CN113078668B - Method, system, equipment and storage medium for realizing demand side response virtual power station - Google Patents

Method, system, equipment and storage medium for realizing demand side response virtual power station Download PDF

Info

Publication number
CN113078668B
CN113078668B CN202110622326.8A CN202110622326A CN113078668B CN 113078668 B CN113078668 B CN 113078668B CN 202110622326 A CN202110622326 A CN 202110622326A CN 113078668 B CN113078668 B CN 113078668B
Authority
CN
China
Prior art keywords
base station
power supply
supply system
time
ampere
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110622326.8A
Other languages
Chinese (zh)
Other versions
CN113078668A (en
Inventor
黄世回
王一鸣
王汝钢
白海江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PLUKE TECH Inc
Original Assignee
PLUKE TECH Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PLUKE TECH Inc filed Critical PLUKE TECH Inc
Priority to CN202110622326.8A priority Critical patent/CN113078668B/en
Publication of CN113078668A publication Critical patent/CN113078668A/en
Application granted granted Critical
Publication of CN113078668B publication Critical patent/CN113078668B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/28Arrangements for balancing of the load in a network by storage of energy
    • H02J3/32Arrangements for balancing of the load in a network by storage of energy using batteries with converting means
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00006Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment
    • H02J13/00016Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment using a wired telecommunication network or a data transmission bus
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00006Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment
    • H02J13/00022Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment using wireless data transmission
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00006Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment
    • H02J13/00028Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment involving the use of Internet protocols
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/007Arrangements for selectively connecting the load or loads to one or several among a plurality of power lines or power sources
    • H02J3/0075Arrangements for selectively connecting the load or loads to one or several among a plurality of power lines or power sources for providing alternative feeding paths between load and source according to economic or energy efficiency considerations, e.g. economic dispatch
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/04Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
    • H02J9/06Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2213/00Indexing scheme relating to details of circuit arrangements for providing remote indication of network conditions of for circuit arrangements for providing remote control of switching means in a power distribution network
    • H02J2213/10Indexing scheme relating to details of circuit arrangements for providing remote indication of network conditions of for circuit arrangements for providing remote control of switching means in a power distribution network using simultaneously two or more different transmission means
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2310/00The network for supplying or distributing electric power characterised by its spatial reach or by the load
    • H02J2310/50The network for supplying or distributing electric power characterised by its spatial reach or by the load for selectively controlling the operation of the loads
    • H02J2310/56The network for supplying or distributing electric power characterised by its spatial reach or by the load for selectively controlling the operation of the loads characterised by the condition upon which the selective controlling is based
    • H02J2310/62The condition being non-electrical, e.g. temperature
    • H02J2310/64The condition being economic, e.g. tariff based load management
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B90/00Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02B90/20Smart grids as enabling technology in buildings sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/14Energy storage units
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/12Energy storage units, uninterruptible power supply [UPS] systems or standby or emergency generators, e.g. in the last power distribution stages
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/248UPS systems or standby or emergency generators

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)

Abstract

The invention provides a method, a system, equipment and a storage medium for realizing a virtual power station with demand side response, wherein the method comprises the following steps: receiving battery status data from each base station power supply system accessed to the virtual private network; in the peak time of the power load, sending a first instruction to the main controllers of all base station power supply systems meeting a first preset condition, and sending a second instruction to the main controllers of all base station power supply systems meeting a second preset condition; in the power load valley period, sending a third instruction to all the main controllers of the base station power supply systems meeting a third preset condition; and sending a second instruction to all the main controllers of the base station power supply systems which do not meet the third preset condition. The invention can balance the load of the power grid, realize the response of the demand side and realize the load reduction of the power grid at the peak time of the power load.

Description

Method, system, equipment and storage medium for realizing demand side response virtual power station
Technical Field
The present invention relates to the field of communication base stations, and in particular, to a method, a system, a device, and a storage medium for implementing a virtual power station with demand side response.
Background
With the continuous development of the 5G communication technology in China, 5G communication base stations are built in large quantities, and meanwhile, the 4G base stations on stock are gradually transformed into 5G base stations. Compared with 4G communication, 5G communication has an ultra-high information capacity, and its terminal equipment has an ultra-fast download rate, and in addition, high-density 5G communication base station setting is one of important measures in addition to using high-performance 5G communication equipment.
The most key technical problem for deploying the 5G base station is to solve the problem of the power supply of the 5G base station. Up to now, a major disturbing factor of 5G base station operation which has been upgraded and reconstructed from 4G base stations is the problem of overload of the existing power line load during peak period of power grid load; meanwhile, the newly-built 5G base station increases the power utilization requirement, and particularly in the peak price period, the power cost is directly increased due to the increase of the power fee. The storage batteries of the base station direct current system are combined by using the Internet of things to form a virtual power station, demand side response is realized at a user side, and the power load of a power grid is flexibly adjusted, so that the method is one of key directions of future engineering application.
Disclosure of Invention
The technical problem to be solved by the present invention is to provide a method, a system, a computer device and a storage medium for implementing a virtual power station with demand side response, aiming at the above-mentioned problems of overload of the power line and high power consumption cost of the 5G communication base station.
The technical solution for solving the above technical problem is to provide a method for implementing a virtual power station with demand side response, where the method includes:
receiving battery state data from each base station power supply system accessed to a virtual private network, wherein each base station power supply system comprises a main controller, a UPS (uninterrupted power supply) module, a storage battery pack and a monitoring module, and the base station power supply system is accessed to the virtual private network through the main controller;
sending a first instruction to a main controller of all base station power supply systems meeting a first preset condition in a power load peak period, wherein the first instruction is used for enabling the main controller to control a local UPS power module to output a first voltage, and the first voltage is smaller than or equal to the nominal voltage of a local storage battery pack; sending a second instruction to a main controller of all base station power supply systems meeting a second preset condition, wherein the second instruction is used for enabling the main controller to control a local UPS power module to output a second voltage, and the second voltage is larger than the nominal voltage of a local storage battery pack and smaller than the charging voltage of the local storage battery pack;
in a power load valley period, sending a third instruction to a main controller of all base station power supply systems meeting a third preset condition, wherein the third instruction is used for enabling the main controller to control a local UPS power module to output a third voltage, and the third voltage is greater than the charging voltage of a local storage battery pack; and sending a second instruction to all the main controllers of the base station power supply systems which do not meet the third preset condition.
As a further improvement of the present invention, the power load peak time period is formed by M preset time periods, the communication base stations meeting the first preset condition are divided into M groups, and M is an integer greater than or equal to 2;
the sending of the first instruction to the main controllers of all the base station power supply systems meeting the first preset condition includes:
and at the M preset time intervals, sequentially sending first instructions to M groups of main controllers of the base station power supply systems meeting the first preset condition, and only sending the first instructions to a group of main controllers of the base station power supply systems meeting the first preset condition at each preset time interval.
As a further improvement of the present invention, the method further comprises:
calculating the mean power according to a power load response curve issued by power grid dispatching, wherein the power load curve is received from an external power management system;
the time period in the power load curve greater than the mean power is taken as a power load peak period, and the time period in the power load curve less than or equal to the mean power is taken as a power load valley period.
As a further improvement of the present invention, the sending a first instruction to the main controller of all base station power supply systems meeting the first preset condition includes:
and adjusting the number of the communication base stations which receive the first instruction and perform demand side response according to the change of the power load curve, and sending the number of the communication base stations which perform demand side response and the total power information to a power dispatching system.
As a further improvement of the present invention, the method further comprises: establishing a reference ampere-hour capacity of each base station power supply system according to battery state data received from each base station power supply system, wherein the battery state data comprise the ampere-hour capacity of each single battery in a storage battery pack of the base station power supply system, and the reference ampere-hour capacity of the base station power supply system is the minimum value of the ampere-hour capacity of each single battery;
the first preset condition includes: the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is 0.8 times larger than the reference ampere-hour capacity;
the second preset condition includes: the real-time ampere-hour capacity of the storage battery pack of the base station power supply system is less than or equal to 80% of the reference ampere-hour capacity, or the storage battery pack of the base station power supply system discharges to reach a preset discharge depth;
the third preset condition includes: and the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is smaller than the reference ampere-hour capacity.
As a further improvement of the present invention, the method further comprises: establishing a reference ampere-hour capacity of each base station power supply system according to battery state data received from each base station power supply system, wherein the battery state data comprise the ampere-hour capacity of each single battery in a storage battery pack of the base station power supply system, and the reference ampere-hour capacity of the base station power supply system is the minimum value of the ampere-hour capacity of each single battery;
the first preset condition includes: the current time is in peak price time, and the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is greater than 0.8 time of the reference ampere-hour capacity;
the second preset condition includes: when the current time is in non-peak time, the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is less than or equal to 80% of the reference ampere-hour capacity, or the storage battery pack of the base station power supply system discharges to reach a preset discharge depth;
the third preset condition includes: the current time is at the valley price time and the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is smaller than the reference ampere-hour capacity.
As a further improvement of the present invention, the method further comprises:
recording the discharge duration t of each base station power supply system in a preset perioddAnd a time period t of chargingcThe base station power supply system discharges when the local UPS power module outputs a first voltage and charges when the local UPS power module outputs a third voltage;
calculating the energy-saving electric charge of the virtual power station responded by the demand side according to a preset period:
Figure 406621DEST_PATH_IMAGE001
wherein n is the number of base station power supply systems in the virtual power station, MzFor energy-saving electricity charges of the virtual power station, MiFElectric charge at peak price time for the power supply system of the ith base station, and MiF=PiF×td×Yd,PiFReal-time power at discharge, Y, for the ith base station power supply systemdA unit price of electricity rate which is a peak price time; miGElectricity charge at the valley time for the power supply system of the ith base station, and MiG=PiG×tc×Yc,PiGReal-time power during charging, Y, for the ith base station power supply systemcA unit price of electricity rate which is a valley price time; miBCompensating electricity charges for the power supply system of the ith base station, and MiB=PiF×td×Yf,YfThe unit price of the electricity fee is compensated for the demand side response of the peak price time.
The invention also provides a virtual power station implementation system with demand side response, which comprises a VPN server for maintaining a virtual private network, a plurality of base station power supply systems respectively accessed to the virtual private network, and a platform server accessed to the virtual private network, wherein each base station power supply system comprises a main controller, a UPS power module, a storage battery pack and a monitoring module;
the platform server receives battery state data from each base station power supply system accessed to a virtual private network, and the base station power supply system is accessed to the virtual private network through the main controller;
the platform server sends a first instruction to a main controller of all base station power supply systems meeting a first preset condition in a power load peak period, wherein the first instruction is used for enabling the main controller to control a local UPS power module to output a first voltage, and the first voltage is smaller than or equal to the nominal voltage of a local storage battery pack; sending a second instruction to a main controller of all base station power supply systems meeting a second preset condition, wherein the second instruction is used for enabling the main controller to control a local UPS power module to output a second voltage, and the second voltage is larger than the nominal voltage of a local storage battery pack and smaller than the charging voltage of the local storage battery pack;
the platform server sends a third instruction to all base station power supply system main controllers meeting a third preset condition in a power load valley period, wherein the third instruction is used for enabling the main controllers to control local UPS power modules to output a third voltage, and the third voltage is larger than the charging voltage of local storage battery packs; and sending a second instruction to all the main controllers of the base station power supply systems which do not meet the third preset condition.
The invention also provides a computer device comprising a memory and a processor, wherein the memory stores a computer program executable in the processor, and the processor executes the computer program to realize the steps of the virtual power station implementation method for demand side response.
The present invention also provides a computer-readable storage medium having stored thereon computer-executable instructions for causing a computer to perform the steps of the demand side responsive virtual power plant implementation method as described above.
The virtual power station implementation method, the system, the computer equipment and the storage medium for demand side response utilize a virtual private network to communicate with a base station power supply system of all communication base stations in the same region, and utilize the standby storage battery energy of the communication base stations to supply power to communication loads during peak periods of regional power loads, thereby reducing or not using power grid electric energy and realizing the effect of reducing the load of a power grid.
Drawings
Fig. 1 is a schematic flow chart of a virtual power station implementation method for demand side response according to an embodiment of the present invention;
fig. 2 is a schematic flow chart of generating an electric load peak period and an electric load valley period in a virtual power station implementation method for demand side response according to an embodiment of the present invention;
FIG. 3 is a schematic structural diagram of a virtual power plant implementation system for demand side response provided by an embodiment of the present invention;
fig. 4 is a schematic diagram of a base station power supply system in a virtual power station implementation system with demand side response provided in an embodiment of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
As shown in fig. 1, the flowchart of the virtual power station implementation method for demand side response provided in the embodiment of the present invention is schematic, where the virtual power station implementation method can implement a virtual power station that has a dc load (e.g., a communication device load) and needs to be formed by networking a system using a backup power supply, such as a communication base station (e.g., a 5G communication base station, a 4G communication base station), a server station, and the like. The method of the embodiment can be implemented in a platform server accessed to a virtual private network, and the virtual private network includes a base station power supply system of all communication base stations in the same power dispatching area. For each communication base station, the base station power supply system comprises a main controller, a UPS power module, a storage battery pack and a monitoring module, and the communication equipment load in the communication base station is supplied with power through the UPS power module and the storage battery pack. Each main controller is provided with a unique fixed IP address, the base station power supply system is accessed to the virtual private network through the main controller, and the VPN server in the virtual private network maintains the virtual private network and transmits instruction data and state data through the fixed IP addresses.
Specifically, the method of this embodiment may be specifically executed by a platform server, and includes the following steps:
step S11: the platform server receives battery status data from each base station power supply system that is accessed to the virtual private network.
The battery state data can be collected by a monitoring module in the base station power supply system and include ampere-hour capacity of each single battery in a local storage battery pack (namely, a storage battery pack in the same base station power supply system). Of course, in practical applications, the battery status data may also include other data of each battery pack, such as voltage, discharge current, internal resistance, and the like. In the power supply system of the base station, the monitoring module can be connected to a storage battery loop and is in signal connection with the main controller through a serial port and the like.
Step S12: during the peak time of the power load, the platform server sends a first instruction to the main controller of the base station power supply system meeting a first preset condition, and the main controller receiving the first instruction can execute the first instruction and control the local UPS power module (i.e., the UPS power module located in the same base station power supply system as the main controller) to output a first voltage, where the first voltage is less than or equal to the nominal voltage of the local storage battery (i.e., the storage battery located in the same base station power supply system as the main controller), for example, when the nominal voltage of the storage battery is 48V, the first voltage may be 48V. At the moment, in the base station power supply system, the storage battery pack supplies power to the communication equipment load, so that the communication base station does not need external power supply, and the load of a power grid is reduced. The power supply peak period is a load peak period of power in an area where the communication base station is located.
And during the peak time of the power load, the platform server further sends a second instruction to the main controllers of all the base station power supply systems meeting a second preset condition, and the main controller receiving the second instruction can execute the second instruction and control the local UPS power module to output a second voltage, where the second voltage is greater than the nominal voltage of the local storage battery pack and less than the charging voltage of the local storage battery pack, and for example, when the nominal voltage of the storage battery pack is 48V and the charging voltage is 55V, the second voltage is 53.5V. At this time, in the base station power supply system, the UPS power module supplies power to the communication equipment load, and the storage battery pack is in an unfilled state.
By setting the second preset condition, the storage battery pack with relatively poor performance can be protected, meanwhile, the corresponding communication base station can be ensured to continuously operate in the state of power grid outage, and the phenomenon that the communication base station is disconnected due to the fact that the storage battery pack cannot provide enough electric energy is avoided.
Step S13: in the power load valley period, the platform server sends a third instruction to the main controllers of all the base station power supply systems meeting a third preset condition, and the main controllers receiving the third instruction can execute the third instruction and control the local UPS power module to output a third voltage, where the third voltage is greater than the charging voltage of the local storage battery pack, for example, when the nominal voltage of the storage battery pack is 48V and the charging voltage is 55V, the third voltage is 56.5V. At the moment, in the power supply system of the base station, the UPS module supplies power to the communication equipment load, and meanwhile, the UPS module also charges the storage battery pack, so that redundant electric energy of a power grid is consumed.
In the power load off-peak period, the platform server also sends a second instruction to the main controllers of all base station power supply systems which do not conform to the third preset condition, so that the UPS power supply module supplies power to the communication equipment load in the corresponding base station power supply system, and the storage battery pack is in an unfilled state.
In the virtual power station implementation of demand-side response, the steps S12 and S13 may be executed alternately or at intervals according to the peak time and the valley time of the power load, and the step S11 may be executed synchronously during the execution of the steps S11 and S12. The virtual power station implementation method utilizes the virtual private network to communicate with base station power supply systems of all communication base stations in the same region, and utilizes the reserve storage battery energy of the communication base stations to supply power to communication loads at peak time of regional power loads, thereby reducing or not using electric energy of a power grid and realizing the effect of reducing load of the power grid. And because the corresponding instruction is generated by the platform server, the operation is only needed on the platform server when the control strategy is adjusted, and the operation on the base station power supply system of each communication base station is not needed, so that the system maintenance process is greatly simplified.
In one embodiment of the present invention, to further balance the influence of the communication base stations on the grid load, the peak time of the power load may be divided into M preset time periods, and meanwhile, the communication base stations meeting the first preset condition are divided into M groups, where M is an integer greater than or equal to 2. Accordingly, in step S12, when the platform server sends the first instruction to the master controllers of all the base station power supply systems meeting the first preset condition, the platform server may send the first instruction to the M groups of the master controllers of the base station power supply systems meeting the first preset condition in sequence in M preset time periods, and send the first instruction only to one group of the master controllers of the base station power supply systems meeting the first preset condition in each preset time period, so as to discharge the storage battery packs of the base station power supply systems in the virtual private network in batches.
Specifically, M may determine the durations of the M preset periods according to the duration of the peak period of the power load and the duration of the discharging of the storage battery pack in the communication base station from the full-power state to the preset depth of discharge. For example, when the duration of the peak period of the power load is 3 hours, and the duration of the discharge of the storage battery pack in the communication base station from the full state to the preset discharge depth is 1.5 hours, M may be 2. When 100 communication base stations are included in the virtual private network, the battery pack of 50 communication base stations can be discharged by the first instruction in the first 1.5 hours of the power load peak period; and at the last 1.5 hours of the peak period of the power load, the battery packs in the other 50 communication base stations are discharged by the first instruction.
Of course, in practical applications, the value of M and the number of base station power supply systems receiving the first instruction in each group may be determined according to the number of base station power supply systems in the virtual private network.
Similarly, the power load valley period may be divided into M preset periods, and correspondingly, in step S13, when the platform server sends the third instruction to the main controllers of all the base station power supply systems meeting the third preset condition, the platform server may also send the third instruction to the main controllers of M groups of base station power supply systems meeting the third preset condition in sequence in the M preset periods, and send the third instruction only to the main controllers of one group of base station power supply systems meeting the third preset condition in each preset period, so that the storage battery packs of the base station power supply systems in the virtual private network are charged in batches, and the communication base stations are prevented from being charged at the same time to cause impact on the power grid.
In one embodiment of the present invention, as illustrated in connection with fig. 2, the electrical load peak periods and the electrical load valley periods may be generated by:
step S15: calculating the mean power according to a power load curve issued by power grid dispatching, wherein the power load curve is received from an external power management system;
step S16: and taking a time period in the power load curve larger than the average power as a power load peak time period, and taking a time period in the power load curve smaller than or equal to the average power as a power load valley time period.
In the power grid power utilization scheduling management, a power department sends a power load response curve of a certain area to a power utilization unit in advance through a power management system, so that the power utilization unit is encouraged to close part of the power loads in the peak period of the power loads, namely the power loads are disengaged hard, economic compensation is given, and the power utilization unit is encouraged to use more power in the low peak period of the power loads, so that the load is contributed to a power grid, and the power grid electric energy is absorbed. According to the embodiment, the peak time and the valley time of the power load are automatically calculated and generated directly according to the power load curve from the power department, so that the automatic adjustment of the peak time and the valley time of the power load can be realized, the power load of a power distribution network can be better matched, and meanwhile, the manual operation is reduced.
In another embodiment of the present invention, in step S12, the first instruction is sent to the main controller of all base station power supply systems meeting the first preset condition, the number of communication base stations receiving the first instruction and performing demand-side response may also be adjusted according to the change of the power load curve, and the information of the number of communication base stations performing demand-side response and the total power sum is sent to the power scheduling system, so that the power scheduling system is facilitated to allocate power. That is, the durations of the M preset time periods may be different, and the number of the base station power supply systems (meeting the first preset condition) that each group receives the first command at the same time may be different. For example, the time when the electrical load exceeds the average power by less than 20%, and the time when the electrical load exceeds the average power by more than 20% may be respectively used as two preset time periods, and accordingly, the number of the base station power supply systems receiving the first instruction is larger in the preset time period corresponding to the time when the electrical load exceeds the average power by 20%. For example, when the virtual private network includes 100 communication base stations, a first instruction is sent to a base station power supply system of 70 communication base stations in a preset time period corresponding to the power load exceeding the average power by 20%; and sending a first instruction to the base station power supply systems of the other 30 communication base stations in a preset time period corresponding to the power utilization load not exceeding 20% of the average power, so as to balance the power grid load.
In an embodiment of the present invention, the method for implementing a demand-side responsive virtual power station includes, in addition to steps S11-S13: and establishing the reference ampere-hour capacity of each base station power supply system according to the battery state data received from each base station power supply system, wherein the reference ampere-hour capacity of the base station power supply system is the minimum value of the ampere-hour capacity in the single battery of the storage battery pack of the base station power supply system. This step may be performed at full battery pack conditions for all base station power supply systems, for example at the end of each power load valley period.
Accordingly, the first preset condition in step S12 includes: the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is 0.8 times larger than the reference ampere-hour capacity. The second preset condition includes: the real-time ampere-hour capacity of the storage battery pack of the base station power supply system is less than or equal to 80% of the reference ampere-hour capacity, or the storage battery pack of the base station power supply system discharges to reach a preset discharge depth (for example, 60%).
The third preset condition in step S13 includes: the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is smaller than the reference ampere-hour capacity.
For regions where peak to valley electricity prices are present, the method further comprises: and establishing the reference ampere-hour capacity of each base station power supply system according to the battery state data received from each base station power supply system, wherein the reference ampere-hour capacity of the base station power supply system is the minimum value of the ampere-hour capacity in the single battery.
Accordingly, the first preset condition in step S12 includes: the current time is in peak price time, and the real-time ampere-hour capacity of a storage battery pack of a base station power supply system is greater than 0.8 time of the reference ampere-hour capacity; the second preset condition includes: when the current time is in the non-peak time, the real-time ampere-hour capacity of the storage battery pack of the base station power supply system is less than or equal to 80% of the reference ampere-hour capacity, or the storage battery pack of the base station power supply system discharges to reach the preset discharge depth.
The third preset condition in step S13 includes: the current time is at the valley price time and the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is smaller than the reference ampere-hour capacity.
In addition, as a further improvement of the present invention, the method of the present invention further comprises:
recording the discharge duration t of each base station power supply system in a preset perioddAnd a time period t of chargingcThe base station power supply system discharges when the local UPS power module outputs a first voltage (namely, the storage battery pack discharges), and charges when the local UPS power module outputs a third voltage (namely, the storage battery pack charges);
calculating the energy-saving electric charge of the virtual power station responded by the demand side according to a preset period:
Figure 536251DEST_PATH_IMAGE001
wherein n is the number of base station power supply systems in the virtual power station, MzFor energy-saving electricity charges of the virtual power station, MiFElectric charge at peak price time for the power supply system of the ith base station, and MiF=PiF×td×Yd,PiFFor the ith base stationReal time power at discharge, YdA unit price of electricity rate which is a peak price time; miGElectricity charge at the valley time for the power supply system of the ith base station, and MiG=PiG×tc×Yc,PiGReal-time power during charging, Y, for the ith base station power supply systemcA unit price of electricity rate which is a valley price time; miBCompensating electricity charges for the power supply system of the ith base station, and MiB=PiF×td×Yf,YfThe unit price of the electricity fee is compensated for the demand side response of the peak price time. The unit price of the electric power rate at the peak rate time, the unit price of the electric power rate at the valley rate time, and the unit price of the demand-side response compensation electric power rate at the peak rate time are provided by the power supply institution or the relevant power management department.
In practical applications, the preset period may be 24 hours.
With reference to fig. 3-4, the present invention further provides a virtual power station implementation system for demand-side response, which includes a VPN server 32 for maintaining a virtual private network, a plurality of base station power supply systems 31 respectively accessing the virtual private network, and a platform server 33 accessing the virtual private network, each base station power supply system includes a main controller 311, a UPS power module 312, a battery pack 313, and a monitoring module 314, wherein a dc output terminal of the UPS power module 312 and an output terminal of the battery pack are connected in parallel to a power consumption terminal of a communication device load 315 in a communication base station, and the monitoring module 314 is configured to monitor a state of the battery pack 313. Specifically, the battery pack 313 may be constructed of a plurality of valve-regulated lead acid battery cells having a nominal voltage of 2.0V.
The virtual private network in this embodiment may be established on a public Internet network, and by configuring the VPN server 32, the virtual private network is established to cover the base station power supply system of all communication base stations in the local power area, so as to implement a data communication link network of energy storage aggregation of the base station power supply system, and ensure the data communication safety of the system. The UPS power module 312 in each base station power supply system needs to have an open regulation communication protocol and a serial communication interface, so that the main controller 311 can control the operation thereof.
In order not to affect the operation safety of the communication base station, the actual ampere-hour capacity of the battery pack 313 in the base station power supply system 31 must reach more than 80% of the rated ampere-hour capacity C in the full charge state, and the monitoring module 314 is used for monitoring the real-time state of the battery pack, including voltage and current, so as to measure the ampere-hour capacity. The monitoring module has a serial communication function and performs serial communication with the main controller 311. The main controller 311 has a communication interface of the LAN and a GPRS wireless communication module of 4G or more, the main controller 311 of each base station power supply system has a unique fixed IP address, and the VPN server 32 maintains the base station power supply system in the virtual private network by using the fixed IP address.
The platform server 33 receives battery status data from each base station power supply system 31 accessed to the virtual private network, and the base station power supply system accesses the virtual private network through the main controller 311.
The platform server 33 sends a first instruction to the main controller of all base station power supply systems meeting a first preset condition during the peak time of the power load, where the first instruction is used for enabling the main controller to control the local UPS power module to output a first voltage, and the first voltage is less than or equal to the nominal voltage of the local storage battery; sending a second instruction to a main controller of all base station power supply systems meeting a second preset condition, wherein the second instruction is used for enabling the main controller to control a local UPS power module to output a second voltage, and the second voltage is greater than the nominal voltage of a local storage battery pack and smaller than the charging voltage of the local storage battery pack;
the platform server 33 further sends a third instruction to the main controller of all base station power supply systems meeting a third preset condition in the low-valley period of the power load, where the third instruction is used for enabling the main controller to control a local UPS power module to output a third voltage, and the third voltage is greater than the charging voltage of a local storage battery; and sending a second instruction to all the main controllers of the base station power supply systems which do not meet the third preset condition.
The virtual power station implementation system in this embodiment and the virtual power station implementation method in the embodiment corresponding to fig. 1-2 belong to the same concept, and specific implementation processes thereof are detailed in the corresponding method embodiments, and technical features in the method embodiments are correspondingly applicable in this device embodiment, which is not described herein again.
An embodiment of the present invention further provides a computer device, such as the platform server 33 in fig. 3. The computer device of the embodiment includes a memory and a processor, wherein the memory stores a computer program executable in the processor, and the processor executes the computer program to implement the steps of the virtual power station implementation method for demand side response as described in the embodiments of fig. 1-2.
The computer device in this embodiment and the virtual power station implementation method in the embodiment corresponding to fig. 1-2 belong to the same concept, and specific implementation processes thereof are described in detail in the corresponding method embodiments, and technical features in the method embodiments are correspondingly applicable in this device embodiment, and are not described herein again.
One embodiment of the present invention provides a computer-readable storage medium having stored thereon computer-executable instructions for causing a computer to perform the virtual power plant implementation of demand-side responses method as described above.
The computer-readable storage medium in this embodiment and the virtual power station implementation method in the embodiment corresponding to fig. 1-2 belong to the same concept, and specific implementation processes thereof are detailed in the corresponding method embodiments, and technical features in the method embodiments are correspondingly applicable in this storage medium embodiment, which is not described herein again.
It should be understood that, the sequence numbers of the steps in the foregoing embodiments do not imply an execution sequence, and the execution sequence of each process should be determined by its function and inherent logic, and should not constitute any limitation to the implementation process of the embodiments of the present application.
In the above embodiments, the descriptions of the respective embodiments have respective emphasis, and reference may be made to the related descriptions of other embodiments for parts that are not described or illustrated in a certain embodiment.
Those of ordinary skill in the art will appreciate that the various illustrative elements and algorithm steps described in connection with the embodiments disclosed herein may be implemented as electronic hardware or combinations of computer software and electronic hardware. Whether such functionality is implemented as hardware or software depends upon the particular application and design constraints imposed on the implementation. Skilled artisans may implement the described functionality in varying ways for each particular application, but such implementation decisions should not be interpreted as causing a departure from the scope of the present application.
In the embodiments provided in the present application, it should be understood that the disclosed virtual power station implementation system of demand side response, and computer device, may be implemented in other ways.
All or part of the flow in the method of the embodiments may be implemented by a computer program, which may be stored in a computer readable storage medium and executed by a processor, to instruct related hardware to implement the steps of the embodiments of the methods. Wherein the computer program comprises computer program code, which may be in the form of source code, object code, an executable file or some intermediate form, etc. The computer-readable medium may include: any physical or interface switching device, recording medium, usb disk, removable hard disk, magnetic disk, optical disk, computer Memory, Read-Only Memory (ROM), Random Access Memory (RAM), electrical carrier wave signal, telecommunication signal, software distribution medium, etc., capable of carrying said computer program code. It should be noted that the computer readable medium may contain other components which may be suitably increased or decreased as required by legislation and patent practice in jurisdictions, for example, in some jurisdictions, computer readable media which may not include electrical carrier signals and telecommunications signals in accordance with legislation and patent practice.
The embodiments of the present invention have been described in detail with reference to the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge of those skilled in the art without departing from the gist of the present invention. Furthermore, the embodiments of the present invention and the features of the embodiments may be combined with each other without conflict.

Claims (8)

1. A virtual power station implementation method for demand side response is characterized by comprising the following steps:
receiving battery state data from each base station power supply system accessed to a virtual private network, wherein each base station power supply system comprises a main controller, a UPS (uninterrupted power supply) module, a storage battery pack and a monitoring module, and the base station power supply system is accessed to the virtual private network through the main controller;
sending a first instruction to a main controller of all base station power supply systems meeting a first preset condition in a power load peak period, wherein the first instruction is used for enabling the main controller to control a local UPS power module to output a first voltage, and the first voltage is smaller than or equal to the nominal voltage of a local storage battery pack; sending a second instruction to a main controller of all base station power supply systems meeting a second preset condition, wherein the second instruction is used for enabling the main controller to control a local UPS power module to output a second voltage, and the second voltage is larger than the nominal voltage of a local storage battery pack and smaller than the charging voltage of the local storage battery pack;
in a power load valley period, sending a third instruction to a main controller of all base station power supply systems meeting a third preset condition, wherein the third instruction is used for enabling the main controller to control a local UPS power module to output a third voltage, and the third voltage is greater than the charging voltage of a local storage battery pack; sending a second instruction to all the main controllers of the base station power supply systems which do not accord with the third preset condition;
the method further comprises the following steps: establishing a reference ampere-hour capacity of each base station power supply system according to battery state data received from each base station power supply system, wherein the battery state data comprise the ampere-hour capacity of each single battery in a storage battery pack of the base station power supply system, and the reference ampere-hour capacity of the base station power supply system is the minimum value of the ampere-hour capacity of each single battery;
the first preset condition includes: the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is 0.8 times larger than the reference ampere-hour capacity; the second preset condition includes: the real-time ampere-hour capacity of the storage battery pack of the base station power supply system is less than or equal to 80% of the reference ampere-hour capacity, or the storage battery pack of the base station power supply system discharges to reach a preset discharge depth; the third preset condition includes: the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is smaller than the reference ampere-hour capacity; alternatively, the first and second electrodes may be,
the first preset condition includes: the current time is in peak price time, and the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is greater than 0.8 time of the reference ampere-hour capacity; the second preset condition includes: when the current time is in non-peak time, the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is less than or equal to 80% of the reference ampere-hour capacity, or the storage battery pack of the base station power supply system discharges to reach a preset discharge depth; the third preset condition includes: the current time is at the valley price time and the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is smaller than the reference ampere-hour capacity.
2. The method as claimed in claim 1, wherein the peak period of the power load is formed by M preset periods, the communication base stations meeting the first preset condition are divided into M groups, and M is an integer greater than or equal to 2;
the sending of the first instruction to the main controllers of all the base station power supply systems meeting the first preset condition includes:
and at the M preset time intervals, sequentially sending first instructions to M groups of main controllers of the base station power supply systems meeting the first preset condition, and only sending the first instructions to a group of main controllers of the base station power supply systems meeting the first preset condition at each preset time interval.
3. The demand side responsive virtual power plant implementation method of claim 1, further comprising:
calculating the mean power according to a power load curve issued by power grid dispatching, wherein the power load curve is received from an external power dispatching management system;
the time period in the power load curve greater than the mean power is taken as a power load peak period, and the time period in the power load curve less than or equal to the mean power is taken as a power load valley period.
4. The method for implementing the demand side response virtual power station as claimed in claim 3, wherein the sending the first command to the master controller of all the base station power supply systems meeting the first preset condition includes:
and adjusting the number of the communication base stations which receive the first instruction and perform demand side response according to the change of the power load curve, and sending the number of the communication base stations which perform demand side response and the total power information to a power dispatching system.
5. The demand side responsive virtual power plant implementation method of claim 1, further comprising:
recording the discharge duration t of each base station power supply system in a preset perioddAnd a time period t of chargingcThe base station power supply system discharges when the local UPS power module outputs a first voltage and charges when the local UPS power module outputs a third voltage;
calculating the energy-saving electric charge of the virtual power station responded by the demand side according to a preset period:
Figure 11028DEST_PATH_IMAGE001
wherein n is the number of base station power supply systems in the virtual power station, MzFor energy-saving electricity charges of the virtual power station, MiFElectric charge at peak price time for the power supply system of the ith base station, and MiF=PiF×td×Yd,PiFReal-time power at discharge, Y, for the ith base station power supply systemdA unit price of electricity rate which is a peak price time; miGElectricity charge at the valley time for the power supply system of the ith base station, and MiG=PiG×tc×Yc,PiGReal-time power during charging, Y, for the ith base station power supply systemcA unit price of electricity rate which is a valley price time; miBCompensating electricity charges for the power supply system of the ith base station, and MiB=PiF×td×Yf,YfThe unit price of the electricity fee is compensated for the demand side response of the peak price time.
6. A virtual power station implementation system with demand side response is characterized by comprising a VPN server for maintaining a virtual private network, a plurality of base station power supply systems respectively accessed to the virtual private network, and a platform server accessed to the virtual private network, wherein each base station power supply system comprises a main controller, a UPS power module, a storage battery pack and a monitoring module;
the platform server receives battery state data from each base station power supply system accessed to a virtual private network, and the base station power supply system is accessed to the virtual private network through the main controller;
the platform server sends a first instruction to a main controller of all base station power supply systems meeting a first preset condition in a power load peak period, wherein the first instruction is used for enabling the main controller to control a local UPS power module to output a first voltage, and the first voltage is smaller than or equal to the nominal voltage of a local storage battery pack; sending a second instruction to a main controller of all base station power supply systems meeting a second preset condition, wherein the second instruction is used for enabling the main controller to control a local UPS power module to output a second voltage, and the second voltage is larger than the nominal voltage of a local storage battery pack and smaller than the charging voltage of the local storage battery pack;
the platform server sends a third instruction to all base station power supply system main controllers meeting a third preset condition in a power load valley period, wherein the third instruction is used for enabling the main controllers to control local UPS power modules to output a third voltage, and the third voltage is larger than the charging voltage of local storage battery packs; sending a second instruction to all the main controllers of the base station power supply systems which do not accord with the third preset condition;
the first preset condition includes: the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is 0.8 times larger than the reference ampere-hour capacity; the second preset condition includes: the real-time ampere-hour capacity of the storage battery pack of the base station power supply system is less than or equal to 80% of the reference ampere-hour capacity, or the storage battery pack of the base station power supply system discharges to reach a preset discharge depth; the third preset condition includes: the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is smaller than the reference ampere-hour capacity; alternatively, the first and second electrodes may be,
the first preset condition includes: the current time is in peak price time, and the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is greater than 0.8 time of the reference ampere-hour capacity; the second preset condition includes: when the current time is in non-peak time, the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is less than or equal to 80% of the reference ampere-hour capacity, or the storage battery pack of the base station power supply system discharges to reach a preset discharge depth; the third preset condition includes: the current time is at the valley price time and the real-time ampere-hour capacity of a storage battery pack of the base station power supply system is smaller than the reference ampere-hour capacity.
7. Computer device comprising a memory and a processor, characterized in that said memory has stored therein a computer program executable in said processor, and that said processor, when executing said computer program, implements the steps of the virtual power plant implementation method of demand side response according to any of the claims 1 to 5.
8. A computer readable storage medium storing computer executable instructions for causing a computer to perform the steps of the demand side responsive virtual power plant implementing method of any one of claims 1 to 5.
CN202110622326.8A 2021-06-04 2021-06-04 Method, system, equipment and storage medium for realizing demand side response virtual power station Active CN113078668B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110622326.8A CN113078668B (en) 2021-06-04 2021-06-04 Method, system, equipment and storage medium for realizing demand side response virtual power station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110622326.8A CN113078668B (en) 2021-06-04 2021-06-04 Method, system, equipment and storage medium for realizing demand side response virtual power station

Publications (2)

Publication Number Publication Date
CN113078668A CN113078668A (en) 2021-07-06
CN113078668B true CN113078668B (en) 2021-09-03

Family

ID=76617064

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110622326.8A Active CN113078668B (en) 2021-06-04 2021-06-04 Method, system, equipment and storage medium for realizing demand side response virtual power station

Country Status (1)

Country Link
CN (1) CN113078668B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116979514B (en) * 2023-07-20 2024-05-03 一能充电科技(深圳)股份有限公司 Intelligent regulation and control system for power consumption

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000316239A (en) * 1999-04-28 2000-11-14 Nec Corp Uninterruptible power supply and power supply control method for the uninterruptible power supply
EP2299557A2 (en) * 2009-09-18 2011-03-23 Renesas Electronics Corporation Power supply cooperation system and uninterruptible power supply device
CN204118757U (en) * 2014-10-22 2015-01-21 中塔新兴通讯技术有限公司 A kind of communication power supply peak load shifting system of online quick charge
CN104466994A (en) * 2013-09-12 2015-03-25 中国电信股份有限公司 Peak-load-shifting energy storage system of communication power supply
CN107332266A (en) * 2017-08-25 2017-11-07 浙江南都电源动力股份有限公司 User side energy-accumulating power station and its application model
CN207098631U (en) * 2017-08-14 2018-03-13 柳州紫荆循环能源科技有限公司 The energy management device of communication base station lead-acid accumulator
CN109193724A (en) * 2018-10-11 2019-01-11 福建星云电子股份有限公司 A kind of intelligent base station standby energy storage power and control method
CN208369223U (en) * 2018-03-15 2019-01-11 深圳市普禄科智能检测设备有限公司 Backup battery energy storage discharge control system
CN109193723A (en) * 2018-10-11 2019-01-11 福建星云电子股份有限公司 A kind of knockdown base station standby energy storage power and control method
CN109286198A (en) * 2018-10-29 2019-01-29 深圳市伊力科电源有限公司 UPS energy storage control method and system
CN109560545A (en) * 2018-12-10 2019-04-02 湖南丰日电源电气股份有限公司 A kind of energy storage battery system applied to the standby electricity service of communications equipment room and standby method for electrically
CN211266576U (en) * 2019-11-18 2020-08-14 上海国动网络通信有限公司 Energy-saving power supply system for communication base station

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000316239A (en) * 1999-04-28 2000-11-14 Nec Corp Uninterruptible power supply and power supply control method for the uninterruptible power supply
EP2299557A2 (en) * 2009-09-18 2011-03-23 Renesas Electronics Corporation Power supply cooperation system and uninterruptible power supply device
CN104466994A (en) * 2013-09-12 2015-03-25 中国电信股份有限公司 Peak-load-shifting energy storage system of communication power supply
CN204118757U (en) * 2014-10-22 2015-01-21 中塔新兴通讯技术有限公司 A kind of communication power supply peak load shifting system of online quick charge
CN207098631U (en) * 2017-08-14 2018-03-13 柳州紫荆循环能源科技有限公司 The energy management device of communication base station lead-acid accumulator
CN107332266A (en) * 2017-08-25 2017-11-07 浙江南都电源动力股份有限公司 User side energy-accumulating power station and its application model
CN208369223U (en) * 2018-03-15 2019-01-11 深圳市普禄科智能检测设备有限公司 Backup battery energy storage discharge control system
CN109193724A (en) * 2018-10-11 2019-01-11 福建星云电子股份有限公司 A kind of intelligent base station standby energy storage power and control method
CN109193723A (en) * 2018-10-11 2019-01-11 福建星云电子股份有限公司 A kind of knockdown base station standby energy storage power and control method
CN109286198A (en) * 2018-10-29 2019-01-29 深圳市伊力科电源有限公司 UPS energy storage control method and system
CN109560545A (en) * 2018-12-10 2019-04-02 湖南丰日电源电气股份有限公司 A kind of energy storage battery system applied to the standby electricity service of communications equipment room and standby method for electrically
CN211266576U (en) * 2019-11-18 2020-08-14 上海国动网络通信有限公司 Energy-saving power supply system for communication base station

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
Optimal scheduling of energy storage system for self-sustainable base station operation considering battery wear-out cost;Yohwan Choi;Hongseok Kim;《2016 Eighth International Conference on Ubiquitous and Future Networks (ICUFN)》;20161231;全文 *
考虑需求侧响应的虚拟电厂优化调度;高明 等;《电力科学与工程》;20201128;全文 *

Also Published As

Publication number Publication date
CN113078668A (en) 2021-07-06

Similar Documents

Publication Publication Date Title
CN109301849B (en) Energy management combination control strategy for user-side battery energy storage power station
US20210044146A1 (en) Energy internet system, energy routing conversion device, and energy control method
CN110429624B (en) Energy storage capacity configuration method applied to data center energy storage system
EP4194257A1 (en) Power control method and system for battery charging and swap station, medium, apparatus, and battery charging and swap station
CN109193723B (en) Combined base station backup energy storage power supply and control method
CN113193582A (en) High-efficiency charging and discharging energy storage control method and system
US20230173940A1 (en) Power control method and system for battery charging and swap station, medium, apparatus, and battery charging and swap station
CN113557647A (en) Grid edge controller for uninterruptible power supplies and method of operating the same
CN207234517U (en) A kind of storage battery parallel power supply system based on straight-flow system
CN113078668B (en) Method, system, equipment and storage medium for realizing demand side response virtual power station
CN114844078A (en) Method, device and system for scheduling electric energy in battery replacement station and battery replacement station
JP2023535099A (en) Charging and discharging device, battery charging and discharging method, and charging and discharging system
CN109193724B (en) Intelligent base station backup energy storage power supply and control method
CN112467774B (en) Energy storage system control method and device based on global energy efficiency optimization and SOC self-adaption
CN115027316A (en) Energy storage and charging integrated battery replacement station and energy storage and charging battery replacement system
CN113452049A (en) Communication base station electric energy adjusting method, system, control equipment and storage medium
Akel et al. Dual-purposing telecom backup systems for cloud energy storage and grid ancillary services
JP2021005985A (en) Dc power network
CN211151596U (en) Multithreading-based energy distribution system
CN116072998B (en) Communication method, device, system, equipment, medium and product of energy storage system
CN217159298U (en) Battery pack charging and discharging active equalization device
CN117200282B (en) Flywheel energy storage array control method, system, array and storage medium
JP7450645B2 (en) Battery charging method and charging/discharging device
CN210244565U (en) Moving ring monitoring FSU device
CN114614556A (en) Controller for uninterruptible power supply and method of operating the same

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant