CN113322737A - Prefabricated road panel connecting structure and mounting method based on tongue-and-groove bent bolt connection - Google Patents

Prefabricated road panel connecting structure and mounting method based on tongue-and-groove bent bolt connection Download PDF

Info

Publication number
CN113322737A
CN113322737A CN202110678810.2A CN202110678810A CN113322737A CN 113322737 A CN113322737 A CN 113322737A CN 202110678810 A CN202110678810 A CN 202110678810A CN 113322737 A CN113322737 A CN 113322737A
Authority
CN
China
Prior art keywords
concrete pavement
precast concrete
tongue
groove
slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110678810.2A
Other languages
Chinese (zh)
Inventor
周大兴
方宏伟
曹青
武利平
董磊
张亚齐
侯立群
殷炳帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Group Co Ltd
Original Assignee
China Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Group Co Ltd filed Critical China Railway Construction Group Co Ltd
Priority to CN202110678810.2A priority Critical patent/CN113322737A/en
Publication of CN113322737A publication Critical patent/CN113322737A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C5/00Pavings made of prefabricated single units
    • E01C5/06Pavings made of prefabricated single units made of units with cement or like binders
    • E01C5/08Reinforced units with steel frames
    • E01C5/10Prestressed reinforced units ; Prestressed coverings from reinforced or non-reinforced units
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/02Arrangement or construction of joints; Methods of making joints; Packing for joints
    • E01C11/04Arrangement or construction of joints; Methods of making joints; Packing for joints for cement concrete paving
    • E01C11/06Methods of making joints

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a prefabricated pavement panel connecting structure and a prefabricated pavement panel connecting method based on tongue-and-groove bent bolt connection. The invention has the beneficial effects that: the precast concrete pavement panel has simple connection structure, single type of precast concrete pavement panel, is beneficial to industrial production, and the problem of different and disordered assembled plate types is not needed to be considered on site. The design of the arc-shaped chamfer angle of the precast concrete pavement panel reduces the damage of corners in the processes of production, transportation, storage, construction and later-stage airplane rolling. The precast concrete pavement panel assembly is processed and finished in a factory, is transported to a site for hoisting and installation, has high industrialization degree, convenient site installation and high construction speed, has good economic and social benefits, and is suitable for the rapid assembly construction of airport pavement.

Description

Prefabricated road panel connecting structure and mounting method based on tongue-and-groove bent bolt connection
Technical Field
The invention relates to a precast concrete pavement slab, in particular to a precast pavement slab connection structure and an installation method based on tongue-and-groove bent bolt connection, and belongs to the technical field of airport pavement construction.
Background
The construction process of the assembled concrete pavement has the advantages of less field wet operation, high construction speed, industrial production and guaranteed pavement slab quality.
At present, the airport pavement in China generally adopts a cast-in-place concrete construction technology, the wet operation is more, the concrete curing time is long, the pavement surface layer process is complicated, the construction quality requirement is extremely high, and the whole construction period is long. When an emergency happens, the traditional cast-in-place concrete construction technology cannot meet the capacity of rapid construction.
Disclosure of Invention
The invention aims to solve the problems and provide a prefabricated road panel connecting structure and a prefabricated road panel mounting method based on tongue-and-groove bent bolt connection.
The invention realizes the purpose through the following technical scheme: the prefabricated pavement panel connecting structure based on tongue-and-groove bent bolt connection comprises a prefabricated concrete pavement panel, a convex tongue-and-groove, a concave tongue-and-groove, a reserved mounting groove, a reserved pore channel and a bent bolt; the prefabricated concrete pavement slab is characterized in that concave tongue-and-groove openings and convex tongue-and-groove openings are arranged on four sides of the prefabricated concrete pavement slab, reserved mounting grooves and reserved pore passages are symmetrically arranged in the prefabricated concrete pavement slab, and four hoisting grouting holes are formed in the upper surface of the prefabricated concrete pavement slab; the precast concrete pavement slab is fixedly connected by adopting a convex rabbet, a concave rabbet and a bent bolt; the precast concrete pavement slab is precast by adopting a light inorganic material.
As a still further scheme of the invention: the precast concrete pavement slab is manufactured by factory prefabrication, the concave tongue-and-groove, the convex tongue-and-groove, the reserved pore channel and the hoisting grouting hole are reserved in advance in the pavement slab prefabrication process, the hoisting grouting hole is designed by combining the hoisting hole with the grouting hole, and the precast concrete pavement slab can be used as the grouting hole after the hoisting construction assembly is completed.
As a still further scheme of the invention: the precast concrete pavement panels are sequentially spliced according to the principle that the convex rabbet is inserted into the concave rabbet, and then are fixedly connected through the bent bolts, the bent bolts penetrate through the reserved hole channels from the reserved mounting grooves, the fixed steel plates at the two ends and the nuts are screwed and fixed, and the reserved mounting grooves are tightly filled with filling materials after the installation is finished.
As a still further scheme of the invention: the gap between the precast concrete pavement slab and the lower base layer can be firmly bonded through hoisting grouting holes.
As a still further scheme of the invention: the slab joints between the precast concrete pavement slabs are sealed through grouting, and the slab joints on the upper surface are compacted through sealant.
As a still further scheme of the invention: the precast concrete pavement slab is made of light inorganic materials, and light aggregate concrete or other fiber reinforced concrete and other materials can be selected.
The installation method of the prefabricated road panel connection structure based on tongue-and-groove bent bolt connection comprises the following steps:
1) the construction of the airport field road base layer is completed, and the airport is guaranteed to have certain strength, rigidity and flatness so as to meet the splicing construction requirement of the precast concrete pavement slab of the subsequent road;
2) positioning and paying off a base layer, wherein according to the integral division condition of a working surface, each working surface respectively determines the positioning of an initial plate, and a positioning line is arranged at a certain distance to prevent the accumulative error of the plate from being overlarge;
3) laying precast concrete pavement slabs, accurately placing a member slab prepared in advance at an initial slab position through hoisting equipment, and sequentially laying subsequent slabs according to the sequence principle that a convex rabbet is inserted into a concave rabbet;
4) connecting and fixing the precast concrete pavement panels, sequentially connecting and fixing the adjacent precast concrete pavement panels by using bent bolts, checking a positioning line, preventing overlarge accumulated installation errors, adjusting the installation errors in time by adjusting the fastening degree of a nut, and sealing and filling the tightly reserved installation groove by using a filling material after the installation is finished;
5) grouting the bottom of the precast concrete pavement slab, wherein the precast concrete pavement slab and the lower base layer can be firmly bonded through grouting of hoisting grouting holes;
6) and gluing and sealing the plate joints, sealing the plate joints between the precast concrete pavement slabs through grouting, compacting the plate joints with sealant, and finishing the structural assembling work of the precast concrete pavement slabs.
The invention has the beneficial effects that: the prefabricated pavement panel connecting structure based on the tongue-and-groove bent bolt connection and the installation method are reasonable in design, the prefabricated concrete pavement panel connecting structure is simple, the prefabricated concrete pavement panel is single in plate type, industrial production is facilitated, and the problem that assembled plate types are different and disordered is not needed to be considered on site. The design of the arc-shaped chamfer angle of the precast concrete pavement panel reduces the damage of corners in the processes of production, transportation, storage, construction and later-stage airplane rolling. The precast concrete pavement panel assembly is processed and finished in a factory, is transported to a site for hoisting and installation, has high industrialization degree, convenient site installation and high construction speed, has good economic and social benefits, and is suitable for the rapid assembly construction of airport pavement.
Drawings
FIG. 1 is a sectional view of a precast concrete pavement connection structure according to the present invention;
FIG. 2 is a schematic plan view of a precast concrete pavement slab according to the present invention;
fig. 3 is a side view of a precast concrete pavement panel according to the present invention.
In the figure: 1. the concrete pavement slab comprises a precast concrete pavement slab, 2 convex tongue-and-groove parts, 3 concave tongue-and-groove parts, 4 reserved mounting grooves, 5 reserved pore channels, 6 bent bolts, 7 fixed steel plates, 8 nut parts, 9 filling materials, 10 hoisting grouting holes.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example one
Referring to fig. 1 to 3, the precast concrete pavement slab connection structure based on tongue-and-groove bent bolt connection includes a precast concrete pavement slab 1, a convex tongue-and-groove 2, a concave tongue-and-groove 3, a reserved installation groove 4, a reserved hole passage 5 and a bent bolt 6; the four sides of the precast concrete pavement slab 1 are provided with concave tongue-and-groove 2 and convex tongue-and-groove 3, a reserved mounting groove 4 and a reserved pore passage 5 are symmetrically arranged in the precast concrete pavement slab 1, and the upper surface of the precast concrete pavement slab 1 is provided with four hoisting grouting holes 10; the precast concrete pavement slab 1 is fixedly connected with a bent bolt 6 by adopting a male rabbet 2 and a female rabbet 3 in a socket-and-spigot manner; the precast concrete pavement slab 1 is precast by adopting a light inorganic material.
In the embodiment of the invention, the precast concrete pavement slab 1 is prefabricated in a factory, the concave rabbet 2, the convex rabbet 3, the groove 4, the reserved pore channel 5 and the hoisting grouting hole 11 are reserved in advance in the pavement slab prefabrication process, the hoisting grouting hole 5 is designed by combining the hoisting hole with the grouting hole, and the precast concrete pavement slab can be used as the grouting hole after the hoisting construction assembly is finished.
In the embodiment of the invention, the precast concrete pavement panels 1 are sequentially spliced according to the principle that the convex rabbet 2 is inserted into the concave rabbet 3, and are connected and fixed through the bent bolt 6, the bent bolt 6 penetrates through the reserved hole channel 5 from the reserved mounting groove 4, the fixed steel plates 7 at two ends and the screw cap 8 are screwed and fixed, and the reserved mounting groove 4 is tightly filled with the filling material 9 after the installation is finished.
In the embodiment of the invention, the gap between the precast concrete pavement slab 1 and the lower base layer can be firmly bonded through grouting through the hoisting grouting holes 10.
In the embodiment of the invention, slab joints among the precast concrete pavement slabs 1 are sealed by grouting, and the joints among the upper surface slabs are compacted by using sealing glue.
In the embodiment of the present invention, the light inorganic material adopted by the precast concrete pavement slab 1 may be light aggregate concrete or other fiber reinforced concrete.
Example two
The installation method of the prefabricated road panel connection structure based on tongue-and-groove bent bolt connection comprises the following steps:
1) the construction of the airport field road base layer is completed, and the airport is guaranteed to have certain strength, rigidity and flatness so as to meet the splicing construction requirement of the precast concrete pavement slab 1 of the subsequent road;
2) positioning and paying off a base layer, wherein according to the integral division condition of a working surface, each working surface respectively determines the positioning of an initial plate, and a positioning line is arranged at a certain distance to prevent the accumulative error of the plate from being overlarge;
3) laying a precast concrete pavement slab 1, accurately placing a prepared component board at an initial board position through hoisting equipment, and sequentially laying subsequent boards according to the sequence principle that the convex rabbet 3 is inserted into the concave rabbet 4;
4) connecting and fixing the precast concrete pavement slabs 1, sequentially connecting and fixing the adjacent precast concrete pavement slabs 1 by using bent bolts 6, checking a positioning line, preventing overlarge accumulated installation error, adjusting the installation error in time by adjusting the fastening degree of a nut 8, and sealing and filling the tightly reserved installation groove 4 by using a filling material 9 after the installation is finished;
5) grouting the bottom of the precast concrete pavement slab 1, wherein the precast concrete pavement slab 1 and the lower base layer can be firmly bonded through grouting through the hoisting grouting holes 10;
6) and (3) gluing and sealing the plate joints, sealing the plate joints between the precast concrete pavement slabs 1 through grouting, compacting the plate joints with sealant, and finishing the structural assembling work of the precast concrete pavement slabs.
The working principle is as follows: the four sides of the precast concrete pavement slab 1 are provided with concave-convex tongues and grooves, a reserved mounting groove 4 and a reserved pore passage 5 are arranged in the precast concrete pavement slab 1, and the upper surface of the precast concrete pavement slab 1 is provided with four hoisting grouting holes 10 (two holes are integrated); the precast concrete pavement slab 1 is fixedly connected by adopting concave-convex rabbet socket joint connection and a bent bolt 6, and the reserved mounting groove 4 is tightly sealed and filled by filling materials 9 after the mounting is finished; the gap between the precast concrete pavement slab 1 and the lower base layer can be firmly bonded through grouting of the grouting holes; the slab joints between the precast concrete pavement slabs 1 are grouted and sealed, and the concrete chamfers on the upper surface are compacted through sealant.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (7)

1. Prefabricated railway panel connection structure based on tongue-and-groove bent bolted connection, its characterized in that: the prefabricated concrete pavement slab comprises a prefabricated concrete pavement slab (1), a convex rabbet (2), a concave rabbet (3), a reserved mounting groove (4), a reserved pore channel (5) and a bent bolt (6); concave tongue-and-groove joints (2) and convex tongue-and-groove joints (3) are arranged on four sides of the precast concrete pavement slab (1), reserved mounting grooves (4) and reserved pore channels (5) are symmetrically arranged in the precast concrete pavement slab (1), and four hoisting grouting holes (10) are formed in the upper surface of the precast concrete pavement slab (1); the precast concrete pavement slab (1) is fixedly connected with a bent bolt (6) by adopting a male tongue-and-groove (2) and a female tongue-and-groove (3) in a socket joint mode, and the precast concrete pavement slab (1) is precast by adopting a light inorganic material.
2. The precast pavement panel connection construction based on tongue-and-groove bolt connection according to claim 1, wherein: precast concrete pavement slab (1) adopts the prefabricated preparation of batch production, and concave tongue-and-groove (2), protruding rabbet (3), recess (4), reservation pore (5) and hoist and mount grout hole (11) are all reserved in advance at the pavement slab prefabrication in-process, and hoist and mount grout hole (5) are two hole unification designs of hole for hoist and mount and grout hole, treat that the hoist and mount construction is assembled and is accomplished the back, do the grout hole use concurrently.
3. The precast pavement panel connection construction based on tongue-and-groove bolt connection according to claim 1, wherein: the precast concrete pavement slab (1) is sequentially spliced according to the principle that the convex rabbet (2) is inserted into the concave rabbet (3), and then is fixedly connected through the bent bolt (6), the bent bolt (6) penetrates through the reserved hole channel (5) from the reserved mounting groove (4), the fixing steel plates (7) at two ends and the screw cap (8) are screwed and fixed, and the reserved mounting groove (4) is tightly filled with a filling material (9) after the installation is finished.
4. The precast pavement panel connection construction based on tongue-and-groove bolt connection according to claim 1, wherein: the gap between the precast concrete pavement slab (1) and the lower base layer can be firmly bonded through grouting through the hoisting grouting holes (10).
5. The precast pavement panel connection construction based on tongue-and-groove bolt connection according to claim 1, wherein: the slab joints between the precast concrete pavement slabs (1) are sealed through grouting, and the slab joints are compacted through sealant.
6. The precast pavement panel connection construction based on tongue-and-groove bolt connection according to claim 1, wherein: the precast concrete pavement slab (1) is made of light inorganic materials, and light aggregate concrete or other fiber reinforced concrete materials can be selected.
7. A method for installing a tongue-and-groove bolt connection-based precast pavement panel connection structure according to claim 1, comprising the steps of:
1) the construction of the airport field road base layer is completed, and the airport is guaranteed to have certain strength, rigidity and flatness so as to meet the splicing construction requirement of the precast concrete pavement slab (1) of the subsequent road;
2) positioning and paying off a base layer, wherein according to the integral division condition of a working surface, each working surface respectively determines the positioning of an initial plate, and a positioning line is arranged at a certain distance to prevent the accumulative error of the plate from being overlarge;
3) laying a precast concrete pavement slab (1), accurately placing a prepared component plate at an initial plate position through hoisting equipment, and sequentially laying subsequent plates according to the sequence principle that the convex rabbet (3) is inserted into the concave rabbet (4);
4) connecting and fixing the precast concrete pavement slabs (1), sequentially connecting and fixing the adjacent precast concrete pavement slabs (1) by using bent bolts (6), checking a positioning line to prevent overlarge accumulated installation errors, adjusting the installation errors in time by adjusting the fastening degree of a nut (8), and filling a compact reserved installation groove (4) by using a filling material (9) after the installation is finished;
5) grouting the bottom of the precast concrete pavement slab (1), wherein the precast concrete pavement slab (1) and the lower base layer can be firmly bonded through grouting in the hoisting grouting holes (10);
6) and (3) gluing and sealing the plate joints, sealing the plate joints between the precast concrete pavement slabs (1) through grouting, compacting the plate joints with sealant, and finishing the structural assembling work of the precast concrete pavement slabs.
CN202110678810.2A 2021-06-18 2021-06-18 Prefabricated road panel connecting structure and mounting method based on tongue-and-groove bent bolt connection Pending CN113322737A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110678810.2A CN113322737A (en) 2021-06-18 2021-06-18 Prefabricated road panel connecting structure and mounting method based on tongue-and-groove bent bolt connection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110678810.2A CN113322737A (en) 2021-06-18 2021-06-18 Prefabricated road panel connecting structure and mounting method based on tongue-and-groove bent bolt connection

Publications (1)

Publication Number Publication Date
CN113322737A true CN113322737A (en) 2021-08-31

Family

ID=77423969

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110678810.2A Pending CN113322737A (en) 2021-06-18 2021-06-18 Prefabricated road panel connecting structure and mounting method based on tongue-and-groove bent bolt connection

Country Status (1)

Country Link
CN (1) CN113322737A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114263076A (en) * 2021-11-26 2022-04-01 中建科技集团有限公司 Assembled precast concrete pavement slab and construction method thereof
CN114411473A (en) * 2022-01-29 2022-04-29 中铁二十局集团房地产开发有限公司 Assembled repeatedly usable haydite concrete yard floor
CN115081072A (en) * 2022-06-27 2022-09-20 中建科技集团有限公司 Bolt connection assembly type airport pavement structure design method
CN115142314A (en) * 2022-06-28 2022-10-04 中国五冶集团有限公司 Turnover splicing type construction access road and construction process

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204780504U (en) * 2015-05-19 2015-11-18 山西省交通科学研究院 Prefabricated cement concrete pavement of assembling
CN209619780U (en) * 2018-12-20 2019-11-12 中国雄安集团基础建设有限公司 A kind of Prefabricated road plate of bolt with one end bent back connection
CN209798465U (en) * 2018-12-10 2019-12-17 中交天津港湾工程设计院有限公司 Assembled concrete slab
US20210040741A1 (en) * 2018-12-12 2021-02-11 Dalian University Of Technology Design and Rapid Construction Method for Flush Assembly of the Prefabricated Steel Beam and the Floor Slab
CN112726316A (en) * 2021-01-01 2021-04-30 中建科技集团有限公司 Assembly type precast concrete pavement slab assembly, pavement structure and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204780504U (en) * 2015-05-19 2015-11-18 山西省交通科学研究院 Prefabricated cement concrete pavement of assembling
CN209798465U (en) * 2018-12-10 2019-12-17 中交天津港湾工程设计院有限公司 Assembled concrete slab
US20210040741A1 (en) * 2018-12-12 2021-02-11 Dalian University Of Technology Design and Rapid Construction Method for Flush Assembly of the Prefabricated Steel Beam and the Floor Slab
CN209619780U (en) * 2018-12-20 2019-11-12 中国雄安集团基础建设有限公司 A kind of Prefabricated road plate of bolt with one end bent back connection
CN112726316A (en) * 2021-01-01 2021-04-30 中建科技集团有限公司 Assembly type precast concrete pavement slab assembly, pavement structure and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114263076A (en) * 2021-11-26 2022-04-01 中建科技集团有限公司 Assembled precast concrete pavement slab and construction method thereof
CN114411473A (en) * 2022-01-29 2022-04-29 中铁二十局集团房地产开发有限公司 Assembled repeatedly usable haydite concrete yard floor
CN115081072A (en) * 2022-06-27 2022-09-20 中建科技集团有限公司 Bolt connection assembly type airport pavement structure design method
CN115142314A (en) * 2022-06-28 2022-10-04 中国五冶集团有限公司 Turnover splicing type construction access road and construction process

Similar Documents

Publication Publication Date Title
CN113322737A (en) Prefabricated road panel connecting structure and mounting method based on tongue-and-groove bent bolt connection
CN107974891B (en) Municipal road assembling unit and construction method thereof
CN113279301A (en) Precast concrete pavement panel connection structure based on prestress series connection and installation method
CN112593644B (en) Prefabricated assembly type shear wall vertical joint connecting structure and construction method thereof
CN112726316A (en) Assembly type precast concrete pavement slab assembly, pavement structure and construction method thereof
CN113355966A (en) Precast concrete pavement panel connection structure based on ground anchor fixation and installation method
CN217078222U (en) Assembled ballastless track based on dry-type connection
CN110656573B (en) Glue-pouring high-strength bolt shear connector
CN209799160U (en) split integrated type double-T plate structure for concrete member
CN214938941U (en) Assembly type cement concrete pavement joint leveling and force transmission structure
CN113322738A (en) Prefabricated road panel connecting structure and mounting method based on groove bent bolt connection
CN112695896A (en) Precast concrete beam-plate connecting structure and mounting method
CN209779987U (en) one-way superimposed sheet bottom plate of piece pre-compaction
CN215164272U (en) Assembled precast concrete pavement slab assembly and pavement structure
CN213926983U (en) Splicing node of prefabricated profiled steel sheet and concrete composite board
CN211228068U (en) Festival segmentation pier convenient to installation
CN115637722A (en) Prefabricated independent foundation
CN112554563A (en) Construction method of full-assembly type concrete building system
CN214461728U (en) Novel assembled building block for building and wall body composed of building blocks
CN110735504A (en) rotatable energy-dissipating and shock-absorbing stair node connecting device
CN217351980U (en) Precast concrete pavement panel based on prestressing force series connection
CN213418322U (en) Wall brick connecting structure with fixed side surface and stable and firm side surface
CN110607866A (en) Fabricated floor based on reinforced concrete frame structure and connecting method thereof
CN214940354U (en) GIS equipment modularization assembled concrete font basis
CN220889050U (en) Prefabricated wallboard of heat preservation integration

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210831

RJ01 Rejection of invention patent application after publication