CN113356189A - Full-sleeve hole forming construction method for rotary drilling rig - Google Patents

Full-sleeve hole forming construction method for rotary drilling rig Download PDF

Info

Publication number
CN113356189A
CN113356189A CN202110686817.9A CN202110686817A CN113356189A CN 113356189 A CN113356189 A CN 113356189A CN 202110686817 A CN202110686817 A CN 202110686817A CN 113356189 A CN113356189 A CN 113356189A
Authority
CN
China
Prior art keywords
pile
rotary drilling
drilling rig
construction
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110686817.9A
Other languages
Chinese (zh)
Inventor
王涛
王俊才
田国锐
高志峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN202110686817.9A priority Critical patent/CN113356189A/en
Publication of CN113356189A publication Critical patent/CN113356189A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B27/00Containers for collecting or depositing substances in boreholes or wells, e.g. bailers, baskets or buckets for collecting mud or sand; Drill bits with means for collecting substances, e.g. valve drill bits
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B3/00Rotary drilling

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Geology (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Civil Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to the technical field of full-casing cast-in-place pile construction, in particular to a full-casing hole forming construction method of a rotary drilling rig. The method comprises the following steps: s1, construction preparation: s11, leveling and hardening the field; s12, testing the pile before the full-sleeve rotary-digging pile is formed; s2, construction of guide walls: s21, leveling the field; s22, pile position measuring and placing; s23, excavating a guide wall groove; s24, binding steel bars; s25, constructing a template; s26, performing concrete pouring construction; s3, constructing the full-casing rotary excavating pile: s31, positioning the rotary drilling rig; s32, installing a steel sleeve driving sleeve device of the rotary drilling rig and connecting a steel sleeve; s33, taking soil and forming holes; s34, hoisting the reinforcement cage; s35, pouring concrete; and S36, forming a pile by drawing a pipe. The invention obviously improves the construction efficiency while ensuring the construction quality, has no mud pollution in the construction process and is green and environment-friendly. The method is mainly applied to the aspect of full casing pipe hole forming construction of the rotary drilling rig.

Description

Full-sleeve hole forming construction method for rotary drilling rig
Technical Field
The invention relates to the technical field of full-casing cast-in-place pile construction, in particular to a full-casing hole forming construction method of a rotary drilling rig.
Background
In recent years, a rotary drilling rig is used as a relatively advanced construction machine in cast-in-situ bored pile construction, and has the advantages of wide pile diameter application range, adaptability to various geological conditions, accurate pile position positioning, good hole forming quality, high automation degree, flexibility and convenience in movement and the like, so that the rotary drilling rig is particularly environment-friendly and high in working efficiency, and shows obvious superiority in the construction of urban high-rise building foundations and expressway bridge pile foundations.
The mud retaining wall process is generally adopted for hole forming of the rotary drilling rig, when the geological conditions are poor, the mud retaining wall process of the rotary drilling rig hardly ensures the pile forming quality, and the stress release of surrounding strata is easily caused, so that deformation and settlement of surrounding buildings and the ground are easily caused; the slurry protection wall pile of the rotary drilling rig has poor appearance quality. Therefore, the existing enclosure structure of the deep foundation pit of the front-line city generally does not adopt a mud dado construction process of a rotary drilling rig, but adopts a hydraulic steel sleeve full-length dado and a mechanical punching and grabbing hole forming process, but the construction efficiency of the hydraulic steel sleeve full-length dado and mechanical punching and grabbing hole forming process is too slow, the difference from the hole forming construction efficiency of the rotary drilling rig is larger, and the hydraulic steel sleeve full-length dado and mechanical punching and grabbing hole forming process needs a plurality of machines to cooperate with each other to operate and occupy a larger field.
Disclosure of Invention
In order to overcome the defects in the prior art, the invention provides a rotary drilling rig full casing pipe hole forming construction method which has strong site adaptability and high construction speed, reduces the construction cost, improves the construction quality, has small environmental pollution and is easy to popularize and use for reference.
In order to solve the technical problems, the technical scheme adopted by the invention is as follows:
a rotary drilling rig full casing pipe hole forming construction method comprises the following steps:
s1, construction preparation: s11, leveling and hardening the field; s12, testing the pile before the full-sleeve rotary-digging pile is formed;
s2, construction of guide walls:
s21, leveling the field: removing impurities on the surface of the ground, and filling and rolling the groove for the migration of the ground pipeline;
s22, pile position measuring and placing;
s23, excavating a guide wall groove: after the pile position lofting line meets the requirements, the groove can be excavated, and the groove is excavated by adopting mechanical cooperation and manual operation;
s24, binding steel bars;
s25, template construction: the template adopts a self-made integral steel mold, and the diameter of the template of the positioning hole of the guide wall reserved occlusive pile is 4cm larger than the diameter of the pile;
s26, concrete pouring construction: when concrete is poured, the two sides are symmetrically and alternately carried out, and the mold is strictly prevented from moving;
s3, constructing the full-casing rotary excavating pile:
s31, positioning the rotary drilling rig;
s32, installing a steel sleeve driving sleeve device of the rotary drilling rig and connecting a steel sleeve;
s33, taking soil and forming holes: after the pile driver is in place, aligning the center of the steel sleeve to the center of the pile position, aligning the verticality of the mast, rotating the driving sleeve to press the steel sleeve downwards, then detaching the driving sleeve and the steel sleeve, and taking soil from the sleeve by using a rotary drilling bit;
s34, hoisting the reinforcement cage: the top elevation of the reinforcement cage is controlled to be correct when the reinforcement cage is installed;
s35, pouring concrete;
s36, forming a pile by drawing a pipe: and (3) pouring concrete and drawing the pipe, and keeping the bottom of the sleeve not less than 2.5m lower than the concrete surface all the time.
In the step S22, the coordinates of the center line of the row pile are calculated according to the coordinates provided by the design drawing and the external placement of 100mm, the total station is adopted to perform on-site lofting according to the plane control point, and the fender pile is made to serve as the control center line of the guide wall construction.
In the step S24, after the trench is excavated, wall-guiding reinforcing steel bars are bound, the wall-guiding reinforcing steel bars are formed by phi 12 deformed steel bars, the wall-guiding reinforcing steel bars are arranged in a single-layer bidirectional manner, the reinforcing steel bars are arranged at intervals of 200 × 200, and the horizontal reinforcing steel bars are arranged on the inner side.
In the step S31, after the strength of the guide wall reaches the standard, the template is removed, the center position of the rotary drilling pile is repositioned, the point position is detected on the top surface of the guide wall and is used as a positioning control point of the rotary drilling rig, the rotary drilling rig is moved to the correct position, and the center of the drill bit of the rotary drilling rig is aligned with the center position of the rotary drilling pile.
In the step S32, the maximum height of the driving head of the rotary drilling rig from the ground is 5m, the length of the standard section of the steel sleeve is designed to be 4m, and the length of the first section of the steel sleeve of the pipe section with the tool bit is designed to be 5 m. Drilling a hole by a rotary drilling rig at a proper position near a pile position, wherein the drilling depth is 3-4 m, then hoisting a first section of steel sleeve into an auxiliary hole by using an auxiliary hook of the rotary drilling rig, detaching a barrel drill bit and a collision bearing body from the rotary drilling rig, installing a driving sleeve device, then reinstalling an upper barrel drill bit, horizontally moving a drill rod, inserting a driving sleeve into the first section of steel sleeve, and locking the driving sleeve and the steel sleeve together by rotating the driving sleeve.
In the step S33, the depth of the bottom opening of the casing pipe ahead of the excavation surface is always kept to be not less than 0.5m, after soil sampling is completed, the next section of steel casing pipe is connected with the driving sleeve in the auxiliary hole, and finally two sections of steel casing pipes are connected by adopting the same method.
In the step S35, if there is water in the hole, an underwater concrete pouring method is used for construction, and if there is no water in the hole, a dry hole pouring method is used for construction, and concrete vibration should be reinforced.
Compared with the prior art, the invention has the beneficial effects that:
the chassis of the rotary drilling rig is crawler-type, so that the rotary drilling rig is convenient to walk. The front end of the rotary drilling rig is provided with a drill bit, so that the rotary drilling rig is small in size, free of other auxiliary facilities and strong in adaptability to narrow places; the steel sleeve pressing speed and the pile core soil taking speed are increased, so that the hole forming speed is greatly increased; the service time of the construction machine is reduced; the method can effectively solve the problems of hole collapse, necking, high filling coefficient and the like when the ordinary construction method is adopted for cast-in-place pile construction in urban high fill, karst landform, quicksand and the like, and the construction method has wide corresponding range. The invention obviously improves the construction efficiency while ensuring the construction quality, has no mud pollution in the construction process and is green and environment-friendly.
Detailed Description
The technical solutions in the embodiments of the present invention are clearly and completely described below, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
A rotary drilling rig full casing pipe hole forming construction method comprises the following steps:
s1, construction preparation: s11, leveling and hardening the site, hardening the temporary construction road by adopting concrete, filling the ground of the rest site by stone powder or broken bricks and concrete slag, wherein the thickness is not less than 300mm, and rolling firmly and flatly to ensure the safe walking of the construction machinery; adopting mechanical cooperation to manually dig grooves and flatten the guide plate of the secant pile, wherein the elevation error is less than +/-20 mm, and the flatness is less than 10 mm;
s12, testing the pile before the full-sleeve rotary-digging pile is formed; the purpose of pile testing is to verify the design geology and obtain detailed geological parameters; providing a basis for finally determining the pile length; the adaptability of the rotary drilling rig in drilling construction and the construction efficiency of the rotary drilling rig in each stratum are researched; determining a hole cleaning method suitable for the full-casing rotary drilling hole; researching the optimal method for the reliability and the setting of the measure of the protective layer of the reinforcement cage; determining a reasonable mechanical and personnel configuration scheme through a test; verifying the rationality of the concrete pouring mode and the process of the rotary excavating pile; the construction process of the full-casing rotary excavating pile and the reasonable design of a drilling machine can be verified through pile testing, and the concrete supply capacity of a mixing station can be verified, so that improvement can be realized in construction. The lifting speed, the rotating speed, the drill bit diameter and the like of the drill rod of the rotary drilling rig can be verified through pile testing.
S2, construction of guide walls:
s21, leveling the field: removing impurities on the surface of the ground, and filling and rolling the groove for the migration of the ground pipeline;
s22, pile position measuring and placing;
s23, excavating a guide wall groove: after the pile position lofting line meets the requirements, the groove can be excavated, and the groove is excavated by adopting mechanical cooperation and manual operation; after the excavation is finished, the central line is immediately led into the bottom of the groove to control the template construction and ensure the correctness of the central line of the guide wall.
S24, binding steel bars;
s25, template construction: the template adopts a self-made integral steel mold, and the diameter of the template of the positioning hole of the guide wall reserved occlusive pile is 4cm larger than the diameter of the pile; the template is reinforced and supported by steel pipes, the supporting distance is not more than 1 m, the reinforcement is firm, the template is strictly prevented from running, the accuracy of the axis and the clearance is ensured, and before concrete pouring, whether the perpendicularity and the center line of the template and the diameter of a pile hole meet the requirements is checked.
S26, concrete pouring construction: when concrete is poured, the two sides are symmetrically and alternately carried out, and the mold is strictly prevented from moving; and if the formwork walking occurs, stopping pouring of concrete immediately, reinforcing the formwork again, correcting to the designed position, and then continuing pouring of the concrete. The vibrating adopts an inserted vibrator, the vibrating distance is about 500mm, the non-uniform vibrating is prevented, and the phenomenon of mold walking caused by over-vibration at one position is also prevented.
S3, constructing the full-casing rotary excavating pile:
s31, positioning the rotary drilling rig;
s32, installing a steel sleeve driving sleeve device of the rotary drilling rig and connecting a steel sleeve;
s33, taking soil and forming holes: after the pile driver is in place, aligning the center of the steel sleeve to the center of the pile position, aligning the verticality of the mast, rotating the driving sleeve to press the steel sleeve downwards, then detaching the driving sleeve and the steel sleeve, and taking soil from the sleeve by using a rotary drilling bit;
s34, hoisting the reinforcement cage: the top elevation of the reinforcement cage is controlled to be correct when the reinforcement cage is installed;
s35, pouring concrete;
s36, forming a pile by drawing a pipe: and (3) pouring concrete and drawing the pipe, and keeping the bottom of the sleeve not less than 2.5m lower than the concrete surface all the time.
Preferably, in step S22, the coordinates of the center line of the row pile are calculated according to the coordinates provided by the design drawing and the external placement of 100mm, a total station is used for performing on-site lofting according to the plane control point, and a fender pile is made to serve as the control center line for the guide wall construction.
Preferably, in step S24, after the trench excavation is completed, the guide wall reinforcing steel bars are bound, the guide wall reinforcing steel bars are formed by phi 12 deformed steel bars, the guide wall reinforcing steel bars are arranged in a single-layer bidirectional manner, the reinforcing steel bar spacing is 200 × 200, and the horizontal reinforcing steel bars are arranged on the inner side.
Preferably, in step S31, after the strength of the guide wall reaches the standard, the template is removed, the center position of the rotary drilling pile is repositioned, the point position is detected on the top surface of the guide wall and is used as a positioning control point of the rotary drilling rig, the rotary drilling rig is moved to the correct position, and the center of the drill bit of the rotary drilling rig is aligned with the center position of the rotary drilling pile.
Preferably, in step S32, the maximum height of the driving head of the rotary drilling rig from the ground is 5m, the length of the standard section of the steel sleeve is 4m, and the length of the first section of the steel sleeve of the pipe section with the cutter head is 5 m. Drilling a hole by a rotary drilling rig at a proper position near a pile position, wherein the drilling depth is 3-4 m, then hoisting a first section of steel sleeve into an auxiliary hole by using an auxiliary hook of the rotary drilling rig, detaching a barrel drill bit and a collision bearing body from the rotary drilling rig, installing a driving sleeve device, then reinstalling an upper barrel drill bit, horizontally moving a drill rod, inserting a driving sleeve into the first section of steel sleeve, and locking the driving sleeve and the steel sleeve together by rotating the driving sleeve.
Preferably, in step S33, the depth of the bottom opening of the casing pipe ahead of the excavation surface is always kept to be not less than 0.5m, after the soil sampling is completed, the next steel casing pipe is connected with the driving sleeve in the auxiliary hole, and finally the two steel casing pipes are connected by the same method. And finally, connecting the two sections of steel sleeves by adopting the same method. And (4) pressing the steel sleeve, taking soil and connecting the steel sleeve in sequence until the designed hole bottom elevation is reached.
Preferably, in step S35, if there is water in the hole, the underwater concrete pouring method is used for construction, and if there is no water in the hole, the dry hole pouring method is used for construction, and the concrete should be reinforced and vibrated.
Although only the preferred embodiments of the present invention have been described in detail, the present invention is not limited to the above embodiments, and various changes can be made without departing from the spirit of the present invention within the knowledge of those skilled in the art, and all changes are encompassed in the scope of the present invention.

Claims (7)

1. A rotary drilling rig full casing pipe hole forming construction method is characterized by comprising the following steps:
s1, construction preparation: s11, leveling and hardening the field; s12, testing the pile before the full-sleeve rotary-digging pile is formed;
s2, construction of guide walls:
s21, leveling the field: removing impurities on the surface of the ground, and filling and rolling the groove for the migration of the ground pipeline;
s22, pile position measuring and placing;
s23, excavating a guide wall groove: after the pile position lofting line meets the requirements, the groove can be excavated, and the groove is excavated by adopting mechanical cooperation and manual operation;
s24, binding steel bars;
s25, template construction: the template adopts a self-made integral steel mold, and the diameter of the template of the positioning hole of the guide wall reserved occlusive pile is 4cm larger than the diameter of the pile;
s26, concrete pouring construction: when concrete is poured, the two sides are symmetrically and alternately carried out, and the mold is strictly prevented from moving;
s3, constructing the full-casing rotary excavating pile:
s31, positioning the rotary drilling rig;
s32, installing a steel sleeve driving sleeve device of the rotary drilling rig and connecting a steel sleeve;
s33, taking soil and forming holes: after the pile driver is in place, aligning the center of the steel sleeve to the center of the pile position, aligning the verticality of the mast, rotating the driving sleeve to press the steel sleeve downwards, then detaching the driving sleeve and the steel sleeve, and taking soil from the sleeve by using a rotary drilling bit;
s34, hoisting the reinforcement cage: the top elevation of the reinforcement cage is controlled to be correct when the reinforcement cage is installed;
s35, pouring concrete;
s36, forming a pile by drawing a pipe: and (3) pouring concrete and drawing the pipe, and keeping the bottom of the sleeve not less than 2.5m lower than the concrete surface all the time.
2. The rotary drilling rig full casing pipe hole forming construction method according to claim 1, characterized in that: in the step S22, the coordinates of the center line of the row pile are calculated according to the coordinates provided by the design drawing and the external placement of 100mm, the total station is adopted to perform on-site lofting according to the plane control point, and the fender pile is made to serve as the control center line of the guide wall construction.
3. The rotary drilling rig full casing pipe hole forming construction method according to claim 1, characterized in that: in the step S24, after the trench is excavated, wall-guiding reinforcing steel bars are bound, the wall-guiding reinforcing steel bars are formed by phi 12 deformed steel bars, the wall-guiding reinforcing steel bars are arranged in a single-layer bidirectional manner, the reinforcing steel bars are arranged at intervals of 200 × 200, and the horizontal reinforcing steel bars are arranged on the inner side.
4. The rotary drilling rig full casing pipe hole forming construction method according to claim 1, characterized in that: in the step S31, after the strength of the guide wall reaches the standard, the template is removed, the center position of the rotary drilling pile is repositioned, the point position is detected on the top surface of the guide wall and is used as a positioning control point of the rotary drilling rig, the rotary drilling rig is moved to the correct position, and the center of the drill bit of the rotary drilling rig is aligned with the center position of the rotary drilling pile.
5. The rotary drilling rig full casing pipe hole forming construction method according to claim 1, characterized in that: in the step S32, the maximum height of the driving head of the rotary drilling rig from the ground is 5m, the length of the standard section of the steel sleeve is designed to be 4m, and the length of the first section of the steel sleeve of the pipe section with the tool bit is designed to be 5 m. Drilling a hole by a rotary drilling rig at a proper position near a pile position, wherein the drilling depth is 3-4 m, then hoisting a first section of steel sleeve into an auxiliary hole by using an auxiliary hook of the rotary drilling rig, detaching a barrel drill bit and a collision bearing body from the rotary drilling rig, installing a driving sleeve device, then reinstalling an upper barrel drill bit, horizontally moving a drill rod, inserting a driving sleeve into the first section of steel sleeve, and locking the driving sleeve and the steel sleeve together by rotating the driving sleeve.
6. The rotary drilling rig full casing pipe hole forming construction method according to claim 1, characterized in that: in the step S33, the depth of the bottom opening of the casing pipe ahead of the excavation surface is always kept to be not less than 0.5m, after soil sampling is completed, the next section of steel casing pipe is connected with the driving sleeve in the auxiliary hole, and finally two sections of steel casing pipes are connected by adopting the same method.
7. The rotary drilling rig full casing pipe hole forming construction method according to claim 1, characterized in that: in the step S35, if there is water in the hole, an underwater concrete pouring method is used for construction, and if there is no water in the hole, a dry hole pouring method is used for construction, and concrete vibration should be reinforced.
CN202110686817.9A 2021-06-21 2021-06-21 Full-sleeve hole forming construction method for rotary drilling rig Pending CN113356189A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110686817.9A CN113356189A (en) 2021-06-21 2021-06-21 Full-sleeve hole forming construction method for rotary drilling rig

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110686817.9A CN113356189A (en) 2021-06-21 2021-06-21 Full-sleeve hole forming construction method for rotary drilling rig

Publications (1)

Publication Number Publication Date
CN113356189A true CN113356189A (en) 2021-09-07

Family

ID=77535414

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110686817.9A Pending CN113356189A (en) 2021-06-21 2021-06-21 Full-sleeve hole forming construction method for rotary drilling rig

Country Status (1)

Country Link
CN (1) CN113356189A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114508097A (en) * 2022-03-22 2022-05-17 中铁十一局集团有限公司 Rotary drilling construction method for railway line slope pile foundation

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103276723A (en) * 2013-04-27 2013-09-04 瑞华建设集团有限公司 Construction method of concrete bored secant pile
JP2015132062A (en) * 2014-01-10 2015-07-23 株式会社奈良重機工事 Ground reinforcement method using small diameter concrete cast-in-place pile
CN108130904A (en) * 2017-12-25 2018-06-08 浙江大学城市学院 A kind of construction method of the composite bushing drill-pouring pilework of neighbouring existing subway
CN111236214A (en) * 2020-01-18 2020-06-05 深圳市穿山甲工程技术有限公司 Construction method for constructing secant pile by lengthening protective cylinder of rotary drilling rig

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103276723A (en) * 2013-04-27 2013-09-04 瑞华建设集团有限公司 Construction method of concrete bored secant pile
JP2015132062A (en) * 2014-01-10 2015-07-23 株式会社奈良重機工事 Ground reinforcement method using small diameter concrete cast-in-place pile
CN108130904A (en) * 2017-12-25 2018-06-08 浙江大学城市学院 A kind of construction method of the composite bushing drill-pouring pilework of neighbouring existing subway
CN111236214A (en) * 2020-01-18 2020-06-05 深圳市穿山甲工程技术有限公司 Construction method for constructing secant pile by lengthening protective cylinder of rotary drilling rig

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张炳信: "套管旋挖灌注桩施工技术研究及应用", 《广东土木与建筑》 *
李金茸: "谈旋挖钻进施工技术", 《企业科技与发展》 *
王召磊等: "旋挖咬合灌注桩在基坑支护工程中的应用", 《岩土工程学报》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114508097A (en) * 2022-03-22 2022-05-17 中铁十一局集团有限公司 Rotary drilling construction method for railway line slope pile foundation

Similar Documents

Publication Publication Date Title
CN108842819B (en) Urban rail transit cable line tunnel construction method
CN109555116A (en) A kind of high density karst intense development area fully-sleeved filled pile construction method
CN104895055A (en) Building grouting pile foundation construction method
CN111962504A (en) Construction method for covering and digging top-down permanent steel pipe column
CN112900450A (en) Rotary drilling and full-rotation combined back-inserting method positioning method for steel pipe structure pile by reverse construction method
CN111636455A (en) Comprehensive construction method of TRD (Top gas recovery device) and rotary drilling lead hole depth waterproof curtain
CN113216832A (en) Water-mill drilling construction method for pile hole in karst area
CN112411530A (en) Construction method for controlling verticality of sea-filling stratum casing secant pile
CN112392049A (en) Excavation construction method for deep foundation pit in weak stratum
CN114737602A (en) Method for positioning concrete filled steel tube center column in cover-excavation top-down construction of subway station
CN113756286A (en) Construction method for implementing underground water soil continuous steel wall by TRD method
CN113356189A (en) Full-sleeve hole forming construction method for rotary drilling rig
CN110374109B (en) Application method of construction method pile enclosure in comprehensive pipe gallery foundation pit
CN218148483U (en) Tower crane foundation structure
CN112878315A (en) End-bearing rotary-digging hole-forming cast-in-place pile based on Civil 3D technology and construction method
CN218060412U (en) Utility tunnel enclosure wall construction structures
CN114411761B (en) Advanced pre-supporting system and method for subway tunnel to be built in new building construction
CN115853009A (en) Photovoltaic support foundation suitable for sandy soil geology and construction method thereof
CN115075249A (en) Pile foundation clearing device and pile foundation clearing process
CN114922195A (en) Construction method of soft soil deep and large foundation pit adjacent to protected object
CN114703831A (en) Construction method of reinforced concrete cast-in-place pile under complex geological condition
CN112726565A (en) Construction method for rotary digging pile penetrating through construction waste
CN112267892B (en) Secondary pipe jacking construction operation method and system
CN220550565U (en) Underground continuous wall system
CN217150251U (en) Digital verticality adjusting system for reverse steel stand column

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210907

RJ01 Rejection of invention patent application after publication