CN113236263B - Construction method of open TBM front-mounted type advanced pipe shed - Google Patents

Construction method of open TBM front-mounted type advanced pipe shed Download PDF

Info

Publication number
CN113236263B
CN113236263B CN202110710340.3A CN202110710340A CN113236263B CN 113236263 B CN113236263 B CN 113236263B CN 202110710340 A CN202110710340 A CN 202110710340A CN 113236263 B CN113236263 B CN 113236263B
Authority
CN
China
Prior art keywords
pipe shed
pipe
shed
construction
grouting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110710340.3A
Other languages
Chinese (zh)
Other versions
CN113236263A (en
Inventor
郑传赞
齐梦学
曾绍毅
杨国清
刘晓春
张全洲
李晓伟
祖尧
段朋伸
谢志强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Tunnel Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Tunnel Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd, Tunnel Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN202110710340.3A priority Critical patent/CN113236263B/en
Publication of CN113236263A publication Critical patent/CN113236263A/en
Application granted granted Critical
Publication of CN113236263B publication Critical patent/CN113236263B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
    • E21D9/087Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield with a rotary drilling-head cutting simultaneously the whole cross-section, i.e. full-face machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0642Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield having means for additional processing at the front end
    • E21D9/065Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield having means for additional processing at the front end with devices for provisionally supporting the front face
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
    • E21D9/087Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield with a rotary drilling-head cutting simultaneously the whole cross-section, i.e. full-face machines
    • E21D9/0873Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield with a rotary drilling-head cutting simultaneously the whole cross-section, i.e. full-face machines the shield being provided with devices for lining the tunnel, e.g. shuttering
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a construction method of an open TBM front-mounted type advanced pipe shed, which comprises the following steps: 1) Applying a hollow anchor rod for grouting, and reinforcing the side arch of the shield and the cutter head region; 2) Conducting guide hole construction; 3) Setting an advanced pipe shed; 4) Backfilling a gap between the pipe shed and the guide hole by grouting; 5) Installing an exhaust pipe and a grout stop plug; 6) And grouting the pipe shed. The method has the advantages of convenient construction, simple process and low cost, ensures the success of the pipe shed, the effective coverage area of the pipe shed and the grouting effect of the pipe shed to the greatest extent, can ensure that the TBM quickly and safely passes through the fault fracture zone, effectively solves the problem of blocking, improves the construction efficiency and reduces the construction cost.

Description

Construction method of open type TBM front-mounted type advanced pipe shed
Technical Field
The invention relates to a TBM construction method, in particular to an open TBM front-mounted type advanced pipe shed construction method.
Background
At present, when an open type TBM is used for tunnel (tunnel) excavation, once unfavorable geology such as surrounding rock weathering, erosion, fault fracture zone and the like is met, the TBM is easy to cause blocking, the TBM construction efficiency is seriously influenced, the construction period is delayed, and the resource waste of people, materials, machines and the like is caused, so that great loss is caused.
The invention patent application named as 'a novel TBM with pipe shed construction capability and a construction method thereof' is disclosed in CN107435541A, and comprises the TBM, a pipe shed drilling machine and an annular track, wherein the pipe shed drilling machine is arranged on a drilling machine supporting seat, and a pitching oil cylinder and a pushing oil cylinder are arranged at the lower part of the drilling machine supporting seat; the annular rail is sleeved on a main girder of the TBM, and the drilling machine supporting seat is connected with the annular rail through the pitching oil cylinder and the pushing oil cylinder. The construction method is stated in claim 6 of the invention patent application: the method comprises the following steps: (1) when the tunnel is excavated, excavating an area to be excavated in a self-stable rock stratum by adopting a TBM cutter head; (2) when a TBM is adopted to excavate a tunnel and meets an area of an unstable rock-soil layer, a pipe shed drilling machine is adopted to drill the unstable rock-soil layer and a pipe shed is adopted for supporting; (3) and (4) continuously excavating the pipe shed supporting area by using TBM after the pipe shed supporting is finished. Although the novel TBM related to the method has the capacity of constructing the pipe shed, the pipe shed is constructed only on the outer side of the shield of the TBM, the camber angle of the pipe shed is large, the effective grouting range of a pipe shed supporting area is small, the material waste is caused, and the pipe shed effect is poor.
The invention patent application named as 'an open TBM shield' is disclosed in CN111287761A, and comprises a shield, a first conduit, a second conduit and a sealing part; the first guide pipe is sleeved and fixed in a pilot hole of the shield, and a preset external inserting angle is formed between the axial direction of the first guide pipe and the axial direction of the shield; the second guide pipe is connected with the first guide pipe when advancing the shed support so as to form a long straight pipe structure for a drill rod of the shed drilling machine system to pass through with the first guide pipe, and the end part of the second guide pipe extends to the slag collecting area of the main beam; the sealing component is used for replacing the second conduit to be connected with the first conduit during tunneling so as to seal the first conduit; the second conduit and the sealing component are respectively detachably connected with the first conduit. Patent claim 4 of the present patent application explicitly states that: the preset external insertion angle is 6 degrees. The application of the invention makes up the defects of the previous patent, but the camber angle is still large, the construction length of the advanced pipe shed is greatly shortened in the actual construction, and the patent fails to research the construction method of the pipe shed under the TBM shield.
The invention discloses an invention patent named as 'an open TBM shield structure and an advanced reinforcement construction method' in CN110939452A, which is an application and comprises an upper preformed hole arranged on a top shield of the open TBM, side preformed holes which are arranged on two side shields of the open TBM and symmetrically distributed, and a lower preformed hole arranged on a bottom support of the open TBM, wherein seamless steel pipes are arranged in the side preformed holes and the lower preformed hole, and the seamless steel pipes are obliquely distributed, and the method comprises the following steps: 1. laying a preformed hole in an open TBM shield; 2. installing a seamless steel pipe; 3. installing a plug; 4. and (5) performing advanced grouting reinforcement in the TBM tunneling process. Compared with the first patent, the method describes that the pipe shed construction is carried out in the shield structure, but the aim of carrying out the pipe shed construction in the shield of the TBM, grouting to reinforce surrounding rocks in front of the TBM and then carrying out tunneling construction is not really achieved only by grouting the pipe shed after the TBM is tunneled.
Disclosure of Invention
The invention aims to provide a construction method of an open type TBM front-mounted type advanced pipe shed, which has high construction efficiency and enables a TBM to quickly pass through a fault fracture zone.
The invention aims to realize the technical scheme that the construction method of the open TBM front-mounted type advanced pipe shed comprises the following steps: 1) Applying a hollow anchor rod for grouting, and reinforcing the side arch of the shield and the cutter head region; 2) Conducting guide hole construction; 3) Arranging an advanced pipe shed; 4) Backfilling a gap between the pipe shed and the guide hole by grouting; 5) Installing an exhaust pipe and a grout stop plug; 6) And grouting the pipe shed.
In the step 1), a hollow anchor rod is respectively constructed in the tail part of the shield and the cutter head, and the hollow anchor rod is used for grouting and solidifying to form the annular grout stopping wall.
Further describing, in the step 1), a hollow anchor rod with the diameter of 30mm is constructed from the tail of the shield along the direction of a camber angle, the construction range is 150 degrees, the rock-entering depth is 3m, and the annular interval is 1m; a glass fiber hollow anchor rod with the diameter of 30mm is radially constructed in a cutter head, the construction range is 150 degrees, the rock-entering depth is 0.5-1.5 m, and the annular distance is 1m; wherein, resin double-liquid slurry is poured into the side arch through the hollow anchor rod and the glass fiber hollow anchor rod for consolidation and reinforcement.
In order to effectively avoid the invasion of the advanced pipe shed into an excavation contour line, in the step 2), the advanced pipe shed drilling machine moves forwards to a pipe shed construction position, the camber angle of the drilling machine is adjusted to be 4-5 degrees, a core taking drill bit and a core taking pipe are installed, a drill rod is connected to a rock entering position, the core taking length is 1m, and a guide hole is formed after the core taking is completed.
Further describing, in the step 3), the coring bit is withdrawn, the down-the-hole bit is replaced, and the tail end of the pipe shed is positioned outside the excavation contour line of the tunnel; and no grout overflow hole is reserved at the position 4.5-4.8 m away from one end of the TBM cutter head of the pipe shed.
In order to prevent slurry from flowing back during grouting of the pipe shed, in the step 4), a steel pipe with the diameter of 10mm is inserted into a gap between the pipe shed and the hole wall through a gap filling tool, the front end of the steel pipe exceeds the tail end of the pipe shed by 1-1.2 m, resin double-slurry is poured into the steel pipe to plug the gap, and the steel pipe is withdrawn while being poured.
Further describing, in the step 5), a PVC exhaust pipe with the diameter of 20mm is connected with an exhaust hole of the three-hole grout stopping plug, and the total length of the PVC exhaust pipe and the three-hole grout stopping plug is slightly shorter than the length of the pipe shed; the PVC exhaust pipe and the grout stop plug are inserted into the pipe shed together according to the design position, water is injected through the water injection hole of the grout stop plug and the pressure is increased to 1MPa, and the grout stop plug is confirmed to be fully expanded at the tail of the sleeve of the pipe shed.
In order to effectively reinforce the front weak surrounding rock, in the step 6), cement-based variable-speed setting materials are injected through the hollow anchor rods for grouting, the grout stop plugs are decompressed and removed after grouting is completed, the guide pipe plugs are installed, and TBM tunneling construction is recovered.
By adopting the technical scheme, the method has the advantages of convenience and quickness in construction, simple process and low cost, the success of the pipe shed, the effective coverage area of the pipe shed and the grouting effect of the pipe shed are guaranteed to the greatest extent, the TBM can quickly and safely pass through a fault fracture zone, the problem of blocking is effectively solved, the construction efficiency is improved, and the construction cost is reduced.
Drawings
The drawings of the invention are illustrated as follows:
FIG. 1 is a schematic structural diagram of an open TBM shield and forepoling rig of the present invention;
FIG. 2 is a schematic view of the outer side of the shield of the present invention applied with a hollow anchor rod;
FIG. 3 is a schematic view of a cutterhead contour of the present invention applied as a fiberglass bolt;
FIG. 4 is a schematic view of the structure of the caulking tool of the present invention;
FIG. 5 is a schematic view of the pipe shed of the present invention;
FIG. 6 is a schematic view of the orifice plugging of the present invention;
fig. 7 is a schematic view of grouting of the pipe shed according to the invention.
Detailed Description
The following detailed description of the embodiments of the present invention will be described in detail with reference to the accompanying drawings, but the present invention is not limited to these embodiments, and any modifications or substitutions in the basic spirit of the embodiments will still fall within the scope of the present invention claimed in the claims.
Example 1: as shown in fig. 1 to 7, a construction method of an open type TBM front-mounted type advanced pipe shed includes the following steps: 1) Applying a hollow anchor rod 7 for grouting, and reinforcing the side arch of the shield 1 and the cutter head 2; 2) Conducting guide hole construction; 3) Arranging an advanced pipe shed 9; 4) Backfilling a gap between the pipe shed 9 and the guide hole by grouting; 5) Installing an exhaust pipe 11 and a grout stop plug 10; 6) Grouting the pipe shed 9.
In the step 1), a hollow anchor rod 7 is respectively applied from the tail of the shield and the inside of the cutter head 2, and the hollow anchor rod 7 is used for grouting and consolidation to form the annular grout stop wall.
Further describing, in the step 1), a hollow anchor rod 7 with the diameter of 30mm is constructed from the tail of the shield along the direction of a camber angle, the construction range is 150 degrees at the vault, the rock-entering depth is 3m, and the annular interval is 1m; a glass fiber hollow anchor rod 8 with the diameter of 30mm is radially constructed in a cutter head 2, the construction range is 150 degrees, the rock-entering depth is 0.5-1.5 m, and the annular distance is 1m; wherein, resin double-liquid slurry is poured into the side arch through the hollow anchor rod 7 and the glass fiber hollow anchor rod 8 for consolidation and reinforcement.
Advance shed stand pipe 3 by shield 2 inboard reservation core trompil, can effectively avoid advancing shed 9 to invade the excavation outline line like this in step 2), advance shed rig 4 moves forward to shed 9 and carries out the position, and 4 degrees positions at the adjustment rig 4 camber angle are installed and are got core bit 12, core pipe, and the drilling rod that continues to the position of going into the rock, and core length 1m gets the core and finishes the back, forms the guiding hole promptly.
Further, in the step 3), the lead pipe shed 9 is designed, and the method is carried out as follows: the coring bit 12 is withdrawn, the down-the-hole bit is replaced, and the tail end of the pipe shed 9 is positioned outside the tunnel excavation contour line; no grout overflow hole is reserved at the position 4.5m away from one end of the TBM cutter head of the pipe shed 9, and the grout overflow hole is reserved at the end far away from the TBM cutter head.
In order to effectively prevent slurry from flowing back when the pipe shed 9 is grouted, in the step 4), a steel pipe 14 with the diameter of 10mm is inserted into a gap between the pipe shed 9 and the hole wall through a gap filling tool 13, the front end of the steel pipe 14 exceeds the tail end of the pipe shed 9 by 1-1.2 m, resin double-slurry is poured into the steel pipe 14 to plug the gap, and the steel pipe 14 is poured while retreating.
Further describing, in the step 5), a PVC exhaust pipe 11 with the diameter of 20mm is connected with an exhaust hole of the three-hole grout stopping plug 10, and the total length of the PVC exhaust pipe 11 and the three-hole grout stopping plug 10 is slightly shorter than the length of the pipe shed 9; the PVC exhaust pipe 11 and the grout stop plug 10 are inserted into the pipe shed 9 together according to the design position, water is injected through the water injection hole of the grout stop plug 10 and the pressure is increased to 1MPa, and the grout stop plug 10 is determined to be fully expanded at the tail part of the sleeve of the pipe shed 9.
Further describing, in the step 6), cement-based variable-speed setting materials are injected through the hollow anchor rods 7 for grouting, the grout stop plugs 10 are decompressed and removed after grouting is completed, the guide pipe plugs 15 are installed, and TBM tunneling construction is resumed.
In the invention, steps 2) to 6) only describe the construction method of a single pipe shed, and partial processes can be synchronously carried out in the implementation process of the whole ring pipe shed.
Example 2: the difference from example 1 is that: in the step 1), a hollow anchor rod 7 is respectively applied from the tail of the shield and the inside of the cutter head 2, and the hollow anchor rod 7 is used for grouting and consolidation to form the annular grout stop wall.
Further describing, in the step 1), a hollow anchor rod 7 with the diameter of 30mm is constructed from the tail of the shield along the direction of a camber angle, the construction range is 150 degrees at the vault, the rock-entering depth is 3m, and the annular interval is 1m; a glass fiber hollow anchor rod 8 with the diameter of 30mm is radially constructed in a cutter head 2, the construction range is 150 degrees, the rock-entering depth is 0.5-1.5 m, and the annular distance is 1m; wherein, resin double-liquid slurry is poured into the side arch through the hollow anchor rod 7 and the glass fiber hollow anchor rod 8 for consolidation and reinforcement.
In the step 1), a hollow anchor rod with the diameter of 30mm is constructed from the tail part of the shield along the direction of a camber angle, the construction range is 140 degrees at the vault, the rock-entering depth is 5m, and the circumferential distance is 0.8m; a glass fiber hollow anchor rod with the diameter of 30mm is radially constructed in a cutter head, the construction range is 130 degrees, the rock-entering depth is 0.5-1.5 m, and the annular distance is 0.8m; wherein, resin double-liquid slurry is poured into the side arch through the hollow anchor rod and the glass fiber hollow anchor rod for consolidation and reinforcement.

Claims (6)

1. An open TBM front-mounted type advanced pipe shed construction method is characterized by comprising the following steps:
1) Applying a hollow anchor rod for grouting, and reinforcing the side arch of the shield and the cutter head region;
2) Conducting guide hole construction;
in the step 2), a front pipe shed drilling machine moves forwards to a pipe shed construction position, the camber angle of the drilling machine is adjusted to be 4-5 degrees, a core taking drill bit and a core taking pipe are installed, a drill rod is connected to a rock entering position, the core taking length is 1m, and a guide hole is formed after core taking is finished;
3) Arranging an advanced pipe shed;
4) Backfilling a gap between the pipe shed and the guide hole by grouting;
in the step 4), inserting a steel pipe with the diameter of 10mm into a gap between the pipe shed and the hole wall through a gap filling tool, wherein the front end of the steel pipe exceeds the tail end of the pipe shed by 1-1.2 m, and injecting resin double-liquid slurry into the steel pipe to plug the gap and retreat while injecting;
5) Installing an exhaust pipe and a grout stop plug;
6) And grouting the pipe shed.
2. The construction method of the open type TBM front-mounted type advanced pipe shed as claimed in claim 1, wherein: in the step 1), a hollow anchor rod is respectively applied from the tail part of the shield and the inside of the cutter head, and is solidified by grouting through the hollow anchor rod to form the annular grout stop wall.
3. The construction method of the open type TBM front-mounted type advanced pipe shed as claimed in claim 2, is characterized in that: in the step 1), a hollow anchor rod with the diameter of 30mm is constructed from the tail part of a shield along the direction of a camber angle, the construction range is 140-150 degrees at the vault, the rock-entering depth is 3-5 m, and the circumferential distance is 0.8-1 m; a glass fiber hollow anchor rod with the diameter of 30mm is radially constructed in a cutter head, the construction range is 130-150 degrees, the rock-entering depth is 0.5-1.5 m, and the annular distance is 0.8-1 m; wherein, resin double-liquid slurry is poured into the side arch through the hollow anchor rod and the glass fiber hollow anchor rod for consolidation and reinforcement.
4. The construction method of the open type TBM front-mounted type advanced pipe shed as claimed in claim 3, wherein: in the step 3), the coring bit is withdrawn, the down-the-hole bit is replaced, and the tail end of the pipe shed is positioned outside the tunnel excavation contour line; and no grout overflow hole is reserved at the position 4.5-4.8 m away from one end of the TBM cutter head of the pipe shed.
5. The construction method of the open type TBM front-mounted type advanced pipe shed as claimed in claim 4, is characterized in that: in the step 5), a PVC exhaust pipe with the diameter of 20mm is connected with an exhaust hole of the three-hole grout stopping plug, and the total length of the PVC exhaust pipe and the three-hole grout stopping plug is slightly shorter than the length of the pipe shed; the PVC exhaust pipe and the grout stop plug are inserted into the pipe shed together according to the design position, water is injected through the water injection hole of the grout stop plug and the pressure is increased to 1MPa, and the grout stop plug is confirmed to be fully expanded at the tail of the sleeve of the pipe shed.
6. The construction method of the open type TBM front-mounted type advanced pipe shed as claimed in claim 5, wherein: and 6), injecting a cement-based variable-speed setting material through the hollow anchor rod for grouting, releasing pressure of a grout stop plug after grouting is finished, removing the grout stop plug, installing a guide pipe plug, and recovering TBM tunneling construction.
CN202110710340.3A 2021-06-25 2021-06-25 Construction method of open TBM front-mounted type advanced pipe shed Active CN113236263B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110710340.3A CN113236263B (en) 2021-06-25 2021-06-25 Construction method of open TBM front-mounted type advanced pipe shed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110710340.3A CN113236263B (en) 2021-06-25 2021-06-25 Construction method of open TBM front-mounted type advanced pipe shed

Publications (2)

Publication Number Publication Date
CN113236263A CN113236263A (en) 2021-08-10
CN113236263B true CN113236263B (en) 2023-03-24

Family

ID=77140861

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110710340.3A Active CN113236263B (en) 2021-06-25 2021-06-25 Construction method of open TBM front-mounted type advanced pipe shed

Country Status (1)

Country Link
CN (1) CN113236263B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102134998A (en) * 2011-04-27 2011-07-27 中铁二局股份有限公司 Construction method for wind-blown sand tunnel
CN110939452A (en) * 2019-12-31 2020-03-31 中国水利水电第三工程局有限公司 Open type TBM shield structure and advanced reinforcement construction method
JP2020079481A (en) * 2018-11-12 2020-05-28 清水建設株式会社 Circumferential shield excavator
CN112502720A (en) * 2020-12-08 2021-03-16 中铁隧道局集团有限公司 Method for breaking zone by passing open TBM through fault

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101408106B (en) * 2007-10-12 2010-10-13 中煤第三建设(集团)有限责任公司 Small tube shed pre-grouting method
CN106194204A (en) * 2016-09-08 2016-12-07 长安大学 A kind of drift cobble tunnel advanced support structure and method for protecting support
CN207598242U (en) * 2017-12-07 2018-07-10 中铁十八局集团有限公司 A kind of TBM advance supports reassembling type guider
CN112412475A (en) * 2020-11-26 2021-02-26 中铁五局集团第一工程有限责任公司 Method for reinforcing and excavating surrounding rock of ice water accumulation body tunnel under influence of seasonal rainfall and surrounding rock support
CN112502723B (en) * 2020-12-04 2023-09-29 中铁十九局集团第一工程有限公司 Single-shield TBM blocking machine escaping construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102134998A (en) * 2011-04-27 2011-07-27 中铁二局股份有限公司 Construction method for wind-blown sand tunnel
JP2020079481A (en) * 2018-11-12 2020-05-28 清水建設株式会社 Circumferential shield excavator
CN110939452A (en) * 2019-12-31 2020-03-31 中国水利水电第三工程局有限公司 Open type TBM shield structure and advanced reinforcement construction method
CN112502720A (en) * 2020-12-08 2021-03-16 中铁隧道局集团有限公司 Method for breaking zone by passing open TBM through fault

Also Published As

Publication number Publication date
CN113236263A (en) 2021-08-10

Similar Documents

Publication Publication Date Title
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
JP2022500579A (en) Support structure of two-stage high-speed closed tunnel with reverse arch and its construction method
CN103334770B (en) One is grown up reverse-slope tunnel ultra high water pressure rich water zone of fracture construction method
CN110735653A (en) deep-hole retreating type grouting water plugging construction method for igneous rock water-rich fault
CN107762533A (en) A kind of front pre-grouting method of high-pressure water-enriched weak surrounding rock mountain tunnel
CN112502723B (en) Single-shield TBM blocking machine escaping construction method
CN103410527A (en) Preliminary bracing construction method for tunnel with surrounding rocks containing collapsible loess and soft rocks
CN105351001B (en) A kind of method based on gob side entry retaining region reinforcement gas pumping
CN107965341A (en) A kind of large-section underground pipe canopy pipe network concrete support method
CN110017145A (en) A kind of sea area shield mine joins jointing and its construction method in Tunnel
CN112196582A (en) Method for controlling severe deformation of strong-earthquake deep-buried soft rock stratum tunnel
CN106522981B (en) Pass through the method for protecting support in goaf tunnel
CN111472801A (en) Construction method for passing existing line under shallow-buried underground excavation drainage gallery
CN110905536A (en) Construction method for receiving complex stratum earth pressure shield in underground excavation tunnel
CN116804369A (en) TBM (Tunnel boring machine) combined construction method for crossing bad stratum
CN210422621U (en) Multi-mode hard rock heading machine
CN105041327A (en) Subsurface tunnel reverse shield receiving method
CN111075457A (en) In-hole repairing method for shield deformation of tail shield of shield tunneling machine under complex geological condition
CN207406345U (en) Rich water sand-pebble layer shield tunnel end horizontal grouting ruggedized construction
CN114109442A (en) Tunnel karst broken zone collapse half-section curtain forward grouting reinforcement treatment method
CN103615265B (en) Soft rock tunnel horizontal jet grouting construction method
CN113236263B (en) Construction method of open TBM front-mounted type advanced pipe shed
CN114718582B (en) Construction method for small-clear-distance horizontal joint shale geological tunnel portal section
CN108222948A (en) A kind of traversing shallow-buried Faults in Tunnels Construction of Transition Section method
Clark et al. The greatest challenges in TBM tunneling: Experiences from the field

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant