CN113107778B - Intensive wind power hoisting platform and hoisting method - Google Patents

Intensive wind power hoisting platform and hoisting method Download PDF

Info

Publication number
CN113107778B
CN113107778B CN202110292835.9A CN202110292835A CN113107778B CN 113107778 B CN113107778 B CN 113107778B CN 202110292835 A CN202110292835 A CN 202110292835A CN 113107778 B CN113107778 B CN 113107778B
Authority
CN
China
Prior art keywords
platform
hoisting
wind power
transportation road
hoisting operation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110292835.9A
Other languages
Chinese (zh)
Other versions
CN113107778A (en
Inventor
黄大伟
苑森
刘伟
李利飞
崔飞龙
孟瑾
李鹏
史琬男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Hebei Electric Power Engineering Co Ltd
Original Assignee
PowerChina Hebei Electric Power Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Hebei Electric Power Engineering Co Ltd filed Critical PowerChina Hebei Electric Power Engineering Co Ltd
Priority to CN202110292835.9A priority Critical patent/CN113107778B/en
Publication of CN113107778A publication Critical patent/CN113107778A/en
Application granted granted Critical
Publication of CN113107778B publication Critical patent/CN113107778B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/10Assembly of wind motors; Arrangements for erecting wind motors
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2230/00Manufacture
    • F05B2230/60Assembly methods
    • F05B2230/61Assembly methods using auxiliary equipment for lifting or holding
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • Sustainable Energy (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Wind Motors (AREA)

Abstract

The invention discloses an intensive wind power hoisting platform and a hoisting method, wherein the hoisting platform comprises an entering platform transportation road, an exiting platform transportation road and a hoisting operation field, the entering platform transportation road and the exiting platform transportation road are communicated with the hoisting operation field to form a wind power generator set assembly space, a fan impeller is arranged in one side corner close to the exiting platform transportation road in the hoisting operation field, a first wind power generator blade, a second wind power generator blade and a third wind power generator blade which form an angle of 120 degrees with each other are arranged on the fan impeller, a fan foundation is arranged in one side corner of the hoisting operation field far away from the entering platform transportation road, a step-up transformer is arranged on a connecting line of a current collecting line pole tower and the fan foundation outside the hoisting operation field, a main crane and an auxiliary crane are also arranged in the hoisting operation field, the invention provides operation conditions for the integral hoisting of three wind power generator blades of a wind power generator set, meanwhile, the floor area of the hoisting platform is saved.

Description

Intensive wind power hoisting platform and hoisting method
Technical Field
The invention relates to the technical field of electric power engineering, road engineering and geotechnical engineering, in particular to an intensive wind power hoisting platform and a hoisting method.
Background
Wind power generation, one of the representatives of clean energy, has experienced a high-speed increase of globalization since 1980, and is an important way to achieve "carbon neutralization" and "carbon peaking". China has abundant wind energy resources, and the development space of wind power generation in China is huge. The main equipment of wind power generation is a wind turbine generator, and the wind turbine generator has the characteristics of large size (the diameter of a fan blade wheel is more than 140 meters), heavy equipment (the weight of an engine room is more than 70 tons) and large height (the height of a fan tower barrel is more than 90 meters), so that the transportation and installation of the wind turbine generator in the construction of wind power engineering are important difficult points. The transportation of the wind power equipment mainly depends on the existing road network outside the wind farm and the newly built road in the wind farm. The installation mainly depends on hoisting equipment to hoist and install in the hoisting place.
The wind turbine generator hoisting scheme is divided into two modes of assembling three blades on the ground, hoisting the whole impeller at high altitude, assembling the three blades on the ground or assembling two blades, and finally hoisting a single blade at high altitude according to the assembling sequence of the fan blades. The hoisting mode of the blade ground assembly is simple in process and low in assembly cost, but the hoisting platform is required to have the size enough for assembling the blade, and the earth surface obstacle in the range of the blade is located. The hoisting process for high-altitude assembly of the blades is complex, the requirement on the size of a hoisting platform is relatively low, the cost is high, and the construction progress is often influenced by weather.
In actual engineering, in order to guarantee the construction progress, the wind power engineering is carried out the fan blade and then is lifted by crane at the wheel hub height position after assembling on ground for many choices, but this kind of hoisting platform size often is great, and needs to clear up the earth's surface attachment in near hoisting platform blade sweep-out range. In order to realize the hoisting platform or the operation space, more engineering cost is usually required in mountain wind power or plain area wind power with more surface attachments.
Disclosure of Invention
The invention provides an intensive wind power hoisting platform and a hoisting method, and provides a wind power unit hoisting scheme for assembling three blades on the ground and hoisting the whole impeller in high altitude under a small hoisting platform area. The method is suitable for hoisting and installing operation of wind power in mountainous regions with complex terrain and wind power in plain regions with more surface attachments, and is easy to implement, high in safety and good in economical efficiency.
In order to solve the technical problems, the technical scheme adopted by the invention is as follows: an intensive wind power hoisting platform comprises a platform entering transportation road, a platform exiting transportation road, a wind power generator set point position connecting the platform entering transportation road and the platform exiting transportation road to form an on-site transportation network, a wind power generator assembly space is formed by the platform entering transportation road and the platform exiting transportation road being communicated with a hoisting operation site, a fan impeller is arranged in one side corner of the hoisting operation site close to the platform exiting transportation road, a first wind power generator blade, a second wind power generator blade and a third wind power generator blade which are 120 degrees mutually are arranged on the fan impeller, a fan foundation is arranged in one side corner of the hoisting operation site far away from the platform entering transportation road, the fan foundation and the fan impeller are positioned at the opposite angle position of the hoisting operation site, a step-up transformer is arranged on a connecting line of a current collecting line pole tower and the fan foundation outside the hoisting operation site, and the step-up transformer is positioned in the hoisting operation site, and a main crane and an auxiliary crane are further arranged in the hoisting operation field.
The technical scheme of the invention is further improved as follows: the total area of the hoisting operation field is not less than 1750 square meters, and the long edge of the hoisting operation field is not less than 50 m.
The technical scheme of the invention is further improved as follows: and the longitudinal slope of the road of the platform entering transport road and the platform exiting transport road is not more than 2% within the range of 50m outside the boundary of the hoisting operation field.
The technical scheme of the invention is further improved as follows: the straight line distance between the center of the fan impeller and the fan foundation is 25 +/-5 m.
The technical scheme of the invention is further improved as follows: the central positions of the main crane, the fan impeller and the fan foundation form a triangular position relation.
The technical scheme of the invention is further improved as follows: the distance between the booster transformer and the center of the fan foundation is 18 +/-2 m.
A hoisting method of an intensive wind power hoisting platform comprises the following steps:
step S1: determining the position and elevation of a hoisting operation field: determining the plane position and the zero meter elevation of the field of hoisting operation by combining the landform and the landform of the position of the wind driven generator;
step S2: determining the installation position of a fan impeller according to the position of a fan foundation;
step S3: installing a step-up transformer according to the positions of a fan foundation and a current collection line tower;
step S4: implementing a platform entering transportation road and a platform exiting transportation road according to the installation position of the fan impeller, so that the center of the fan impeller forms an included angle of 120 degrees with the center line of the platform entering transportation road and the platform exiting transportation road, and the longitudinal slope of the road in the range of 50m outside the boundary of the hoisting operation field is not more than 2 percent;
step S5: installing a main crane and an auxiliary crane on a hoisting operation site;
step S6: the first wind driven generator blade, the second wind driven generator blade, the third wind driven generator blade and the fan impeller are assembled and checked in the space of a hoisting operation field, a platform transportation road and a platform transportation road, and after construction weather, wind speed and mechanical equipment meet conditions, the fan impeller, the first wind driven generator blade, the second wind driven generator blade and the third wind driven generator blade are integrally hoisted to a designed height, so that the fan impeller and a cabin are assembled. The technical scheme of the invention is further improved as follows: the field level zero meter elevation of the hoisting operation field in the step S1 is determined according to the selected plane position, and when the plane position of the hoisting operation field is positioned at the top of a mountain, the field level zero meter elevation is determined according to the principle that excavation is mainly performed and filling is assisted when the construction platform is constructed; and when the plane position of the hoisting operation field is located in a flat area, determining the level of the field level zero meter according to the principle that the height difference between the hoisting operation field and the elevation difference between the platform entering transportation road and the elevation difference between the hoisting operation field and the platform exiting transportation road are not more than 1 meter.
Due to the adoption of the technical scheme, the invention has the technical progress that:
1. the invention provides operation conditions for the integral hoisting of the three wind driven generator blades of the wind driven generator set, and saves the floor area of the hoisting platform;
2. the invention is suitable for the hoisting and installation operation of mountain wind power with complex terrain and plain area wind power with more surface attachments, fully utilizes the space in a hoisting operation field and the road transportation space around the hoisting operation field to assemble the fan blade on the ground, and then integrally lifts the impeller to carry out high-altitude installation;
3. the hoisting platform is easy to implement, high in safety, favorable for project schedule control, good in economic performance and outstanding in environmental protection benefit.
Drawings
FIG. 1 is a schematic view of the overall structure of the hoisting platform of the present invention;
fig. 2 is a schematic view of the overall structure of a hoisting platform according to embodiment 1 of the present invention;
fig. 3 is a schematic view of the overall structure of a hoisting platform according to embodiment 2 of the present invention;
the wind power generation system comprises a platform transportation road, a lifting operation field, a fan impeller, a first wind driven generator blade, a second wind driven generator blade, a third wind driven generator blade, a fan foundation, a current collection line tower, a step-up transformer, a step-up crane, a main crane, a step-up crane and an auxiliary crane, wherein the step-up operation field comprises 1, 2, 3 and 4.
Detailed Description
The present invention will be described in further detail with reference to the following examples:
as shown in fig. 1, the intensive wind power hoisting platform comprises a platform transportation road 1, a platform transportation road 2, a site location of an adjacent wind power generator set, wherein the platform transportation road 1 and the platform transportation road 2 are connected to form an on-site transportation traffic network, the platform transportation road 1 and the platform transportation road 2 are communicated with a hoisting operation site 3 to form a wind power generator set assembly space, the total area of the hoisting operation site 3 is not less than 1750 square meters, and the long edge of the hoisting operation site 3 is not less than 50 m. And the longitudinal slope of the road of the platform entering transport road 1 and the platform exiting transport road 2 is not more than 2% within the range of 50m outside the boundary of the hoisting operation field 3.
A fan impeller 4 is arranged in a corner of one side, close to the platform transportation road 2, in the hoisting operation field 3, a first wind driven generator blade 5-1, a second wind driven generator blade 5-2 and a third wind driven generator blade 5-3 which form an angle of 120 degrees with each other are arranged on the fan impeller 4, and the straight line distance from the center of the fan impeller 4 to the fan foundation 6 is 25 +/-5 m. The central lines of the platform entering transport road 1 and the platform exiting transport road 2 form an included angle of 120 degrees with the center of the fan impeller 4, and the first wind driven generator blade 5-1 and the second wind driven generator blade 5-2 are respectively positioned on the platform entering transport road 1 and the platform exiting transport road 2.
The utility model discloses a wind turbine generator system, including hoist and mount operation place 3, be provided with fan basis 6 and fan wheel 4 in the corner of one side of getting into platform haulage road 1 in the hoist and mount operation place 3 and be located the diagonal position of hoist and mount operation place 3, be provided with step up transformer 8 and step up transformer 8 on the line of current collecting line shaft tower 7 and fan basis 6 outside being located hoist and mount operation place 3 and be located hoist and mount operation place 3, do benefit to electric energy and fan equipment hoist and mount, step up transformer 8 and fan basis 6's central point put the distance and be 18 m. A main crane 9 and an auxiliary crane 10 are further arranged in the hoisting operation field 3. The central positions of the main crane 9, the fan impeller 4 and the fan foundation 6 form a triangular position relation.
A hoisting method of an intensive wind power hoisting platform comprises the following steps:
step S1: determining the position and elevation of a hoisting operation field 3:
the position of the wind driven generator in the actual engineering is provided by a design unit after various design factors are comprehensively considered, and the design input data of the intensive hoisting platform of the invention is combined with the landform and the geomorphic feature of the position of the wind driven generator to determine the plane position and the zero meter elevation of the hoisting operation field 3; the field level zero meter elevation of the hoisting operation field 3 is determined according to the selected plane position, and when the plane position of the hoisting operation field 3 is positioned on the mountain top, the field level zero meter elevation is determined according to the principle that excavation is mainly performed and filling is assisted when the construction platform is performed; when the plane position of the hoisting operation field 3 is located in a flat area, the level of the field level zero meter is determined according to the principle that the height difference between the level of the hoisting operation field 3 and the level of the platform entering transport road 1 and the level of the platform exiting transport road 2 is not more than 1 meter, and the blades of the wind driven generator can be conveniently arranged and assembled;
the total area of the hoisting operation field 3 is required to be not less than 1750 square meters and the long edge of the hoisting operation field 3 is required to be not less than 50m, and the fan foundation 6 is arranged in the corner of one side of the hoisting operation field 3 far away from the access platform transportation road 1;
step S2: installing a fan impeller 4 according to the position of a fan foundation 6;
the straight-line distance between the center of the fan impeller 4 and the fan foundation 6 is required to be 25 +/-5 m, the fan impeller 4 is arranged in the hoisting operation field 3, and the fan impeller 4 and the fan foundation 6 are located at the diagonal position of the hoisting operation field 3;
step S3: installing a booster transformer 8 according to the position of the fan foundation 6;
the step-up transformer 8 steps up the electric energy generated by the wind driven generator from 690V to 35000V, the distance between the step-up transformer 8 and the central position of the wind turbine foundation 6 is 18m, the requirement of grounding is met, and meanwhile, the blade assembly position needs to be avoided and the blade assembly position needs to be close to the current collecting line tower 7.
Step S4: determining the positions and elevations of the platform entering transport road 1 and the platform exiting transport road 2;
according to the position relation between the wind generating sets and the adjacent wind generating sets, the wind generating set point positions are connected to the platform transport road 1 and the platform transport road 2 to form an on-site transport traffic network, and the wind generating set point positions and the fan impeller 4 installation center positions form an included angle of 120 degrees between the platform transport road 1 and the platform transport road 2. In order to ensure that the first wind driven generator blade 5-1, the second wind driven generator blade 5-2 and the third wind driven generator blade 5-3 are not collided in a space range when being assembled and facilitate the temporary fixation of the first wind driven generator blade 5-1, the second wind driven generator blade 5-2 and the third wind driven generator blade 5-3, the longitudinal slope of the road entering the platform transportation road 1 and the longitudinal slope of the road exiting the platform transportation road 2 are not more than 2% within a range of 50m outside the boundary of the hoisting operation field 3, and the installation and the assembly of the wind driven generator blades are facilitated.
Step S5: installing a main crane 9 and an auxiliary crane 10 on the hoisting operation site 3:
the main crane 9, the central position of the fan impeller 4 and the central position of the fan foundation 6 form a triangular position relation.
Step S6: the first wind driven generator blade 5-1, the second wind driven generator blade 5-2, the third wind driven generator blade 5-3 and the fan impeller 4 are assembled and checked in the space of the hoisting operation field 3, the platform transportation road 1 and the space out of the platform transportation road 2, and after the construction weather, the wind speed and the mechanical equipment meet the conditions, the main crane 9 integrally hoists the assembled fan impeller 4, the first wind driven generator blade 5-1, the second wind driven generator blade 5-2 and the third wind driven generator blade 5-3 to a high altitude position, and the auxiliary crane 10 helps the main crane 9 to control the position and the orientation of the fan impeller 4, so that the assembly of the fan impeller 4 and the engine room is completed.
Specific example 1:
the wind power project is located on a steep mountain land, the wind power generator set is of a type with single machine capacity of 2.5MW, the lengths of the first wind power generator blade 5-1, the second wind power generator blade 5-2 and the third wind power generator blade 5-3 are all 56.5m, the height of the fan impeller 4 is 90m, the total weight of the fan impeller 4 is 60.9t, and the intensive hoisting platform is adopted.
The size of a hoisting operation field is designed to be 35m multiplied by 50m according to the position of a wind driven generator and topographic factors, the vertical zero meter elevation of the hoisting platform field is designed to be 798.0m, the linear distance between the center of a fan impeller 4 and a fan foundation 6 is 30m, a booster station transformer 8 is positioned on a connecting line of the fan foundation 6 and a current collecting line tower 7 in the hoisting operation field 3, which is beneficial to electric energy transmission and fan equipment hoisting, the distance between the central position of the booster transformer 8 and the fan foundation 6 is 18m to meet the requirement of grounding, the plane positions of an entering platform transport road 1 and an exiting platform transport road 2 and the center position of the impeller form an included angle of 120 degrees, the vertical elevation of the entering platform transport road 1 and the exiting platform transport road 2 in the range of 50m of the long edge of the hoisting operation field 3 is 798.0 +/-1.0 m, and a main crane 9 and an auxiliary crane 10 are positioned in the range of the hoisting operation field 3, the central positions of the main crane 9, the fan impeller 4 and the fan base 6 form a triangular position relationship, the distance between the central positions of the main crane 9 and the fan base 6 is 25m, and the distance between the central positions of the main crane 9 and the fan impeller 4 is 25 m.
The hoisting operation field 3 of the embodiment is realized by excavating the mountain top, and the excavated earth and stone are more and deepestAnd the excavation is 11.8m, and the construction difficulty is high. In the platform implementation process, an intensive hoisting platform and a hoisting method thereof are adopted, and the distance between the platform and the hoisting platform is about 1800m2The hoisting operation field area realizes the high-altitude installation of the first wind driven generator blade 5-1, the second wind driven generator blade 5-2 and the third wind driven generator blade 5-3 and the fan impeller 4 after ground assembly, and the hoisting field area is less than 2000 m provided by a hoisting factory2The standard operation field scheme not only saves about 1340m of the excavated volume of the hoisting platform3And the project construction period is saved, and the economical and environment-friendly properties of the intensive hoisting platform and the hoisting method thereof are proved.
Specific example 2:
the wind power project is located in a plain area, the wind power generator set is of a type with single machine capacity of 3.3MW, the lengths of the first wind power generator blade 5-1, the second wind power generator blade 5-2 and the third wind power generator blade 5-3 are 69m, the height of the fan impeller 4 is 120m, the total weight of the fan impeller 4 is 82t, and the intensive hoisting platform is adopted.
The size of a hoisting operation field is designed to be 35m multiplied by 50m according to the position of a wind driven generator and topographic factors, the vertical zero meter elevation of the hoisting platform field is designed to be 11.0m, the linear distance between the center of a fan impeller 4 and a fan foundation 6 is 30m, a booster station transformer 8 is positioned on a connecting line of the fan foundation 6 and a current collecting line tower 7 in the hoisting operation field 3, so that electric energy transmission and fan equipment hoisting are facilitated, the distance between the central position of the booster transformer 8 and the fan foundation 6 is 18m to meet the requirement of grounding, the plane positions of an entering platform transport road 1 and an exiting platform transport road 2 and the center position of the impeller form an included angle of 120 degrees, the vertical elevation of the entering platform transport road 1 and the exiting platform transport road 2 in the range of 50m of the long edge of the hoisting operation field 3 is 11.0 +/-1.0 m, and a main crane 9 and an auxiliary crane 10 are positioned in the range of the hoisting operation field 3, the central positions of the main crane 9, the fan impeller 4 and the fan foundation 6 form a triangular position relationship, the distance between the central positions of the main crane 9 and the fan foundation 6 is 23m, and the distance between the central positions of the main crane 9 and the fan impeller 4 is 24 m.
The lifting platform of the embodiment has more trees around the field, and is used for realizing the lifting of the wind power equipmentThe method has large opinion amount and large construction difficulty. In the platform implementation process, an intensive hoisting platform and a hoisting method thereof are adopted, and the distance between the platform and the hoisting platform is about 1800m2The area of the hoisting operation field realizes the three-blade ground assembly and the high-altitude impeller installation, and the area of the hoisting field is less than 2500m provided by a hoisting manufacturer2The standard operation field scheme saves about 265 trees removed from the hoisting platform, and the project construction period is also saved by integrally hoisting the three blades. The economical and environment-friendly properties of the intensive hoisting platform and the hoisting method thereof are proved.

Claims (1)

1. The utility model provides an intensive wind-powered electricity generation hoist and mount platform which characterized in that: the wind power generation system comprises a platform transportation road (1), a platform transportation road (2), a platform transportation road (1) and a platform transportation road (2), wherein the platform transportation road (1) and the platform transportation road (2) are connected with adjacent wind power generation unit point positions to form an on-site traffic transportation network, the platform transportation road (1) and the platform transportation road (2) are communicated with a hoisting operation site (3) to form a wind power generator assembly space, the total area of the hoisting operation site (3) is not less than 1750 square meters, the long edge of the hoisting operation site (3) is not less than 50m, the road longitudinal slope of the platform transportation road (1) and the platform transportation road (2) is not more than 2% within the range of 50m outside the boundary of the hoisting operation site (3), a fan impeller (4) is arranged in one side corner, close to the platform transportation road (2), of the hoisting operation site (3), and a first wind power generator blade (5-1) and a fan impeller (4) are installed on the first wind power generator blade (5-1), wherein the angle of the first wind power generator blade and the first wind power generator blade of the first wind power generator blade of the second wind power generator of the platform transportation road of the platform (4) is 120 degrees, the platform of the, The wind power generation system comprises a second wind power generator blade (5-2) and a third wind power generator blade (5-3), wherein the central lines of the wind power generator blades entering the platform transportation road (1) and going out of the platform transportation road (2) form an included angle of 120 degrees with the center of the fan impeller (4), the first wind power generator blade (5-1) and the second wind power generator blade (5-2) are respectively located on the platform transportation road (1) and the platform transportation road (2), a fan foundation (6) is arranged in the corner of one side, far away from the platform transportation road (1), of the hoisting operation field (3), the fan foundation (6) and the fan impeller (4) are located at the diagonal position of the hoisting operation field (3), the straight line distance from the center of the fan impeller (4) to the fan foundation (6) is 25 +/-5 m, and a step-up transformer (8) is arranged on the connecting line of a current collection line pole tower (7) and the fan foundation (6) outside the hoisting operation field (3) ) The booster transformer (8) is positioned in the hoisting operation field (3), the distance between the booster transformer (8) and the central position of the fan foundation (6) is 18 +/-2 m, a main crane (9) and an auxiliary crane (10) are further arranged in the hoisting operation field (3), and the central positions of the main crane (9), the fan impeller (4) and the central position of the fan foundation (6) form a triangular position relation;
a hoisting method of an intensive wind power hoisting platform comprises the following steps:
step S1: determining the position and elevation of a hoisting operation field (3): determining the plane position and the zero meter elevation of the hoisting operation field (3) by combining the landform and the landform of the position of the wind driven generator; the field level zero meter elevation of the hoisting operation field (3) is determined according to the selected plane position, and when the plane position of the hoisting operation field (3) is positioned at the top of a mountain, the field level zero meter elevation is determined according to the principle that excavation is mainly performed and filling is assisted when the construction platform is built; when the plane position of the hoisting operation field (3) is located in a flat area, the elevation difference between the hoisting operation field (3) and the elevation difference between the platform entering transportation road (1) and the platform exiting transportation road (2) is not more than 1 meter, and the elevation of the field is determined according to the principle that the elevation difference is not more than 1 meter;
step S2: determining the installation position of the fan impeller (4) according to the position of the fan foundation (6);
step S3: installing a step-up transformer (8) according to the positions of the fan foundation (6) and the current collecting line tower (7);
step S4: the method comprises the following steps that a platform entering transportation road (1) and a platform exiting transportation road (2) are implemented according to the installation position of a fan impeller (4), so that the center of the fan impeller (4) forms an included angle of 120 degrees with the center line of the platform entering transportation road (1) and the center line of the platform exiting transportation road (2), and the longitudinal slope of the road entering the platform transportation road (1) and the road exiting the platform transportation road (2) is not more than 2% within the range of 50m outside the boundary of a hoisting operation field (3);
step S5: a main crane (9) and an auxiliary crane (10) are installed on a hoisting operation site (3);
step S6: the first wind driven generator blade (5-1), the second wind driven generator blade (5-2), the third wind driven generator blade (5-3) and the fan impeller (4) are assembled and checked in the space of a hoisting operation field (3), a platform transportation road (1) and a platform transportation road (2), and after construction weather, wind speed and mechanical equipment meet conditions, the fan impeller (4), the first wind driven generator blade (5-1), the second wind driven generator blade (5-2) and the third wind driven generator blade (5-3) are integrally hoisted to a designed height to complete the assembly of the fan impeller (4) and a cabin.
CN202110292835.9A 2021-03-18 2021-03-18 Intensive wind power hoisting platform and hoisting method Active CN113107778B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110292835.9A CN113107778B (en) 2021-03-18 2021-03-18 Intensive wind power hoisting platform and hoisting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110292835.9A CN113107778B (en) 2021-03-18 2021-03-18 Intensive wind power hoisting platform and hoisting method

Publications (2)

Publication Number Publication Date
CN113107778A CN113107778A (en) 2021-07-13
CN113107778B true CN113107778B (en) 2022-05-31

Family

ID=76711671

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110292835.9A Active CN113107778B (en) 2021-03-18 2021-03-18 Intensive wind power hoisting platform and hoisting method

Country Status (1)

Country Link
CN (1) CN113107778B (en)

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204151640U (en) * 2014-10-20 2015-02-11 四川电力设计咨询有限责任公司 Mountain region wind energy turbine set road route
CN110687560A (en) * 2019-10-12 2020-01-14 中国电建集团贵州工程有限公司 Impeller combination rapid positioning method

Also Published As

Publication number Publication date
CN113107778A (en) 2021-07-13

Similar Documents

Publication Publication Date Title
CN2777235Y (en) Net work frame structure functional tower for wind-power electric generator
KR101318111B1 (en) Substructure of hybrid offshore wind turbine with multi-pile for reducing wave forces, and constructing method for the same
US8952558B2 (en) Wind generating device
Zafar Literature review of wind turbines
CN103243732A (en) Installing method of marine anemometer tower base structure
CN202416341U (en) Steel truss automatically-standing seaborne anemometer tower
CN113107778B (en) Intensive wind power hoisting platform and hoisting method
CN102174926A (en) Tower-type wind power station structure
CN102808419B (en) Combined pile foundation structure
CN103195660B (en) A kind of pylon of truss structure
CN113864124B (en) Wind power blade hoisting construction method under mountain condition
CN201461229U (en) Wind ball
CN115928785A (en) Wind power stepped assembly type foundation suitable for mountain region and assembly method thereof
CN205153666U (en) Communication base station
CN105507646A (en) Communication base station
CN206545568U (en) A kind of new floating marine formula may move wind power plant
CN215170538U (en) Multi-pile concrete supporting structure for land wind turbine generator system
CN104595127A (en) Three-dimensional triangular vertical shaft common-structure cascaded power generating wind tower and implementation method
CN218622307U (en) Box transformer and fan foundation combined arrangement structure in wind power generation field
CN214092144U (en) Impeller assembling and fixing device of wind generating set
Pernpeintner Offshore siting of large wind energy converter systems in the north sea and baltic sea regions
CN213625679U (en) Double-strut type fan foundation
CN211116407U (en) Floating type offshore high-altitude wind power generation system
CN217651843U (en) Mountain area overhead pile wall fan foundation
CN106545469A (en) Removable wind power plant of a kind of new floating marine formula and preparation method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant