CN113323504A CN202110714990.5A CN202110714990A CN113323504A CN 113323504 A CN113323504 A CN 113323504A CN 202110714990 A CN202110714990 A CN 202110714990A CN 113323504 A CN113323504 A CN 113323504A
Authority
CN
China
Prior art keywords
bracing piece
pile
dovetail
fender
piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110714990.5A
Other languages
Chinese (zh)
Inventor
仲跻峰
邵裕辉
徐进
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Construction Design And Research Institute Co ltd
Original Assignee
Nantong Construction Design And Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Construction Design And Research Institute Co ltd filed Critical Nantong Construction Design And Research Institute Co ltd
Priority to CN202110714990.5A priority Critical patent/CN113323504A/en
Publication of CN113323504A publication Critical patent/CN113323504A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H17/00Fencing, e.g. fences, enclosures, corrals
    • E04H17/14Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
    • E04H17/16Fences constructed of rigid elements, e.g. with additional wire fillings or with posts using prefabricated panel-like elements, e.g. wired frames
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H17/00Fencing, e.g. fences, enclosures, corrals
    • E04H17/14Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
    • E04H17/20Posts therefor
    • E04H17/23Posts therefor lateral supporting elements, e.g. braces, tie downs, or cables

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a fender is enclosed in enclosing of material storage yard relates to and encloses the fender, and it includes fender pile and the batter pile that is located fender pile one side, the batter pile is provided with a plurality of, the batter pile includes first bracing piece and second bracing piece, interconnect between first bracing piece and the fender pile, the spread groove that supplies first bracing piece to insert the establishment is offered towards the one end of first bracing piece direction to the second bracing piece, the inside wall of spread groove and the lateral wall threaded connection of first bracing piece, be provided with drive assembly on the batter pile, drive assembly is used for driving the second bracing piece and rotates on the lateral wall of first bracing piece. This application has and is convenient for extract the batter pile from earth when enclosing to keep off the recovery, reduces workman's the operation degree of difficulty, improves the effect of efficiency of construction.

Description

Fence of material storage yard
Technical Field
The application relates to a fence, in particular to a fence of a material yard.
Background
At present, the enclosure is a device for supporting and enclosing materials in a building site, such as gravel and stones, and the enclosure can support the materials so as to reduce the diffusion of the materials.
When using enclosing the fender among the correlation technique, in order to improve the intensity of enclosing the fender, mostly support enclosing the fender through the batter pile, but when retrieving to the batter pile and enclosing the fender, because the batter pile slope sets up, the workman operates very inconvenient when retrieving, wastes time and energy, has reduced the efficiency of construction.
Disclosure of Invention
In order to facilitate extracting the batter pile from earth when enclosing the fender recovery, reduce workman's the operation degree of difficulty, improve the efficiency of construction, this application provides a fender is enclosed in material storage yard.
The application provides a enclose fender of material storage yard adopts following technical scheme:
the utility model provides a fender is enclosed in material storage yard, includes fender pile and the batter pile that is located fender pile one side, the batter pile is provided with a plurality of, the batter pile includes first bracing piece and second bracing piece, interconnect between first bracing piece and the fender pile, the spread groove that supplies first bracing piece to insert the establishment is offered towards the one end of first bracing piece direction to the second bracing piece, the inside wall of spread groove and the lateral wall threaded connection of first bracing piece, be provided with drive assembly on the batter pile, drive assembly is used for driving the second bracing piece and rotates on the lateral wall of first bracing piece.
By adopting the technical scheme, when the enclosure pile supports and maintains material cargoes, the second support rod is driven to rotate on the outer side wall of the first support rod through the driving component, the inner side wall of the connecting groove is in threaded connection with the outer side wall of the first support rod, the second support rod slides in the direction away from the enclosure pile while rotating, the second support rod is inserted into the mud head while sliding, the inclined pile is obliquely arranged on one side of the enclosure pile, the inclined pile can support the enclosure pile, the supporting and maintaining effects of the enclosure pile on the material cargoes are improved, when the enclosure is required to be recovered, the second support rod is driven to rotate on the outer side wall of the first support rod through the driving motor, the second support rod is driven to slide in the direction of the enclosure pile, the second support rod is quickly pulled out of the mud, the operation is convenient and quick, the operation difficulty of workers is reduced, and the construction efficiency is improved, the enclosure is beneficial to recycling, and the effects of energy conservation and environmental protection are achieved.
Optionally, drive assembly includes motor, actuating lever, insection and gear, motor fixed mounting is on first bracing piece, the drive shaft fixed connection of actuating lever and motor, the length direction of actuating lever sets up along the length direction of first bracing piece, the insection is fixed to be set up on the lateral wall of actuating lever, the fixed cover of gear is established on the lateral wall of second bracing piece, intermeshing between gear and the insection.
Through adopting above-mentioned technical scheme, when needing to drive the second bracing piece and rotate on first bracing piece and drive the second bracing piece and slide, drive the actuating lever through the motor and rotate, insection and gear on the actuating lever offset this moment, and then drive the second bracing piece and rotate, and control convenient and fast need not artificially to drive the second bracing piece and rotates, and the rotation intensity of second bracing piece is high.
Optionally, one end of the second support rod, which is far away from the connecting groove, is integrally provided with a tip, and a thread section is fixedly arranged on the outer side wall of the second support rod.
Through adopting above-mentioned technical scheme, drive assembly drives the second bracing piece and rotates, and the second bracing piece pivoted is removed to keeping away from fender pile direction in the time, and the tip has reduced the area of contact between second bracing piece tip and the earth when the second bracing piece bores soil, and the second bracing piece pivoted cooperates the screw thread section to carry out the breakage to earth in the time, is favorable to the second bracing piece to squeeze into earth fast.
Optionally, the one end that first bracing piece is close to the fender post direction is provided with the dovetail piece, set up along its direction of height on the lateral wall of fender post and supply the dovetail piece to insert and establish and the dovetail that slides, first bracing piece rotates and sets up on one side that the dovetail direction was kept away from to the dovetail piece, be provided with the locking subassembly on the dovetail piece, the locking subassembly is used for fixing the dovetail piece in the dovetail.
Through adopting above-mentioned technical scheme, can drive the dovetail piece and slide in the dovetail, adjust the height of dovetail piece, and then the height of first bracing piece has been adjusted, fix the dovetail piece in the dovetail this moment through the locking subassembly, rotate first bracing piece, change inclination between batter pile and the fender post, so that the batter pile inserts and establishes to the earth of different positions in, be convenient for adjust the best support angle of batter pile on the one hand, ensure that the batter pile has good supporting effect to the fender post, on the other hand makes the fender can satisfy different construction environment, the adaptability of device has been improved.
Optionally, the locking subassembly includes screw rod and butterfly handle, the screw rod symmetry is provided with a plurality of on the dovetail piece, the screw rod runs through the dovetail piece, the equidistance is seted up a plurality of and is supplied the screw that the screw rod inserted and establish on the diapire of dovetail, threaded connection between screw rod and the screw, the butterfly handle is fixed to be set up in the screw rod and keeps away from the one end of screw direction.
Through adopting above-mentioned technical scheme, the drive dovetail piece slides in the dovetail, adjusts the height of dovetail piece, treats that screw rod and screw hole are at the same time level each other, inserts the screw rod and establishes to the screw in, drive butterfly handle rotates, fixes the screw rod in the screw hole, and the screw rod offsets with screw and dovetail piece simultaneously this moment to the realization is fixed dovetail piece, and convenient operation is swift, and is fixed effectual.
Optionally, the fender post includes a plurality of splice plates, splice blocks are fixedly arranged on the end walls of the splice plates along the height direction of the splice plates, splice grooves for the splice blocks to be inserted are formed in one ends of the splice plates far away from the splice block direction, and the splice grooves are matched with the splice blocks.
Through adopting above-mentioned technical scheme, set the fender pile into a plurality of splice plates, when installing the fender pile, insert the splice plate in proper order in earth, insert the splice block simultaneously and establish to the splice groove on the adjacent splice plate in, the splice plate offsets with the splice groove inside wall to in installing and retrieving the fender pile, reduced the construction degree of difficulty.
Optionally, a supporting sleeve is fixedly arranged on one side of the splicing plate facing the direction of the oblique pile, a butt rod penetrates through the supporting sleeve, the outer side wall of the butt rod is in threaded connection with the inner side wall of the supporting sleeve, and a butt disc is arranged at the bottom end of the butt rod.
Through adopting above-mentioned technical scheme, the splice plate rotates the butt rod when supporting the material goods, drives the butt rod and slides in supporting the sleeve, makes butt plate and ground counterbalance, and support sleeve, butt rod and butt plate can support the splice plate this moment, have further improved splice plate intensity, have strengthened the supporting effect of fender post to the material goods.
Optionally, the top of butt rod is fixed and is provided with helping hand pole, the butt dish includes rotary disk and pressure dish, interconnect between rotary disk and the butt pole, the pressure dish sets up the below at the rotary disk, a plurality of embedding groove has been seted up on the surface of pressure dish, the embedding inslot rotation is provided with the ball that offsets with the rotary disk lower surface.
Through adopting above-mentioned technical scheme, when needing to extract the fender pile from earth, through rotating the helping hand pole, drive the butt pole and rotate, and then drive the rotary disk and rotate, the rotary disk pivoted while offsets with the ball, the ball is at the embedding inslot rotation this moment, thereby make pressure disc and ground offset, make the abutment sleeve slide on the outside wall of butt pole, drive the splice plate when the abutment sleeve slides and remove to keeping away from the ground direction, thereby extract ground with single splice plate, be favorable to retrieving the fender pile.
Optionally, a plurality of limiting rods are symmetrically and fixedly arranged on the pressure disc, the outer side wall of each limiting rod abuts against the outer side wall of the rotating disc, a limiting block is fixedly arranged at the top end of each limiting rod, and the limiting blocks abut against the upper surface of the rotating disc.
Through adopting above-mentioned technical scheme, when rotating helping hand pole and driving the rotary disk and rotate on the pressure disc, the stop lever is spacing to the rotary disk on the horizontal direction, and the stopper is spacing to the rotary disk on vertical direction, has improved the stability of being connected between rotary disk and the pressure disc, avoids rotary disk and ball to break away from each other.
In summary, the present application includes at least one of the following beneficial technical effects:
1. by arranging the first support rod, the second support rod, the connecting groove, the motor, the driving rod, the insection and the gear, when the inclined pile is recovered, the driving rod is driven to rotate by the motor, so that the second support rod is driven to rotate on the outer side wall of the first support rod, and further the second support rod is driven to slide towards the direction of the fender pile, so that the second support rod can quickly pull out soil, the operation is convenient and quick, the operation difficulty of workers is reduced, the construction efficiency is improved, the repeated utilization is facilitated, and the effects of energy conservation and environmental protection are achieved;
2. the height of the top of the inclined pile is adjusted by arranging the dovetail block, the dovetail groove, the screw hole and the butterfly-shaped handle, and the inclination angle between the inclined pile and the enclosure pile is changed, so that on one hand, the optimal supporting angle of the inclined pile is convenient to adjust, the inclined pile is ensured to have a good supporting effect on the enclosure pile, on the other hand, the enclosure can meet different construction environments, and the applicability of the device is improved;
3. through setting up splice plate, splice block, splice groove, abutment sleeve, butt joint pole, helping hand pole and butt dish, rotate helping hand pole and drive the butt pole and rotate, make the abutment sleeve slide to keeping away from the ground direction on butt pole lateral wall to extract ground with single splice plate, be favorable to retrieving the fender post.
Drawings
Fig. 1 is a schematic structural view of an enclosure of a material yard in an embodiment.
FIG. 2 is a schematic diagram of the connection between a dovetail block and a batter post used in embodiments.
FIG. 3 is a schematic view of the connection between the support sleeve and the abutment rod for embodying the embodiments.
Description of reference numerals: 1. a fender pile; 11. splicing plates; 2. oblique piles; 21. a first support bar; 22. a second support bar; 221. connecting grooves; 222. a sharp nozzle; 223. a threaded segment; 3. a drive assembly; 31. a motor; 32. a drive rod; 33. insection; 34. a gear; 4. a dovetail block; 41. a dovetail groove; 5. a locking assembly; 51. a screw; 511. a screw hole; 52. a butterfly handle; 6. splicing blocks; 61. splicing grooves; 7. a support sleeve; 71. a butting rod; 72. a booster lever; 8. a butting tray; 81. rotating the disc; 82. a pressure disc; 821. an embedding groove; 822. a ball bearing; 9. a limiting rod; 91. and a limiting block.
Detailed Description
The present application is described in further detail below with reference to figures 1-3.
The embodiment of the application discloses enclose fender of material storage yard. Referring to fig. 1 and 2, the fender pile comprises a fender pile 1 arranged in a vertical direction and an oblique pile 2 obliquely arranged on one side of the fender pile 1, wherein the fender pile 1 and the oblique pile 2 are driven into soil, the fender pile 1 supports materials, and the oblique pile 2 supports the fender pile 1. Batter pile 2 is provided with a plurality of, and batter pile 2 includes first bracing piece 21 and second bracing piece 22, interconnect between first bracing piece 21 and the fender pile 1, and the length direction of second bracing piece 22 sets up along the length direction of first bracing piece 21, and the one end that first bracing piece 21 direction was kept away from to second bracing piece 22 is squeezed into in the earth.
Referring to fig. 1 and 2, a connection groove 221 for the first support bar 21 to be inserted is formed at one end of the second support bar 22 facing the direction of the first support bar 21, the length direction of the connection groove 221 is arranged along the length direction of the second support bar 22, and the inner side wall of the connection groove 221 is in threaded connection with the outer side wall of the first support bar 21. Be provided with drive assembly 3 on the batter pile 2, when needs retrieve batter pile 2, drive second bracing piece 22 through drive assembly 3 and rotate, because spread groove 221 and first bracing piece 21 threaded connection make second bracing piece 22 take place to slide on first bracing piece 21 lateral wall to extract earth with second bracing piece 22 fast.
Referring to fig. 1 and 2, the driving assembly 3 includes a motor 31, a driving rod 32, a tooth pattern 33 and a gear 34, the motor 31 is fixedly installed on an outer side wall of the first support bar 21, the driving rod 32 is fixedly connected with a driving shaft of the motor 31, a length direction of the driving rod 32 is arranged along a length direction of the first support bar 21, the tooth pattern 33 is integrally arranged on an outer side wall of the driving rod 32, and a length direction of the tooth pattern 33 is arranged along a length direction of the driving rod 32. The gear 34 is fixedly sleeved on the outer side wall of the second support rod 22 through welding, the gear 34 is coaxially arranged with the second support rod 22, and the gear 34 is meshed with the insections 33. The driving rod 32 is driven by the motor 31 to rotate, so as to drive the insection 33 to abut against the gear 34, and further drive the second supporting rod 22 to rotate on the outer side wall of the first supporting rod 21, so that the second supporting rod 22 can be inserted into or pulled out of the soil.
Referring to fig. 2, the one end of the second support rod 22 away from the connecting groove 221 is integrally provided with the sharp nozzle 222, the outer side wall of the second support rod 22 is integrally provided with the threaded section 223, and the second support rod 22 rotates while driving the threaded section 223 to crush soil, so that the inclined pile 2 is inserted into the soil through the driving assembly 3.
Referring to fig. 1 and 2, a dovetail block 4 is arranged at one end of the first support rod 21 close to the direction of the fender pile 1, and the first support rod 21 and the dovetail block 4 are rotatably connected through a rotating shaft. The outer side wall of the fender post 1 is provided with a dovetail groove 41 along the height direction, the dovetail block 4 is arranged in the dovetail groove 41 in a sliding mode, the dovetail block 4 is driven to slide in the dovetail groove 41, and the height of the batter post 2 can be adjusted. The dovetail block 4 is provided with a locking assembly 5, the locking assembly 5 comprises two screw rods 51 and a butterfly handle 52, the two screw rods 51 are symmetrically arranged on the dovetail block 4, and the screw rods 51 penetrate through the dovetail block 4. A plurality of screw holes 511 for the screws 51 to be inserted are equidistantly formed in the bottom wall of the dovetail groove 41, the screws 51 are in threaded connection with the screw holes 511, and the butterfly handle 52 is fixedly arranged at one end of the screw 51 far away from the screw holes 511. After adjusting the height of batter pile 2, insert screw rod 51 and establish to screw 511 in to rotate butterfly handle 52, fix screw rod 51 in screw 511, can fix forked tail piece 4, rotate batter pile 2 this moment, can squeeze into different positions with second bracing piece 22, be convenient for adjust the best support angle of batter pile 2 on the one hand, ensure that batter pile 2 has good supporting effect to fender pile 1, on the other hand encloses the fender and can adapt to different construction environment.
Referring to fig. 1, the fender post 1 includes a plurality of splice plates 11, and the end walls of splice plates 11 are mutually laminated, and splice blocks 6 are integrally arranged on the end walls of splice plates 11 along the height direction, and a splice groove 61 for splicing blocks 6 to be inserted is provided at one end of splice plates 11 far away from the direction of splice blocks 6, and the splice groove 61 is mutually matched with splice blocks 6. When installing fender pile 1, mutually support through splice groove 61 and concatenation piece 6, assemble fender pile 1, reduced the construction degree of difficulty.
Referring to fig. 1 and 3, the splice plate 11 is provided with a support sleeve 7 towards one side of the oblique pile 2 direction in a welding fixed manner, the support sleeve 7 is arranged along the vertical direction, a butt rod 71 is arranged on the inner side wall of the support sleeve 7 in a threaded manner, a boosting rod 72 is integrally arranged at the top end of the butt rod 71, the length direction of the boosting rod 72 is perpendicular to the butt rod 71, and the bottom end of the butt rod 71 is connected with a butt plate 8. When supporting the material goods through splice plate 11 and maintaining, rotate helping hand pole 72 and drive butt joint pole 71 and rotate, make butt joint dish 8 move in vertical direction, offset butt joint dish 8 and ground, support sleeve 7, butt pole 71 and butt joint dish 8 can support splice plate 11 this moment, have improved fender post 1's intensity.
Referring to fig. 1 and 3, the abutting disc 8 includes a rotating disc 81 and a pressure disc 82, the rotating disc 81 is fixedly welded to the bottom end of the abutting rod 71, the pressure disc 82 is located below the rotating disc 81, a plurality of embedding grooves 821 are formed in the upper surface of the pressure disc 82, and a plurality of balls 822 abutting against the lower surface of the rotating disc 81 are rotatably arranged in the embedding grooves 821. The pressure plate 82 is symmetrically welded and fixed with a plurality of limiting rods 9, the outer side walls of the limiting rods 9 are abutted to the outer side walls of the rotating plate 81, and the limiting rods 9 limit the rotating plate 81 in the horizontal direction. The top end of the limiting rod 9 is fixedly welded with a limiting block 91, the limiting block 91 abuts against the upper surface of the rotating disc 81, and the limiting block 91 limits the rotating disc 81 in the vertical direction. When needing to retrieve fender pile 1, drive rotary disk 81 through rotating helping hand pole 72 and rotate, ball 822 is at the rotation of embedding groove 821 this moment, and pressure disc 82 offsets with ground, and support sleeve 7 slides on the outside wall of butt pole 71, and then drives splice plate 11 and removes to keeping away from the ground direction, realizes retrieving single splice plate 11, retrieves the recycle to fender pile 1 after being convenient for support.
The implementation principle of the enclosure of the material storage yard in the embodiment of the application is as follows: when supporting the material through enclosing the fender, after squeezing into earth with splice plate 11 in proper order, drive actuating lever 32 through motor 31 and rotate, make insection 33 offset with gear 34, and then drive second bracing piece 22 and rotate on the lateral wall of first bracing piece 21, because spread groove 221 and first bracing piece 21 threaded connection, the tip of second bracing piece 22 removes to keeping away from fender pile 1 direction when second bracing piece 22 pivoted, thereby drive second bracing piece 22 and insert and establish to earth, batter pile 2 can support fender pile 1 this moment. Need drive second bracing piece 22 antiport through motor 31 when enclosing to keep off the recovery to extract earth fast with second bracing piece 22, drive butt rod 71 through rotating helping hand pole 72 and rotate, make butt dish 8 and ground counterbalance, the support sleeve 7 slides at butt rod 71 and drives splice plate 11 and extract earth fast, convenient operation is swift, be convenient for retrieve and recycle enclosing to keeping off, improved the efficiency of construction, reach environmental protection and energy saving's effect.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (9)

1. The utility model provides a fender that encloses of material storage yard, includes fender pile (1) and batter pile (2) that are located fender pile (1) one side, batter pile (2) are provided with a plurality of, its characterized in that: batter pile (2) are including first bracing piece (21) and second bracing piece (22), interconnect between first bracing piece (21) and fender pile (1), second bracing piece (22) are offered towards the one end of first bracing piece (21) direction and are supplied first bracing piece (21) to insert spread groove (221) of establishing, the inside wall of spread groove (221) and the lateral wall threaded connection of first bracing piece (21), be provided with drive assembly (3) on batter pile (2), drive assembly (3) are used for driving second bracing piece (22) and rotate on the lateral wall of first bracing piece (21).
2. The enclosure of a material yard according to claim 1, wherein: drive assembly (3) include motor (31), actuating lever (32), insection (33) and gear (34), motor (31) fixed mounting is on first bracing piece (21), the drive shaft fixed connection of actuating lever (32) and motor (31), the length direction of length direction along first bracing piece (21) of actuating lever (32) sets up, insection (33) are fixed to be set up on the lateral wall of actuating lever (32), gear (34) are fixed to be established on the lateral wall of second bracing piece (22), intermeshing between gear (34) and insection (33).
3. The enclosure of a material yard according to claim 2, wherein: one end of the second support rod (22) far away from the connecting groove (221) is integrally provided with a sharp nozzle (222), and the outer side wall of the second support rod (22) is fixedly provided with a threaded section (223).
4. The enclosure of a material yard according to claim 1, wherein: one end that first bracing piece (21) are close to fender pile (1) direction is provided with dovetail piece (4), offer along its direction of height on the lateral wall of fender pile (1) and supply dovetail piece (4) to insert dovetail (41) of establishing and sliding, first bracing piece (21) rotate the setting and keep away from one side of dovetail (41) direction at dovetail piece (4), be provided with locking subassembly (5) on dovetail piece (4), locking subassembly (5) are used for fixing dovetail piece (4) in dovetail (41).
5. The enclosure of a material yard according to claim 4, wherein: locking subassembly (5) include screw rod (51) and butterfly handle (52), screw rod (51) symmetry is provided with a plurality of on forked tail piece (4), dovetail piece (4) is run through in screw rod (51), screw hole (511) that a plurality of confession screw rod (51) were inserted and are established are seted up to the equidistance on the diapire of dovetail (41), threaded connection between screw rod (51) and screw hole (511), butterfly handle (52) are fixed to be set up in screw rod (51) and are kept away from the one end of screw hole (511) direction.
6. The enclosure of a material yard according to claim 1, wherein: the fender post (1) comprises a plurality of splicing plates (11), splicing blocks (6) are fixedly arranged on the end walls of the splicing plates (11) along the height direction of the splicing plates, splicing grooves (61) for the splicing blocks (6) to be inserted are formed in one ends, far away from the direction of the splicing blocks (6), of the splicing plates (11), and the splicing grooves (61) are matched with the splicing blocks (6) mutually.
7. The enclosure of a material yard according to claim 6, wherein: splice plate (11) are provided with supporting sleeve (7) towards fixed on one side of batter pile (2) direction, it is provided with butt rod (71) to run through in supporting sleeve (7), the lateral wall of butt rod (71) and the inside wall threaded connection of supporting sleeve (7), the bottom of butt rod (71) is provided with butt dish (8).
8. The enclosure of a material yard of claim 7, wherein: the top of butt pole (71) is fixed and is provided with helping hand pole (72), butt dish (8) are including rotary disk (81) and pressure disc (82), interconnect between rotary disk (81) and butt pole (71), pressure disc (82) set up the below at rotary disk (81), a plurality of embedding groove (821) have been seted up on the surface of pressure disc (82), embedding groove (821) internal rotation is provided with ball (822) that offsets with rotary disk (81) lower surface.
9. The enclosure of a material yard of claim 8, wherein: the fixed a plurality of gag lever post (9) that is provided with of symmetry on pressure dish (82), the lateral wall of gag lever post (9) offsets with the lateral wall of rotary disk (81), the fixed stopper (91) that is provided with in top of gag lever post (9), stopper (91) offset with the upper surface of rotary disk (81).
CN202110714990.5A 2021-06-25 2021-06-25 Fence of material storage yard Pending CN113323504A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110714990.5A CN113323504A (en) 2021-06-25 2021-06-25 Fence of material storage yard

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110714990.5A CN113323504A (en) 2021-06-25 2021-06-25 Fence of material storage yard

Publications (1)

Publication Number Publication Date
CN113323504A true CN113323504A (en) 2021-08-31

Family

ID=77424894

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110714990.5A Pending CN113323504A (en) 2021-06-25 2021-06-25 Fence of material storage yard

Country Status (1)

Country Link
CN (1) CN113323504A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU38807U1 (en) * 2004-03-26 2004-07-10 Соколова Инна Ефимовна TEMPORARY CONSTRUCTION FENCING
CN210032899U (en) * 2019-02-28 2020-02-07 重庆三峡学院 A security fence for hydraulic and hydroelectric engineering
CN211229606U (en) * 2019-10-20 2020-08-11 广东鸿狮建设工程有限公司 Building engineering safety device
CN211736448U (en) * 2020-01-19 2020-10-23 河北世展建筑工程有限公司 Fixing device for mounting prefabricated external wall panel
CN211900051U (en) * 2020-01-20 2020-11-10 安徽韩伟钢结构有限公司 Integrated assembly type green construction enclosure
CN111927127A (en) * 2020-09-08 2020-11-13 甘肃路桥建设集团有限公司 Temporary supporting structure for construction
CN112031418A (en) * 2020-08-17 2020-12-04 浙江舜杰建筑集团股份有限公司 Temporary supporting device of aluminum formwork for building construction
CN212295720U (en) * 2020-04-14 2021-01-05 江苏扬建集团有限公司 Assembled wallboard strutting arrangement
CN213269284U (en) * 2020-09-08 2021-05-25 广东烽煌建设工程有限公司 Green construction environmental protection encloses fender

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU38807U1 (en) * 2004-03-26 2004-07-10 Соколова Инна Ефимовна TEMPORARY CONSTRUCTION FENCING
CN210032899U (en) * 2019-02-28 2020-02-07 重庆三峡学院 A security fence for hydraulic and hydroelectric engineering
CN211229606U (en) * 2019-10-20 2020-08-11 广东鸿狮建设工程有限公司 Building engineering safety device
CN211736448U (en) * 2020-01-19 2020-10-23 河北世展建筑工程有限公司 Fixing device for mounting prefabricated external wall panel
CN211900051U (en) * 2020-01-20 2020-11-10 安徽韩伟钢结构有限公司 Integrated assembly type green construction enclosure
CN212295720U (en) * 2020-04-14 2021-01-05 江苏扬建集团有限公司 Assembled wallboard strutting arrangement
CN112031418A (en) * 2020-08-17 2020-12-04 浙江舜杰建筑集团股份有限公司 Temporary supporting device of aluminum formwork for building construction
CN111927127A (en) * 2020-09-08 2020-11-13 甘肃路桥建设集团有限公司 Temporary supporting structure for construction
CN213269284U (en) * 2020-09-08 2021-05-25 广东烽煌建设工程有限公司 Green construction environmental protection encloses fender

Similar Documents

Publication Publication Date Title
IL280320B2 (en) Threaded truss foundations and related systems, methods, and machines
CN113323504A (en) Fence of material storage yard
KR100919730B1 (en) A horizontal excavator
CN111893999B (en) Pile pulling guide frame and pile pulling method for waste inclined piles
CN113136861B (en) Prefabricated cylinder retaining wall of manual hole digging pile and construction method
CN213867842U (en) Building engineering underground structure
CN213508484U (en) Foundation pit supporting structure
CN214738190U (en) Foundation pit drainage structure
CN211922626U (en) Guide frame for positioning insertion sleeve
CN205370117U (en) Gardens are instrument of driving piles fast
CN210134429U (en) Good building pile driver of stability
CN209145418U (en) A kind of combined type can relocation housing build construction protection column
CN219772991U (en) Foundation pit supporting device
CN216218667U (en) Soil drilling machine for garden construction
CN114319470B (en) Engineering foundation pile detection fixing device for construction engineering detection
CN214697443U (en) House door opening node additional strengthening
CN111236228A (en) Earth anchor for electric power construction
CN215979195U (en) Support stable highway engineering and use bore a device
CN217601456U (en) Deep foundation pit supporting beam frame structure for geotechnical engineering
CN216075155U (en) Pit-in-pit edge fender pile mounting structure
CN211267630U (en) Forestry trees are planted with digging device
CN220978054U (en) Deep foundation pit supporting device for pipeline engineering
CN111519608B (en) Uplift pile capable of quickly connecting pile
CN218405360U (en) Foundation detection device for hydraulic engineering
CN219101227U (en) Small rotary digging machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210831