CN113513320A - Tunnel tunneling support method for preventing rock burst and rockfall - Google Patents

Tunnel tunneling support method for preventing rock burst and rockfall Download PDF

Info

Publication number
CN113513320A
CN113513320A CN202110478087.3A CN202110478087A CN113513320A CN 113513320 A CN113513320 A CN 113513320A CN 202110478087 A CN202110478087 A CN 202110478087A CN 113513320 A CN113513320 A CN 113513320A
Authority
CN
China
Prior art keywords
tunnel
steel pipe
rockfall
tunneling
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110478087.3A
Other languages
Chinese (zh)
Inventor
李建斌
郑军
张仁川
高旭东
张浩文
刘伟
李恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Engineering Service Co Ltd
Original Assignee
China Railway Engineering Service Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Engineering Service Co Ltd filed Critical China Railway Engineering Service Co Ltd
Priority to CN202110478087.3A priority Critical patent/CN113513320A/en
Publication of CN113513320A publication Critical patent/CN113513320A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches

Abstract

The invention discloses a tunnel tunneling support method for preventing rockfall and rockfall, belongs to the technical field of tunnel support, and solves the problems that in the prior art, a safe support mode in a rockfall area is complicated in construction, construction progress is influenced, the support effect is poor, and safety is low. The invention comprises the following steps: step 1: construction preparation, prefabricating steel pipe sheets; step 2: drilling blasting, namely performing drilling blasting at a preset position according to design requirements; and step 3: slag is discharged, and soil and stones generated by blasting are cleaned and transported out of the tunnel; and 4, step 4: spraying concrete, namely spraying the concrete to the blasted surrounding rock; and 5: assembling the steel pipe sheets, namely assembling the steel pipe sheets on the surrounding rock after the concrete is sprayed; step 6: repeating the step 2-5, and performing tunneling and supporting of the next ring; and 7: and after the rear end surrounding rock is deformed stably, disassembling the steel pipe sheet at the rear end of the tunnel and assembling the steel pipe sheet at the front end of the tunnel for surrounding rock supporting. The invention can effectively improve the production efficiency, reduce the construction time and has higher safety.

Description

Tunnel tunneling support method for preventing rock burst and rockfall
Technical Field
The invention belongs to the technical field of tunneling, and particularly relates to a tunnel tunneling support method for preventing rockburst and rockfall.
Background
With the development of tunnel engineering, many hard rock tunnels pass through areas with high ground stress or expansion stress, however, when the areas with high ground stress or expansion stress are excavated, due to the influence of excavation load, the surrounding rocks are subjected to stress concentration and strain energy accumulation, so that the surrounding rocks are subjected to rock burst phenomena of random spatial cracking, ejection and throwing, which are commonly found in deep-buried tunnel faces, vaults and vaults. At present, the rockburst area is mainly protected by the following measures: (1) drilling an anchor rod hole to perform pressure relief treatment; (2) increasing the interval time between blasting excavation and subsequent procedures; (3) and (4) supporting by using a protective net or a trolley vertical frame.
In the existing tunnel construction, the phenomenon of rock burst is frequently generated when the tunnel passes through a region with high ground stress or expansion stress. The anchor rod hole pressure relief treatment or the passive protection of increasing the interval time between blasting excavation and subsequent processes is adopted, so that the construction progress is influenced, and the stress release degree is difficult to judge. In addition, a protective net or a trolley vertical frame support can be adopted for active protection. The protective net has the advantages of long service life, standardized installation procedure, easy spreading and the like, but the construction procedure is more complicated and complicated, and the construction progress cannot be ensured; the support of the trolley vertical frame can reduce the threat of rock burst to constructors and construction equipment to a certain extent, but the support effect is not good, and the safety is lower.
Disclosure of Invention
The invention provides a tunnel tunneling support method for preventing rockfall and rockburst, aiming at solving the problems that in the prior art, a safe support mode in a rockburst area is complicated in construction, influences construction progress, is poor in support effect and is low in safety, and the tunnel tunneling support method comprises the following steps: the production efficiency and the safety are improved, and the threat to constructors and equipment is reduced.
The technical scheme adopted by the invention is as follows:
a tunnel tunneling support method for preventing rock burst and rockfall comprises the following steps:
step 1: construction preparation, prefabricating steel pipe sheets;
step 2: drilling blasting, namely performing drilling blasting at a preset position according to design requirements;
and step 3: slag is discharged, and soil and stones generated by blasting are cleaned and transported out of the tunnel;
and 4, step 4: spraying concrete, namely spraying the concrete to the blasted surrounding rock;
and 5: assembling the steel pipe sheets, namely assembling the steel pipe sheets on the surrounding rock after the concrete is sprayed;
step 6: repeating the step 2-5, and performing tunneling and supporting of the next ring;
and 7: after the rear end surrounding rock is deformed stably, disassembling the steel pipe sheet at the rear end of the tunnel and assembling the steel pipe sheet at the front end of the tunnel for surrounding rock supporting;
and 8: and repeating the steps until the tunnel construction is completed.
After the technical scheme is adopted, when the tunnel is subjected to rock burst, the steel pipe sheet is extruded, the supporting counter force of the steel pipe sheet can resist the pressure of surrounding rock during rock burst, the stability of a rock body is further improved, the exposure time of the surrounding rock is reduced, the occurrence of rock burst and rock collapse is effectively prevented, small rock bursts and rock collapse are limited in a certain space, and finally the safety protection of the rock burst tunnel is realized. Compared with the pressure relief treatment of the anchor rod hole, the increase of the interval time between blasting excavation and subsequent procedures and the protective net, the method can realize the separation of drilling and blasting excavation and supporting, shortens the excavation circulation, is simple and convenient to operate, can effectively improve the production efficiency, and reduces the construction time. Compared with the support of the trolley vertical frame, the support of the method is more stable, the threat to constructors and equipment is further reduced, and the safety is higher.
Preferably, the size of the steel pipe sheet in the step 1 is adapted to the size of the tunnel profile, and the steel pipe sheet is provided with a prepared hole for anchor rod construction.
After the preferable scheme is adopted, anchor rod construction can be carried out through the preformed hole on the steel pipe sheet, and the strength and the safety of support are further improved.
Preferably, a three-armed drill jumbo is used for drilling in step 2.
Preferably, in the step 3, before tapping, the fan is turned on to ventilate the tunnel until the air in the tunnel reaches the specification.
After the adoption of the optimal scheme, the circulation of air in the tunnel can be accelerated, so that the air in the tunnel meets the construction requirement as soon as possible, and the construction safety is ensured.
Preferably, loose soil and stones on the tunnel face are cleaned during slag discharge in the step 3.
After adopting this preferred scheme, can prevent when strutting loose soil stone on the face and drop and injure constructor's the condition by a crashing object, the security is higher.
Preferably, in the step 5, the steel pipe pieces are assembled in the order from bottom to top.
After the preferred scheme is adopted, the segment assembly is more convenient and the construction is more convenient.
Preferably, when the steel pipe piece is assembled, the first pipe piece and the previous ring pipe piece are accurately leveled by using the leveling ruler, and the longitudinal bolt and the circumferential bolt are simultaneously screwed down, so that the steel pipe piece and the previous ring steel pipe piece are positioned on the same plane.
After the preferred scheme is adopted, the flatness of the assembled duct pieces can be improved.
In summary, due to the adoption of the technical scheme, the invention has the beneficial effects that:
1. when rock burst takes place in the tunnel, will extrude the steel-pipe piece, the pressure when surrounding rock burst can be kept out to the supporting counter-force of steel-pipe piece, and then improves the stability of rock mass, reduces the exposure time of surrounding rock, effectively prevents the emergence that the rock burst collapses the stone to with the fritter limit in certain space, finally realize the safety protection in rock burst tunnel.
2. Compared with the pressure relief treatment of the anchor rod hole, the increase of the interval time between blasting excavation and subsequent procedures and the protective net, the method can realize the separation of drilling and blasting excavation and supporting, shortens the excavation circulation, is simple and convenient to operate, can effectively improve the production efficiency, and reduces the construction time.
3. Compared with the support of the trolley vertical frame, the support of the method is more stable, the threat to constructors and equipment is further reduced, and the safety is higher.
Drawings
The invention will now be described, by way of example, with reference to the accompanying drawings, in which:
FIG. 1 is a schematic view of the present invention;
fig. 2 is a schematic structural view of a steel pipe sheet.
The drilling platform comprises a 1-three-arm drilling jumbo, a 2-tracked vehicle provided with a segment erector, 3-steel pipe segments and 4-reserved holes.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present application clearer, the technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are only a part of the embodiments of the present application, and not all the embodiments. The components of the embodiments of the present application, generally described and illustrated in the figures herein, can be arranged and designed in a wide variety of different configurations. Thus, the following detailed description of the embodiments of the present application, presented in the accompanying drawings, is not intended to limit the scope of the claimed application, but is merely representative of selected embodiments of the application. All other embodiments, which can be derived by a person skilled in the art from the embodiments of the present application without making any creative effort, shall fall within the protection scope of the present application.
In the description of the embodiments of the present application, it should be noted that the terms "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings or orientations or positional relationships that the products of the present invention are usually placed in when used, and are only used for convenience of description and simplicity of description, but do not indicate or imply that the devices or elements that are referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present application. Furthermore, the terms "first," "second," "third," and the like are used solely to distinguish one from another and are not to be construed as indicating or implying relative importance.
The present invention will be described in detail with reference to fig. 1.
A tunnel tunneling support method for preventing rock burst and rockfall comprises the following steps:
step 1: construction preparation:
mechanical preparation: the construction machinery and equipment (such as a three-arm rock drilling jumbo 1 in fig. 1 and a crawler 2 provided with a segment erector) to be used in the tunnel construction process are prepared, and the construction machinery is subjected to omnibearing inspection to ensure that the construction machinery can normally work.
Technical preparation: before construction, drawings and plan books are carefully consulted, specific geological conditions, hydrological environments, buildings around tunnels and the like of projects are comprehensively mastered, and top-to-bottom technical interaction work is carried out.
Preparing materials: preparing materials needed by construction, and ensuring that the materials can enter a field only when meeting relevant quality requirements. The steel pipe piece 3 is processed and finished in a prefabrication factory according to design parameters, the outer side of the processed steel pipe piece is ensured to be tightly attached to a tunnel rock wall, a preformed hole 4 (used for anchor rod construction and not shown in the figure) is formed in the steel pipe piece, and threaded holes are formed in the periphery of the steel pipe piece and used for longitudinal and circumferential connection between the steel pipe pieces.
Step 2: and (3) drilling and blasting, wherein corresponding construction lofting work is carried out according to the standard of a drawing before drilling, specific positions of peripheral holes, auxiliary holes and cut holes are sequentially found, the number of the peripheral holes, the auxiliary holes and the cut holes is accurately determined, then the three-arm rock drilling trolley is used for drilling, and then explosives are installed for blasting.
And step 3: and (5) deslagging, cleaning soil and stones generated by blasting and transporting the soil and stones out of the tunnel. And after the blasting, opening a fan to carry out ventilation work, and carrying out the next hole-entering slag-discharging work only when the gas in the hole body reaches the slag-discharging standard. The all-round cleaning work is carried out to loose soil and stones on the tunnel face in the deslagging link, so that the phenomenon that people are injured due to falling in the supporting link is avoided, and the next supporting work can be carried out after the deslagging work is completed.
And 4, step 4: and (4) spraying concrete, namely spraying the concrete to the blasted surrounding rock, wherein the spraying thickness is controlled to be 6-10 cm.
And 5: assembling the steel pipe sheets, namely assembling the steel pipe sheets on the surrounding rock after the concrete is sprayed. Before assembly, garbage and accumulated water at the installation part are thoroughly removed, and meanwhile, the steel pipe sheet must be accurately positioned, particularly the first ring needs to be placed in the middle; during assembly, a principle of bottom to top is adopted, the flatness of the duct piece, the advance amount of the ring surface and the ovality need to be well held, and a first duct piece and a previous ring pipe piece need to be accurately leveled by a horizontal ruler; adopt bolted connection between the steel-pipe piece, assemble the section of jurisdiction while screwing up and indulge, hoop connecting bolt, each section of jurisdiction need paste tightly and carry out safety protection through bolt adjustment gap and dislocation condition when assembling.
Step 6: repeating the steps 2-5, and performing tunneling and supporting of the next ring;
and 7: and after the rear-end surrounding rock is deformed stably, disassembling the steel pipe sheet at the rear end of the tunnel by using a pipe sheet assembling machine on the crawler and assembling the steel pipe sheet at the front end of the tunnel for surrounding rock supporting.
And 8: and repeating the steps, after the front end is tunneled and the concrete is sprayed, continuously disassembling the steel pipe sheet at the rear end to the front end for supporting until the tunnel construction is completed.
By adopting the invention, the safety protection can be carried out on the rock burst tunnel, the support of surrounding rocks is more stable, the threat to constructors and equipment is further lightened, the safety is higher, the working efficiency can be improved, the steel pipe sheet can be recycled, and the construction cost is reduced.
The above-mentioned embodiments only express the specific embodiments of the present application, and the description thereof is more specific and detailed, but not construed as limiting the scope of the present application. It should be noted that, for those skilled in the art, without departing from the technical idea of the present application, several changes and modifications can be made, which are all within the protection scope of the present application.

Claims (7)

1. A tunnel tunneling support method for preventing rock burst and rockfall is characterized by comprising the following steps:
step 1: construction preparation, prefabricating steel pipe sheets;
step 2: drilling blasting, namely performing drilling blasting at a preset position according to design requirements;
and step 3: slag is discharged, and soil and stones generated by blasting are cleaned and transported out of the tunnel;
and 4, step 4: spraying concrete, namely spraying the concrete to the blasted surrounding rock;
and 5: assembling the steel pipe sheets, namely assembling the steel pipe sheets on the surrounding rock after the concrete is sprayed;
step 6: repeating the step 2-5, and performing tunneling and supporting of the next ring;
and 7: after the rear end surrounding rock is deformed stably, disassembling the steel pipe sheet at the rear end of the tunnel and assembling the steel pipe sheet at the front end of the tunnel for surrounding rock supporting;
and 8: and repeating the steps until the tunnel construction is completed.
2. The tunneling and supporting method for preventing rockfall according to claim 1, wherein the size of the steel pipe sheet in the step 1 is adapted to the size of the tunnel profile, and the steel pipe sheet is provided with a prepared hole for anchor rod construction.
3. The method for tunneling and supporting rock burst prevention according to claim 1, wherein in the step 2, a three-arm rock drilling jumbo is used for drilling.
4. The tunneling support method for preventing rockfall and rockfall according to claim 1, wherein in the step 3, before slag tapping, the fan is started to ventilate the tunnel until air in the tunnel meets the specification requirements.
5. The tunneling support method for preventing rockfall according to claim 1, wherein in the step 3, loose earth and stones on the tunnel face are cleaned during deslagging.
6. The tunneling and supporting method for preventing rockfall according to claim 1, wherein in step 5, the steel pipes are assembled in a bottom-up order.
7. The tunneling support method for preventing rockfall and rockfall according to claim 1, wherein during the assembly of the steel pipe pieces, a first pipe piece and a previous ring pipe piece are accurately leveled by using a level ruler, and longitudinal and circumferential bolts are tightened simultaneously, so that the steel pipe pieces and the previous ring of steel pipe pieces are positioned on the same plane.
CN202110478087.3A 2021-04-30 2021-04-30 Tunnel tunneling support method for preventing rock burst and rockfall Pending CN113513320A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110478087.3A CN113513320A (en) 2021-04-30 2021-04-30 Tunnel tunneling support method for preventing rock burst and rockfall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110478087.3A CN113513320A (en) 2021-04-30 2021-04-30 Tunnel tunneling support method for preventing rock burst and rockfall

Publications (1)

Publication Number Publication Date
CN113513320A true CN113513320A (en) 2021-10-19

Family

ID=78063625

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110478087.3A Pending CN113513320A (en) 2021-04-30 2021-04-30 Tunnel tunneling support method for preventing rock burst and rockfall

Country Status (1)

Country Link
CN (1) CN113513320A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110129300A1 (en) * 2009-11-30 2011-06-02 Dimillo Tony Steel liners for tunnels
KR101838663B1 (en) * 2016-12-01 2018-03-14 주식회사 호반건설산업 strengthening method of rock tunnel fault fractured zone
CN108518232A (en) * 2018-04-11 2018-09-11 中铁十七局集团有限公司 The anti-rock burst method for protecting support of single-track railway tunnel of corresponding different rock burst intensity grades
CN110374636A (en) * 2019-07-09 2019-10-25 中铁十七局集团第二工程有限公司 A kind of construction method of tunnel rock burst security protection
CN110939468A (en) * 2019-12-27 2020-03-31 中水北方勘测设计研究有限责任公司 Assembly type supporting steel pipe piece of open type TBM (tunnel boring machine) and combined supporting method of assembly type supporting steel pipe piece and spray anchor
CN111350509A (en) * 2020-01-21 2020-06-30 中铁二十二局集团轨道工程有限公司 Muck improvement and grouting method for sandy gravel stratum tunnel shield construction
CN112343613A (en) * 2020-09-25 2021-02-09 辽宁三三工业有限公司 Construction method combining shield method and spray anchor support

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110129300A1 (en) * 2009-11-30 2011-06-02 Dimillo Tony Steel liners for tunnels
KR101838663B1 (en) * 2016-12-01 2018-03-14 주식회사 호반건설산업 strengthening method of rock tunnel fault fractured zone
CN108518232A (en) * 2018-04-11 2018-09-11 中铁十七局集团有限公司 The anti-rock burst method for protecting support of single-track railway tunnel of corresponding different rock burst intensity grades
CN110374636A (en) * 2019-07-09 2019-10-25 中铁十七局集团第二工程有限公司 A kind of construction method of tunnel rock burst security protection
CN110939468A (en) * 2019-12-27 2020-03-31 中水北方勘测设计研究有限责任公司 Assembly type supporting steel pipe piece of open type TBM (tunnel boring machine) and combined supporting method of assembly type supporting steel pipe piece and spray anchor
CN111350509A (en) * 2020-01-21 2020-06-30 中铁二十二局集团轨道工程有限公司 Muck improvement and grouting method for sandy gravel stratum tunnel shield construction
CN112343613A (en) * 2020-09-25 2021-02-09 辽宁三三工业有限公司 Construction method combining shield method and spray anchor support

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
徐建军: "岩土工程爆破技术", vol. 2015, 31 July 2015, 北京:冶金工业出版社, pages: 97 - 105 *

Similar Documents

Publication Publication Date Title
CN110487138B (en) Full-section smooth blasting construction method for high-altitude small-section long steep slope tunnel
CN104612695B (en) One acutely collapses shaft wall restoring and fastening method
US10662771B2 (en) Drill and blast method and apparatus for the same
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
CN108590711B (en) Lining structure of tunnel rock explosion section
CN108871131B (en) Carbon dioxide static blasting construction method for roadbed rock
CN113006825B (en) Arch changing construction method for tunnel collapse position
CN102278128B (en) High-stress poor rock roadway supporting process
CN110566236B (en) Combined supporting device and supporting method for pipe shed and steel support
CN111594179A (en) One-step forming construction method for excavation of large-section arch cover of underground excavated station of subway
CN112228079B (en) Construction method for newly-built tunnel by crossing existing line at small angle
CN113513320A (en) Tunnel tunneling support method for preventing rock burst and rockfall
CN112502730A (en) Steel arch frame for preventing collapse of roadway at underground rock crushing section and supporting method thereof
CN112796810A (en) Rock burst prevention multi-section anchoring energy consumption supporting device and supporting method
CN116517573A (en) Tunnel excavation method
JP2020159061A (en) Method for constructing work pit intersection in mountain tunnel construction
CN215170076U (en) A safety support structure for rock burst tunnel
CN115012429A (en) Supporting structure for exposing foundation pit for long time and construction method thereof
JPH09511036A (en) How to drill a rock cavity
CN113338979A (en) Hydraulic tunnel drilling trolley excavation construction method and device
KR101972268B1 (en) Detachable compensating plate tip structure and horizontal boring driving system including same and blasting method using same
CN111255473A (en) Excavation construction method of soft rock tunnel cantilever type heading machine
CN215890049U (en) Mine tunnel supporting device
CN113653516B (en) Active supporting structure and method for surrounding rock intrusion deformation after tunnel excavation supporting
CN113982639B (en) Tunnel lining full-ring dismantling and replacing construction method in unfavorable geological region

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination