CN113123321A - Method for synchronous construction of pile foundation and soft foundation treatment by adopting compound vacuum preloading and pile loading - Google Patents

Method for synchronous construction of pile foundation and soft foundation treatment by adopting compound vacuum preloading and pile loading Download PDF

Info

Publication number
CN113123321A
CN113123321A CN201911413465.9A CN201911413465A CN113123321A CN 113123321 A CN113123321 A CN 113123321A CN 201911413465 A CN201911413465 A CN 201911413465A CN 113123321 A CN113123321 A CN 113123321A
Authority
CN
China
Prior art keywords
construction
pile
area
foundation
soft foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911413465.9A
Other languages
Chinese (zh)
Other versions
CN113123321B (en
Inventor
任泓帆
刘涛
叶曾豹
潘宁
赵静飞
陈文凯
范垚垚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201911413465.9A priority Critical patent/CN113123321B/en
Publication of CN113123321A publication Critical patent/CN113123321A/en
Application granted granted Critical
Publication of CN113123321B publication Critical patent/CN113123321B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a soft foundation treatment and pile foundation synchronous construction method, which comprises the following steps: leveling the field and confirming a soft foundation area (3); dividing a construction area outside the soft foundation area (3) into a construction area (2) with a strong influence range and a construction area (1) with a weak influence range; a pile machine is arranged on the weak influence range construction area (1), a soil body side shift monitoring point (4) is arranged on the strong influence range construction area (2), and a vacuum preloading system is arranged in the soft foundation area (3); when the pile foundation construction of the weak influence range construction area (1) is carried out, a vacuum preloading system is adopted to carry out soft foundation treatment on the soft foundation area (3); completing pile foundation construction and reaching the design requirement area, and constructing a bottom plate; when the pile foundation construction and the soft foundation treatment simultaneously meet the design requirements, the first layer of pile loading in the soft foundation area (3) starts construction; when the bottom plate meets the design requirement, the soft foundation area (3) at the joint of the bottom plate is firstly subjected to second layer stacking construction until the last layer stacking is completed.

Description

Method for synchronous construction of pile foundation and soft foundation treatment by adopting compound vacuum preloading and pile loading
Technical Field
The invention belongs to the technical field of construction of constructional engineering, and particularly relates to a method for synchronously constructing a pile foundation by combining compound vacuum preloading soft foundation treatment with pile loading.
Background
The soft foundation treatment, also called soft foundation treatment, is a process of treating a soft foundation to ensure that the settlement of the soft foundation becomes firm enough and the consolidation degree and stability of the soft foundation are improved to the design requirements in order to prevent accidents such as unstable buildings and the like caused by the sinking and the tensile cracking of the foundation after the construction if the foundation is not firm enough before the construction.
With the continuous development of economy in coastal areas, the increase of factory buildings, ports, airports, highways and residential buildings, the treatment and the use of soft soil foundations become more and more extensive; because the bearing capacity of the soft soil is low, the deformation after construction is large, the consolidation settlement time is long, and the requirements of engineering can not be met, the treatment of the soft soil foundation is the focus of the foundation treatment attention in coastal areas all the time; at present, the soft soil foundation treatment methods are many, and can be divided into a drainage consolidation method (a preloading method, a vacuum preloading method and a combined preloading method), a composite foundation method and the like according to the foundation treatment and consolidation principle.
At present, compound vacuum preloading combined loading soft foundation treatment is carried out at home, pile foundation construction is carried out after soil is stabilized, the construction method needs to be divided into two stages of soft foundation treatment and pile foundation construction, and construction period is long.
The above problems are urgently needed to be improved and to be solved.
Disclosure of Invention
In order to overcome the defects of the prior art, a method for synchronously constructing the pile foundation and the soft foundation treatment by combining compound vacuum preloading and pile loading is provided.
The technical scheme adopted by the invention is as follows: the method for synchronous construction of pile foundation and soft foundation treatment by adopting compound vacuum preloading and pile loading comprises the following steps:
s1, leveling the field and confirming a soft foundation area;
s2, dividing the construction area outside the soft foundation area into a construction area with a strong influence area and a construction area with a weak influence area according to the influence area of the soft foundation treatment on the peripheral soil body, and marking the construction areas;
s3, arranging pile machines on the construction area with the weak influence range, arranging soil body side shift monitoring points on the construction area with the strong influence range, and arranging a vacuum preloading system in the soft foundation area;
s4, performing soft foundation treatment on the soft foundation area by adopting a vacuum preloading system while constructing the pile foundation in the weak influence area construction area;
s5, completing pile foundation construction and reaching the design requirement area, and starting bottom plate construction;
s6, when pile foundation construction and soft foundation treatment are completed and design requirements are met simultaneously, construction is started on the first layer of stacking load in the soft foundation area;
and S7, when the bottom plate is finished and meets the design requirement, the soft foundation area at the joint of the bottom plate is firstly subjected to second layer stacking construction until the last layer stacking is finished.
Preferably, in step S1, the soft foundation area range is confirmed according to a design drawing.
Wherein the soft foundation area is a range which needs foundation treatment and is marked in a design drawing by a designer according to a geological survey report.
Preferably, in step S2, the soft foundation treatment is performed on the soil body, and the method includes performing crack and deflection control calculation on the pile foundation according to the normal use limit state of the pile foundation to obtain the lateral allowable deformation value Δ L of the pile foundation0Then establishing a finite element model, and calculating the maximum lateral deformation accumulated value L of the soil body at the foundation pile position of each row of piles through simulationiOutside the soft foundation region (3), Δ L0≤LiPart is set as a construction area with a strong influence range, Delta L0>LiAnd setting the part as a construction area with a weak influence range.
In the soft foundation treatment process, adverse effects can be caused to the surrounding soil body, such as soil foundation loosening, sinking and the like, and the buildings on the soil body are naturally damaged to a certain extent; before the soft foundation treatment, the influence range of the soil body is determined, and three construction areas are divided according to the influence range of the soft foundation treatment on the soil body.
Preferably, in step S3, the soil mass lateral movement monitoring points in the construction area with the strong influence range are expanded by 10-50 m from the foundation treatment boundary, one soil mass lateral movement monitoring point is radially arranged every 5m, the number of the soil mass lateral movement monitoring points in the radial direction is taken as a group, and the number of the groups uniformly arranged in the circumferential direction is determined according to the construction drawing and the monitoring range.
Preferably, in step S3, a plurality of pile machines are circumferentially and uniformly arranged in the construction area with a weak influence range, and the vacuum preloading system performs construction according to a design drawing.
The determination of the number of the pile machines needs to be determined according to factors such as the number of the pile machines in the drawing, the construction progress of the pile machines, the soft foundation processing time and the like.
Preferably, in step S4, the pile foundation is constructed from the outside of the weak influence range construction area (1) to the inside, the finite element model is corrected according to the monitoring data to obtain a time axis graph of the pile position soil lateral deformation accumulated value of the strong influence range construction area, and the maximum value L of the pile position soil lateral deformation accumulated value is calculated according to the time axis graphiSubtracting pile foundation lateral allowable deformation value delta L0Give L'iAnd obtaining a construction time node by the corresponding relation between the pile position soil body lateral deformation accumulated value and the time axis curve graph so as to judge whether the pile foundation can be constructed.
Preferably, when the pile foundation construction in step S5 is completed and reaches more than 80% of the design strength value, the bottom plate starts block construction.
Preferably, in step S6, the pile foundation engineering is completed and reaches more than 80% of the design strength, and after the vacuum preloading system runs fully for 30d, the soft foundation area first sand pad layer stacking construction starts, and the vacuum preloading system keeps running fully at the same time.
Wherein the first sand cushion layer stacking thickness is 1 m.
Preferably, the first layer and the subsequent stacking construction are paved from the center of the soft foundation area to the periphery.
The first layer of stacking construction is paved from the center to the periphery and is constructed by the bottom plate in blocks, and normal construction of other machines is not hindered by adopting the construction scheme, so that the construction site is well-ordered.
Preferably, in step S7, when the floor finish block reaches the design strength value of more than 80%, the soft foundation area at the joint with the floor is subjected to the second layer stacking construction first until the last layer stacking is finished.
The invention has the beneficial effects that: according to the method for synchronously constructing the composite vacuum preloading combined preloading soft foundation treatment and the pile foundation engineering, the three construction areas are divided, the vacuum preloading system is arranged in the soft foundation area, and the pile machine is arranged in the non-soft foundation area, so that the pile foundation construction and the soft foundation treatment are simultaneously carried out, and the problem of long construction period of the pile foundation engineering construction after the composite vacuum preloading combined preloading soft foundation treatment is firstly constructed is solved; the construction method adopts the base plate to carry out block construction, and sets the sequence of pile foundation and pile loading construction, so that the scientific and reasonable construction process arrangement greatly shortens the construction period, and simultaneously, the soft foundation treatment effect and the pile foundation engineering quality are ensured.
Drawings
FIG. 1 is a construction area division diagram of the method for synchronous construction of pile foundation and soft foundation treatment by combining compound vacuum preloading;
fig. 2 is a construction floor plan of fig. 1.
In the figure: 1-weak influence range construction area 2-strong influence range construction area 3-soft foundation area 4-soil body side shift monitoring point.
Detailed Description
The invention is further described below with reference to the specific drawings.
As shown in fig. 1 and 2, the method for synchronous construction of soft foundation treatment and pile foundation by adopting compound vacuum preloading and pile loading comprises the following steps:
and S1, firstly, lofting and confirming the construction area according to the design drawing, dividing the area by using color flags or other markers, then carrying out leveling treatment on the construction area by using a digging machine, and then marking the area by using the color flags or other markers according to the soft foundation area 3 confirmed by the design drawing. .
S2, the soft foundation treatment can cause damage to the surrounding soil body in different degrees, and the control calculation of the crack and deflection of the pile foundation is carried out according to the normal use limit state of the pile foundation to obtain the lateral allowable deformation value Delta L of the pile foundation0Then establishing a finite element model, and calculating the maximum lateral deformation accumulated value L of the soil body at the foundation pile position of each row of piles through simulationiOutside the soft foundation region (3), Δ L0≤LiThe part is set as a construction area 2 with a strong influence range delta L0>LiAnd the part of the construction area is set as a weak influence area construction area 1, the area is divided by using color flags or other markers, and a dividing line can be used as a reference line of the construction area, so that the construction becomes well-ordered.
S3, after the construction area is divided, determining that 32 required pile machines are needed, arranging mechanical approaches of the pile machines, a vacuum preloading system and the like, uniformly arranging the pile machines in the radial direction according to the outermost circle of the construction area 1 with a weak influence range, simultaneously installing instruments such as a sand cushion layer, a drainage plate, a pipe network and the like in the soft foundation area 3 by the vacuum preloading system in sequence, arranging soil body side shift monitoring points 4 in the construction area 2 with a strong influence range according to a construction drawing and a monitoring range, expanding the soil body side shift monitoring points 20m from the boundary of the soft foundation area 3, respectively arranging one soil body side shift monitoring point 4 at every 5m intervals in the radial direction, and uniformly arranging 12 groups (see figure 2) in the circumferential direction by taking the number of the radial 5 soil body side shift monitoring points.
S4, the pile foundation begins to be constructed inwards from the outer side of the weak influence range construction area 1, meanwhile, after the vacuum preloading system is installed in the soft foundation area 3, the vacuum preloading system is vacuumized to 0.06MPa in advance to check whether the vacuum pipe leaks air, if no problem exists, the vacuum degree is increased to be more than 0.087MPa for full-load operation, and meanwhile, the pile foundation construction in the strong influence range construction area 2 is organized according to data measured by soil body side shift monitoring points 4.
S5, when the pile foundation in the weak influence range construction area 1 and the strong influence range construction area 2 is completely constructed, the pile foundation strength is detected, when the pile foundation strength is detected to reach more than 80% of design strength value, the digging machine begins to excavate the area meeting the design requirement, then the back pouring belt is used for reasonably and conveniently dividing the bottom plate into blocks, then the bottom plate construction is carried out according to the blocks according to construction drawings and construction schemes, the bottom plate adopts block construction, the labor force can be effectively reduced, the labor efficiency is improved, the construction collision is avoided, and the construction period is greatly shortened.
And S6, when the pile foundation meets the condition of the step S5 and the pile foundation is fully loaded in a vacuum preloading mode for 30d, the first layer of stacking load of the soft foundation area 3 begins to be spread from the center to the periphery, and the first layer of stacking load adopts a sand cushion layer with the thickness of 1 m.
S7, when the bottom board finishes the block reaching over 80% design strength value, the soft foundation area 3 connected with the bottom board of the block is firstly carried out the second layer of stacking construction until the last layer of stacking is finished.

Claims (10)

1. The method for synchronous construction of pile foundation and soft foundation treatment by adopting compound vacuum preloading and pile loading is characterized by comprising the following steps of: the method comprises the following steps:
s1, leveling the field, and confirming a soft foundation area (3);
s2, dividing the construction area outside the soft foundation area (3) into a strong influence area construction area (2) and a weak influence area construction area (1) according to the influence area of the soft foundation treatment on the peripheral soil mass, and marking the construction areas;
s3, arranging a pile machine on the weak influence range construction area (1), arranging soil body side shift monitoring points (4) on the strong influence range construction area (2), and arranging a vacuum preloading system in the soft foundation area (3);
s4, performing soft foundation treatment on the soft foundation area (3) by adopting a vacuum preloading system while constructing the pile foundation in the weak influence area construction area (1);
s5, completing pile foundation construction and reaching the design requirement area, and starting bottom plate construction;
s6, when pile foundation construction and soft foundation treatment are completed and design requirements are met simultaneously, construction is started at the first layer of stacking load of the soft foundation area (3);
and S7, when the bottom plate is finished and meets the design requirement, the soft foundation area (3) at the joint of the bottom plate is firstly subjected to second layer stacking construction until the last layer stacking is finished.
2. The method for synchronous construction of soft foundation treatment and pile foundation by adopting compound vacuum preloading and pile loading as claimed in claim 1, wherein: in the step S1, the soft foundation area (3) range is confirmed according to the design drawing.
3. The method for synchronous construction of soft foundation treatment and pile foundation by adopting compound vacuum preloading and pile loading as claimed in claim 1, wherein: in step S2, the soft foundation treatment is performed on the soil body, and the method includes performing crack and deflection control calculation on the pile foundation according to the normal use limit state of the pile foundation to obtain the lateral allowable deformation value Δ L of the pile foundation0Then establishing a finite element model, and calculating the maximum lateral deformation accumulated value L of the soil body at the foundation pile position of each row of piles through simulationiOutside the soft foundation region (3), Δ L0≤LiThe part is set as a construction area (2) with a strong influence range, Delta L0>LiThe part is set as a weak influence range construction area (1).
4. The method for synchronous construction of soft foundation treatment and pile foundation by adopting compound vacuum preloading and pile loading as claimed in claim 1, wherein: in the step S3, the soil body side shift monitoring points (4) in the construction area (2) with the strong influence range are expanded by 10-50 m from the boundary of the soft foundation area (3), one soil body side shift monitoring point (4) is respectively arranged at every 5m in the radial direction, the number of the soil body side shift monitoring points (4) in the radial direction is used as a group, and the number of the groups uniformly arranged in the circumferential direction is determined according to the construction drawing and the monitoring range.
5. The method for synchronous construction of soft foundation treatment and pile foundation by adopting compound vacuum preloading and pile loading as claimed in claim 1, wherein: in the step S3, a plurality of pile machines are circumferentially and uniformly arranged in the weak influence range construction area (1), and the vacuum preloading system carries out construction according to a design drawing.
6. The method for synchronous construction of soft foundation treatment and pile foundation by adopting compound vacuum preloading and pile loading as claimed in claim 1, wherein: in the step S4, the pile foundation is constructed from the outside of the weak influence range construction area (1) to the inside, and the finite element model is corrected according to the monitoring data to obtain the time axis graph of the pile position soil lateral deformation accumulated value of the strong influence range construction area (2), and the maximum value L of the pile position soil lateral deformation accumulated value of the pile foundation is used as the time axis graphiSubtracting pile foundation lateral allowable deformation value delta L0Give L'iAnd obtaining a construction time node by the corresponding relation between the pile position soil body lateral deformation accumulated value and the time axis curve graph so as to judge whether the pile foundation can be constructed.
7. The method for synchronous construction of soft foundation treatment and pile foundation by adopting compound vacuum preloading and pile loading as claimed in claim 1, wherein: in step S5, when the pile foundation construction is completed and reaches a design strength value of 80% or more, the bottom plate starts block construction according to the post-cast strip.
8. The method for synchronous construction of soft foundation treatment and pile foundation by adopting compound vacuum preloading and pile loading as claimed in claim 1, wherein: in the step S6, the pile foundation engineering is completed and reaches more than 80% of design strength, and after the vacuum preloading system runs fully for 30d, the first sand cushion layer stacking construction in the soft foundation region (3) begins, and the vacuum preloading system keeps running fully at the same time.
9. The method for synchronous construction of soft foundation treatment and pile foundation by adopting compound vacuum preloading and pile loading as claimed in claim 8, wherein: and the first layer and the subsequent stacking construction are paved from the center of the soft foundation area (3) to the periphery.
10. The method for synchronous construction of soft foundation treatment and pile foundation by adopting compound vacuum preloading and pile loading as claimed in claim 1, wherein: in step S7, when the floor panel has finished the block to reach the design strength value of more than 80%, the soft foundation area (3) connected to the floor panel is first constructed for the second layer of stacking until the last layer of stacking is finished.
CN201911413465.9A 2019-12-31 2019-12-31 Synchronous construction method for treating soft foundation by adopting compound vacuum preloading and surcharge loading Active CN113123321B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911413465.9A CN113123321B (en) 2019-12-31 2019-12-31 Synchronous construction method for treating soft foundation by adopting compound vacuum preloading and surcharge loading

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911413465.9A CN113123321B (en) 2019-12-31 2019-12-31 Synchronous construction method for treating soft foundation by adopting compound vacuum preloading and surcharge loading

Publications (2)

Publication Number Publication Date
CN113123321A true CN113123321A (en) 2021-07-16
CN113123321B CN113123321B (en) 2022-11-25

Family

ID=76770407

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911413465.9A Active CN113123321B (en) 2019-12-31 2019-12-31 Synchronous construction method for treating soft foundation by adopting compound vacuum preloading and surcharge loading

Country Status (1)

Country Link
CN (1) CN113123321B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005207164A (en) * 2004-01-26 2005-08-04 Maruyama Kogyo Kk Soil improvement method for weak ground, and filled structure prepared by using the method
CN103225267A (en) * 2013-03-29 2013-07-31 天津二十冶建设有限公司 Construction method of deep and thick soft soil foundation bed bridge abutment
CN106049412A (en) * 2016-07-02 2016-10-26 天鸿建设集团有限公司 Construction method of heaping pre-compression soft foundation reinforcement
CN208815506U (en) * 2018-08-02 2019-05-03 陈淑青 A kind of soft base joint preloading structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005207164A (en) * 2004-01-26 2005-08-04 Maruyama Kogyo Kk Soil improvement method for weak ground, and filled structure prepared by using the method
CN103225267A (en) * 2013-03-29 2013-07-31 天津二十冶建设有限公司 Construction method of deep and thick soft soil foundation bed bridge abutment
CN106049412A (en) * 2016-07-02 2016-10-26 天鸿建设集团有限公司 Construction method of heaping pre-compression soft foundation reinforcement
CN208815506U (en) * 2018-08-02 2019-05-03 陈淑青 A kind of soft base joint preloading structure

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
李树奇等: "潮差带地区水下真空预压加固软基技术", 《工程排水与加固技术理论与实践—第八届全国工程排水与加固技术研讨会论文集》, 31 December 2011 (2011-12-31), pages 21 - 27 *
杨国涛等: "有轨电车一般路段软土地基处理技术研究", 《河北工程大学学报(自然科学版)》 *
杨国涛等: "有轨电车一般路段软土地基处理技术研究", 《河北工程大学学报(自然科学版)》, 30 June 2017 (2017-06-30), pages 17 - 21 *

Also Published As

Publication number Publication date
CN113123321B (en) 2022-11-25

Similar Documents

Publication Publication Date Title
CN107301305B (en) Modeling method for realizing structural mechanical property of three-dimensional loaded duct piece
CN105863287A (en) Method for jacking storey-addition and shock insulation of framework-structure building
CN113356219A (en) Synchronous excavation construction method for foundation pits at different depths on two sides of operation subway
CN102444130B (en) Support replacing construction method in deep foundation pit project
CN103541364A (en) Design and construction method of large area foundation pit deformation control with roundabout method
CN109610466B (en) Unsynchronized construction method and structure of irregular deep foundation pits on two sides of built subway station
CN102031785A (en) Foundation pit supporting technique for replacing temporary enclosing purlin by using plate belt of permanent structure
CN112854229A (en) Earth excavation method for foundation pit groups at different depths on two sides of operation subway
CN103911983A (en) Tire-gravel drainage pile composite foundation treatment method
CN104975606A (en) Method for handling high-low strides at adjacent parts of reverse building foundation pit and adjacent foundation pit
CN105113514B (en) Foundation pit enclosure system with underground continuous wall as vertical cantilever fulcrum and construction method
CN107313430A (en) The deep big foundation pit subregion construction method of three face Nearby Structures
CN111878083A (en) Advanced grouting construction method for underground excavated tunnel
CN209855277U (en) Conversion layer structure for underground added layer of existing building
CN102979102B (en) Open-excavation sequential-operation deformation-control design method for deep and large circular foundation ditch in soft soil areas
CN113123321B (en) Synchronous construction method for treating soft foundation by adopting compound vacuum preloading and surcharge loading
CN102465534B (en) The construction method of adjacent double ditches
CN111576438A (en) Support system for deep foundation pit and construction method thereof
CN210239677U (en) Structural system for controlling deformation of subway shield tunnel
CN102116029A (en) Method for reinforcing circular support under condition of unbalanced soil pressure
CN106436760B (en) A kind of adverse construction method method
CN111364460A (en) Construction method and structure for inner support plate type quick support replacement in deep foundation pit
CN110258679A (en) The lifting inclination-correcting method of blower foundation
CN115467335B (en) Construction method for controlling foundation pit deformation by asymmetric earth excavation of subway-facing deep foundation pit
CN113486434B (en) Rock embedding depth determination method for closed type impervious wall of mountain valley steep slope section

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant