CN102444130B - Support replacing construction method in deep foundation pit project - Google Patents

Support replacing construction method in deep foundation pit project Download PDF

Info

Publication number
CN102444130B
CN102444130B CN201110321079.4A CN201110321079A CN102444130B CN 102444130 B CN102444130 B CN 102444130B CN 201110321079 A CN201110321079 A CN 201110321079A CN 102444130 B CN102444130 B CN 102444130B
Authority
CN
China
Prior art keywords
foundation pit
replacement
rib
ribs
basement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110321079.4A
Other languages
Chinese (zh)
Other versions
CN102444130A (en
Inventor
李�真
郭颖
张云富
高菲菲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co ltd Of China Construction Sixth Engineering Bureau
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Third Construction Engineering Co Ltd of China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd, Third Construction Engineering Co Ltd of China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201110321079.4A priority Critical patent/CN102444130B/en
Publication of CN102444130A publication Critical patent/CN102444130A/en
Application granted granted Critical
Publication of CN102444130B publication Critical patent/CN102444130B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明公开了一种深基坑工程中的快速换撑施工方法,包括步骤1)将第一道换撑肋板设置在地下室砼底板与基坑支护结构之间,为间隔设置的多个,每个第一道换撑肋板的外侧与基坑支护结构的内侧相连接,内侧与地下室砼底板相连接;第一道换撑肋板与地下室砼底板同时施工,待地下室砼底板和第一道换撑肋板拆模后,拆除基坑底部最下一道临时支撑,在相邻的第一道换撑肋板之间回填土方并夯实;换撑肋板有两种,第一种为水平砼肋板,第二种为T形砼肋板,T形砼肋板的中间立板与基坑支护结构垂直。本发明还公开了另一种采用竖向砼肋板作为换撑肋板的快速换撑方法。本发明能够比较容易地控制施工工期和施工质量及安全,适宜超深超大基坑的支护体系。

Figure 201110321079

The invention discloses a construction method for rapid brace replacement in deep foundation pit engineering, which comprises step 1) arranging a first brace replacement rib between the basement concrete floor and foundation pit support structure, and a plurality of brace replacement ribs arranged at intervals , the outer side of each first replacement rib is connected to the inner side of the foundation pit support structure, and the inner side is connected to the basement concrete floor; the first replacement rib and the basement concrete floor are constructed at the same time, and the basement concrete floor and After the formwork removal of the first supporting rib, remove the last temporary support at the bottom of the foundation pit, backfill and tamp the earthwork between the adjacent first supporting ribs; there are two types of supporting ribs, the first It is a horizontal concrete rib, and the second type is a T-shaped concrete rib. The middle vertical plate of the T-shaped concrete rib is perpendicular to the foundation pit support structure. The invention also discloses another quick support replacement method using vertical concrete ribs as the support replacement ribs. The invention can relatively easily control the construction period, construction quality and safety, and is suitable for the supporting system of ultra-deep and ultra-large foundation pits.

Figure 201110321079

Description

深基坑工程中的快速换撑施工方法The construction method of rapid support replacement in deep foundation pit engineering

技术领域 technical field

本发明涉及一种深基坑换撑的施工方法,特别是涉及一种超深超大基坑施工快速换撑施工方法。  The invention relates to a construction method for brace replacement in deep foundation pits, in particular to a construction method for fast brace replacement in ultra-deep and super-large foundation pit construction. the

背景技术 Background technique

深基坑工程中的换撑,是在特定的条件下采取一定的技术措施来逐步取代发挥临时支撑作用的内支撑结构体系,从而保证临时性内支撑拆除后,工程施工能继续安全顺利地进行,其实质是应力的安全有序的调整、转移和再分配。  The support replacement in deep foundation pit engineering is to take certain technical measures under specific conditions to gradually replace the internal support structure system that plays the role of temporary support, so as to ensure that the construction can continue safely and smoothly after the temporary internal support is removed. , its essence is the safe and orderly adjustment, transfer and redistribution of stress. the

换撑原理:让支护桩因内支撑拆除所产生的部分应力通过传力构件传递给具有足够承载能力的第三者,从而达到新的受力平衡。它除可采用刚性支撑件(斜撑、水平支撑)连接支护桩和地下室结构来控制变形、实现应力传递外,也可采用回填方式来实现。在此转换过程中,围护体系本身依然承担相当的支护作用。  The principle of support replacement: Let the part of the stress generated by the removal of the inner support of the support pile be transmitted to the third party with sufficient bearing capacity through the force transmission member, so as to achieve a new force balance. In addition to using rigid supports (diagonal braces, horizontal supports) to connect the support piles and the basement structure to control deformation and realize stress transfer, it can also be realized by backfilling. During the conversion process, the enclosure system itself still plays a considerable supporting role. the

目前,深基坑换撑有两种常见方式:一种是设置斜撑,工期短、投入少,但支撑点选择困难,难以布设全面(尤其是建筑物四角部位),换撑的整体作用效果差,易被破坏,且往往由于支护桩与墙体距离短,斜撑往往需穿过墙体与地下室砼底板牛腿相连,这样会增加防水施工难度,拆除斜撑还会延误工期。另一种是直接采用水平刚性构件换撑连梁进行换撑,将支护桩的应力通过楼梁板最终实现。其优点是受力效果好、施工简单又无需进行拆除施工,因此在工期较紧的工程较为合适。由于靠现浇楼梁板来承受基坑内力,对工程本身的结构安全性提出了更高的要求,必须采取必要的技术措施,以确保施工的顺利进行。常规施工方法是将底板混凝土浇灌完成后,拆除模板,将底板与支护桩之间的空隙回填土方(另一种回填料为碎石料来进行坑内换撑回填,其特点是传力带的受力均匀性好,但实际施工时,往往防水施工介入较晚,且回填料密实度很难控制,对较大基坑的内力传递无法保证,因此回填料作传力带只作辅助之用。)并夯实,再在回填土上方浇灌一道250-400MM厚混凝土水平环带作为换撑,待该部分混凝土达到设计要求强度后,才能进行临时支撑系统的拆除工序。但对于特大型深基坑或结构受力极其复杂的工程,这种方法施工层次复杂,实际操作困难,工期较长,且基坑围护体系结构安全风险几率明显增大,严重地影响着基坑工期,这样就导致换撑技术一直是困扰着深基坑施工中的重要突出问题。  At present, there are two common ways to replace braces in deep foundation pits: one is to set diagonal braces, which has a short construction period and less investment, but it is difficult to select support points and it is difficult to arrange them comprehensively (especially at the four corners of the building). The overall effect of brace replacement Poor, easy to be damaged, and often due to the short distance between the support pile and the wall, the diagonal brace often needs to pass through the wall to connect with the corbel of the basement concrete floor, which will increase the difficulty of waterproof construction, and the removal of the diagonal brace will also delay the construction period. The other is to directly use horizontal rigid components to replace the braces and connect the beams, and finally realize the stress of the supporting piles through the floor beams. Its advantages are good stress effect, simple construction and no need for demolition construction, so it is more suitable for projects with tight construction schedules. Since the internal force of the foundation pit is borne by the cast-in-place floor beams and slabs, higher requirements are put forward for the structural safety of the project itself, and necessary technical measures must be taken to ensure the smooth progress of the construction. The conventional construction method is to remove the formwork after pouring the bottom slab concrete, and backfill the gap between the bottom slab and the support piles with earthwork (the other kind of backfill is gravel to replace the backfill in the pit, which is characterized by the force transmission belt. The force uniformity is good, but in actual construction, the waterproofing construction is often involved late, and the density of the backfill is difficult to control, and the internal force transmission of large foundation pits cannot be guaranteed, so the backfill is used as a force transmission belt only for auxiliary purposes ) and compacted, and then pour a 250-400MM thick concrete horizontal ring on top of the backfill as a replacement support. The removal process of the temporary support system can only be carried out after this part of the concrete reaches the design required strength. However, for very large deep foundation pits or projects with extremely complex structural forces, this method has complex construction levels, difficult practical operations, and a long construction period, and the safety risk probability of the foundation pit enclosure system structure increases significantly, which seriously affects the foundation. The pit construction period has caused the support replacement technology to be an important and prominent problem in the construction of deep foundation pits. the

发明内容 Contents of the invention

本发明为解决公知技术中存在的技术问题而提供两种深基坑工程中的快速换撑施工方法,该两种施工方法能够比较容易地控制施工工期和施工质量及安全,能够适宜超深超大基坑的支护体系。  In order to solve the technical problems existing in the known technology, the present invention provides two construction methods for rapid support replacement in deep foundation pit engineering. The two construction methods can relatively easily control the construction period, construction quality and safety, and can be suitable for ultra-deep and super-large The support system of the foundation pit. the

本发明为解决公知技术中存在的技术问题所采取的一个技术方案是:一种深基坑工 程中的快速换撑施工方法,包括步骤1)第一道换撑肋板的施工:  A technical scheme that the present invention takes for solving the technical problems existing in the known technology is: a kind of quick support replacement construction method in deep foundation pit engineering, including step 1) the construction of the first support replacement rib:

第一道换撑肋板设置在地下室砼底板与基坑支护结构之间,为间隔设置的多个,每个第一道换撑肋板的外侧与基坑支护结构的内侧相连接,内侧与地下室砼底板相连接;  The first support ribs are arranged between the basement concrete floor and the foundation pit support structure, and there are multiple intervals. The outer side of each first support rib is connected with the inner side of the foundation pit support structure. The inner side is connected with the concrete floor of the basement;

第一道换撑肋板与地下室砼底板同时施工,待地下室砼底板和第一道换撑肋板拆模后,拆除基坑底部最下一道临时支撑,在相邻的第一道换撑肋板之间回填土方并夯实;  The first replacement rib and the concrete floor of the basement are constructed at the same time. After the basement concrete floor and the first replacement rib are demolished, the bottom temporary support at the bottom of the foundation pit is removed, and the adjacent first replacement rib Backfill the earthwork between the slabs and compact them;

所述换撑肋板有两种,第一种为水平砼肋板,第二种为T形砼肋板,T形砼肋板的中间立板与基坑支护结构垂直。  There are two kinds of support ribs, the first type is horizontal concrete ribs, the second is T-shaped concrete ribs, and the middle vertical plate of the T-shaped concrete ribs is perpendicular to the support structure of the foundation pit. the

上述施工方法还包括步骤2)第二道换撑肋板的施工:  Above-mentioned construction method also comprises step 2) the construction of the second road replacement rib:

第二道换撑肋板设置在地下室最下面一层的顶板与基坑支护结构之间,为间隔设置的多个,每个第二道换撑肋板的外侧与基坑支护结构的内侧相连接,内侧与地下室的墙板相连接;  The second replacement rib is arranged between the roof of the bottom floor of the basement and the foundation pit support structure, and there are multiple intervals, and the outer side of each second replacement rib is connected to the foundation pit support structure. The inner side is connected, and the inner side is connected with the wall panel of the basement;

所有第二道换撑肋板与地下室的墙板同时施工;在第二道换撑肋板施工前,在第一道换撑肋板上回填土方并夯实;  All the second ribs are constructed at the same time as the wall panels of the basement; before the construction of the second ribs, earthwork is backfilled and compacted on the first ribs;

待地下室的墙板和第二道换撑肋板拆模后,拆除基坑的第二道临时支撑,在相邻的第二道换撑肋板之间回填土方并夯实。  After the basement wall panels and the second replacement ribs are removed from the formwork, the second temporary support of the foundation pit is removed, and earthwork is backfilled and compacted between the adjacent second replacement ribs. the

上述施工方法还包括步骤3)第三道换撑肋板的施工:  Above-mentioned construction method also comprises step 3) the construction of the 3rd road replacement rib plate:

第三道换撑肋板设置在地下室一层以下的顶板与基坑支护结构之间,为间隔设置的多个,每个第三道换撑肋板的外侧与基坑支护结构的内侧相连接,内侧与地下室的墙板相连接;所有第三道换撑肋板与地下室的墙板同时施工,施工步骤与步骤2)相同。  The third replacement rib is arranged between the roof below the first floor of the basement and the foundation pit support structure. There are multiple intervals, and the outer side of each third replacement rib is connected to the inner side of the foundation pit support structure. The inner side is connected with the wall panels of the basement; all the third support ribs are constructed simultaneously with the wall panels of the basement, and the construction steps are the same as step 2). the

本发明为解决公知技术中存在的技术问题所采取的另一个技术方案是:一种深基坑工程中的快速换撑施工方法,采用竖向砼肋板作为换撑肋板,竖向砼肋板设置在地下室墙板与基坑支护结构之间,为间隔设置的多个,每个竖向砼肋板的外侧与基坑支护结构的内侧相连接,内侧与地下室墙板相连接;  Another technical solution adopted by the present invention to solve the technical problems existing in the known technology is: a quick support replacement construction method in deep foundation pit engineering, using vertical concrete ribs as the support replacement ribs, vertical concrete ribs The panels are arranged between the basement wall panel and the foundation pit support structure, and are arranged at intervals, and the outer side of each vertical concrete rib is connected with the inner side of the foundation pit support structure, and the inner side is connected with the basement wall panel;

竖向砼肋板与地下室墙板同时施工,待地下室墙板和竖向砼肋板拆模后,拆除相应部位的临时支撑,在相邻的竖向砼肋板之间回填土方并夯实。  The vertical concrete ribs and the basement wall panels are constructed at the same time. After the basement wall panels and vertical concrete ribs are removed from the formwork, the temporary supports at the corresponding parts are removed, and earthwork is backfilled and compacted between adjacent vertical concrete ribs. the

本发明具有的优点和积极效果是:采用肋板换撑,并且肋板与地下室砼底板/墙板同时支模、同时浇筑、同时养护,底板/墙板混凝土达到强度的同时,换撑肋板也达到了强度,自然也就起到了换撑的作用,可以连续施工地下结构不必等待土方回填,不影响地下工程的工期,工期效果显现突出,明显地体现了快速换撑效果;能够比较容易地控制施工工期和工程质量及生产安全,适宜超深超大基坑的支护体系。并且本发明便于工序安排和协调,便于施工;施工过程安全可靠,便于安全管理。  The advantages and positive effects of the present invention are: the ribs are used to replace the braces, and the ribs and the basement concrete floor/wallboard are simultaneously molded, poured and maintained at the same time, and the floor/wallboard concrete reaches strength, and the braced ribs are replaced It has also reached the strength, and naturally it also plays the role of changing braces. The underground structure can be continuously constructed without waiting for earthwork backfilling, without affecting the construction period of the underground project. Control the construction period, project quality and production safety, and is suitable for the support system of ultra-deep and super-large foundation pits. Moreover, the invention is convenient for process arrangement and coordination, and convenient for construction; the construction process is safe and reliable, and convenient for safety management. the

附图说明 Description of drawings

图1为本发明应用的水平砼肋板的示意图;  Fig. 1 is the schematic diagram of the horizontal concrete rib plate that the present invention applies;

图2为本发明应用水平砼肋板施工的局部平面图;  Fig. 2 is the local plan view of the application of horizontal concrete rib construction in the present invention;

图3为本发明应用水平砼肋板施工的立面图;  Fig. 3 is the elevation view of the application of horizontal concrete rib construction in the present invention;

图4为本发明应用的竖向砼肋板示意图;  Fig. 4 is the vertical concrete floor schematic diagram of application of the present invention;

图5为本发明应用竖向砼肋板施工的局部平面图;  Fig. 5 is the local plan view of the application of vertical concrete rib construction in the present invention;

图6为本发明应用竖向砼肋板施工的立面图;  Fig. 6 is the elevation view of the application of vertical concrete rib construction in the present invention;

图7为本发明应用的T形砼肋板的示意图;  Fig. 7 is the schematic diagram of the T-shaped concrete rib plate that the present invention applies;

图8为本发明应用T形砼肋板施工的局部平面图;  Fig. 8 is the local plane view of the application of T-shaped concrete rib construction in the present invention;

图9为本发明应用T形砼肋板施工的立面图。  Fig. 9 is an elevation view of the construction of the present invention using T-shaped concrete ribs. the

具体实施方式 Detailed ways

为能进一步了解本发明的发明内容、特点及功效,兹例举以下实施例,并配合附图详细说明如下:  In order to further understand the invention content, characteristics and effects of the present invention, the following examples are given hereby, and detailed descriptions are as follows in conjunction with the accompanying drawings:

实施例1,请参阅图1~图3和图7~图9。  Embodiment 1, please refer to FIGS. 1 to 3 and FIGS. 7 to 9 . the

一种深基坑工程中的快速换撑施工方法:  A quick support replacement construction method in deep foundation pit engineering:

1)第一道换撑肋板的施工:  1) Construction of the first replacement rib: 

第一道换撑肋板12设置在地下室砼底板5与基坑支护结构1之间,为间隔设置的多个,每个第一道换撑肋板12的外侧与基坑支护结构1的内侧相连接,内侧与地下室砼底板5相连接;  The first replacement rib 12 is arranged between the basement concrete floor 5 and the foundation pit support structure 1, and is arranged at intervals, and the outer side of each first replacement rib 12 is connected to the foundation pit support structure 1. The inner side is connected, and the inner side is connected with the concrete floor 5 of the basement;

第一道换撑肋板12与地下室砼底板5同时施工,即与地下室砼底板5同时支模,同时浇筑,同时养护,待底板混凝土达到拆模强度的同时,换撑肋板也达到了拆模强度,已起到了支撑作用,即可安排临时支撑系统的拆除工序。对应此处的临时支撑为基坑底部最下一道临时支撑,在相邻的第一道换撑肋板12之间回填土方并夯实。  The first replacement rib 12 is constructed at the same time as the basement concrete floor 5, that is, the basement concrete floor 5 is molded at the same time, poured at the same time, and maintained at the same time. The strength of the mold has played a supporting role, and the dismantling process of the temporary support system can be arranged. The temporary support corresponding to this is the bottom temporary support at the bottom of the foundation pit, and the earthwork is backfilled and compacted between the adjacent first replacement ribs 12 . the

2)第二道换撑肋板的施工:  2) Construction of the second replacement rib:

第二道换撑肋板22设置在地下室最下面一层的顶板6与基坑支护结构1之间,为间隔设置的多个,每个第二道换撑肋板22的外侧与基坑支护结构1的内侧相连接,内侧与地下室的墙板4相连接;  The second supporting rib 22 is arranged between the top plate 6 of the bottom floor of the basement and the foundation pit support structure 1, and is arranged at intervals, and the outer side of each second supporting rib 22 is in contact with the The inner side of the support structure 1 is connected, and the inner side is connected with the wall panel 4 of the basement;

所有第二道换撑肋板22与地下室的墙板4同时施工;即施工地下室墙板4时,第二道换撑肋板22与地下室墙板4同时支模,同时浇筑砼,同时养护,待达到拆模强度后,该肋板22已起到了支撑作用,即可安排临时支撑系统的拆除工序。对应此处的临时支撑为基坑的第二道临时支撑,在相邻的第二道换撑肋板22之间回填土方3并夯实。在第二道换撑肋板施工前,在第一道换撑肋板上回填土方并夯实。  All the second supporting ribs 22 are constructed simultaneously with the basement wall panels 4; that is, when the basement wall panels 4 are being constructed, the second supporting ribs 22 and the basement wall panels 4 are molded at the same time, concrete is poured at the same time, and maintenance is performed at the same time. After reaching the demolition strength, the ribs 22 have played a supporting role, and the removal process of the temporary support system can be arranged. The temporary support corresponding to this is the second temporary support of the foundation pit, and the earthwork 3 is backfilled and compacted between the adjacent second replacement ribs 22 . Before the construction of the second rib, backfill the earthwork on the first rib and compact it. the

3)第三道换撑肋板的施工:  3) Construction of the third replacement rib:

第三道换撑肋板设置在地下室一层以下的顶板与基坑支护结构之间,为间隔设置的多个,每个第三道换撑肋板的外侧与基坑支护结构的内侧相连接,内侧与地下室的墙板相连接;所有第三道换撑肋板与地下室的墙板同时施工;施工步骤与步骤2)相同。对应第三道换撑肋板的临时支撑通常为基坑的最后一道临时支撑。至此已经完成了基坑的 全部换撑。  The third replacement rib is arranged between the roof below the first floor of the basement and the foundation pit support structure. There are multiple intervals, and the outer side of each third replacement rib is connected to the inner side of the foundation pit support structure. The inner side is connected with the wall panels of the basement; all the third support ribs are constructed simultaneously with the wall panels of the basement; the construction steps are the same as step 2). The temporary support corresponding to the third replacement rib is usually the last temporary support of the foundation pit. So far, all the support replacement of the foundation pit has been completed. the

上述步骤中在相邻的上下两道肋板之间为回填并夯实的土方3。  In the above steps, there is backfilled and compacted earthwork 3 between the adjacent upper and lower ribs. the

至于需要几道换撑,应根据基坑的具体情况确定,例如,地下室只有一层,只需要完成步骤1)即可;地下室有二层,只需要完成步骤1)和步骤2)即可;地下室有三层,需要视具体情况确定是不是需要进行到步骤3)。  As for how many support replacements are needed, it should be determined according to the specific conditions of the foundation pit. For example, if the basement has only one floor, only step 1) needs to be completed; if the basement has two floors, only step 1) and step 2) need to be completed; There are three floors in the basement, and it needs to be determined whether it is necessary to proceed to step 3) depending on the specific situation. the

上述换撑肋板有二种结构:  There are two structures of the above-mentioned replacement ribs:

第一种为水平砼肋板,为浇筑形成的水平砼板;第二种为T形砼肋板,其中间立板与基坑支护结构垂直。  The first type is a horizontal concrete rib plate, which is a horizontal concrete plate formed by pouring; the second type is a T-shaped concrete rib plate, in which the middle vertical plate is perpendicular to the support structure of the foundation pit. the

实施例2,请参阅图4~图6。  Embodiment 2, please refer to Fig. 4 to Fig. 6 . the

一种深基坑工程中的快速换撑施工方法:该方法采用竖向砼肋板作为换撑肋板,其为浇筑形成的与基坑支护结构1垂直的竖向砼板。 A construction method for rapid brace replacement in deep foundation pit engineering: the method uses vertical concrete ribs as the brace replacement ribs, which are vertical concrete slabs formed by pouring and perpendicular to the foundation pit support structure 1 .

竖向砼肋板2设置在地下室墙板4与基坑支护结构1之间,为间隔设置的多个,每个竖向砼肋板2的外侧与基坑支护结构1的内侧相连接,内侧与地下室墙板4相连接;  The vertical concrete ribs 2 are arranged between the basement wall board 4 and the foundation pit support structure 1, and are arranged in multiples at intervals, and the outer side of each vertical concrete rib 2 is connected with the inner side of the foundation pit support structure 1 , the inner side is connected with the basement wall panel 4;

竖向砼肋板2与地下室墙板4同时施工,即与地下室墙板4同时支模,同时浇筑,同时养护,待地下室墙板4的混凝土达到拆模强度的同时,也达到了拆模强度,已起到了支撑作用,即可安排临时支撑系统的拆除工序。在相邻的竖向砼肋板2之间回填土方3并夯实。  The vertical concrete ribs 2 and the basement wall panels 4 are constructed at the same time, that is, the basement wall panels 4 are molded at the same time, poured at the same time, and maintained at the same time. When the concrete of the basement wall panels 4 reaches the formwork removal strength, it also reaches the formwork removal strength. , has played a supporting role, the removal process of the temporary support system can be arranged. Earthwork 3 is backfilled between adjacent vertical concrete ribs 2 and compacted. the

尽管上面结合附图对本发明的优选实施例进行了描述,但是本发明并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,并不是限制性的,本领域的普通技术人员在本发明的启示下,在不脱离本发明宗旨和权利要求所保护的范围情况下,还可以作出很多形式,这些均属于本发明的保护范围之内。  Although the preferred embodiments of the present invention have been described above in conjunction with the accompanying drawings, the present invention is not limited to the above-mentioned specific embodiments. The above-mentioned specific embodiments are only illustrative and not restrictive. Those of ordinary skill in the art Under the enlightenment of the present invention, people can also make many forms without departing from the purpose of the present invention and the scope of protection of the claims, and these all belong to the protection scope of the present invention. the

Claims (1)

1. the fast support replacing job practices in a deep-foundation pit engineering, it is characterized in that, adopt vertical concrete floor as the support replacement floor, vertical concrete floor is arranged between basement wallboard and foundation pit supporting construction, vertical concrete floor is vertical with foundation pit supporting construction, for spaced a plurality of, the outside of each vertical concrete floor is connected with the inboard of foundation pit supporting construction, inboardly with the basement wallboard, is connected;
Vertical concrete floor and basement wallboard are constructed simultaneously, after basement wallboard and vertical concrete floor form removal, remove the temporary supporting of corresponding site, the backfill earthwork compacting between adjacent vertical concrete floor.
CN201110321079.4A 2011-10-20 2011-10-20 Support replacing construction method in deep foundation pit project Active CN102444130B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110321079.4A CN102444130B (en) 2011-10-20 2011-10-20 Support replacing construction method in deep foundation pit project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110321079.4A CN102444130B (en) 2011-10-20 2011-10-20 Support replacing construction method in deep foundation pit project

Publications (2)

Publication Number Publication Date
CN102444130A CN102444130A (en) 2012-05-09
CN102444130B true CN102444130B (en) 2014-01-01

Family

ID=46007039

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110321079.4A Active CN102444130B (en) 2011-10-20 2011-10-20 Support replacing construction method in deep foundation pit project

Country Status (1)

Country Link
CN (1) CN102444130B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103015432B (en) * 2012-12-07 2014-12-17 天津住宅集团建设工程总承包有限公司 Construction method for changing steel pipe supports of ramp foundation pit
CN104141310B (en) * 2013-05-07 2017-04-26 上海市政工程设计研究总院(集团)有限公司 Method for constructing assembly type pre-stress fish-belly sill internal support system
CN103572763B (en) * 2013-11-18 2015-08-26 中建二局第三建筑工程有限公司 Large-span steel supports pattern foundation pit supporting structure Demolition Construction method
CN103603360A (en) * 2013-11-27 2014-02-26 上海建工七建集团有限公司 Foundation pit enveloping method
CN104032744B (en) * 2014-05-21 2016-05-04 中国建筑第八工程局有限公司 Support replacement construction method in the engineering of group hole
CN105332380B (en) * 2015-11-16 2017-04-12 上海建工五建集团有限公司 Strut changing structure and method for underground building
CN109944253B (en) * 2019-03-26 2024-06-14 中国建筑第八工程局有限公司 Reinforced concrete blade wall supporting system and deep foundation pit support changing construction method thereof
CN113550326B (en) * 2021-08-12 2022-10-11 中建八局第二建设有限公司 Foundation pit support removing and basement structure and construction method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476331A (en) * 2007-12-12 2009-07-08 中国二十冶建设有限公司 Closed demolition blasting method for internal concrete reinforcement bracing of basement foundation ditch
CN201746839U (en) * 2010-06-13 2011-02-16 中建三局建设工程股份有限公司 Low-environment-disturbance device for removing supports from foundation pit
JP2011157719A (en) * 2010-02-01 2011-08-18 Toda Constr Co Ltd Earth retaining method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476331A (en) * 2007-12-12 2009-07-08 中国二十冶建设有限公司 Closed demolition blasting method for internal concrete reinforcement bracing of basement foundation ditch
JP2011157719A (en) * 2010-02-01 2011-08-18 Toda Constr Co Ltd Earth retaining method
CN201746839U (en) * 2010-06-13 2011-02-16 中建三局建设工程股份有限公司 Low-environment-disturbance device for removing supports from foundation pit

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
周以大等.深基坑支护系统的换撑技术.《建筑施工》.1995,第17卷第6-8页.
建筑深基坑安全支护工程换撑设计与施工;徐卫国;《广东建材》;20080720(第7期);第84页左栏第1-2段、右栏倒数第2段及图1 *
徐卫国.建筑深基坑安全支护工程换撑设计与施工.《广东建材》.2008,(第7期),第84页左栏第1-2段、右栏倒数第2段及图1.
朱小军.软土深基坑工程控制拆撑变形的换撑设计方法.《岩土工程学报》.2010,第32卷第257页左栏第1-2段及图2.
深基坑支护系统的换撑技术;周以大等;《建筑施工》;19950530;第17卷;全文 *
软土深基坑工程控制拆撑变形的换撑设计方法;朱小军;《岩土工程学报》;20100715;第32卷;第257页左栏第1-2段及图2 *

Also Published As

Publication number Publication date
CN102444130A (en) 2012-05-09

Similar Documents

Publication Publication Date Title
CN102444130B (en) Support replacing construction method in deep foundation pit project
CN104328789B (en) The overhanging type support replacement construction method of the horizontal inner support of a kind of steel concrete
CN110080244A (en) A kind of super-sized foundation pit support replacement backfill structure and construction method
CN105951843A (en) Construction method of deep foundation pit
CN102587410A (en) Design and construction method of reinforced concrete retaining wall
CN107326816A (en) A kind of method for improving of prefabricated pinner and bridge
CN110593269A (en) A turnable structural support system and its construction method
CN208072415U (en) Deep foundation pit reinforced concrete support part changes structure
CN110130355B (en) Foundation bottom plate post-cast strip force transmission structure and construction method thereof
CN202247904U (en) Quick support changing structure for ultra-deep and oversized foundation pit construction
CN105332380A (en) Strut changing structure and method for underground building
CN103061509B (en) Construction process for implementing post-cast strip casting by post-cast strip stiff steel pipe support system
CN106164380A (en) Wind-driven generator fabricated base
CN110453729A (en) Steel form partition assembly and construction method for construction of flexible granular waterproof protective layer
CN105040709A (en) Construction method for support replacement of fender-post retaining and protecting of deep foundation pit
CN205399397U (en) A vertical support structure of variable cross section wall formula for reverse construction method
CN202247905U (en) Fast support replacing structure for deep foundation pit
CN202247906U (en) Quick support changing structure for use in deep foundation pit project
CN105926657B (en) A construction method for prefabricated concrete foundation slabs
CN203066083U (en) Supporting structure for two adjacent foundation pits
CN103114594B (en) Supporting structure of adjacent two foundation trenches and construction method thereof
CN206070570U (en) A kind of building structure
CN105781159A (en) Construction process for reinforced concrete coal hopper of power plant main building
CN117605492A (en) A construction method of steel frame rock wall combined support for double-side guide pits in a four-lane tunnel
CN104594917A (en) Construction method of counter weight type inverted arch and short side wall whole template

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200323

Address after: 300451 No. 72, Hangzhou Road, Binhai New Area, Tianjin

Co-patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING BUREAU INSTALLATION ENGINEERING Co.,Ltd.

Address before: 300456 No. 75, Xingang Road, Tanggu District, Tianjin

Co-patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION NO.3 CONSTRUCTION ENGINEERING Co.,Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee after: China Construction Sixth Engineering Bureau Northwest Construction Co.,Ltd.

Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Address before: No. 72 Hangzhou Road, Tianjin Binhai New Area, 300451

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING BUREAU INSTALLATION ENGINEERING Co.,Ltd.

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee after: The First Construction Co.,Ltd. of China Construction Sixth Engineering Bureau

Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Address before: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee before: China Construction Sixth Engineering Bureau Northwest Construction Co.,Ltd.

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.