the mutual joint of first joint portion, still set up on the pendant and be used for making the long straight flute of second joint portion at its internalization, first joint portion with long straight flute communicates each other, first spout has been seted up on the roof, the bottom of buckle lines be provided with first spout complex picture peg, the second spout has been seted up on the pendant.
Further, the second clamping portion comprises a fixing plate, a gap groove is formed in the fixing plate, and a protrusion is arranged on the second clamping portion.
Further, first joint portion is the rectangular channel, bellied cross section adopts the design of right trapezoid.
Further, the fixing plate is integrally formed at the top of the buckle line.
Further, the cross section of the hanging piece is the same as that of the second sliding groove, and the hanging piece penetrates through the second sliding groove.
A method of installing an assembled suspended ceiling connection structure, comprising the steps of: .
Firstly, measuring the decoration size of the top wall surface to be decorated, calculating the decoration position of a suspender of the top wall surface according to the measurement size, then marking marks on the top wall surface by using a marking pen, assembling the suspender to the marking positions of the top wall surface by using an expansion bolt, then assembling a hanging piece on the hanging piece, fixing the hanging piece and the suspender mutually by using a clamping strip (not shown in the figure), adjusting the height of the suspender by adjusting the expansion bolt, measuring the levelness of the hanging piece by using auxiliary equipment of a level gauge, finally enabling the hanging piece to be horizontal, then assembling a buckle line upwards by using a sucker so that the buckle line can be clamped on the hanging piece, pushing the buckle line forwards to enable one end of the buckle line to be abutted against the side wall surface, enabling the distance between the other end of the buckle line and the side wall surface to be 1.2 times of the length of a top plate, and pulling the sucker downwards to enable the sucker to be separated from the buckle line, sequentially inserting each top plate in a first row of top plates (excluding the last top plate) into the buckle lines through the suckers, after the top plates are installed, using a negative pressure sucker to suck the last top plate and lift the last top plate to the height of the installed top plate and align the top plates, using a negative pressure sucker to suck the buckle lines by another person to move the buckle lines to enable the distances between two ends of each buckle line and two side wall surfaces to be equal, at the moment, installing the last top plate on each buckle line to realize the installation of the first row of top plates, then, sequentially installing a second row of top plates and a third row of top plates until the top plates are fully arranged on the top wall surface to be decorated, and finally, adopting an edge folding process (putty scraping and latex paint brushing for edge folding treatment) to fold the gaps between the side wall surfaces and the top plates and the gaps between the top plates;
the second clamping portion on the buckle line is clamped with the first clamping portion on the pendant, so that the buckle line and the pendant can be fixed, and the buckle line is provided with the long straight groove communicated with the second clamping portion, so that the buckle line has an upward moving movement trend when being subjected to an upward acting force;
compared with the prior art, the invention has the beneficial effects that:
firstly, the method comprises the following steps: only one leveling is needed in the process of installing the top plate, and two leveling is not needed, so that the installation efficiency is improved;
II, secondly: the hanging piece is movably fixed on the hanging piece, and the top plate is movably arranged on the buckle line, so that the top plate can be conveniently and quickly installed, and no gap exists between the installed top plate;
thirdly, the method comprises the following steps: the first clamping portion is communicated with the long straight groove and can move in the long straight groove, so that the top plates are convenient to disassemble;
in conclusion, the assembly type suspended ceiling connecting structure and the installation method thereof can achieve the purpose of efficient installation and disassembly without nailing.
Drawings
Fig. 1 is a schematic perspective view of an assembled suspended ceiling attachment structure according to an embodiment of the present invention;
fig. 2 is a perspective view of a top panel of a fabricated suspended ceiling attachment structure in an embodiment of the present invention;
FIG. 3 is a perspective view of a pendant of the fabricated suspended ceiling connection in an embodiment of the present invention;
fig. 4 is a perspective view of a snap line of an assembled suspended ceiling attachment structure in an embodiment of the present invention;
fig. 5 is a perspective view of the mounting effect of the fabricated suspended ceiling attachment structure in an embodiment of the present invention.
In the figure: 1. hanging a piece; 2. a boom; 3. hanging parts; 31. a first clamping part; 311. a rectangular groove; 32. a long straight groove; 33. a second chute; 4. buckling a line; 41. a second clamping part; 411. a fixing plate; 4111. a clearance groove; 412. a protrusion; 42. inserting plates; 5. a top plate; 51. a first chute; m, a first row of top plates.
Detailed Description
To explain the technical content, structural features, attained objects and effects of the present invention in detail, embodiments are described below in detail with reference to the accompanying drawings.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc., indicate orientations or positional relationships based on those shown in the drawings, and are used merely for convenience in describing the present invention and for simplifying the description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be taken as limiting the scope of the present invention.
The first embodiment is as follows:
referring to fig. 1 and fig. 2-5, in order to achieve the above object, the present invention provides an assembly type suspended ceiling connection structure, which includes a hanging piece 1, a hanging rod 2 for fixing the hanging piece 1, a plurality of hanging pieces 3, a fastening line 4 and a top plate 5, wherein the hanging pieces 3 are movably fixed on the hanging piece 1;
the hanger 3 is provided with a first clamping portion 31, the buckle strip 4 is provided with a second clamping portion 41 which is mutually clamped with the first clamping portion 31, the hanger 3 is further provided with a long straight groove 32 which enables the second clamping portion 41 to move in the long straight groove, the first clamping portion 31 is communicated with the long straight groove 32, the top plate 5 is provided with a first sliding groove 51, the bottom end of the buckle strip 4 is provided with an inserting plate 42 which is matched with the first sliding groove 51, and the hanger 3 is provided with a second sliding groove 33;
firstly, measuring the decoration size of the top wall surface to be decorated, calculating the decoration position of a suspender 2 of the top wall surface according to the measurement size, then marking marks on the top wall surface by using a marking pen, assembling the suspender 2 to the marking positions of the top wall surface by using an expansion bolt, then assembling a hanger 3 on a hanger sheet 1, then fixing the hanger sheet 1 and the suspender 2 mutually by using a clamping strip (not shown in the figure), adjusting the height of the suspender 2 by adjusting the expansion bolt, measuring the levelness of the hanger sheet 1 by using an auxiliary device of a level gauge, finally enabling the hanger sheet 1 to be horizontal, then upwards assembling a buckle line 4 by using a sucking disc so that the buckle line 4 can be clamped on the hanger 3, pushing the buckle line 4 forwards to enable one end of the buckle line 4 to be abutted against the side wall surface, and enabling the distance from the other end of the buckle line 4 to the side wall surface to be 1.2 times of the length of a top plate 5, the sucker is pulled downwards to separate the sucker from the buckle line 4, then the top plates 5 in the first row of top plates M (excluding the last top plate 5) are sequentially inserted into the buckle line 4 through the sucker, after the loading is finished, one person uses the negative pressure sucker to suck the last top plate 5 and lift the last top plate to the height of the installed first row of top plates M and align the top plates, the other person uses the negative pressure sucker to suck the buckle line 4 and move the buckle line 4 to enable the distance between the two ends of the buckle line 4 and the side wall surfaces at the two sides to be equal, at the moment, the last top plate 5 is also arranged on the buckle line 4, so that the first row of top plates M is arranged, then, sequentially installing a second row of top plates and a third row of top plates until the top wall surface to be decorated is full of the top plate 5, and finally adopting an edge closing process (putty scraping and emulsion paint brushing for edge closing treatment) to close the gap between the side wall surface and the top plate 5 and the gap between the top plate 5 and the top plate 5;
the second clamping portion 41 on the buckle line 4 is clamped with the first clamping portion 31 on the pendant 3, so that the buckle line 4 and the pendant 3 can be fixed, and the buckle line 4 is provided with the long straight groove 32 communicated with the second clamping portion 41, so that the buckle line 4 has an upward moving trend when being subjected to an upward acting force, when one top plate 5 needs to be disassembled, the buckle line 4 has an upward moving trend under the action of an external force and pushes the top plate 5 to be disassembled upwards, and the top plate 5 can be rapidly disassembled by a certain height difference between the two buckle lines 4;
firstly, the method comprises the following steps: only one leveling is needed in the process of installing the top plate 5, and two leveling is not needed, so that the installation efficiency is improved;
II, secondly: the hanging piece 3 is movably fixed on the hanging piece 1, and the top plate 5 is movably arranged on the buckle line 4, so that the top plate 5 can be conveniently and quickly installed, and no gap exists between the installed top plate 5;
thirdly, the method comprises the following steps: the first clamping portion 31 is communicated with the long straight groove 32, and the first clamping portion 31 can move in the long straight groove 32, so that the top plates 5 can be conveniently detached;
in conclusion, the assembly type suspended ceiling connecting structure and the installation method thereof can achieve the purpose of efficient installation and disassembly without nailing.
Example two:
referring to fig. 3 and 4, a buckle line 4 and a hanging member 3 of an assembly type suspended ceiling connection structure according to a second embodiment of the present invention are shown, and this embodiment further provides the following improved technical solution on the basis of the above embodiments, where the second clamping portion 41 includes a fixing plate 411, a gap groove 4111 is formed on the fixing plate 411, a protrusion 412 is arranged on the second clamping portion 41, the first clamping portion 31 is a rectangular groove 311, a cross section of the protrusion 412 is designed in a right trapezoid shape, by adopting the above structural arrangement, especially a length of a short side of the protrusion 412 designed in a right trapezoid shape is smaller than a length of the fixing plate 411, so that the second clamping portion 41 is conveniently clamped in the rectangular groove 311, and after the clamping is completed, a bottom of the protrusion 412 and a side surface of the fixing plate 411 are both abutted against the rectangular groove 311, so that a situation that the buckle line 4 does not shake after the clamping is completed, the connection is more stable.
Example three:
referring to fig. 4, a fastening line 4 of a connection structure of a fabricated suspended ceiling according to a third embodiment of the present invention is shown, and the present embodiment further provides the following improvements on the basis of the above embodiments: the fixed plate integrated into one piece is in the top of buckle lines sets up through adopting the casting process, plays the purpose of conveniently processing production buckle lines 4 to and the joint strength's of reinforcing fixed plate 411 and buckle lines 4 purpose, because buckle lines 4 are bearing the weight of roof 5 at the actual process, therefore stress concentration phenomenon can appear in the junction of fixed plate 411 and buckle lines 4, adopts this kind of technology can effectually solve this kind of problem.

Claims (9)

1. The utility model provides an assembled suspended ceiling connection structure which characterized in that: the hanging piece fixing device comprises a hanging piece (1), a hanging rod (2) used for fixing the hanging piece (1), a plurality of hanging pieces (3), a buckle line (4) and a top plate (5), wherein the hanging pieces (3) can be movably fixed on the hanging piece (1);
seted up first joint portion (31) on pendant (3), be equipped with on buckle lines (4) with second joint portion (41) of first joint portion (31) mutual joint, still seted up on pendant (3) and be used for making second joint portion (41) long straight flute (32) of activity in it, first joint portion (31) with long straight flute (32) communicate each other, first spout (51) have been seted up on roof (5), the bottom of buckle lines (4) be provided with first spout (51) complex picture peg (42), second spout (33) have been seted up on pendant (3).
2. An assembled suspended ceiling attachment structure as set forth in claim 1, wherein: second joint portion (41) are including fixed plate (411), clearance groove (4111) has been seted up on fixed plate (411), be equipped with arch (412) on second joint portion (41).
3. An assembled suspended ceiling attachment structure according to claim 2, wherein: the first clamping portion (31) is a rectangular groove (311), and the cross section of the protrusion (412) is designed in a right trapezoid shape.
4. An assembled suspended ceiling attachment structure as set forth in claim 3, wherein: the fixing plate (411) is integrally formed at the top of the buckle line (4).
5. An assembled suspended ceiling attachment structure as set forth in claim 1, wherein: the cross section of the hanging piece (1) is the same as that of the second sliding groove (33), and the hanging piece (1) penetrates through the second sliding groove (33).
6. An installation method using the fabricated suspended ceiling connection structure of any one of claims 1 to 5, wherein: the method comprises the following steps:
s1: installing a suspender, measuring the decoration size of the top wall surface to be decorated, calculating the decoration position of the suspender of the top wall surface according to the measurement size, then performing dotting identification on the top wall surface, and assembling the suspender to the dotting identification of the top wall surface through an expansion bolt;
s2: assembling a hanging piece and a hanging piece, wherein the hanging piece is inserted into the second sliding groove of the hanging piece, so that the hanging piece is installed on the hanging piece;
s3: mounting hanging pieces, namely mounting the hanging pieces between two adjacent hanging rods, fixing the hanging pieces and the hanging rods by adopting clamping strips, and adjusting the heights of the hanging rods by adjusting expansion bolts so as to keep the hanging pieces horizontal;
s4: installing a buckle line, and installing the second clamping part of the buckle line on the first clamping part of the pendant to ensure that the buckle line and the pendant are mutually fixed;
s5: installing a first row of top plates, pushing the buckle lines to enable one ends of the buckle lines to abut against the side wall surface, enabling the length of a gap between the other ends of the buckle lines and the side wall surface to be 1-2 times of the length of the top plates, sequentially inserting the top plates into the buckle lines, and enabling the plug boards to be inserted into the second sliding grooves;
s6: when the last top plate of the first row is installed, the last top plate is lifted to the height of the installed top plate and aligned, the buckle line slides towards the direction far away from the side wall surface until the inserting plate is inserted into the second sliding groove of the last top plate, and the installation of the top plates of the first row is completed;
s7: repeating the steps S2 to S6 to complete the installation of the top plates in a plurality of rows.
7. The method of installing an assembled suspended ceiling attachment structure according to claim 6, wherein: after the step S7 is executed, an edge folding process is performed between the top plates close to the wall and the wall, and an edge folding process is also performed between the top plates of each row.
8. The method of installing an assembled suspended ceiling attachment structure according to claim 6, wherein: when the step S3 is executed, the level of the hanging piece is measured by the auxiliary device of the level measuring instrument, and finally the hanging piece can be kept horizontal.
9. The method of installing an assembled suspended ceiling attachment structure according to claim 6, wherein: when step S5 is executed, when one end of the buckle line abuts against the side wall surface, the gap length between the other end of the buckle line and the side wall surface is 1.2 times the length of the top plate.
CN202110958539.8A 2021-08-20 2021-08-20 Assembly type suspended ceiling connecting structure and mounting method thereof Pending CN113622585A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110958539.8A CN113622585A (en) 2021-08-20 2021-08-20 Assembly type suspended ceiling connecting structure and mounting method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110958539.8A CN113622585A (en) 2021-08-20 2021-08-20 Assembly type suspended ceiling connecting structure and mounting method thereof

Publications (1)

Publication Number Publication Date
CN113622585A true CN113622585A (en) 2021-11-09

Family

ID=78386818

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110958539.8A Pending CN113622585A (en) 2021-08-20 2021-08-20 Assembly type suspended ceiling connecting structure and mounting method thereof

Country Status (1)

Country Link
CN (1) CN113622585A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114541639A (en) * 2022-04-11 2022-05-27 重庆集凯科技服务有限公司 Ceiling component and mounting method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016011902A1 (en) * 2014-07-25 2016-01-28 杨东佐 Suspended ceiling
KR20180094264A (en) * 2017-02-15 2018-08-23 대림산업 주식회사 Module Bar and Ceiling Finish Installation Structure using such Module Bar
CN110761479A (en) * 2019-11-29 2020-02-07 金螳螂精装科技(苏州)有限公司 Mounting structure and mounting method of assembly type ceiling
CN210597834U (en) * 2019-07-30 2020-05-22 北新集团建材股份有限公司 Assembled furred ceiling structure
CN112443076A (en) * 2020-11-25 2021-03-05 浙江亚厦装饰股份有限公司 Connecting member of ceiling decorative panel, ceiling system and mounting method
CN216305104U (en) * 2021-08-20 2022-04-15 浙江亚厦装饰股份有限公司 Assembled suspension type furred ceiling connection structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016011902A1 (en) * 2014-07-25 2016-01-28 杨东佐 Suspended ceiling
KR20180094264A (en) * 2017-02-15 2018-08-23 대림산업 주식회사 Module Bar and Ceiling Finish Installation Structure using such Module Bar
CN210597834U (en) * 2019-07-30 2020-05-22 北新集团建材股份有限公司 Assembled furred ceiling structure
CN110761479A (en) * 2019-11-29 2020-02-07 金螳螂精装科技(苏州)有限公司 Mounting structure and mounting method of assembly type ceiling
CN112443076A (en) * 2020-11-25 2021-03-05 浙江亚厦装饰股份有限公司 Connecting member of ceiling decorative panel, ceiling system and mounting method
CN216305104U (en) * 2021-08-20 2022-04-15 浙江亚厦装饰股份有限公司 Assembled suspension type furred ceiling connection structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114541639A (en) * 2022-04-11 2022-05-27 重庆集凯科技服务有限公司 Ceiling component and mounting method thereof

Similar Documents

Publication Publication Date Title
CN216305104U (en) Assembled suspension type furred ceiling connection structure
CN113622585A (en) Assembly type suspended ceiling connecting structure and mounting method thereof
CN1338555A (en) Metallic ceiling with curved decorative plate
CN203593498U (en) Elevator car wall structure with replaceable local decoration
CN207194279U (en) Integrated top mounting structure
CN114046013A (en) Dual-leveling decorative wall surface assembled type overhead mounting structure
CN202575643U (en) Inserted and hung type decorating component for elevator car interior decoration
CN216713478U (en) But quick assembly disassembly's prefabricated assembled indoor partition wall with finish coat
CN111305452A (en) Assembled ceiling structure and construction method thereof
CN211396425U (en) Assembled wall decoration back system
CN216076085U (en) Assembled wall leveling structure
CN205296536U (en) Joint formula keel connecting piece
CN113463822A (en) Embedded keel connecting piece, ceiling system and mounting method of ceiling system
CN112343278A (en) Metal plate mounting hook pendant based on clamping type keel system and facing wall construction method
RU132823U1 (en) INVISIBLE FASTENERS "ZIGZAG" FOR MOUNTING THE FACING BOARD
CN208473210U (en) A kind of fast-assembling cladding system
CN111456363A (en) Combined keel applied to wall surface installation plate and installation method thereof
CN214195368U (en) Assembled structure fitment integration building system
CN108222339B (en) High-precision unit system easy to construct
CN219011794U (en) Wall surface connecting structure for integrated kitchen and bathroom and wall surface system for integrated kitchen and bathroom
CN219080840U (en) Waterproof ceramic tile dry-hanging system
CN215594486U (en) Wallboard connection structure in decorating
CN216641218U (en) Wall mounting structure is maked somebody a mere figurehead to ready-package that wallboard reutilization can
CN216787474U (en) Panel connection structure and whole kitchen guarding
CN205329958U (en) Novel fossil fragments system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination