CN113565118A - Reverse construction steel platform foundation structure and construction method thereof - Google Patents

Reverse construction steel platform foundation structure and construction method thereof Download PDF

Info

Publication number
CN113565118A
CN113565118A CN202110899740.3A CN202110899740A CN113565118A CN 113565118 A CN113565118 A CN 113565118A CN 202110899740 A CN202110899740 A CN 202110899740A CN 113565118 A CN113565118 A CN 113565118A
Authority
CN
China
Prior art keywords
steel
welding
steel beam
steel pipe
reverse
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110899740.3A
Other languages
Chinese (zh)
Inventor
王春雷
白少亮
李瑞泽
童瑞华
张伟圣
杨和富
徐剑剑
于加元
韩尚甫
杨和金
张桂玲
程丽颖
仲刘佳
赵志慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingjian Group Co Ltd
Original Assignee
Qingjian Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingjian Group Co Ltd filed Critical Qingjian Group Co Ltd
Priority to CN202110899740.3A priority Critical patent/CN113565118A/en
Publication of CN113565118A publication Critical patent/CN113565118A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a reverse steel platform foundation structure, which comprises a steel pipe support, a column top cover plate and a cross steel beam, wherein the steel pipe support is arranged on the column top cover plate; the column top cover plate is fixedly arranged at the top of the steel tube support; the number of the steel pipe supports is four, and the steel pipe supports are respectively and fixedly arranged on the lower flange of the cross steel beam. The structure is reasonable in design and more stable; the labor intensity of constructors can be reduced, the construction period is shortened, and the cost of a large project part is saved; the problem that the free height of the tower crane cannot be met due to the fact that the site is narrow and small and surrounding buildings are dense is solved.

Description

Reverse construction steel platform foundation structure and construction method thereof
Technical Field
The invention relates to the field of buildings, in particular to a foundation structure of a reverse steel platform and a construction method thereof.
Background
The existing urbanization process of China is high in speed, urban land resources are short, a building to be built is often in the central zone of a city, and the surrounding environment is complex. And the owners are more normalized in pursuing the maximum utilization of the underground space. Research shows that under the condition of urban complex terrains, the construction site of a high-rise building is narrow, and if a truck crane is adopted for construction, the efficiency is very low while the construction cost is greatly increased. For projects with tight construction periods, the difficulty in achieving project goals is very great. In order to solve the problems in the prior art, the application provides a foundation structure of a reverse steel platform,
the reverse steel platform construction technology can solve the problems that the site is narrow and small, surrounding buildings are dense and the free height of the tower crane cannot be met, so that the reverse steel platform construction technology is very wide in application amount in future urbanization development.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provides a reverse steel platform foundation structure and a construction method thereof.
In order to solve the technical problems, the technical scheme provided by the invention is that the foundation structure of the reverse steel platform comprises the following components:
the steel pipe support comprises a steel pipe support, a column top cover plate and a cross steel beam;
the column top cover plate is fixedly arranged at the top of the steel tube support;
the number of the steel pipe supports is four, and the steel pipe supports are respectively and fixedly arranged on the lower flange of the cross steel beam.
As an improvement, the joint of the column top cover plate and the steel pipe support is welded by groove welding, and the grade of the welding line is first grade.
As the improvement, the cross girder steel includes that a main girder steel and two assist the girder steel to constitute, assist the one end fixed connection of girder steel in the middle part of main girder steel.
As an improvement, the lower flange of the cross-shaped steel beam is fully welded with the column top cover plate, the welding line of the fully welded part is groove welding, and the grade of the welding line is two-stage.
As an improvement, one end of the auxiliary steel beam is connected to the middle of the main steel beam in a welding mode and a bolt fixing mode.
As an improvement, two adjacent steel pipe supports are provided with connecting steel plates.
A construction method of a foundation structure of a reverse steel platform comprises the step of constructing the foundation structure of the reverse steel platform.
The method comprises the following steps:
firstly, positioning and paying off;
step two, the pile machinery takes place;
step three, rechecking;
fourthly, opening the drill;
fifthly, detecting that the mud proportion, the drilling depth and the sediment thickness meet the design and related specifications;
sixthly, installing a reinforcement cage and a steel pipe pile;
step seven, installing a concrete pouring guide pipe;
step eight, pouring concrete;
step nine, detecting the integrity of the pile body after 7 days;
step ten, picking and chiseling the pile head;
step eleven, detecting small strain;
step twelve, pass;
step thirteen, full welding of the flange of the lower opening of the ring plate;
fourteen, carrying out full welding on the upper opening of the ring plate;
fifthly, fully welding the lower opening seam of the ring plate;
sixthly, welding the steel beam 2(HN400x200x8x 13);
seventhly, welding the steel beam 1(HH800x500x20x 30);
eighteen, detecting whether the welding line meets the requirements of design and relevant acceptance specifications by ultrasonic waves;
nineteen, meeting the design requirements and relevant specifications;
twenty, mounting a tower crane;
twenty one, reinforcing the steel pipe column;
and twenty-two steps, reinforcing the basic nodes and performing waterproof treatment.
Compared with the prior art, the invention has the advantages that: the structure is reasonable in design and more stable; the labor intensity of constructors can be reduced, the construction period is shortened, and the cost of a large project part is saved; the problem that the free height of the tower crane cannot be met due to the fact that the site is narrow and small and surrounding buildings are dense is solved.
Drawings
Fig. 1 is a schematic top view of a foundation structure of a reverse steel platform and a construction method thereof according to the present invention.
FIG. 2 is a schematic structural diagram of a reverse steel platform foundation structure and a construction method thereof according to the present invention.
FIG. 3 is a schematic view of a steel pipe supporting structure of a reverse steel platform foundation structure and a construction method thereof according to the present invention.
FIG. 4 is a schematic diagram of a column top cover plate structure of a reverse steel platform foundation structure and a construction method thereof.
FIG. 5 is a schematic structural diagram of GL1 and column top cover plate of the reverse steel platform foundation structure and the construction method thereof.
FIG. 6 is a schematic view of a tower crane bearing platform beam GL1 at an elevation position of the foundation structure of the reverse construction steel platform and the construction method thereof.
FIG. 7 is a schematic view of a steel beam connection plane of a reverse steel platform foundation structure and a construction method thereof according to the present invention.
As shown in the figure: 1. steel pipe supports, 2, post crown plate, 3, cross girder steel, 4, main girder steel, 5, the supplementary girder steel, 6, the steel sheet.
Detailed Description
The following describes a reverse steel platform foundation structure in further detail with reference to the accompanying drawings.
With the combination of the attached drawings, the foundation structure of the reverse steel platform comprises a steel pipe support 1, a column top cover plate 2 and a cross-shaped steel beam 3;
the column top cover plate 2 is fixedly arranged at the top of the steel tube support 1;
the number of the steel pipe supports 1 is four, and the steel pipe supports are respectively and fixedly arranged on the lower flange of the cross steel beam 3.
And the joint part of the column top cover plate 2 and the steel pipe support 1 is welded by groove welding, and the grade of the welding line is one grade.
The cross steel beam 3 comprises a main steel beam 4 and two auxiliary steel beams 5, and one end of each auxiliary steel beam 5 is fixedly connected to the middle of the main steel beam 4.
The lower flange of the cross steel beam 3 is fully welded with the column top cover plate 2, the welding line of the fully welded part is groove welding, and the grade of the welding line is two-stage.
One end of the auxiliary steel beam 5 is connected to the middle of the main steel beam 4 in a welding mode and a bolt fixing mode.
Two adjacent steel pipe supports 1 are provided with connecting steel plates 6.
A construction method of a foundation structure of a reverse steel platform comprises the steps of constructing the foundation structure of the reverse steel platform,
the method comprises the following steps:
firstly, positioning and paying off;
step two, the pile machinery takes place;
step three, rechecking;
fourthly, opening the drill;
fifthly, detecting that the mud proportion, the drilling depth and the sediment thickness meet the design and related specifications;
sixthly, installing a reinforcement cage and a steel pipe pile;
step seven, installing a concrete pouring guide pipe;
step eight, pouring concrete;
step nine, detecting the integrity of the pile body after 7 days;
step ten, picking and chiseling the pile head;
step eleven, detecting small strain;
step twelve, pass;
step thirteen, full welding of the flange of the lower opening of the ring plate;
fourteen, carrying out full welding on the upper opening of the ring plate;
fifthly, fully welding the lower opening seam of the ring plate;
sixthly, welding the steel beam 2(HN400x200x8x 13);
seventhly, welding the steel beam 1(HH800x500x20x 30);
eighteen, detecting whether the welding line meets the requirements of design and relevant acceptance specifications by ultrasonic waves;
nineteen, meeting the design requirements and relevant specifications;
twenty, mounting a tower crane;
twenty one, reinforcing the steel pipe column;
and twenty-two steps, reinforcing the basic nodes and performing waterproof treatment.
The invention is embodied in conjunction with the accompanying figures 1-7. A reverse steel platform foundation structure comprises a steel pipe support 1, a column top cover plate 2 and a cross steel beam 3; the column top cover plate 2 is fixedly arranged at the top of the steel tube support 1; the number of the steel pipe supports 1 is four, and the steel pipe supports are respectively and fixedly arranged on the lower flange of the cross steel beam 3. The joint of the column top cover plate 2 and the steel pipe support 1 is welded by groove welding, and the grade of the welding line is first grade. The cross girder steel 3 includes that a main girder steel 4 and two assist girder steel 5 to constitute, and the one end fixed connection of assisting girder steel 5 is in the middle part of main girder steel 4. The lower flange of the cross steel beam 3 is fully welded with the column top cover plate 2, the welding line of the fully welded part is groove welding, and the grade of the welding line is two-stage. One end of the auxiliary steel beam 5 is connected to the middle part of the main steel beam 4 in a welding mode and a bolt fixing mode. Two adjacent steel pipe supports 1 are provided with connecting steel plates 6. The process flow of the reverse tower crane foundation is as follows: positioning and paying-off → pile machinery in place → rechecking → drilling → detecting mud weight, drilling depth and sediment thickness which meet design and relevant specifications → installing a steel reinforcement cage and a steel pipe pile → installing a concrete pouring guide pipe → concrete pouring → 7 days later detecting the integrity of a pile body → picking a pile head → small strain detection → qualification → full welding of a flange at the lower opening of a ring plate → full welding of a broken seam at the upper opening of the ring plate → full welding of a seam at the lower opening of the ring plate → full welding of a welded steel beam 2(HN400x200x8x13) → welded steel beam 1(HH800x500x20x30) → ultrasonic detecting whether the weld meets the requirements of the design and relevant acceptance specifications → meets the design requirements and relevant specifications → tower crane installation → steel pipe column reinforcement → foundation node reinforcement and waterproof treatment.
The present invention and its embodiments have been described above, and the description is not intended to be limiting, and the drawings are only one embodiment of the present invention, and the actual structure is not limited thereto. In summary, those skilled in the art should appreciate that they can readily use the disclosed conception and specific embodiments as a basis for designing or modifying other structures for carrying out the same purposes of the present invention without departing from the spirit and scope of the invention as defined by the appended claims.

Claims (7)

1. The utility model provides a contrary steel platform foundation structure of doing which characterized in that: comprises a steel pipe support (1), a column top cover plate (2) and a cross steel beam (3);
the column top cover plate (2) is fixedly arranged at the top of the steel tube support (1);
the number of the steel pipe supports (1) is four, and the steel pipe supports are respectively and fixedly arranged on the lower flange of the cross steel beam (3).
2. The inverted steel platform infrastructure of claim 1, wherein:
and the joint part of the column top cover plate (2) and the steel pipe support (1) is welded by groove welding, and the grade of the welding line is one grade.
3. The inverted steel platform infrastructure of claim 1, wherein:
the cross steel beam (3) comprises a main steel beam (4) and two auxiliary steel beams (5), and one end of each auxiliary steel beam (5) is fixedly connected to the middle of the main steel beam (4).
4. The inverted steel platform infrastructure of claim 1, wherein:
the lower flange of the cross steel beam (3) is fully welded with the column top cover plate (2), the welding line of the fully welded part is groove welding, and the grade of the welding line is two-stage.
5. A reverse steel platform substructure according to claim 3, characterized in that:
one end of the auxiliary steel beam (5) is connected to the middle of the main steel beam (4) in a welding mode and a bolt fixing mode.
6. The inverted steel platform infrastructure of claim 1, wherein:
and two adjacent steel pipe supports (1) are provided with connecting steel plates (6).
7. A construction method of a reverse steel platform foundation structure, comprising a reverse steel platform foundation structure, the reverse steel platform foundation structure being one of claims 1 to 6, characterized in that:
the method comprises the following steps:
firstly, positioning and paying off;
step two, the pile machinery takes place;
step three, rechecking;
fourthly, opening the drill;
fifthly, detecting that the mud proportion, the drilling depth and the sediment thickness meet the design and related specifications;
sixthly, installing a reinforcement cage and a steel pipe pile;
step seven, installing a concrete pouring guide pipe;
step eight, pouring concrete;
step nine, detecting the integrity of the pile body after 7 days;
step ten, picking and chiseling the pile head;
step eleven, detecting small strain;
step twelve, pass;
step thirteen, full welding of the flange of the lower opening of the ring plate;
fourteen, carrying out full welding on the upper opening of the ring plate;
fifthly, fully welding the lower opening seam of the ring plate;
sixthly, welding the steel beam 2(HN400x200x8x 13);
seventhly, welding the steel beam 1(HH800x500x20x 30);
eighteen, detecting whether the welding line meets the requirements of design and relevant acceptance specifications by ultrasonic waves;
nineteen, meeting the design requirements and relevant specifications;
twenty, mounting a tower crane;
twenty one, reinforcing the steel pipe column;
and twenty-two steps, reinforcing the basic nodes and performing waterproof treatment.
CN202110899740.3A 2021-08-06 2021-08-06 Reverse construction steel platform foundation structure and construction method thereof Pending CN113565118A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110899740.3A CN113565118A (en) 2021-08-06 2021-08-06 Reverse construction steel platform foundation structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110899740.3A CN113565118A (en) 2021-08-06 2021-08-06 Reverse construction steel platform foundation structure and construction method thereof

Publications (1)

Publication Number Publication Date
CN113565118A true CN113565118A (en) 2021-10-29

Family

ID=78170658

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110899740.3A Pending CN113565118A (en) 2021-08-06 2021-08-06 Reverse construction steel platform foundation structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN113565118A (en)

Similar Documents

Publication Publication Date Title
CN114482280B (en) Hexagonal section assembled annular supporting system and installation method thereof
CN211228066U (en) Connection structure of assembled steel pier and basis
CN110130387B (en) Construction process of integrated type sleeve cage
CN103866693A (en) Installing method of reinforced concrete bowstring rod arch bridge arch ribs and hanging auxiliary bridge
CN114922286A (en) Assembly type replaceable energy consumption hybrid connection node and installation method
CN110593269A (en) Turnover type structure support changing system and construction method thereof
CN215630078U (en) Reverse steel platform foundation structure
CN209854759U (en) Unilateral bolted connection structure of cavity intermediate layer steel pipe concrete structure shaft tower and basis
CN113565118A (en) Reverse construction steel platform foundation structure and construction method thereof
CN216689329U (en) Drilling platform based on marine steel batter pile support pile basis
CN113863736B (en) Construction process of continuous-span common-column C-shaped stock yard
CN201437613U (en) Steel beam integral feed-through type concrete-filled tubular column and steel beam connecting node
CN211257010U (en) Recoverable connection structure of double steel-pipe pile and steel truss crown beam
CN112252307A (en) Pile column structure for permanently-faced combined double-steel-pipe upright column pile
CN208088873U (en) The construction stress structure of multi-storey basement is extended under a kind of protection groups of building
CN207121922U (en) A kind of foundation structure in digging-free assembled stereoscopic garage
CN114348192B (en) Assembled FRP concrete guy cable tower type damping platform and construction method thereof
CN217840299U (en) Assembled replaceable energy-consumption hybrid connection node
CN212247837U (en) Corner reinforced type double-steel-plate combined hollow pier
CN114313127B (en) Assembled FRP concrete combined guy cable tower type damping platform group and construction method thereof
CN114313126B (en) Assembled FRP concrete combined guy cable tower platform system and construction method thereof
CN218580839U (en) Assembled muffjoint basis
CN218176130U (en) Beam rising column joint
CN218810024U (en) Can have enough to meet need roofing and hang basis
CN216157116U (en) But cyclic utilization's thick pillar formula operation platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination