CN113216390A CN202110450353.1A CN202110450353A CN113216390A CN 113216390 A CN113216390 A CN 113216390A CN 202110450353 A CN202110450353 A CN 202110450353A CN 113216390 A CN113216390 A CN 113216390A
Authority
CN
China
Prior art keywords
module
accommodating cavity
inner sleeve
connecting piece
columns
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110450353.1A
Other languages
Chinese (zh)
Other versions
CN113216390B (en
Inventor
欧进萍
杨超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Harbin Institute of Technology Shenzhen
Original Assignee
Harbin Institute of Technology Shenzhen
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Harbin Institute of Technology Shenzhen filed Critical Harbin Institute of Technology Shenzhen
Priority to CN202110450353.1A priority Critical patent/CN113216390B/en
Publication of CN113216390A publication Critical patent/CN113216390A/en
Application granted granted Critical
Publication of CN113216390B publication Critical patent/CN113216390B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • E04B2001/2406Connection nodes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • E04B2001/2415Brackets, gussets, joining plates
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • E04B2001/2421Socket type connectors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • E04B2001/246Post to post connections

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

本发明提供采用内套筒灌浆连接的模块化钢结构连接节点,其中包括上模块柱、上模块梁、下模块柱、下模块梁、连接件,连接件包括水平连接板以及设置在水平连接板的表面上的至少两个内套筒,内套筒与水平连接板固定,内套筒的侧面设有向外突出的内栓钉,上模块柱及下模块柱的内壁设有向内突出的外栓钉,上模块柱包括上容纳腔,下模块柱包括下容纳腔,连接件的上部的每一内套筒分别设置于每一上模块柱的上容纳腔内,连接件的下部的每一内套筒分别设置于每一下模块柱的下容纳腔内,并在上容纳腔及连接件的上部之间、下容纳腔及接件的下部之间设置灌浆料,灌浆料将上模块柱、下模块柱与连接件固定连接。本发明还提供了一种该连接节点的制造方法。

Figure 202110450353

The invention provides a modular steel structure connection node connected by grouting with an inner sleeve, which includes an upper module column, an upper module beam, a lower module column, a lower module beam and a connecting piece, and the connecting piece includes a horizontal connecting plate and a At least two inner sleeves on the surface of the inner sleeve, the inner sleeve is fixed with the horizontal connecting plate, the side surface of the inner sleeve is provided with inner pegs protruding outward, and the inner walls of the upper and lower module columns are provided with inwardly protruding inner pegs. The outer peg, the upper module column includes an upper accommodating cavity, the lower module column includes a lower accommodating cavity, each inner sleeve of the upper part of the connecting piece is respectively arranged in the upper accommodating cavity of each upper module column, and each lower part of the connecting piece An inner sleeve is respectively arranged in the lower accommodating cavity of each lower module column, and a grouting material is arranged between the upper accommodating cavity and the upper part of the connecting piece, and between the lower accommodating cavity and the lower part of the connecting piece, and the grouting material compresses the upper module column , The lower module column is fixedly connected with the connecting piece. The invention also provides a manufacturing method of the connection node.

Figure 202110450353

Description

Modular steel structure connecting joint adopting inner sleeve grouting connection and mounting method
Technical Field
The invention belongs to the technical field of construction engineering, and particularly relates to a modular steel structure connecting node adopting inner sleeve grouting connection.
Background
In the existing steel structure or combined structure, the connection between steel components generally adopts bolt connection or welded connection, and the existing connection form needs certain operation space, installation error and longer connection time in the connection process. For the modularized steel structure, a plurality of beam columns, multi-surface walls, floor slabs and other members are arranged at the positions of column nodes, and if the existing connection form is adopted, the operation space is lacked, and the connection can not be realized under the condition of not damaging the surrounding members; and the modular structure is sensitive to connection installation errors, the existing connection form is difficult to realize structure assembly under small installation errors, and the modular structure has good bearing and anti-seismic performance. In order to meet the construction and assembly requirements, a large construction error is reserved, and the effect of load transmission of the node is influenced.
Disclosure of Invention
The invention aims to overcome the defects in the prior art and provide a sleeve grouting connecting node between steel structure modules. The construction method can allow large construction and installation errors, and the upper module column and the lower module column can be reliably connected through non-shrinkage grouting material filling in the later period.
The purpose of the invention is realized by the following technical scheme:
the invention provides a modularized steel structure connecting node connected by grouting of inner sleeves, which is used for connecting steel structure modules, and comprises an upper module column, an upper module beam, a lower module column, a lower module beam and a connecting piece, wherein the connecting piece comprises a horizontal connecting plate and at least two inner sleeves arranged on the surface of the horizontal connecting plate, the inner sleeves are fixed with the horizontal connecting plate, the side surfaces of the inner sleeves are provided with inner studs protruding outwards, the inner walls of the upper module column and the lower module column are provided with outer studs protruding inwards, the upper module column comprises an upper accommodating cavity, the lower module column comprises a lower accommodating cavity, each inner sleeve at the upper part of the connecting piece is respectively arranged in the upper accommodating cavity of each upper module column, each inner sleeve at the lower part of the connecting piece is respectively arranged in the lower accommodating cavity of each lower module column, and grouting materials are arranged between the upper accommodating cavity and the upper part of the connecting piece, between the lower accommodating cavity and the lower part of the connecting piece, the grouting material is used for fixedly connecting the upper module column, the lower module column and the connecting piece.
In some embodiments, the plurality of inner pegs are arranged in a plurality of columns on a circumferential side of the inner sleeve, while the plurality of outer pegs are arranged in a plurality of columns within an inner wall of the upper receiving cavity of the upper module column and the lower receiving cavity of the lower module column, wherein the columns of inner pegs are horizontally staggered with respect to the columns of outer pegs.
In some embodiments, the inner peg and each outer peg comprise a circular top plate and a connecting rod fixedly connected to a lower surface of the circular top plate, and the other end of the connecting rod is fixedly connected to the inner sleeve.
In some embodiments, elastic materials are arranged at the bottom end of the outer wall of the upper accommodating cavity and the top end of the outer wall of the lower accommodating cavity, and a closed space is formed between the horizontal connecting plate and the upper accommodating cavity and between the horizontal connecting plate and the lower accommodating cavity.
In some embodiments, four inner sleeves are respectively arranged on the upper side and the lower side of the horizontal connecting plate, four upper module columns are adjacently arranged according to a two-by-two array, two upper module beams are divided into two groups in pairs, the two groups of upper module beams are oppositely arranged on two sides of the four upper module columns, four lower module columns are adjacently arranged according to a two-by-two array, two lower module beams are divided into two groups in pairs, and the two groups of lower module beams are oppositely arranged on two sides of the four lower module columns.
In some embodiments, an avoidance groove is provided at the top end of each lower module column and/or the bottom end of each upper module column, so that the horizontal connecting plate can be received in the avoidance groove after the upper module column and the lower module column are relatively jointed.
In some embodiments, the upper and lower receiving cavities further comprise upper and lower inner partitions, which are respectively located at positions corresponding to the flanges of the upper and lower module beams.
In some embodiments, an upper injection port penetrating to the outside is provided at an axially upper side of a side surface of the upper accommodation chamber, and a lower injection port penetrating to the outside is provided at an axially upper side of a side surface of the lower accommodation chamber.
The invention provides a method for installing the modular steel structure connecting node connected by adopting inner sleeve grouting, which comprises the following steps: s1, vertically arranging the lower module columns of each lower module, wherein the lower accommodating cavities face upwards, arranging 4 lower module columns into a two-by-two array, aligning 4 inner sleeves at the lower part of the connecting piece with 4 lower accommodating cavities respectively, aligning inner bolt nails of the connecting piece with outer bolt nails in the lower accommodating cavities, and further inserting the lower part of the connecting piece into the lower accommodating cavities until the lower surface of a horizontal connecting plate of the connecting piece abuts against the top end of the outer wall of the lower accommodating cavities; s2, pouring grouting material into the fixed space between the lower part of the connecting piece and the lower containing cavity through the lower pouring inlet until the fixed space is filled, and solidifying the grouting material, S3, dividing 4 upper modules into groups and oppositely arranging, wherein the upper containing cavity of each upper module is vertically aligned with an inner sleeve on the upper part of the connecting piece, and then the upper modules and the lower modules are oppositely jointed, so that the upper module beam of each upper module is aligned with the lower module beam of one lower module, S4, pouring grouting material into the fixed space between the upper part of the connecting piece and the upper containing cavity through the upper pouring inlet until the fixed space is filled, and solidifying the grouting material, and completing the connection of the upper modules and the lower modules.
Compared with the prior art, the technical scheme of the invention has the following beneficial effects:
after the inner sleeve is inserted into the preset position in the module column, the connecting piece is grouted at the reserved grouting opening, so that the connection between steel members can be realized, the decoration of a modular building is not influenced, the reliable connection is realized, larger construction installation errors can be reserved between the module and the inner sleeve, and the load can be transmitted between the inner sleeve and the module column through the filling of grouting material.
Drawings
FIG. 1 is a perspective view of an uninstalled state of a modular steel structure connection node using an inner sleeve grout connection according to an embodiment of the present invention;
FIG. 2 shows a partial enlarged view of portion A of FIG. 1;
FIG. 3 shows a side cross-sectional view of the modular steel structural connection node of FIG. 1 in an uninstalled state using an inner sleeve grout connection;
FIG. 4 shows a side cross-sectional view of the connection node of FIG. 3 in a partially installed state;
FIG. 5 is a side cross-sectional view showing the connection node of FIG. 3 in a fully installed state;
FIG. 6 is a transverse cross-sectional view showing the fully installed state of the connection node in FIG. 3;
fig. 7 is a perspective view illustrating an installation completion state of a modular steel structure connection node connected by inner sleeve grouting according to an embodiment of the present invention;
fig. 8 shows a flow chart of a method of installing a modular steel structural connection node using an inner sleeve grout connection according to an embodiment of the present invention.
Detailed Description
The following detailed description is of the best mode presently contemplated for carrying out the present invention. This description is not to be taken in a limiting sense, but is made merely for the purpose of illustrating the general principles of embodiments of the invention. The scope of the invention is best defined by the appended claims. In certain instances, detailed descriptions of well-known devices and mechanisms are omitted so as not to obscure the description of the present invention with unnecessary detail.
As shown in fig. 1, 3 and 5, the modular steel structure connection node using an inner sleeve grouting connection according to an embodiment of the present invention includes a connection member 10, an upper module 20 and a lower module 30, wherein the upper module 20 further includes an upper module column 22 extending upward in a vertical direction and an upper module beam 21 disposed perpendicular to the upper module column 22. The lower module 30 further includes a lower module column 32 extending downward in a vertical direction and a lower module beam 31 disposed perpendicular to the lower module column 32. Wherein, go up module 20 arrange in the upside of connecting piece 10, including the lower open cuboid form that is last chamber 25 that holds, lower module 30 arrange in the downside of connecting piece 10, including the lower chamber 35 that holds that is upwards open cuboid form, go up module 20 with lower module 30 relatively joins, makes the upper portion of connecting piece 10 insert locate in last chamber 25 holds, the lower part of connecting piece 10 is inserted and is located hold under in the chamber 35, just the upside of connecting piece 10 with hold between the chamber 25 on and the downside of connecting piece 10 with hold under and all have fixed space between the chamber 35, injected into no shrink grout material 9 that excels in the fixed chamber to firmly fix last module 20, connecting piece 10, lower module 30 together.
Referring to fig. 1 and 7, in the present embodiment, 4 upper modules 20 and 4 lower modules 30 are provided and connected to one connecting member 10, wherein the upper module column 22 and the lower module column 32 are made of square steel pipes, the upper module beam 21 and the lower module beam 31 are made of H-shaped steel, and the respective beams of each upper module 20 and each lower module 30 are connected by full penetration butt welds. Wherein the upper receiving cavity 25 is formed at the bottom end of the upper module column 22 and the lower receiving cavity 35 is formed at the top end of the lower module column. The upper portion of the upper receiving cavity 25 includes an upper inner partition 23, the lower portion of the lower receiving cavity 35 includes a lower inner partition 33, and the upper inner partition 23 and the lower inner partition 33 are used to separate the upper receiving cavity 25 from the lower receiving cavity 35 relative to the upper module column 22 and the lower module column 32. Preferably, the positions of the lower inner partition 23 and the lower inner partition 33 correspond to the flanges of the module beam, so that the lower inner partition 23 and the lower inner partition 33 can transmit the pulling pressure of the flanges of the module beam, and a closed space can be formed through the inner partitions to facilitate pouring of grouting materials. Two of the upper modules 20 are arranged in parallel and adjacent to two other upper modules 20 which are also arranged in parallel but have opposite upper module beams 21, so that the upper module columns 22 of the four upper modules 20 are arranged adjacent to each other. Similarly, four of the lower modules 30 are divided into two groups, with four lower module posts 32 also disposed adjacent to each other. It will be appreciated that in other embodiments, other numbers of upper and lower modules 20, 30 may be provided, and the upper and lower module beams 21, 31 may be oriented in different directions, for example, two upper modules 20 connected to the upper portion of the connecting member 10 are provided, wherein the two upper module beams 21 are arranged at 90 ° to each other, and similarly, two lower modules 30 are provided to be connected to the connecting member 10, and the two lower module beams 31 of the two lower modules 30 are arranged at 90 ° to each other.
As shown in fig. 2, a connecting member 10 according to an embodiment of the present invention includes a horizontal connecting plate 12, and in this embodiment, the horizontal connecting plate 12 has a substantially square plate shape, and 4 inner sleeves 11 having a square cylindrical shape are fixedly provided on upper and lower surfaces of the horizontal connecting plate by welding or the like. In the present embodiment, the inner sleeve 11 is formed of a square steel pipe. It will be appreciated that in other embodiments not shown, the number of inner sleeves 11 may be adjusted according to the number of upper and lower modules 20, 30 that are required to be connected at a node. One axial end of each inner sleeve 11 is fixedly connected with the horizontal connecting plate 12 through welding and the like, and the other axial end extends away from the horizontal connecting plate along the direction perpendicular to the horizontal connecting plate. A plurality of outwardly protruding inner pegs 13 are fixedly provided on the circumferential outer side of the inner sleeve 11 by welding or the like. The inner walls of the upper accommodating cavity 25 of the upper module 20 and the lower accommodating cavity 35 of the lower module 30 are provided with outer pegs 34 which protrude inwards. The sum of the width of each direction of the inner sleeve 11 and the length of the inner pin 13 of each corresponding surface is smaller than the width of each direction of the corresponding upper accommodating cavity 25 or lower accommodating cavity 35, and the difference between the width of each direction of the upper accommodating cavity 25 or lower accommodating cavity 35 and the length of the inner pin 13 of each corresponding surface is larger than the width of each direction of the inner sleeve 11, namely, each inner sleeve 11 of the upper part and the lower part of the connecting piece 10 can be inserted into one corresponding upper accommodating cavity 25 or lower accommodating cavity 35 respectively. In this embodiment, the inner pin 13 and the outer pin 34 each include a circular top plate and a connecting rod fixedly connected to the lower surface of the top plate, and the other end of the connecting rod is fixedly connected to the inner sleeve 11. The structure of the inner bolt 13 and the outer bolt 34 is used for forming stable connection with solidified non-shrinkage high-strength grouting material 9 after the non-shrinkage high-strength grouting material 9 is poured, the contact area of the bolt and the solidified grouting material is increased by the circular top plate, and then the fixing effect and the shearing strength of the bolt are improved. It will be understood that the present embodiment shows only one possible choice of the shape of the inner peg 13 and the outer peg 34, and that the inner peg 13 and the outer peg 34 may be provided in other shapes, while ensuring sufficient fixing effect and shear strength. The bottom end of the outer wall of the upper accommodating cavity 25 and the top end of the outer wall of the lower accommodating cavity 35 are preferably provided with viscoelastic materials such as rubber, so that a closed space is formed between the horizontal connecting plate 12 and the upper accommodating cavity 25 and the lower accommodating cavity 35, and grouting materials are prevented from flowing out when grouting is performed after the modules are stacked. After the connection is completed, the horizontal connecting plate 12 separates the upper accommodating cavity 25 from the lower accommodating cavity 35, and the horizontal connecting plate 12 can transmit the pulling and pressing force between the modules. Preferably, each the top of lower module post 32 and/or each the bottom of going up module post 22 sets up dodges the recess, makes go up module post 22 with module post 32 is the back of relatively joining down, horizontal connecting plate 12 can be acceptd in dodging the groove, thereby the order go up module 20 with lower module 30 closely laminates for upper and lower module roof beam zero clearance can transmit the vertical load of going up the module roof beam and reach the purpose of upper and lower module roof beam combined work under vertical load effect, also can play the effect of location to connecting piece 10.
Referring also to fig. 6, preferably, a plurality of the inner pegs 13 are arranged in a plurality of columns on the circumferential side of the inner sleeve 11 in the axial direction of the inner sleeve, while a plurality of the outer pegs 34 are arranged in a plurality of columns in the axial direction of the inner walls of the upper and lower receiving cavities 25 and 35 in the inner walls of the upper and lower receiving cavities 25 and 35 of the upper and lower modules 20 and 30. Wherein the vertical rows of the inner pins 13 and the vertical rows of the outer pins 34 are staggered with each other in the horizontal direction, so that after the connecting member 10 is disposed in the upper and lower receiving cavities 25 and 35, the vertical rows of the inner pins 13 are inserted between the vertical rows of the outer pins 34, thereby the inner pins 13 and the outer pins 34 are staggered with each other in the horizontal direction. After the non-shrinkage high-strength grouting material 9 is poured, the inner bolt 13 and the outer bolt 34 are relatively fixed through solidified grouting material, and due to the fact that the inner bolt 13 and the outer bolt 34 are arranged in a staggered mode, load distribution among the fixed inner sleeve 11, the upper module 20 and the lower module 30 is more uniform, and the fixing effect is more reliable.
Referring to fig. 3 to 5, an upper inlet 26 penetrating to the outside is provided on an upper side in the axial direction of a side surface of each of the upper receiving chambers 25, and similarly, a lower inlet 36 penetrating to the outside is provided on an upper side in the axial direction of a side surface of each of the lower receiving chambers 35. The upper injection port 26 and the lower injection port 36 are used as injection ports of grouting material 40 during installation, and as shown in fig. 5, the grouting material 40 is filled in fixing spaces between the upper side of the connecting member 10 and the upper receiving cavity 25 and between the lower side of the connecting member 10 and the lower receiving cavity 35, so as to fix the connecting member 10, the upper module 20, and the lower module 30 together. Preferably, the upper injection port 26 and the lower injection port 36 are respectively provided on a plurality of sides of the upper receiving chamber 25 and the lower receiving chamber 35, so that the operation at the time of grouting is more convenient.
The following describes a method for installing a modular steel structure connection node using an inner sleeve grouting connection according to an embodiment of the present invention with reference to the accompanying drawings. Referring to fig. 8, first, in step S1, the lower module column 32 of each lower module 30 is vertically disposed with the lower receiving cavity 35 facing upward, and 4 lower modules 30 are divided into two groups and oppositely arranged (see above). The 4 inner sleeves 11 at the lower part of the connecting piece 10 are respectively aligned with the 4 lower accommodating cavities 35, and the inner pegs 13 of the connecting piece 10 are aligned with the outer pegs 34 in the lower accommodating cavities 35. And then inserting the lower part of the connecting piece 10 into the lower accommodating cavity 35 until the lower surface of the horizontal connecting plate 12 of the connecting piece 10 abuts against the top end of the outer wall of the lower accommodating cavity 35. Then, in step S2, the non-shrink high-strength grouting material 9 is poured into the fixed space between the lower portion of the connecting member 10 and the lower accommodating cavity 35 through the lower pouring port 36 until the fixed space is filled up, and after the non-shrink high-strength grouting material 9 is solidified, the connecting member 10 is connected to the four lower modules 30. In a subsequent step S3, 4 of the upper modules 20 are grouped into 2 groups and arranged in reverse (see above), the upper receiving cavity 25 of each upper module 20 is vertically aligned with one of the inner sleeves 11 of the upper portion of the connecting member 10, respectively, and the upper modules 20 are brought into abutting engagement with the lower modules 30 such that the upper module beams 21 of each upper module 20 are aligned with the lower module beams 31 of one of the lower modules 30. Then, in step S4, a non-shrink high-strength grouting material 9 is poured into the fixing space between the upper portion of the connecting member 10 and the upper accommodating chamber 25 through the upper injection port 26 until the fixing space is filled up, and after the non-shrink high-strength grouting material 9 is solidified, the connecting member 10 is fixedly connected to the upper module 20, so that the upper module 20 and the lower module 30 are connected.
The modular steel structure connecting joint adopting the inner sleeve grouting connection adopts a simple structure to enhance the stability of the connection between steel structures. This kind of connected node makes simply swiftly, need not to reserve great operating space near connecting portion when making the connection, and need not welding operation, and is low to installer's technical requirement, and error tolerance is big to practice thrift the cost, promote building quality, very be fit for using widely in various building application.
It should be noted that the present invention is not limited to the above-mentioned embodiments, and other changes and modifications can be made by those skilled in the art according to the spirit of the present invention, and these changes and modifications made according to the spirit of the present invention should be included in the scope of the present invention as claimed.

Claims (9)

1.采用内套筒灌浆连接的模块化钢结构连接节点,用于钢结构模块间的连接,其特征在于,包括上模块柱、上模块梁、下模块柱、下模块梁、连接件,所述连接件包括水平连接板以及设置在所述水平连接板的表面上的至少两个内套筒,所述内套筒与所述水平连接板固定,所述内套筒的侧面设有向外突出的内栓钉,所述上模块柱及所述下模块柱的内壁设有向内突出的外栓钉,所述上模块柱包括上容纳腔,所述下模块柱包括下容纳腔,所述连接件的上部的每一所述内套筒分别设置于每一所述上模块柱的所述上容纳腔内,所述连接件的下部的每一所述内套筒分别设置于每一所述下模块柱的所述下容纳腔内,并在所述上容纳腔及所述连接件的上部之间、所述下容纳腔及所述接件的下部之间设置灌浆料,所述灌浆料将所述上模块柱、所述下模块柱与所述连接件固定连接。1. The modular steel structure connection node using inner sleeve grouting connection is used for the connection between the steel structure modules, it is characterized in that, comprises upper module column, upper module beam, lower module column, lower module beam, connector, so The connecting piece includes a horizontal connecting plate and at least two inner sleeves arranged on the surface of the horizontal connecting plate, the inner sleeves are fixed with the horizontal connecting plate, and the sides of the inner sleeve are provided with outwards. Protruding inner pegs, the inner walls of the upper module column and the lower module column are provided with inwardly protruding outer pegs, the upper module column includes an upper accommodating cavity, and the lower module column includes a lower accommodating cavity, so Each of the inner sleeves on the upper part of the connecting piece is respectively arranged in the upper accommodating cavity of each of the upper module columns, and each of the inner sleeves on the lower part of the connecting piece is respectively arranged in each In the lower accommodating cavity of the lower module column, a grouting material is arranged between the upper accommodating cavity and the upper part of the connecting piece, and between the lower accommodating cavity and the lower part of the connecting piece. The grouting material fixedly connects the upper module column, the lower module column and the connecting piece. 2.根据权利要求1所述的采用内套筒灌浆连接的模块化钢结构连接节点,其特征在于,多个所述内栓钉在所述内套筒的周向侧面上排列为多个竖列,同时,多个所述外栓钉在所述上模块柱的上容纳腔以及所述下模块柱的下容纳腔的内壁内排列为多个竖列,其中所述内栓钉组成的竖列与所述外栓钉组成的竖列在水平方向上互相交错。2 . The modular steel structure connection node using inner sleeve grouting connection according to claim 1 , wherein a plurality of the inner pegs are arranged on the circumferential side of the inner sleeve as a plurality of vertical At the same time, a plurality of the outer pegs are arranged in a plurality of vertical columns in the upper accommodating cavity of the upper module column and the inner wall of the lower accommodating cavity of the lower module column, wherein the vertical columns composed of the inner pegs The columns and the vertical columns formed by the outer pegs are staggered with each other in the horizontal direction. 3.根据权利要求2所述的采用内套筒灌浆连接的模块化钢结构连接节点,其特征在于,所述内栓钉及每个所述外栓钉包括一个圆形顶板以及一个与所述圆形顶板的下表面固定连接的连接杆,所述连接杆的另一端与所述内套筒固定连接。3. The modular steel structure connection node using inner sleeve grouting connection according to claim 2, wherein the inner peg and each of the outer pegs comprise a circular top plate and a A connecting rod is fixedly connected to the lower surface of the circular top plate, and the other end of the connecting rod is fixedly connected to the inner sleeve. 4.根据权利要求3所述的采用内套筒灌浆连接的模块化钢结构连接节点,其特征在于,在所述上容纳腔的外壁底端以及所述下容纳腔的外壁顶端设置弹性材料,在所述水平连接板与所述上容纳腔及下容纳腔之间形成密闭空间。4. The modular steel structure connection node using inner sleeve grouting connection according to claim 3, wherein elastic material is provided on the bottom end of the outer wall of the upper accommodating cavity and the top end of the outer wall of the lower accommodating cavity, A closed space is formed between the horizontal connecting plate, the upper accommodating cavity and the lower accommodating cavity. 5.根据权利要求1所述一种采用内套筒灌浆连接的模块化钢结构连接节点,其特征在于,在所述水平连接板的上侧及下侧各设置四个内套筒,四个所述上模块柱按四乘四阵列相邻排布,四个上模块梁两两分为两组,且两组所述上模块梁方向相反地设置在四个所述上模块柱两侧,四个所述下模块柱按四乘四阵列相邻排布,四个下模块梁两两分为两组,且两组所述下模块梁方向相反地设置在四个所述下模块柱两侧。5. The modular steel structure connection node using inner sleeve grouting connection according to claim 1, characterized in that, four inner sleeves are arranged on the upper side and the lower side of the horizontal connecting plate respectively, four The upper module columns are arranged adjacently in a four-by-four array, and the four upper module beams are divided into two groups, and the upper module beams of the two groups are arranged on both sides of the four upper module columns in opposite directions. The four lower module columns are arranged adjacently in a four-by-four array, the four lower module beams are divided into two groups by two, and the lower module beams of the two groups are arranged in opposite directions on the two sides of the four lower module columns. side. 6.根据权利要求1所述一种采用内套筒灌浆连接的模块化钢结构连接节点,其特征在于,在每个所述下模块柱的顶端和/或每个所述上模块柱的底端设置避让凹槽,使得在所述上模块柱与所述下模块柱相对接合后,所述水平连接板能够被收容在所述避让槽中。6. A modular steel structure connection node using inner sleeve grouting connection according to claim 1, characterized in that, at the top of each of the lower module columns and/or the bottom of each of the upper module columns An escape groove is provided at the end, so that after the upper module column is relatively engaged with the lower module column, the horizontal connecting plate can be accommodated in the escape groove. 7.根据权利要求1所述一种采用内套筒灌浆连接的模块化钢结构连接节点,其特征在于,所述上容纳腔内及所述下容纳腔内还包括上内隔板及下内隔板,所述上内隔板及所述下内隔板的位置分别与所述上模块梁及所述下模块梁的翼缘对应。7 . The modular steel structure connection node using inner sleeve grouting connection according to claim 1 , wherein the upper and lower accommodating chambers further comprise an upper inner baffle and a lower inner baffle. 8 . and the positions of the upper inner baffle and the lower inner baffle correspond to the flanges of the upper module beam and the lower module beam respectively. 8.根据权利要求1所述一种采用内套筒灌浆连接的模块化钢结构连接节点,其特征在于,所述上容纳腔的侧面的轴向的上侧设置有向外侧贯通的上注入口,所述下容纳腔的侧面的轴向的上侧设置有向外侧贯通的下注入口。8 . The modular steel structure connection node using inner sleeve grouting connection according to claim 1 , wherein the axial upper side of the side surface of the upper accommodating cavity is provided with an upper injection port that penetrates to the outside. 9 . and the axial upper side of the side surface of the lower accommodating cavity is provided with a lower injection port penetrating to the outside. 9.一种安装根据前述权利要求中任一项所述的采用内套筒灌浆连接的模块化钢结构连接节点的方法,其特征在于,包括以下步骤:9. A method of installing a modular steel structure connection node using an inner sleeve grouting connection according to any one of the preceding claims, characterized in that it comprises the following steps: S1,将每一所述下模块的下模块柱竖直设置,其中所述下容纳腔朝向上方,并将4个所述下模块柱布置为四乘四阵列,将所述连接件的下部的4个所述内套筒分别与4个所述下容纳腔对齐,令所述连接件的内栓钉与所述下容纳腔中的外栓钉对齐,进而将所述连接件的下部插入所述下容纳腔,直至所述连接件的水平连接板的下表面与所述下容纳腔的外壁顶端抵顶;S1, the lower module columns of each of the lower modules are vertically arranged, wherein the lower accommodating cavity faces upward, and the four lower module columns are arranged in a four-by-four array, and the lower The four inner sleeves are respectively aligned with the four lower accommodating cavities, so that the inner pegs of the connecting pieces are aligned with the outer pegs in the lower accommodating cavities, and then the lower parts of the connecting pieces are inserted into the lower accommodating cavities. the lower accommodating cavity until the lower surface of the horizontal connecting plate of the connecting piece abuts against the top end of the outer wall of the lower accommodating cavity; S2,由所述下注入口向所述连接件的下部与所述下容纳腔之间的固定空间中灌注灌浆料直至将所述固定空间填满,令所述灌浆料凝固,S2, pour grouting material into the fixed space between the lower part of the connecting piece and the lower accommodating cavity from the lower injection port until the fixed space is filled, and the grouting material is solidified, S3,将4个所述上模块分为组并相反布置,每一所述上模块的所述上容纳腔分别竖直地与所述连接件的上部的一个所述内套筒对齐,进而将所述上模块与所述下模块相对接合,使得所述每一所述上模块的所述上模块梁与一个所述下模块的所述下模块梁对齐,S3, divide the four upper modules into groups and arrange them in opposite directions, the upper accommodating cavity of each upper module is vertically aligned with one of the inner sleeves on the upper part of the connecting piece, and then the the upper module is relatively engaged with the lower module such that the upper module beam of each of the upper modules is aligned with the lower module beam of one of the lower modules, S4,由所述上注入口向所述连接件的上部与所述上容纳腔之间的固定空间中灌注所述灌浆料直至将所述固定空间填满,令所述灌浆料凝固,完成所述上模块与所述下模块的连接。S4, pour the grouting material into the fixed space between the upper part of the connecting piece and the upper accommodating cavity through the upper injection port until the fixed space is filled up, make the grouting material solidify, and complete the The connection between the upper module and the lower module.
CN202110450353.1A 2021-04-25 2021-04-25 Modularized steel structure connecting node adopting inner sleeve grouting connection and mounting method Active CN113216390B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110450353.1A CN113216390B (en) 2021-04-25 2021-04-25 Modularized steel structure connecting node adopting inner sleeve grouting connection and mounting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110450353.1A CN113216390B (en) 2021-04-25 2021-04-25 Modularized steel structure connecting node adopting inner sleeve grouting connection and mounting method

Publications (2)

Publication Number Publication Date
CN113216390A true CN113216390A (en) 2021-08-06
CN113216390B CN113216390B (en) 2023-08-11

Family

ID=77088959

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110450353.1A Active CN113216390B (en) 2021-04-25 2021-04-25 Modularized steel structure connecting node adopting inner sleeve grouting connection and mounting method

Country Status (1)

Country Link
CN (1) CN113216390B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113969692A (en) * 2021-11-29 2022-01-25 重庆大学 A lattice type wind power tower that is easy to transport
WO2023115952A1 (en) * 2021-12-24 2023-06-29 中建科技集团有限公司 Multi-layer modular home and connecting assembly thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108193772A (en) * 2018-02-08 2018-06-22 天津大学 Full bolt connecting node in the middle part of assembled building module in length and breadth
CN109537810A (en) * 2019-01-17 2019-03-29 中建科技有限公司深圳分公司 The assembly method of steel structure node, prefabricated post and preparation method thereof, column beam
CN109629677A (en) * 2019-01-05 2019-04-16 天津大学 A kind of connecting node of the modularization steel building using outer sleeve connection
CN110878587A (en) * 2019-10-24 2020-03-13 武汉理工大学 Module assembly type building beam column node connection structure
CN211817005U (en) * 2019-11-20 2020-10-30 中冶天工集团有限公司 Pouring type steel module connecting node structure
WO2020234908A1 (en) * 2019-05-21 2020-11-26 Giorgio Grossi System and method for the realization of the aggregation and rapid three-dimensional union of prefabricated modular elements in the shape of a cube or parallelepiped with a steel frame
CN112627336A (en) * 2020-12-11 2021-04-09 天津大学 Detachable conical head bolt steel structure module building unit connection node

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108193772A (en) * 2018-02-08 2018-06-22 天津大学 Full bolt connecting node in the middle part of assembled building module in length and breadth
CN109629677A (en) * 2019-01-05 2019-04-16 天津大学 A kind of connecting node of the modularization steel building using outer sleeve connection
CN109537810A (en) * 2019-01-17 2019-03-29 中建科技有限公司深圳分公司 The assembly method of steel structure node, prefabricated post and preparation method thereof, column beam
WO2020234908A1 (en) * 2019-05-21 2020-11-26 Giorgio Grossi System and method for the realization of the aggregation and rapid three-dimensional union of prefabricated modular elements in the shape of a cube or parallelepiped with a steel frame
CN110878587A (en) * 2019-10-24 2020-03-13 武汉理工大学 Module assembly type building beam column node connection structure
CN211817005U (en) * 2019-11-20 2020-10-30 中冶天工集团有限公司 Pouring type steel module connecting node structure
CN112627336A (en) * 2020-12-11 2021-04-09 天津大学 Detachable conical head bolt steel structure module building unit connection node

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113969692A (en) * 2021-11-29 2022-01-25 重庆大学 A lattice type wind power tower that is easy to transport
WO2023115952A1 (en) * 2021-12-24 2023-06-29 中建科技集团有限公司 Multi-layer modular home and connecting assembly thereof

Also Published As

Publication number Publication date
CN113216390B (en) 2023-08-11

Similar Documents

Publication Publication Date Title
JP7288031B2 (en) Connection system and method for prefabricated volumetric building modules
KR101425941B1 (en) Modular structure
CN113216390A (en) Modular steel structure connecting joint adopting inner sleeve grouting connection and mounting method
US12049753B2 (en) Modular structure and connection method
MXPA04008991A (en) Building frame structure.
KR20150055497A (en) Modular unit having socket connector, Modular unit structure using the same and Construction method of modular unit structure
KR101632681B1 (en) Joint structure of modular system using the plate, Construction method and Modular system thereby
JP4165648B2 (en) Components and methods of moment resistant building frame structures
CN214784740U (en) Modular steel structure connection node with inner sleeve grouting connection
CN115787827A (en) Steel pipe concrete column and node integrated module assembly type structure
CN216810237U (en) Steel pipe concrete column and node integrated module assembly type structure
CN115059307B (en) Construction method of assembled earthquake-resistant building
KR20210001122A (en) Connecting structure for columns
KR101685632B1 (en) Shear connector to increase strength and ductility
JPH06173343A (en) Column-beam joint structure in laminated lumber structure
CN110984380A (en) Steel frame structure of building and assembling method
CN220377657U (en) Dual shear grouting sleeve and modularized building connection node
CA2513038C (en) Quick-set, full-moment-lock, column and beam building frame system and method
CN219508825U (en) Steel mould building structure connected node
CN220377509U (en) Modular steel structure connection nodes
CN214461258U (en) Steel-joint concrete structure column-beam joint structure and assembly type building
KR102722516B1 (en) A Construction method using dry coupling method between PC modulars
CN219219342U (en) Assembled concrete beam column bidirectional insertion beam column connector
CN118793233A (en) Double shear grouting sleeve and modular building connection node
KR20130048857A (en) Connector for jointing concrete filled tube and beam and jointing structure of the same

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant