CN113404534A - Method for preventing rock burst by staged fracturing of L-shaped ground horizontal well - Google Patents
Method for preventing rock burst by staged fracturing of L-shaped ground horizontal well Download PDFInfo
- Publication number
- CN113404534A CN113404534A CN202110770986.0A CN202110770986A CN113404534A CN 113404534 A CN113404534 A CN 113404534A CN 202110770986 A CN202110770986 A CN 202110770986A CN 113404534 A CN113404534 A CN 113404534A
- Authority
- CN
- China
- Prior art keywords
- fracturing
- well
- horizontal
- section
- horizontal section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/18—Methods of underground mining; Layouts therefor for brown or hard coal
Abstract
The invention discloses a method for preventing rock burst by staged fracturing of an L-shaped ground horizontal well, which comprises the following steps of: determining a fracturing layer position and a fracturing interval; constructing an L-shaped horizontal well vertical section on the ground, and embedding a sleeve to fix a well wall; starting deflecting at a design point A and extending to a fracturing layer, and starting constructing a horizontal section of the 1# well when drilling to the horizontal direction; adopting a retreating type fracturing 1# well horizontal section; plugging a deflecting section of the 1# well, then extending the vertical well, beginning reverse deflecting at a position which is not less than 10m below a design point A and extending to a fracturing layer, and beginning construction of a 2# well horizontal section when drilling to the horizontal direction; and adopting a retreating type fracturing 2# well horizontal section. According to the invention, the high-pressure hydraulic staged fracturing is carried out on the hard and difficult-to-collapse rock stratum covered on the coal face, so that the rock stratum is regularly collapsed, the rock stratum large-area suspended ceiling suddenly strides and falls to induce the rock burst of the coal face, and the safe and efficient mining of a mine is realized.
Description
Technical Field
The invention belongs to the technical field of coal face impact disaster prevention and control methods, and particularly relates to a method for preventing rock burst by staged fracturing of an L-shaped ground horizontal well.
Background
Rock burst is one of the main disasters faced by coal mining of deep mines, is getting more and more intense in China in recent years, and causes immeasurable loss to mines and personnel. According to statistics, the roof type rock burst of the deep mine coal face accounts for more than three quarters of the accidents of the roof type rock burst of the coal face, the main inducing factors of the roof type rock burst of the coal face are that large dynamic load is generated by sudden falling of a large-area suspended roof of a hard thick rock layer above a coal seam roof, and the high static load of a superposed working face induces the roof type rock burst of the coal face, so that how to avoid the large-area suspended roof of the hard roof of the coal face becomes the main research direction for solving the roof type rock burst.
Disclosure of Invention
The invention aims to provide a method for preventing rock burst by staged fracturing of an L-shaped ground horizontal well, which solves the problem that rock burst of a coal face is induced by sudden falling of a large-area suspended ceiling of a hard top plate of the existing coal face.
The technical scheme adopted by the invention is as follows: a method for preventing rock burst of an L-shaped ground horizontal well by staged fracturing comprises the following steps:
step 1, determining a fracturing position and a fracturing distance;
step 2, constructing an L-shaped horizontal well vertical section on the ground, and embedding a sleeve to fix a well wall;
step 3, starting deflecting at a design point A and extending to a fracturing layer, and starting constructing a horizontal section of the 1# well when drilling to the horizontal direction;
step 4, adopting a retreating type fracturing 1# well horizontal section;
step 5, after fracturing of the horizontal section of the 1# well is completed, plugging the deflecting section of the 1# well, then extending the vertical well, beginning reverse deflecting at a position which is not less than 10m below a design point A and extending to a fracturing layer, and beginning construction of the horizontal section of the 2# well when drilling to the horizontal direction;
and 6, adopting a retreating type fracturing 2# well horizontal section.
The present invention is also characterized in that,
in the step 1, a key layer of a coal face is determined according to a mine geological comprehensive histogram, three-zone observation of an adjacent working face, theoretical calculation and numerical simulation, a direct caving layer is determined according to the mine geological comprehensive histogram, a microseismic event and a seismic source position, and then a rock stratum between the key layer and the direct caving layer is selected to be determined as a fracturing layer.
In the step 1, the caving step of a rock stratum above a coal layer top plate of the coal face is determined according to the number of microseismic events and the working resistance of a hydraulic support of the working face, and the fracturing step is determined to be 1/2-1/3 of the caving step.
The step 4 specifically comprises the following steps:
4.1, ejecting 4-6 cluster perforations around the hole wall by using a perforating bullet at a fracturing position;
4.2, arranging 2 bridge plugs in the range of 20-50 m before and after the shower hole for plugging;
4.3, injecting high-pressure water into the 2 bridge plugs, and performing 360-degree fracturing on the high-pressure water through a perforation;
and 4.4, after fracturing one section, repeating the steps 4.1-4.3 at the next fracturing position until fracturing the horizontal section of the 1# well.
The retreating type fracturing mode of the 2# well horizontal section is the same as that of the 1# well horizontal section.
The invention has the beneficial effects that: the invention discloses a method for preventing rock burst by staged fracturing of an L-shaped ground horizontal well, which is characterized in that high-pressure hydraulic staged fracturing is carried out on a hard and difficult-to-collapse rock stratum covered on a coal face to enable the rock stratum to collapse regularly, so that the rock stratum large-area suspended ceiling suddenly strides and falls to avoid inducing the rock burst of the coal face, and the safe and efficient mining of a mine is realized.
Drawings
FIG. 1 is an implementation state diagram of a method for preventing rock burst by staged fracturing of an L-shaped ground horizontal well according to the invention;
FIG. 2 is a local state diagram of a deflecting section in the method for preventing and treating rock burst by staged fracturing of an L-shaped ground horizontal well.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings and specific embodiments.
The invention provides a method for preventing and controlling rock burst by staged fracturing of an L-shaped horizontal well on ground, which comprises the following steps as shown in figures 1 and 2:
step 1, determining a key layer of a coal face through a mine geological comprehensive histogram, three-zone observation (a caving zone, a fissure zone and a bending subsidence zone) of an adjacent working face, theoretical calculation and numerical simulation, determining a direct caving layer according to the mine geological comprehensive histogram, a microseismic event and a seismic source position, and then selecting a hard thick rock stratum between the key layer and the direct caving layer to determine the hard thick rock stratum as a fracturing layer; determining the caving step of a hard thick rock layer above a coal layer top plate of a coal face according to the number of microseismic events and the working resistance of a hydraulic support of the working face, wherein the fracturing step is determined to be 1/2-1/3 of the caving step;
step 2, finishing a road surface, erecting a derrick, constructing an L-shaped horizontal well vertical section on the ground, and embedding a sleeve to fix a well wall to prevent underground water from invading the well wall;
step 3, after the construction of the vertical shaft section is finished, the deviation is started at a design point A, the drill bit is accurately controlled to accurately drill along the deviation making section by utilizing the comprehensive geological guiding drilling technology, the horizontal drilling is continued according to the length of the designed horizontal section after the horizontal landing of the target rock stratum fracturing section, and the construction of the horizontal section of the No. 1 well is started;
and 4, after the horizontal section construction of the 1# well is completed, performing staged fracturing on the target rock stratum by using high-pressure water. The hydraulic fracturing adopts a retreating type, and specifically comprises the following steps:
4.1, ejecting 4-6 cluster perforations around the hole wall by using a perforating bullet at a fracturing position;
4.2, arranging 2 bridge plugs for plugging within the range of 20-50 m (based on the fracture spacing not exceeding) before and after the shower hole;
4.3, injecting high-pressure water into the 2 bridge plugs, and performing 360-degree fracturing on the high-pressure water through a perforation;
4.4, after fracturing one section, repeating the steps 4.1-4.3 at the next fracturing position until fracturing the horizontal section of the 1# well;
step 5, after fracturing of the horizontal section of the 1# well is completed, plugging the deflecting section of the 1# well, then extending the vertical well, beginning reverse deflecting at a position which is not less than 10m below a design point A and extending to a fracturing layer, and beginning construction of the horizontal section of the 2# well in the same way as the 1# well when drilling to the horizontal direction;
and 6, after the construction of the horizontal section of the 2# well is finished, repeating the step 4 and fracturing the horizontal section of the 2# well in a retreating mode until all the horizontal sections of the 2# well are fractured.
Through the mode, the method for preventing rock burst through staged fracturing of the L-shaped ground horizontal well disclosed by the invention has the advantages that the rock stratum which is covered on the coal face and hard and difficult to collapse is subjected to high-pressure hydraulic staged fracturing, so that the rock stratum is regularly collapsed, the rock stratum is prevented from suddenly striding over a large area of a suspended roof to induce the rock burst of the coal face, and the safe and efficient mining of a mine is realized. Still possess following characteristics:
1. all the equipment related by the invention is on the ground, and compared with underground construction, the size, power and number of the equipment are not limited, and the construction can be better, faster and more economic.
2. Compared with conventional blasting pressure relief, the hydraulic fracturing is safer.
3. The dual-purpose vertical shaft has the advantages that the dual-purpose vertical shaft is realized, 2L-shaped horizontal wells in different directions are constructed by repeatedly utilizing the vertical shaft section, and the economical efficiency is better.
Claims (5)
1. A method for preventing rock burst by staged fracturing of an L-shaped ground horizontal well is characterized by comprising the following steps of:
step 1, determining a fracturing position and a fracturing distance;
step 2, constructing an L-shaped horizontal well vertical section on the ground, and embedding a sleeve to fix a well wall;
step 3, starting deflecting at a design point A and extending to a fracturing layer, and starting constructing a horizontal section of the 1# well when drilling to the horizontal direction;
step 4, adopting a retreating type fracturing 1# well horizontal section;
step 5, after fracturing of the horizontal section of the 1# well is completed, plugging the deflecting section of the 1# well, then extending the vertical well, beginning reverse deflecting at a position which is not less than 10m below a design point A and extending to a fracturing layer, and beginning construction of the horizontal section of the 2# well when drilling to the horizontal direction;
and 6, adopting a retreating type fracturing 2# well horizontal section.
2. The method for preventing and treating rock burst by staged fracturing of the L-shaped ground horizontal well according to claim 1, wherein in the step 1, the key layer of the coal face is determined according to a mine geological comprehensive histogram, three-zone observation of an adjacent working face, theoretical calculation and numerical simulation, the direct cross-over layer is determined according to the mine geological comprehensive histogram, a microseismic event and a seismic source position, and then a rock stratum between the key layer and the direct collapse layer is selected to be determined as the fracturing horizon.
3. The method for preventing and treating rock burst by staged fracturing of the L-shaped ground horizontal well according to claim 1, wherein the caving step of the rock stratum above the coal stratum top plate of the coal face is determined according to the number of microseismic events and the working resistance of the hydraulic support of the working face in the step 1, and the fracturing step is determined to be 1/2-1/3 of the caving step.
4. The method for preventing and treating rock burst by staged fracturing of an L-shaped horizontal ground well according to claim 1, wherein the step 4 specifically comprises the following steps:
4.1, ejecting 4-6 cluster perforations around the hole wall by using a perforating bullet at a fracturing position;
4.2, arranging 2 bridge plugs in the range of 20-50 m before and after the shower hole for plugging;
4.3, injecting high-pressure water into the 2 bridge plugs, and performing 360-degree fracturing on the high-pressure water through a perforation;
and 4.4, after fracturing one section, repeating the steps 4.1-4.3 at the next fracturing position until fracturing the horizontal section of the 1# well.
5. The method for preventing and treating rock burst by staged fracturing of an L-shaped horizontal ground well according to claim 4, wherein the retreating fracturing mode of the horizontal section of the No. 2 well is the same as that of the horizontal section of the No. 1 well.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110770986.0A CN113404534B (en) | 2021-07-07 | 2021-07-07 | Method for preventing rock burst by staged fracturing of L-shaped ground horizontal well |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110770986.0A CN113404534B (en) | 2021-07-07 | 2021-07-07 | Method for preventing rock burst by staged fracturing of L-shaped ground horizontal well |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113404534A true CN113404534A (en) | 2021-09-17 |
CN113404534B CN113404534B (en) | 2023-05-02 |
Family
ID=77685581
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110770986.0A Active CN113404534B (en) | 2021-07-07 | 2021-07-07 | Method for preventing rock burst by staged fracturing of L-shaped ground horizontal well |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113404534B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113847083A (en) * | 2021-10-28 | 2021-12-28 | 重庆大学 | Rock burst control method for high-position huge-thickness hard top plate area |
CN114382453A (en) * | 2021-11-29 | 2022-04-22 | 陕西彬长孟村矿业有限公司 | Staged fracturing process for horizontal ground well for preventing and treating coal mine rock burst |
CN115030718A (en) * | 2022-04-26 | 2022-09-09 | 重庆大学 | Method for preventing and controlling impact mine pressure of thick and hard rock stratum through regional hydraulic fracturing |
CN115288654A (en) * | 2022-07-28 | 2022-11-04 | 陕西彬长孟村矿业有限公司 | Method for relieving pressure and preventing rock burst in blasting of ground horizontal well |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105807312A (en) * | 2016-03-15 | 2016-07-27 | 大连理工大学 | Coal mine roof rock mass vertical zone determination method based on micro-seismic monitoring |
US20190003258A1 (en) * | 2015-12-18 | 2019-01-03 | Modern Wellbore Solutions Ltd. | Tool Assembly and Process for Drilling Branched or Multilateral Wells with Whip-Stock |
CN109505577A (en) * | 2018-11-12 | 2019-03-22 | 重庆科技学院 | Hot dry rock recovery method |
CN111520119A (en) * | 2020-04-28 | 2020-08-11 | 中煤科工集团西安研究院有限公司 | Method for efficiently extracting coal bed gas by staged fracturing of large-spacing thin coal seam group multi-bottom horizontal well |
CN112855087A (en) * | 2021-03-22 | 2021-05-28 | 河北佐和佑石油技术发展有限公司 | Coal bed gas horizontal well system transformation method |
-
2021
- 2021-07-07 CN CN202110770986.0A patent/CN113404534B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20190003258A1 (en) * | 2015-12-18 | 2019-01-03 | Modern Wellbore Solutions Ltd. | Tool Assembly and Process for Drilling Branched or Multilateral Wells with Whip-Stock |
CN105807312A (en) * | 2016-03-15 | 2016-07-27 | 大连理工大学 | Coal mine roof rock mass vertical zone determination method based on micro-seismic monitoring |
CN109505577A (en) * | 2018-11-12 | 2019-03-22 | 重庆科技学院 | Hot dry rock recovery method |
CN111520119A (en) * | 2020-04-28 | 2020-08-11 | 中煤科工集团西安研究院有限公司 | Method for efficiently extracting coal bed gas by staged fracturing of large-spacing thin coal seam group multi-bottom horizontal well |
CN112855087A (en) * | 2021-03-22 | 2021-05-28 | 河北佐和佑石油技术发展有限公司 | Coal bed gas horizontal well system transformation method |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113847083A (en) * | 2021-10-28 | 2021-12-28 | 重庆大学 | Rock burst control method for high-position huge-thickness hard top plate area |
CN113847083B (en) * | 2021-10-28 | 2024-03-01 | 重庆大学 | Control method for rock burst of high-level huge-thickness hard top plate area |
CN114382453A (en) * | 2021-11-29 | 2022-04-22 | 陕西彬长孟村矿业有限公司 | Staged fracturing process for horizontal ground well for preventing and treating coal mine rock burst |
CN115030718A (en) * | 2022-04-26 | 2022-09-09 | 重庆大学 | Method for preventing and controlling impact mine pressure of thick and hard rock stratum through regional hydraulic fracturing |
CN115288654A (en) * | 2022-07-28 | 2022-11-04 | 陕西彬长孟村矿业有限公司 | Method for relieving pressure and preventing rock burst in blasting of ground horizontal well |
Also Published As
Publication number | Publication date |
---|---|
CN113404534B (en) | 2023-05-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110939442B (en) | Method for treating rock burst by pressure relief source in ground fracturing area | |
CN113404534B (en) | Method for preventing rock burst by staged fracturing of L-shaped ground horizontal well | |
CN113404535B (en) | Method for preventing rock burst by hydraulic fracturing of coal mine underground | |
CN102080518B (en) | Method for extracting gas from coal seam roof complex branched well | |
CN112593936B (en) | Advanced comprehensive control method for multi-disaster area of deep mine | |
CN112780340B (en) | Method for preventing rock burst in advance in underground coal mine area | |
WO2023273091A1 (en) | Method for preventing and controlling rock bursts in development roadway group | |
CN112879011B (en) | Method for controlling height of water guide crack zone by hard overburden rock pre-cracking weakening under aquifer | |
CN104763398A (en) | Mining method for deformed coal coalbed methane for V-shaped well bottom plate auxiliary layer | |
CN111827878B (en) | Method for quickly and accurately probing hidden water inrush channel of coal seam floor | |
AU2021106168A4 (en) | High-gas Coal Seam Group Pressure Relief Mining Method Based on Gob-side Entry Retaining in the First Mining Whole Rock Pressure Relief Working Face | |
CN106869966A (en) | A kind of method for blocking of absciss layer water supply source | |
CN109611146B (en) | Separation layer water drainage grouting method | |
CN114294046B (en) | Coal mine area full-coverage underground three-dimensional extraction method | |
CN115788435A (en) | System and method for preventing rock burst in coal mine from up and down in three-dimensional manner | |
CN113323715A (en) | Hard roof strong mine pressure and goaf gas disaster cooperative treatment method | |
CN113216912A (en) | Perforating gun for reducing mine earthquake grade and method for reducing mine earthquake grade through hydraulic fracturing | |
CN116771348A (en) | Method for reducing dynamic pressure influence of main roadway in last mining and optimizing stoping line coal pillar | |
CN111946343A (en) | Method for solving hard top plate collapse problem through ground vertical hole composite jet fracturing | |
CN108343400B (en) | Method for extracting coal seam group gas by directional drilling bedding | |
CN113107589B (en) | Advanced pre-drainage method for coal seam roof aquifer ground | |
CN114233369B (en) | Method for precisely eliminating coal and gas outburst by up-and-down combination | |
CN218454763U (en) | Outburst prevention structure for rock-lift gate of near-coal-seam shaft construction group | |
CN213980780U (en) | Coal face ground gas drilling hole diameter structure | |
CN217080448U (en) | Hard roof release construction structures in coal mine tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |