CN113089485B - Pipe penetrating and pulling trolley for box girder prestressed duct construction and pipe penetrating and pulling method thereof - Google Patents

Pipe penetrating and pulling trolley for box girder prestressed duct construction and pipe penetrating and pulling method thereof Download PDF

Info

Publication number
CN113089485B
CN113089485B CN202110230204.4A CN202110230204A CN113089485B CN 113089485 B CN113089485 B CN 113089485B CN 202110230204 A CN202110230204 A CN 202110230204A CN 113089485 B CN113089485 B CN 113089485B
Authority
CN
China
Prior art keywords
roller
trolley
pipe
pulling
pipe penetrating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110230204.4A
Other languages
Chinese (zh)
Other versions
CN113089485A (en
Inventor
张光明
李明
唐达昆
杜军良
梅慧浩
陈玉英
刘新华
邵刚强
徐青
刘波
梁盼盼
王镇
陈晓飞
赵成立
王源
王扬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 11th Bureau Group Co Ltd
China Railway 11th Bureau Group Hanjiang Heavy Industry Co Ltd
China Railway 11th Bureau Group Bridge Co Ltd
Original Assignee
China Railway 11th Bureau Group Co Ltd
China Railway 11th Bureau Group Hanjiang Heavy Industry Co Ltd
China Railway 11th Bureau Group Bridge Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 11th Bureau Group Co Ltd, China Railway 11th Bureau Group Hanjiang Heavy Industry Co Ltd, China Railway 11th Bureau Group Bridge Co Ltd filed Critical China Railway 11th Bureau Group Co Ltd
Priority to CN202110230204.4A priority Critical patent/CN113089485B/en
Publication of CN113089485A publication Critical patent/CN113089485A/en
Application granted granted Critical
Publication of CN113089485B publication Critical patent/CN113089485B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed

Abstract

The invention provides a pipe penetrating and pulling trolley for box girder prestress pore construction, which comprises a chassis, a pipe penetrating and pulling mechanism, a working platform, a lifting mechanism and a reel mechanism, wherein when a pipe is penetrated and pulled, the trolley is driven to move to the position of the pipe penetrating and pulling, a transverse moving oil cylinder and a longitudinal moving oil cylinder in the lifting mechanism and the pipe penetrating and pulling mechanism are adjusted to enable a roller component to be aligned to the position of the pipe pre-penetrating and pulling, a driving roller and a clamping roller in the pipe penetrating and pulling mechanism clamp the pipe pre-penetrating and pulling, a motor for driving the rollers is turned on to start the pipe penetrating and pulling, and the reel mechanism is used for placing the pipe pre-penetrating and pulling and straightening and stacking the pulled pipe. The pipe penetrating and drawing trolley can realize the functions of automatic pipe penetrating and drawing, and can automatically perform the straightening and stacking work of rubber pipes.

Description

Pipe penetrating and pulling trolley for box girder prestressed duct construction and pipe penetrating and pulling method thereof
Technical Field
The invention relates to the technical field of bridge construction, in particular to a pipe penetrating and pulling trolley for box girder prestressed duct construction and a pipe penetrating and pulling method thereof.
Background
The box girder is applied with prestress, so that the load generated by positive and negative bending moments and the dead weight of the box girder can be reduced or offset, the bearing capacity of the box girder is improved, and the application of the prestress on the box girder can be realized by stretching and drawing the steel strand penetrating through the prestressed duct on the box girder. When the prefabricated box girder is constructed, a prestressed pore channel is formed by penetrating and pulling the rubber tube on the box girder, specifically, when a steel reinforcement framework of a box girder body is bound, the binding of the designed positioning net and the steel reinforcement framework are performed according to the prestressed pore channel, then, the tube penetrating is performed according to the position of the positioning net, after the tube penetrating is completed, concrete is poured, after the concrete reaches a certain strength, the rubber tube is pulled out again, and the prestressed pore channel can be formed on the box girder. The rubber tube needs to be ensured to be accurately positioned by the positioning net when penetrating into the positioning net, if the positioning net deviates, the deviation amount needs to be controlled within 4mm, and the rubber tube is flat and straight in the box girder. When the pipe is drawn out, cement paste cannot be attached to the rubber pipe required to be drawn out, the wall of the formed prestressed duct is smooth, and no residue is left.
At present, the pipe penetrating operation of a prefabricated box girder is usually completed by a semi-automatic pipe penetrating machine, but the pipe penetrating of the semi-automatic pipe penetrating machine needs three persons to be matched, wherein two persons straighten the rubber pipes and convey the rubber pipes to the pipe penetrating machine, and the other person remotely operates the pipe penetrating machine and pulls and guides in front.
The pipe drawing operation of prefabricated case roof beam adopts the hoist engine to draw the rubber tube, once can draw 2, nevertheless to the damage of rubber tube when drawing great, leads to the rubber tube diameter to attenuate easily, and the rubber tube is pulled out easily, has the potential safety hazard, needs the workman to put things in good order the rubber tube of pulling out after the rubber tube has been pulled out moreover, and puts things in good order more in disorder. In addition, the existing tube drawing machine can be used for drawing tubes, the existing tube drawing machine adopts chain bearing tile staggered tube drawing, the synchronism is poor, the damage to rubber tubes is large, and no rubber tube stacking device is provided.
Disclosure of Invention
Aiming at the defects in the prior art, the invention provides a pipe penetrating and pulling trolley for box girder pre-stress duct construction and a pipe penetrating and pulling method thereof.
The technical scheme adopted for realizing the above purpose of the invention is as follows:
a pipe penetrating and pulling trolley for box girder prestress pore canal construction at least comprises a chassis, wherein wheels and supporting pieces are arranged on the side face of the chassis, a driving motor, a steering oil cylinder and a storage battery are installed on the chassis, a pipe penetrating and pulling mechanism, a working platform, a lifting mechanism and a reel mechanism are arranged on the chassis, two groups of door-shaped frames are arranged in the lifting mechanism, the door-shaped frames are respectively and vertically fixed at the front end and the rear end of the chassis, four corners of the working platform are all installed on vertical rods in the door-shaped frames and are driven by the lifting mechanism to integrally lift up and down;
the pipe penetrating and pulling mechanism comprises an upper frame, a transverse moving oil cylinder, roller assemblies, clamping assemblies, a lower frame and a longitudinal moving oil cylinder, wherein the transverse moving oil cylinder, the roller assemblies and the clamping assemblies are arranged on the upper frame, the longitudinal moving oil cylinder is arranged on the lower frame, the pipe penetrating and pulling mechanism is connected with a working platform through the longitudinal moving oil cylinder and driven by the longitudinal moving oil cylinder to realize the longitudinal movement of the pipe penetrating and pulling mechanism, the lower frame is connected with the upper frame through the transverse moving oil cylinder and driven by the transverse moving oil cylinder to realize the transverse movement of the upper frame, the lower frame, the working platform and a chassis are all frame-type structures, the roller assemblies are arranged in the frame of the upper frame and penetrate through the lower frame, the working platform and the chassis, the roller assemblies comprise driving rollers, roller frames for mounting the driving rollers and driving motors, two groups of the roller assemblies are arranged in the front and back directions of the trolley, the two groups of the roller assemblies are arranged in the middle of the upper frame, and the clamping assemblies are correspondingly arranged on two sides of the upper frame, the clamping assembly comprises a roller frame, a clamping oil cylinder and clamping rollers positioned on the roller frame, the clamping oil cylinder and the roller frame drive the clamping rollers to move, and the clamping rollers correspond to the driving rollers one by one; the working platform is provided with two reel frames corresponding to the roller assemblies and used for placing the reel mechanism, and the reel mechanism comprises an underframe, and a rotating motor, a reel, a fixing device and a guiding device which are arranged on the underframe.
Each group of roller assemblies is provided with more than one driving roller along the axle direction of the trolley, and the clamping assemblies are correspondingly provided with the same number of clamping rollers.
All be provided with the connecting rod on the montant among the door style of calligraphy frame, work platform's four corners department all installs on the connecting rod.
The lifting mechanism is further provided with a lifting oil cylinder, a slide rod is transversely arranged on the door-shaped frame in a crossing mode, the lifting oil cylinder is connected between the slide rod and the trolley, the door-shaped frame is further provided with a chain transmission assembly and a guide assembly, the guide assembly is installed at the upper end and the lower end of the connecting rod, and the chain transmission assembly penetrates through the guide assembly and is connected to the slide rod and the connecting rod.
And more than two top beam assemblies are arranged on one side of the upper frame along the front-rear direction of the trolley.
And a support rod is arranged on the vertical rod of the door-shaped frame.
And the clamping roller and the driving roller are both coated with high-strength rubber.
The invention also provides a pipe penetrating and pulling trolley for box girder pre-stressed duct construction, which comprises the following steps: (1) the driving trolley moves to the pipe penetrating position, and the supporting piece is opened to fix the trolley;
(2) adjusting the lifting mechanism, the transverse moving oil cylinder and the longitudinal moving oil cylinder to enable the roller assembly to be aligned to the position of the pre-penetration pipe;
(3) the rotating motor on the reel pre-wound with the rubber tube works, the fixing device loosens the head of the rubber tube, the rubber tube moves along the guide device and penetrates between the driving roller and the distance adjusting roller, the driving roller works to penetrate the rubber tube;
(4) and (3) after the pipe penetrating is finished, loosening the tail part of the rubber pipe by the fixing device, retracting the supporting mechanism, moving the trolley to the next rubber pipe position, and repeating the steps (1) to (3) to perform pipe penetrating.
The invention also provides a pipe drawing method of the pipe penetrating and drawing trolley for box girder pre-stressed duct construction, which comprises the following steps: (1) the driving trolley moves to the pipe drawing position, and the supporting piece is opened to fix the trolley;
(2) adjusting the lifting mechanism, the transverse moving oil cylinder and the longitudinal moving oil cylinder to enable the roller assemblies to be aligned to the position of the pre-drawn rubber pipe;
(3) penetrating a rubber tube into a space between the driving roller and the distance-adjusting roller, adjusting the clamping assembly to enable the roller to clamp the rubber tube, adjusting the top beam assembly to be supported on the box girder, starting a motor for driving the roller, and starting tube drawing;
(4) the pulled rubber tube is aligned through the guide device and penetrates into the reel, the end head of the rubber tube is fixed by the fixing device, and the pulled rubber tube is wound by the operation of the rotating motor;
(5) and (4) after the tube drawing is finished, fixing the tail part of the rubber tube by the fixing device, retracting the supporting mechanism, and repeating the steps (1) to (4) to draw the tube after the trolley is moved to the next rubber tube position.
Compared with the prior art, the pipe penetrating and pulling trolley for the box girder pre-stressed duct construction and the pipe penetrating and pulling method thereof provided by the invention have the following advantages: 1. the pipe threading and pulling trolley provided by the invention can automatically thread and pull pipes and automatically perform the smoothing and stacking work of rubber pipes, has high pipe threading and pulling efficiency and high quality, saves manpower and reduces the construction time. 2. According to the invention, the lifting mechanism, the transverse moving oil cylinder and the longitudinal moving oil cylinder are arranged, so that the automatic alignment function of the rubber tube is realized, and the automatic alignment device can be used for penetrating and pulling the rubber tubes at different height positions. 3. The two groups of roller assemblies in the pipe threading and pulling trolley provided by the invention can simultaneously thread and pull two rubber pipes, and meanwhile, the two reel mechanisms can realize the smoothing and stacking work of the two rubber pipes, so that the construction time is reduced. 4. According to the invention, through the arrangement of the clamping assembly, the penetration and the pulling of rubber tubes with different pipe diameters can be realized. 5. According to the invention, the top beam assembly is arranged, so that the pipe penetrating and pulling mechanism is prevented from deviating during pipe pulling. 6. All components of the penetrating and pulling pipe are arranged on the chassis of the trolley, so that the field construction and transportation are convenient, and the labor is saved.
Drawings
FIG. 1 is a front view of a pipe penetrating and pulling trolley for box girder pre-stressed duct construction, provided by the invention;
FIG. 2 is a top view of the pipe penetrating and pulling trolley for box girder pre-stress duct construction provided by the invention;
FIG. 3 is a side view of the lift mechanism of the present invention;
FIG. 4 is a front view of the connection of the lift mechanism and the work platform of the present invention;
FIG. 5 is a top view of the reel mechanism of the present invention;
FIG. 6 is a front view of the working mechanism of the present invention;
FIG. 7 is a top view of the working mechanism of the present invention;
in the figure: 1-pipe drawing mechanism, 11-roller assembly, 111-driving roller, 112-driving motor, 12-clamping assembly, 121-clamping rod, 122-clamping cylinder, 123-distance adjusting roller, 13-upper frame, 14-lower frame, 15-traverse cylinder, 16-longitudinal cylinder, 17-top beam assembly, 2-working platform, 21-reel rack, 3-lifting mechanism, 31-door frame, 32-chain transmission assembly, 33-lifting cylinder, 34-guiding assembly, 35-sliding rod, 36-supporting rod, 37-connecting rod, 4-chassis, 41-storage battery, 42-wheel, 5-reel mechanism, 51-chassis, 52-rotating motor, 53-reel, 54-guide means.
Detailed Description
The present invention will be described in detail with reference to the accompanying drawings.
The structure of the pipe penetrating and pulling trolley for box girder pre-stress duct construction provided by the invention is shown in fig. 1 and fig. 2, and at least comprises a chassis 4, wheels 42 and supporting pieces are arranged on the side surface of the chassis, a driving motor, a steering oil cylinder and a storage battery 41 are arranged on the chassis, and a pipe penetrating and pulling mechanism 1, a working platform 2, a lifting mechanism 3 and a reel mechanism 5 are arranged on the chassis.
The side view of elevating system in this embodiment is shown in fig. 3, is provided with two sets of door style of calligraphy frames 31 among the elevating system, door style of calligraphy frame is vertical both ends department around being fixed in the chassis respectively, be provided with bracing piece 36 on door style of calligraphy frame's the montant, door style of calligraphy frame and bracing piece are jointly with elevating system firm connection on the platform truck. All be provided with connecting rod 37 on door style of calligraphy frame's the montant, still be provided with lift cylinder 33 on the elevating system, the door style of calligraphy frame is gone up the stride and is provided with slide bar 35, lift cylinder connects between slide bar and platform truck, still be provided with chain drive subassembly 32 and direction subassembly 34 on the door style of calligraphy frame, direction subassembly installation is in the upper and lower both ends of connecting rod, chain drive subassembly passes the direction subassembly and is connected in on slide bar and the connecting rod. Four corners of the working platform are all installed on the connecting rod, and are driven by the lifting mechanism to lift up and down integrally, a front view of the lifting mechanism and the working platform is shown in fig. 4, a reel frame 21 for placing the reel mechanism is arranged on the working platform, a top view of the reel mechanism is shown in fig. 5, the reel mechanism comprises an underframe 51, and a rotating motor 52, a reel 53, a fixing device and a guiding device 54 which are arranged on the underframe, and two reel mechanisms are arranged corresponding to the roller assemblies in the embodiment.
The pipe penetrating and pulling mechanism in this embodiment comprises an upper frame 13, a traverse cylinder 15, a roller assembly 11, a clamping assembly 12, a top beam assembly 17, a lower frame 14 and a longitudinal moving cylinder 16 arranged on the upper frame, the structure of the pipe penetrating and pulling mechanism provided in this embodiment is as shown in fig. 6 and 7, the pipe penetrating and pulling mechanism is connected with a working platform through the longitudinal moving cylinder and driven by the longitudinal moving cylinder to realize longitudinal movement of the pipe penetrating and pulling mechanism, the lower frame is connected with the upper frame through the traverse cylinder and driven by the traverse cylinder to realize transverse movement of the upper frame, the lower frame, the working platform and a chassis are all frame-type structures, the roller assembly is arranged in the frame of the upper frame and penetrates through the lower frame, the working platform and the chassis, the roller assembly comprises a driving roller 111, a roller frame for mounting the driving roller and a driving motor 112, the trolley is characterized in that two groups of roller assemblies are arranged in the front-rear direction of the trolley, the two groups of roller assemblies are arranged in the middle of the upper frame, the two groups of clamping assemblies are correspondingly arranged on two sides of the upper frame, each clamping assembly comprises a roller frame 121, a clamping oil cylinder 122 and a clamping roller 123 located on the roller frame, the clamping oil cylinders and the roller frames drive the clamping rollers to move, and the clamping rollers correspond to the driving rollers one to one.
Every group wheel components is provided with three drive gyro wheel along platform truck axletree direction in this embodiment, the last correspondence of clamping components is provided with three clamping roller to guarantee to wear the stability of tube drawing process, wheel components is provided with two sets ofly along the platform truck fore-and-aft direction, and two sets of wheel components are installed in the centre of last frame, clamping components and reel mechanism all correspond and are provided with two sets ofly and install in the both sides of last frame, and two rubber tubes just can be worn and drawn simultaneously to this platform truck, and roof beam subassembly is provided with two in this embodiment, and the tube drawing mechanism takes place the skew when can avoiding the tube drawing.
In this embodiment, the clamping roller and the driving roller are both coated with high-strength rubber, so that the strength of the roller is ensured and the friction force of the roller is improved.
The invention also provides a pipe penetrating and pulling trolley for box girder pre-stressed duct construction, which comprises the following steps: (1) the driving trolley moves to the pipe penetrating position, and the supporting piece is opened to fix the trolley;
(2) adjusting the lifting mechanism, the transverse moving oil cylinder and the longitudinal moving oil cylinder to enable the roller assembly to be aligned to the position of the pre-penetration pipe;
(3) the rotating motor on the reel pre-wound with the rubber tube works, the fixing device loosens the head of the rubber tube, the rubber tube moves along the guide device and penetrates between the driving roller and the distance adjusting roller, the driving roller works to penetrate the rubber tube;
(4) and (3) after the pipe penetrating is finished, loosening the tail part of the rubber pipe by the fixing device, retracting the supporting mechanism, moving the trolley to the next rubber pipe position, and repeating the steps (1) to (3) to perform pipe penetrating.
The invention also provides a pipe drawing method of the pipe penetrating and drawing trolley for box girder pre-stressed duct construction, which comprises the following steps: (1) the driving trolley moves to the pipe drawing position, and the supporting piece is opened to fix the trolley;
(2) adjusting the lifting mechanism, the transverse moving oil cylinder and the longitudinal moving oil cylinder to enable the roller assemblies to be aligned to the position of the pre-drawn rubber pipe;
(3) penetrating a rubber tube into a space between the driving roller and the distance-adjusting roller, adjusting the clamping assembly to enable the roller to clamp the rubber tube, turning on a motor for driving the roller, and starting tube drawing;
(4) the pulled rubber tube is aligned through the guide device and penetrates into the reel, the end head of the rubber tube is fixed by the fixing device, and the pulled rubber tube is wound by the operation of the rotating motor;
(5) and (4) after the tube drawing is finished, fixing the tail part of the rubber tube by the fixing device, retracting the supporting mechanism, and repeating the steps (1) to (4) to draw the tube after the trolley is moved to the next rubber tube position.
In addition, when the pipe is pulled out, the adjusting top beam assembly is supported on the box beam, so that the pipe penetrating and pulling mechanism can be prevented from deviating.

Claims (9)

1. The utility model provides a wear tube drawing platform truck for construction of case roof beam prestressing force pore canal, includes the chassis at least, the side on chassis is provided with wheel and support piece, installs driving motor, steering cylinder and battery on the chassis, its characterized in that: the chassis is provided with a pipe penetrating and pulling mechanism, a working platform, a lifting mechanism and a reel mechanism, wherein the lifting mechanism is internally provided with two groups of door-shaped frames which are respectively and vertically fixed at the front end and the rear end of the chassis, and the four corners of the working platform are all arranged on vertical rods in the door-shaped frames and are driven by the lifting mechanism to integrally lift up and down;
the pipe penetrating and pulling mechanism comprises an upper frame, a transverse moving oil cylinder, roller assemblies, clamping assemblies, a lower frame and a longitudinal moving oil cylinder, wherein the transverse moving oil cylinder, the roller assemblies and the clamping assemblies are arranged on the upper frame, the longitudinal moving oil cylinder is arranged on the lower frame, the pipe penetrating and pulling mechanism is connected with a working platform through the longitudinal moving oil cylinder and driven by the longitudinal moving oil cylinder to realize the longitudinal movement of the pipe penetrating and pulling mechanism, the lower frame is connected with the upper frame through the transverse moving oil cylinder and driven by the transverse moving oil cylinder to realize the transverse movement of the upper frame, the lower frame, the working platform and a chassis are all frame-type structures, the roller assemblies are arranged in the frame of the upper frame and penetrate through the lower frame, the working platform and the chassis, the roller assemblies comprise driving rollers, roller frames for mounting the driving rollers and driving motors, two groups of the roller assemblies are arranged in the front and back directions of the trolley, the two groups of the roller assemblies are arranged in the middle of the upper frame, and the clamping assemblies are correspondingly arranged on two sides of the upper frame, the clamping assembly comprises a roller frame, a clamping oil cylinder and clamping rollers positioned on the roller frame, the clamping oil cylinder and the roller frame drive the clamping rollers to move, and the clamping rollers correspond to the driving rollers one by one; the working platform is provided with two reel frames corresponding to the roller assemblies and used for placing the reel mechanism, and the reel mechanism comprises an underframe, and a rotating motor, a reel, a fixing device and a guiding device which are arranged on the underframe.
2. The pipe penetrating and pulling trolley for box girder pre-stressed duct construction according to claim 1, wherein: each group of roller assemblies is provided with more than one driving roller along the axle direction of the trolley, and the clamping assemblies are correspondingly provided with the same number of clamping rollers.
3. The pipe penetrating and pulling trolley for box girder pre-stressed duct construction according to claim 1, wherein: all be provided with the connecting rod on the montant among the door style of calligraphy frame, work platform's four corners department all installs on the connecting rod.
4. The pipe penetrating and pulling trolley for the box girder prestressed duct construction as claimed in claim 3, wherein: the lifting mechanism is further provided with a lifting oil cylinder, a slide rod is transversely arranged on the door-shaped frame in a crossing mode, the lifting oil cylinder is connected between the slide rod and the trolley, the door-shaped frame is further provided with a chain transmission assembly and a guide assembly, the guide assembly is installed at the upper end and the lower end of the connecting rod, and the chain transmission assembly penetrates through the guide assembly and is connected to the slide rod and the connecting rod.
5. The pipe penetrating and pulling trolley for box girder pre-stressed duct construction according to claim 1, wherein: and more than two top beam assemblies are arranged on one side of the upper frame along the front-rear direction of the trolley.
6. The pipe penetrating and pulling trolley for box girder pre-stressed duct construction according to claim 1, wherein: and a support rod is arranged on the vertical rod of the door-shaped frame.
7. The pipe penetrating and pulling trolley for box girder pre-stressed duct construction according to claim 1, wherein: and the clamping roller and the driving roller are both coated with high-strength rubber.
8. The pipe penetrating method of the pipe penetrating and pulling trolley for box girder pre-stressed duct construction, which is claimed in claim 1, is characterized by comprising the following steps: (1) the driving trolley moves to the pipe penetrating position, and the supporting piece is opened to fix the trolley;
(2) adjusting the lifting mechanism, the transverse moving oil cylinder and the longitudinal moving oil cylinder to enable the roller assembly to be aligned to the position of the pre-penetration pipe;
(3) the rotating motor on the reel pre-wound with the rubber tube works, the fixing device loosens the head of the rubber tube, the rubber tube moves along the guide device and penetrates between the driving roller and the clamping roller, and the driving roller works to penetrate the rubber tube;
(4) and (3) after the pipe penetrating is finished, loosening the tail part of the rubber pipe by the fixing device, retracting the supporting mechanism, moving the trolley to the next rubber pipe position, and repeating the steps (1) to (3) to perform pipe penetrating.
9. The pipe drawing method of the pipe penetrating and drawing trolley for box girder prestressed duct construction, which is claimed in claim 1, is characterized by comprising the following steps: (1) the driving trolley moves to the pipe drawing position, and the supporting piece is opened to fix the trolley;
(2) adjusting the lifting mechanism, the transverse moving oil cylinder and the longitudinal moving oil cylinder to enable the roller assemblies to be aligned to the position of the pre-drawn rubber pipe;
(3) penetrating a rubber tube into a space between the driving roller and the clamping roller, adjusting the clamping assembly to enable the roller to clamp the rubber tube, turning on a motor for driving the roller, and starting tube drawing;
(4) the pulled rubber tube is aligned through the guide device and penetrates into the reel, the end head of the rubber tube is fixed by the fixing device, and the pulled rubber tube is wound by the operation of the rotating motor;
(5) and (4) after the tube drawing is finished, fixing the tail part of the rubber tube by the fixing device, retracting the supporting mechanism, and repeating the steps (1) to (4) to draw the tube after the trolley is moved to the next rubber tube position.
CN202110230204.4A 2021-03-02 2021-03-02 Pipe penetrating and pulling trolley for box girder prestressed duct construction and pipe penetrating and pulling method thereof Active CN113089485B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110230204.4A CN113089485B (en) 2021-03-02 2021-03-02 Pipe penetrating and pulling trolley for box girder prestressed duct construction and pipe penetrating and pulling method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110230204.4A CN113089485B (en) 2021-03-02 2021-03-02 Pipe penetrating and pulling trolley for box girder prestressed duct construction and pipe penetrating and pulling method thereof

Publications (2)

Publication Number Publication Date
CN113089485A CN113089485A (en) 2021-07-09
CN113089485B true CN113089485B (en) 2022-04-08

Family

ID=76666189

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110230204.4A Active CN113089485B (en) 2021-03-02 2021-03-02 Pipe penetrating and pulling trolley for box girder prestressed duct construction and pipe penetrating and pulling method thereof

Country Status (1)

Country Link
CN (1) CN113089485B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114961208B (en) * 2022-07-07 2024-01-26 中铁二十二局集团第二工程有限公司 Multifunctional tube drawing and transporting integrated machine

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103015326B (en) * 2012-12-28 2016-04-20 中铁二十四局集团有限公司 A kind ofly automatically wear rubber tube machine and the application process in case beam steel cage thereof
CN204982667U (en) * 2015-06-18 2016-01-20 中铁六局集团有限公司 Prestressing force rubber tube poling machine
CN105862604A (en) * 2016-06-18 2016-08-17 朱学德 Dual-drive automatic tube penetrating machine and method
CN105970828B (en) * 2016-06-18 2018-05-01 浙江广厦建设职业技术学院 A kind of automatic pipe lining machine and method
KR101725734B1 (en) * 2016-07-15 2017-04-12 천진욱 Steel-Concrete Composite Girder And Manufacturing Method Thereof

Also Published As

Publication number Publication date
CN113089485A (en) 2021-07-09

Similar Documents

Publication Publication Date Title
CN111576243A (en) Bridge tensioning trolley with simple support and continuous negative moment
CN113089485B (en) Pipe penetrating and pulling trolley for box girder prestressed duct construction and pipe penetrating and pulling method thereof
CN112030777B (en) Descending movable formwork support bracket crossing type transfer construction method
CN214993129U (en) Pipe penetrating and pulling trolley for box girder prestress pore canal construction
CN208995928U (en) A kind of multi-functional erection crane suitable for composite beam construction
CN102145353B (en) O-forming machine mounting method
CN109505251A (en) A kind of arch steel structure truss bridge erection method
CN212774335U (en) Tunnel trolley for lifting steel frame
CN113529502B (en) Subway guide rail is laid with correcting auxiliary device
JP2768280B2 (en) Bridge construction method
CN211969285U (en) Beam slab transportation reinforcing apparatus
CN110000922B (en) Whole installation device of prefabricated T roof beam pterygoid lamina reinforcing bar of road bridge
CN210766433U (en) Trapezoidal hanging basket structure
CN207739157U (en) Rubber bar penetrates device automatically in railway beam body prestressed pore passage
CN212452314U (en) Bridge tensioning trolley with simple support and continuous negative moment
CN112252195A (en) Assembly type continuous beam prestressed steel strand whole-bundle tensioning operation trolley and use method thereof
CN111392667A (en) Operation trolley for installing reinforcing steel bars on dam panel and using method
CN206417806U (en) Running type jack for precast beam prestressed stretch-draw suspends door frame in midair
CN213763582U (en) Integral bending forming device for arc-shaped reinforcing steel bar net piece
CN210529501U (en) Movable shuttling truss for mounting transverse wet joint reinforcing steel bars on parallel double-width bridge deck
CN220182010U (en) System for transversely moving mobile trolley between high-low parallel tracks
CN218440961U (en) Slope riser installation auxiliary device
CN214618146U (en) PCCP pipeline installation butt joint auxiliary device
CN217376979U (en) New jersey guardrail horizontal type prefabrication method steel reinforcement framework integral hoisting device
CN214695173U (en) Assembled continuous beam prestressed steel strand whole-bundle tensioning operation trolley

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant