CN113404003A - Quick assembly's flood prevention sub-dike frame construction - Google Patents

Quick assembly's flood prevention sub-dike frame construction Download PDF

Info

Publication number
CN113404003A
CN113404003A CN202110831030.7A CN202110831030A CN113404003A CN 113404003 A CN113404003 A CN 113404003A CN 202110831030 A CN202110831030 A CN 202110831030A CN 113404003 A CN113404003 A CN 113404003A
Authority
CN
China
Prior art keywords
type groove
groove
support type
support
flood prevention
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110831030.7A
Other languages
Chinese (zh)
Inventor
张国兴
冯立佳
赵佳林
刘淑丽
赵士瑞
张玉婷
冯国杰
宁振平
张凯
王南
朱永涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Xingguo Flood Control Equipment Technology Co ltd
Original Assignee
Hebei Xingguo Flood Control Equipment Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Xingguo Flood Control Equipment Technology Co ltd filed Critical Hebei Xingguo Flood Control Equipment Technology Co ltd
Priority to CN202110831030.7A priority Critical patent/CN113404003A/en
Publication of CN113404003A publication Critical patent/CN113404003A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • E02B3/106Temporary dykes

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a quick-assembly flood prevention sub-bank frame structure, which comprises: a plurality of support groups that connect gradually, every support group all includes first support type groove and second support type groove, the one end in first support type groove with the one end in second support type groove is articulated so that the second bracing piece can be put into in the recess in first support type groove with be equipped with detachable between the second support type groove and be used for supporting first support type groove with the support type pole in second support type groove set up a plurality of fixed orificess that run through on the terminal surface in second support type groove. The invention has the advantages of quicker assembly, more stable and reliable connection, small occupied space and convenient carrying and storage, and can be folded and stored when not in use.

Description

Quick assembly's flood prevention sub-dike frame construction
Technical Field
The invention relates to the field of flood prevention and flood fighting facilities, in particular to a quickly-assembled flood prevention sub-bank frame structure.
Background
The flood control sub-dike is a small dike temporarily built on the top of the dike, and is a flood control and flood fighting facility for overcoming the dangerous flood overflow. The emergency rescue device is usually reserved as emergency rescue equipment for fixed-point warehouses in countries, drainage basins or provinces and cities, and is also directly equipped for mobile emergency rescue teams in various provinces and cities. The integral type structure that has changed traditional flood control sub-dyke frame has effectively solved traditional flood control sub-dyke frame and has dismantled the difficulty more, and is bulky, and the steadiness is poor, is not convenient for store and transport a difficult problem.
Disclosure of Invention
In order to solve the problems, the invention provides a flood prevention sub-bank frame structure which is convenient to disassemble and assemble.
In order to achieve the purpose, the technical scheme adopted by the invention is as follows:
a quick assembly's flood prevention sub-dike frame construction includes: a plurality of support groups that connect gradually, every support group all includes first support type groove and second support type groove, the one end in first support type groove with the one end in second support type groove is articulated so that the second bracing piece can be put into in the recess in first support type groove with be equipped with detachable between the second support type groove and be used for adjusting first support type groove with the support type pole of second support type groove contained angle set up a plurality of fixed orificess that run through on the terminal surface in second support type groove.
Optionally, the support type pole includes the body of rod, the both ends of the body of rod just have the internal thread for cavity, still include T type connecting piece, seted up on the outer wall of the vertical section of T type connecting piece with the screw thread that body of rod both ends screw thread matched with used, T type connecting piece horizontal segment is a cavity section of thick bamboo, and it is arranged in respectively first support type groove with in the recess in second support type groove, still include the connecting pin pole, the connecting pin pole passes respectively the horizontal segment of T type connecting piece and first support type groove with the lateral wall in second support type groove. The self-help arbitrary adjustment of the support angle of the frame is realized by the arrangement, and the problem of uneven ground on the rescue site is effectively solved.
Optionally, an adjusting handle is further disposed on the rod body.
Optionally, a plurality of pairs of L-shaped groove holes are formed in two side end faces of the first supporting type groove, a connecting groove pipe is arranged between the first supporting type grooves, and the connecting groove pipe is clamped in the L-shaped groove holes.
Optionally, a plurality of pairs of L-shaped groove holes are formed in two side end faces of the second support type groove, a connecting groove pipe is arranged between the second support type grooves, and the connecting groove pipe is clamped in the L-shaped groove holes.
Optionally, the connecting groove pipe is a hollow square groove pipe, connecting pieces are arranged at two ends of the connecting groove pipe, each connecting piece comprises an insertion connecting block inserted in the connecting groove pipe, a limiting block connected with the insertion connecting block, and a limiting cap connected with the limiting block, and the limiting block is clamped in the L-shaped groove hole.
Optionally, the diameter of the limiting cap is larger than the height of the groove hole in the horizontal direction of the L-shaped groove hole, and is smaller than the height of the grooves of the first supporting type groove and the second supporting type groove.
Optionally, two be equipped with between the connecting groove pipe and consolidate the type groove, it has two notches to consolidate type groove both ends, it passes through to consolidate the type groove the notch joint is two between the connecting groove pipe.
Optionally, the water baffle is further included, and the water baffle is fixed on the second support type groove through a bolt penetrating through the fixing hole.
Compared with the prior art, the invention has the technical progress that:
compared with the prior art, the flood control sub-dike frame overcomes the defects that the traditional flood control sub-dike frame cannot be folded and disassembled, the supporting angle cannot be adjusted randomly and the frames are connected unstably, the flood control sub-dike frame is formed by connecting a plurality of groups of supporting groups, each supporting group comprises a first supporting type groove, a second supporting type groove and a supporting type rod, the first supporting type groove and the second supporting type groove are hinged, the second supporting type groove can be directly placed into the first supporting type groove, the supporting type rods are arranged between the first supporting type groove and the second supporting type groove and can be disassembled, and the first supporting type groove and the second supporting type groove can be quickly folded after the lower supporting type rods are disassembled.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention and together with the description serve to explain the principles of the invention and not to limit the invention.
In the drawings:
FIG. 1 is a schematic structural diagram of the present invention.
FIG. 2 is a schematic view of another embodiment of the present invention
FIG. 3 is a schematic view of the T-shaped connector of the present invention.
Fig. 4 is a schematic structural view of the connecting groove pipe and the connecting piece of the present invention.
Fig. 5 is a schematic structural view of a reinforcing profiled groove of the present invention.
In the figure:
1-a first supporting groove, 2-a second supporting groove, 3-a supporting rod, 4-a fixing hole, 5-an L-shaped groove hole, 6-a connecting groove pipe, 7-a connecting piece, 8-a splicing block, 9-a limiting block, 10-a limiting cap, 11-a rod body, 12-a T-shaped connecting piece, 13-a connecting pin rod, 14-a reinforcing groove, 15-a notch and 16-an adjusting handle.
Detailed Description
The following several specific embodiments may be combined with each other, and details of the same or similar concepts or processes may not be repeated in some embodiments. Embodiments of the present invention will be described below with reference to the accompanying drawings.
As shown in fig. 1 and 2, the invention discloses a rapidly assembled flood prevention sub-bank frame structure, a plurality of support groups may be connected to each other, and two support groups are taken as an example in this embodiment. In this embodiment, every support group all includes first support type groove 1 and second support type groove 2, and the one end in first support type groove 1 and the one end in second support type groove 2 are articulated so that first support type groove 1 and second bracing piece 2 rotatable coupling for place second bracing piece 2 in the recess in first support type groove 1, conveniently accomodate and assemble. Be equipped with the support type pole 3 that detachable is used for supporting first support type groove 1 and second support type groove 2 between first support type groove 1 and second support type groove 2, set up a plurality of fixed orificess 4 that run through on the terminal surface in second support type groove 2, still include the breakwater, the breakwater can be fixed the breakwater on second support type groove 2 through the bolt that passes fixed orifices 4 or other mountings, no longer detailed in this embodiment.
Specifically, as shown in fig. 3, the support-type rod 3 includes a rod body 11, two ends of the rod body 11 are hollow and have internal threads, and further includes a T-shaped connector 12, threads matched with the threads at the two ends of the rod body 11 are disposed on an outer wall of a vertical section of the T-shaped connector 12, a horizontal section of the T-shaped connector 12 is a hollow cylinder and is respectively disposed in grooves of the first support-type groove 1 and the second support-type groove 2, and further includes a connection pin 13, the connection pin 13 respectively penetrates through a horizontal section of the T-shaped connector 12 and side walls of the first support-type groove 1 and the second support-type groove 2, so as to limit movement of the T-shaped connector 12, because the rod body 11 can be screwed in and out in the T-shaped connector 12, the present invention can rapidly pack up the first support-type groove 1 and the second support-type groove 2 after the lower support-type rod is disassembled, and can be very conveniently assembled when in use, simultaneously, the angle between the first supporting type groove 1 and the second supporting type groove 2 can be changed by screwing out different lengths through the rod body 11, and different inclination angles are formed to adapt to different use conditions. For better rotation of the lever body 11, an adjustment handle 16 is further provided on the lever body 11 in this embodiment.
Further, in order to make whole more firm, a plurality of L type slot 5 have all been seted up on two side end faces in first support type slot 1, be equipped with connecting slot pipe 6 between two first support type slot 1, connecting slot pipe 6 joint is in L type slot 5, it is same, also a plurality of L type slot 5 of pair have all been seted up on two side end faces in second support type slot 2, be equipped with connecting slot pipe 6 between two second support type slot 2 equally, connecting slot pipe 6 joint is in L type slot 5, connecting slot pipe 6 between two second support type slot 2 is not only for making whole more firm, also can play the supporting role to the breakwater after adding the breakwater.
Specifically, in this embodiment, combine fig. 1 and fig. 4, connecting slot pipe 6 is hollow square groove pipe, is equipped with connecting piece 7 at connecting slot pipe 6 both ends, and connecting piece 7 is including pegging graft in connecting slot pipe 6 interpolation piece 8, with the stopper 9 that the piece 8 is connected of pegging graft and the spacing cap 10 of being connected with stopper 9, and wherein, stopper 9 is the rectangle piece, and its joint forms self-locking structure in L type slotted hole 5, prevents that connecting slot pipe 6 from rotating. The diameter of the limiting cap 10 is larger than the height of the groove hole in the horizontal direction of the L-shaped groove hole 5 and smaller than the height of the grooves of the first supporting type groove 1 and the second supporting type groove 2, the connecting groove pipes 6 are arranged between the two first supporting type grooves 1 and between the two second supporting type grooves 2, so that the stability of the whole frame is guaranteed, and meanwhile, heavy objects can be placed on the connecting groove pipes 6 between the two first supporting type grooves 1, so that the stability of the whole frame is strengthened. Meanwhile, in order to be more stable, a plurality of reinforcing grooves 14 are formed between the two connecting groove pipes 6, and with the aid of the drawings of fig. 1 and 5, two notches 15 are formed in two ends of each reinforcing groove 14, and the reinforcing grooves 14 are clamped between the two connecting groove pipes 6 through the notches 15.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that changes may be made in the embodiments and/or equivalents thereof without departing from the spirit and scope of the invention. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the scope of the claims of the present invention.

Claims (9)

1. The utility model provides a quick assembly's flood prevention sub-dike frame construction which characterized in that includes: a plurality of support groups that connect gradually, every support group all includes first support type groove (1) and second support type groove (2), the one end of first support type groove (1) with the one end of second support type groove (2) is articulated so that second bracing piece (2) can be put into in the recess of first support type groove (1) with be equipped with detachable between second support type groove (2) and be used for supporting first support type groove (1) with support type pole (3) of second support type groove (2) set up a plurality of fixed orificess (4) that run through on the terminal surface of second support type groove (2).
2. The rapidly assembled flood prevention sub-bank frame structure according to claim 1, wherein: support type pole (3) including the body of rod (11), the both ends of the body of rod (11) are the cavity and have the internal thread, still include T type connecting piece (12), seted up on the outer wall of T type connecting piece (12) vertical section with the screw thread that body of rod (11) both ends screw thread cooperateed and uses, T type connecting piece (12) horizontal segment is a cavity section of thick bamboo, and it is arranged in respectively first support type groove (1) with in the recess of second support type groove (2), still including connecting pin pole (13), connecting pin pole (13) are passed respectively the horizontal segment of T type connecting piece (12) and first support type groove (1) with the lateral wall of second support type groove (2).
3. The rapidly assembled flood prevention sub-bank frame structure according to claim 2, wherein: an adjusting handle (16) is also arranged on the rod body (11).
4. The rapidly assembled flood prevention sub-bank frame structure according to claim 1, wherein: a plurality of pairs of L-shaped slotted holes (5) are formed in two side end faces of the first supporting type grooves (1), connecting groove pipes (6) are arranged between the first supporting type grooves (1), and the connecting groove pipes (6) are clamped in the L-shaped slotted holes (5).
5. The rapidly assembled flood prevention sub-bank frame structure according to claim 1, wherein: a plurality of pairs of L-shaped slotted holes (5) are formed in two side end faces of the second supporting type grooves (2), connecting groove pipes (6) are arranged between the second supporting type grooves (2), and the connecting groove pipes (6) are clamped in the L-shaped slotted holes (5).
6. The rapidly assembled flood prevention sub-bank frame structure according to any one of claims 4 or 5, wherein: the connecting groove pipe (6) is a hollow square groove pipe, the two ends of the connecting groove pipe (6) are provided with connecting pieces (7), each connecting piece (7) comprises an insertion block (8) inserted into the connecting groove pipe (6), a limiting block (9) connected with the insertion block (8) and a limiting cap (10) connected with the limiting block (9), and the limiting blocks (9) are clamped in the L-shaped groove holes (5).
7. The rapidly assembled flood prevention sub-bank frame structure according to claim 6, wherein: the diameter of the limiting cap (10) is larger than the height of the horizontal slotted hole of the L-shaped slotted hole (5) and smaller than the height of the grooves of the first supporting type groove (1) and the second supporting type groove (2).
8. The rapidly assembled flood prevention sub-bank frame structure according to claim 7, wherein: two be equipped with between connecting groove pipe (6) and consolidate type groove (14), it has two notch (15) to consolidate type groove (14) both ends, it passes through to consolidate type groove (14) notch (15) joint is two between connecting groove pipe (6).
9. The rapidly assembled flood prevention sub-bank frame structure according to claim 1, wherein: the water baffle is fixed on the second support type groove (2) through bolts penetrating through the fixing holes (4).
CN202110831030.7A 2021-07-22 2021-07-22 Quick assembly's flood prevention sub-dike frame construction Pending CN113404003A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110831030.7A CN113404003A (en) 2021-07-22 2021-07-22 Quick assembly's flood prevention sub-dike frame construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110831030.7A CN113404003A (en) 2021-07-22 2021-07-22 Quick assembly's flood prevention sub-dike frame construction

Publications (1)

Publication Number Publication Date
CN113404003A true CN113404003A (en) 2021-09-17

Family

ID=77687426

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110831030.7A Pending CN113404003A (en) 2021-07-22 2021-07-22 Quick assembly's flood prevention sub-dike frame construction

Country Status (1)

Country Link
CN (1) CN113404003A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030156903A1 (en) * 2002-02-19 2003-08-21 Herb Wiseman Frame members for a portable dam
CN207891823U (en) * 2018-02-05 2018-09-21 中国水利水电第八工程局有限公司 A kind of flood-control water retaining device
CN209277091U (en) * 2018-11-27 2019-08-20 石家庄夯迈动力科技有限公司 Assembled flood control sub-embankment
CN215857481U (en) * 2021-07-22 2022-02-18 河北兴国防汛设备科技有限公司 Quick assembly's flood prevention sub-dike frame construction

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030156903A1 (en) * 2002-02-19 2003-08-21 Herb Wiseman Frame members for a portable dam
CN207891823U (en) * 2018-02-05 2018-09-21 中国水利水电第八工程局有限公司 A kind of flood-control water retaining device
CN209277091U (en) * 2018-11-27 2019-08-20 石家庄夯迈动力科技有限公司 Assembled flood control sub-embankment
CN215857481U (en) * 2021-07-22 2022-02-18 河北兴国防汛设备科技有限公司 Quick assembly's flood prevention sub-dike frame construction

Similar Documents

Publication Publication Date Title
CN215857481U (en) Quick assembly's flood prevention sub-dike frame construction
CN113404003A (en) Quick assembly's flood prevention sub-dike frame construction
CN108979134B (en) Construction method of floor slab supporting system
CN212012032U (en) Internal support device for sleeve box and sleeve box
CN212000881U (en) Foldable flood prevention sub-dike of assembly
CN211200268U (en) Hydraulic dam for disaster relief
CN213573385U (en) Rail guard for building engineering
CN213870440U (en) Anti-toppling pump special for fountain
CN210530477U (en) Disaster relief tent convenient to build and dismantle
CN112539002A (en) Temporary enclosure structure for archaeological construction site
CN216239902U (en) Outer wall supports protection device for construction
CN207383107U (en) The ornamental and afforestation trees fender bracket poured with water storage
CN112127497A (en) Civil engineering antidetonation structure
CN217106323U (en) Supporting construction based on construction safety
CN217269022U (en) Old district reforms transform and uses external reinforcing beam
CN117145116B (en) Vertical self-balancing hyperboloid cable net curtain wall supporting system
CN210462131U (en) Adjustable connecting piece for supporting platform
CN217461556U (en) A antidetonation reinforcing apparatus for construction is built in school's room
CN216840917U (en) High firm large-span food and beverage tent of no stand
CN217269272U (en) Fence convenient to splice for building construction
CN220607922U (en) Connecting framework
CN215803042U (en) Intelligent combined mounting frame for building
CN217759868U (en) Scaffold frame for collapsible building construction
CN219175459U (en) Grid unit structure with elevation adjusting function
CN214273214U (en) Archaeology building site encloses fender structure temporarily

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination