CN113054633B - Time-limited current quick-break protection fixed value optimization method for power distribution network access of energy storage power station - Google Patents

Time-limited current quick-break protection fixed value optimization method for power distribution network access of energy storage power station Download PDF

Info

Publication number
CN113054633B
CN113054633B CN201911383387.2A CN201911383387A CN113054633B CN 113054633 B CN113054633 B CN 113054633B CN 201911383387 A CN201911383387 A CN 201911383387A CN 113054633 B CN113054633 B CN 113054633B
Authority
CN
China
Prior art keywords
current
energy storage
power station
storage power
short
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201911383387.2A
Other languages
Chinese (zh)
Other versions
CN113054633A (en
Inventor
王宝华
邓雨捷
蒋海峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing University of Science and Technology
Original Assignee
Nanjing University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing University of Science and Technology filed Critical Nanjing University of Science and Technology
Priority to CN201911383387.2A priority Critical patent/CN113054633B/en
Publication of CN113054633A publication Critical patent/CN113054633A/en
Application granted granted Critical
Publication of CN113054633B publication Critical patent/CN113054633B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H7/00Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
    • H02H7/26Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured
    • H02H7/28Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured for meshed systems
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H1/00Details of emergency protective circuit arrangements
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H3/00Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection
    • H02H3/006Calibration or setting of parameters

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Marketing (AREA)
  • Game Theory and Decision Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Development Economics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

本发明公开了一种储能电站接入配电网的限时电流速断保护定值优化方法。该方法为:首先定义临界电流、最远短路电流、达标电流,根据配电网参数及储能电站输出电流的最大限制值计算临界电流;然后比较临界电流与最远短路电流的大小关系,判断储能电站输出短路电流是否达到最大电流限制;最后根据储能电站输出短路电流是否达限,确定优化因子α,对储能电站接入点上游线路的限时电流速断保护定值进行优化。本发明无需限制储能电站的接入容量和接入位置,能够在储能电站充电、备用、放电三种工作状态下进行动作,适用性强、可靠性高。

Figure 201911383387

The invention discloses a method for optimizing the setting value of time-limited current quick-break protection for an energy storage power station connected to a distribution network. The method is as follows: first, define the critical current, the farthest short-circuit current and the up-to-standard current, and calculate the critical current according to the parameters of the distribution network and the maximum limit value of the output current of the energy storage power station; then compare the magnitude relationship between the critical current and the farthest short-circuit current to determine Whether the output short-circuit current of the energy storage power station reaches the maximum current limit; finally, according to whether the output short-circuit current of the energy storage power station reaches the limit, the optimization factor α is determined, and the time-limited current quick-break protection setting of the upstream line of the energy storage power station access point is optimized. The invention does not need to limit the access capacity and the access position of the energy storage power station, can operate in the three working states of charging, standby and discharge of the energy storage power station, and has strong applicability and high reliability.

Figure 201911383387

Description

储能电站接入配电网的限时电流速断保护定值优化方法Optimization method of time-limited current quick-break protection setting value for energy storage power station connected to distribution network

技术领域technical field

本发明属于配电自动化领域,特别是一种储能电站接入配电网的限时电流速断保护 定值优化方法。The invention belongs to the field of distribution automation, in particular to a fixed value optimization method for time-limited current quick-break protection of an energy storage power station connected to a distribution network.

背景技术Background technique

随着电力系统的不断发展,能源问题也不断突出,可再生能源以分布式电源的形式 逐渐推广应用,在改善了电力能源产业结构的同时也改变了传统电力系统集中式供电的 格局。但无论是以大容量、高参数机组发电,通过超高压、远距离输电形成大电网供电的传统电力生产模式供电,还是容量较小、分布较为分散的新兴可再生能源模式供电, 都离不开与储能系统的配合。With the continuous development of the power system, energy problems are also becoming more and more prominent. The renewable energy is gradually popularized and applied in the form of distributed power sources, which not only improves the power energy industry structure, but also changes the centralized power supply pattern of the traditional power system. However, whether it is powered by large-capacity, high-parameter units, the traditional power production mode that forms a large grid power supply through ultra-high voltage and long-distance power transmission, or the emerging renewable energy mode with smaller capacity and more dispersed distribution, it is inseparable from the power supply. Cooperate with energy storage system.

储能系统的典型应用场景包括集中式新能源+储能系统、电源侧调频储能、电网侧储能、分布式及微网储能以及用户侧应用。近年来,储能电站因其削峰填谷、提高供电 稳定性等作用,在配电系统中的应用越来越广泛,丰富了配电网的供电结构的同时也给 配电网的安全运行带来了新的问题。Typical application scenarios of energy storage systems include centralized new energy + energy storage systems, power-side frequency modulation energy storage, grid-side energy storage, distributed and micro-grid energy storage, and user-side applications. In recent years, energy storage power stations have become more and more widely used in power distribution systems due to their functions such as shaving peaks and filling valleys and improving power supply stability. brings new problems.

配电网的继电保护是以配电网的放射性结构、单电源供电的特点为基础而设计的, 以三段式电流保护为主,储能电站的接入使得配电网由单电源供电变为多电源供电,而 储能电站又区别于常规电源,其故障特性受其控制策略影响极大,特别对于储能电站接入点上游线路的限时电流速断保护定值整定而言,如果采用常规的定值整定方式,会导 致保护的灵敏度降低,出现拒动现象,威胁配电网的供电安全。The relay protection of the distribution network is designed based on the radioactive structure of the distribution network and the characteristics of a single power supply. It is mainly based on three-stage current protection. It becomes a multi-power supply, and the energy storage power station is different from the conventional power supply. Its fault characteristics are greatly affected by its control strategy, especially for the setting of the time-limited current quick-break protection setting of the upstream line of the energy storage power station access point. The conventional fixed value setting method will lead to the reduction of the sensitivity of the protection, and the phenomenon of refusal to operate, which threatens the power supply security of the distribution network.

发明内容SUMMARY OF THE INVENTION

本发明目的在于提供一种适用性强、可靠性高的储能电站接入配电网的限时电流速 断保护定值优化方法。The purpose of the present invention is to provide a time-limited current quick-break protection setting optimization method for an energy storage power station with strong applicability and high reliability connected to a distribution network.

实现本发明目的的技术解决方案为:一种储能电站接入配电网的限时电流速断保护 定值优化方法,包括以下步骤:The technical solution for realizing the purpose of the present invention is: a method for optimizing the fixed value of time-limited current quick-break protection for an energy storage power station connected to a distribution network, comprising the following steps:

步骤1、构建储能电站等效模型,定义临界电流、最远短路电流、达标电流,根 据配电网参数及储能电站输出电流的最大限制值计算临界电流;Step 1. Construct the equivalent model of the energy storage power station, define the critical current, the farthest short-circuit current, and the up-to-standard current, and calculate the critical current according to the distribution network parameters and the maximum limit value of the output current of the energy storage power station;

步骤2、比较临界电流与最远短路电流的大小关系,判断储能电站输出短路电流是否达到最大电流限制;Step 2. Compare the magnitude relationship between the critical current and the farthest short-circuit current, and determine whether the output short-circuit current of the energy storage power station reaches the maximum current limit;

步骤3、根据储能电站输出短路电流是否达限,确定优化因子α,对储能电站接 入点上游线路的限时电流速断保护定值进行优化。Step 3. Determine the optimization factor α according to whether the output short-circuit current of the energy storage power station reaches the limit, and optimize the time-limited current quick-break protection setting of the upstream line of the access point of the energy storage power station.

进一步地,步骤1中所述的构建储能电站等效模型,具体如下:Further, the construction of the equivalent model of the energy storage power station described in step 1 is as follows:

根据采用恒功率控制的储能电站控制策略及工作特性,建立储能电站等效模型为:According to the control strategy and working characteristics of the energy storage power station using constant power control, the equivalent model of the energy storage power station is established as follows:

Figure BDA0002342845540000021
Figure BDA0002342845540000021

式中,SN为储能电站额定功率,EG为储能电站出口相电压,IG为储能电站输出相 电流,IN为储能电站额定相电流。In the formula, SN is the rated power of the energy storage station, EG is the outlet phase voltage of the energy storage station, IG is the output phase current of the energy storage station, and I N is the rated phase current of the energy storage station.

进一步地,步骤1中所述的定义临界电流、最远短路电流、达标电流,具体如下:Further, the definition of critical current, farthest short-circuit current, and up-to-standard current described in step 1 is as follows:

临界电流的定义为:设定IN为储能电站额定电流,则储能电站输出电流恰好达到最 大电流限制时,即2倍额定电流2IN时流过储能电站接入点上游线路保护的电流,其计算式为:The definition of critical current is: set I N as the rated current of the energy storage power station, when the output current of the energy storage power station just reaches the maximum current limit, that is, when twice the rated current 2IN flows through the protection of the upstream line of the access point of the energy storage power station. current, which is calculated as:

Figure BDA0002342845540000022
Figure BDA0002342845540000022

式中,I1'为临界电流,E为储能电站额定相电压,ZS为系统电源阻抗,Z1为储能 电站接入点上游线路阻抗;In the formula, I 1 ' is the critical current, E is the rated phase voltage of the energy storage power station, Z S is the system power supply impedance, and Z 1 is the upstream line impedance of the energy storage power station access point;

最远短路电流的定义为:储能电站接入点上游线路的限时电流速断保护的保护范围 末端发生短路故障时,流过储能电站接入点上游线路保护的电流;The farthest short-circuit current is defined as: the protection range of the time-limited current quick-break protection of the upstream line of the energy storage power station access point When a short-circuit fault occurs at the end, the current flowing through the protection of the upstream line of the energy storage power station access point;

达标电流的定义为:限时电流速断保护灵敏度恰好满足要求时,储能电站接入点上 游线路限时电流速断保护的定值,其计算式为:The definition of up-to-standard current is: when the sensitivity of the time-limited current quick-break protection just meets the requirements, the fixed value of the time-limited current quick-break protection of the upstream line of the access point of the energy storage power station, and its calculation formula is:

Figure BDA0002342845540000023
Figure BDA0002342845540000023

式中,ID为达标电流,I1m为储能电站接入点上游线路末端两相短路时流过储能电站接入点上游线路保护的电流,Ksen为满足要求的灵敏度。In the formula, I D is the up-to-standard current, I 1m is the current flowing through the protection of the upstream line of the access point of the energy storage power station when the two-phase short-circuit at the end of the upstream line of the energy storage power station access point, and K sen is the sensitivity that meets the requirements.

进一步地,步骤2中所述的比较临界电流与最远短路电流的大小关系来判断储能电 站输出短路电流是否达到最大电流限制,具体如下:Further, the magnitude relation of the comparison critical current and the farthest short-circuit current described in step 2 judges whether the output short-circuit current of the energy storage power station reaches the maximum current limit, specifically as follows:

步骤2.1、定义k点为临界电流对应短路点,k点与储能电站接入点下游线路首端之间的阻抗计算式为:Step 2.1. Define point k as the short-circuit point corresponding to the critical current. The impedance calculation formula between point k and the head end of the downstream line of the access point of the energy storage power station is:

Figure BDA0002342845540000031
Figure BDA0002342845540000031

式中,Z2为储能电站接入点下游线路阻抗,β'为常数;In the formula, Z 2 is the downstream line impedance of the access point of the energy storage power station, and β' is a constant;

根据上式计算出β',若β'≥1,则储能电站输出电流必定达限;若β'<1,则进入步骤2.2;Calculate β' according to the above formula. If β'≥1, the output current of the energy storage power station must reach the limit; if β'<1, go to step 2.2;

步骤2.2、设定最远短路电流小于临界电流,则最远短路电流的计算式为:Step 2.2. Set the farthest short-circuit current to be less than the critical current, then the calculation formula of the farthest short-circuit current is:

Figure BDA0002342845540000032
Figure BDA0002342845540000032

上式中,I″1为最远短路电流,β为常数;In the above formula, I″ 1 is the farthest short-circuit current, and β is a constant;

将β'作为β代入上式计算出最远短路电流I″1,然后将最远短路电流I″1与临界电流I1' 进行比较,若仍满足I″1<I1',则储能电站输出电流未达限;若I″1≥I1',则储能电站输出 电流达限。Substitute β' as β into the above formula to calculate the farthest short-circuit current I″ 1 , and then compare the farthest short-circuit current I″ 1 with the critical current I 1 ′, if I″ 1 <I 1 ' is still satisfied, the energy storage The output current of the power station has not reached the limit; if I″ 1 ≥ I 1 ', the output current of the energy storage power station has reached the limit.

进一步地,步骤3所述的根据储能电站输出短路电流是否达限,确定优化因子α,对储能电站接入点上游线路的限时电流速断保护定值进行优化,具体如下:Further, according to step 3, according to whether the output short-circuit current of the energy storage power station reaches the limit, the optimization factor α is determined, and the time-limited current quick-break protection setting value of the upstream line of the access point of the energy storage power station is optimized, as follows:

步骤3.1、定义h点为达标电流对应短路点,则h点与储能电站接入点下游线路首端之间的阻抗计算式为:Step 3.1. Define point h as the short-circuit point corresponding to the up-to-standard current, then the impedance calculation formula between point h and the head end of the downstream line of the access point of the energy storage power station is:

Figure BDA0002342845540000033
Figure BDA0002342845540000033

式中,SN为储能电站额定容量,βD为常数;In the formula, S N is the rated capacity of the energy storage power station, and β D is a constant;

步骤3.2、根据储能电站输出电流是否达限,确定优化因子α,计算出储能电站接入点下游线路的电流速断保护定值:Step 3.2, according to whether the output current of the energy storage power station reaches the limit, determine the optimization factor α, and calculate the current quick-break protection setting value of the downstream line of the access point of the energy storage power station:

Figure BDA0002342845540000041
Figure BDA0002342845540000041

式中,

Figure BDA0002342845540000042
为储能电站接入点下游线路的电流速断保护定值,
Figure BDA0002342845540000043
为电流速断保护可靠系数;
Figure BDA0002342845540000044
为限时电流速断保护可靠系数;In the formula,
Figure BDA0002342845540000042
It is the setting value for the current quick-break protection of the downstream line of the access point of the energy storage power station.
Figure BDA0002342845540000043
is the reliability factor of current quick-break protection;
Figure BDA0002342845540000044
It is the reliability factor of time-limited current quick-break protection;

步骤3.3、对储能电站接入点上游线路的限时电流速断保护定值进行优化,公式为:Step 3.3, optimize the time-limited current quick-break protection setting of the upstream line of the access point of the energy storage power station, the formula is:

Figure BDA0002342845540000045
Figure BDA0002342845540000045

式中,

Figure BDA0002342845540000046
为储能电站接入点上游线路的限时电流速断保护定值。In the formula,
Figure BDA0002342845540000046
It is a fixed value for the time-limited current quick-break protection of the upstream line of the access point of the energy storage power station.

本发明与现有技术相比,其显著优点在于:(1)从修改保护定值的角度出发来进行保护方案的优化,不必因保护要求而限制储能电站的接入容量和接入位置,适用性强; (2)综合考虑了储能电站的控制策略和工作特性,构建了储能电站的等效模型,使得 改进后的保护在储能电站充电、备用、放电三种工作状态下都能可靠动作,可靠性高。Compared with the prior art, the present invention has significant advantages as follows: (1) the protection scheme is optimized from the perspective of modifying the protection setting, and it is not necessary to limit the access capacity and access position of the energy storage power station due to protection requirements; Strong applicability; (2) The control strategy and working characteristics of the energy storage power station are comprehensively considered, and the equivalent model of the energy storage power station is constructed, so that the improved protection can be used in the three working states of the energy storage power station: charging, standby and discharging. Reliable action and high reliability.

附图说明Description of drawings

图1为本发明储能电站接入配电网的限时电流速断保护定值优化方法的流程示意图。FIG. 1 is a schematic flow chart of the method for optimizing the setting value of the time-limited current quick-break protection for the connection of the energy storage power station to the distribution network according to the present invention.

图2为本发明中PQ控制的储能电站的整体结构框图。FIG. 2 is a block diagram of the overall structure of the PQ-controlled energy storage power station in the present invention.

图3为本发明中典型含储能电站的配电网的拓扑结构图。FIG. 3 is a topological structure diagram of a typical distribution network including an energy storage power station in the present invention.

图4为本发明中储能电站接入点下游线路短路时的等值电路图。FIG. 4 is an equivalent circuit diagram when the downstream line of the access point of the energy storage power station in the present invention is short-circuited.

图5为本发明中储能电站上游线路限时电流速断保护定值优化整体流程图。FIG. 5 is the overall flow chart of the optimization of the setting value of the time-limited current quick-break protection of the upstream line of the energy storage power station in the present invention.

具体实施方式Detailed ways

本发明储能电站接入配电网的限时电流速断保护定值优化方法,包括以下步骤:The time-limited current quick-break protection setting optimization method for an energy storage power station connected to a distribution network of the present invention includes the following steps:

步骤1、构建储能电站等效模型,定义临界电流、最远短路电流、达标电流,根 据配电网参数及储能电站输出电流的最大限制值计算临界电流;Step 1. Construct the equivalent model of the energy storage power station, define the critical current, the farthest short-circuit current, and the up-to-standard current, and calculate the critical current according to the distribution network parameters and the maximum limit value of the output current of the energy storage power station;

步骤2、比较临界电流与最远短路电流的大小关系,判断储能电站输出短路电流是否达到最大电流限制;Step 2. Compare the magnitude relationship between the critical current and the farthest short-circuit current, and determine whether the output short-circuit current of the energy storage power station reaches the maximum current limit;

步骤3、根据储能电站输出短路电流是否达限,确定优化因子α,对储能电站接 入点上游线路的限时电流速断保护定值进行优化。Step 3. Determine the optimization factor α according to whether the output short-circuit current of the energy storage power station reaches the limit, and optimize the time-limited current quick-break protection setting of the upstream line of the access point of the energy storage power station.

进一步地,步骤1中所述的构建储能电站等效模型,具体如下:Further, the construction of the equivalent model of the energy storage power station described in step 1 is as follows:

根据采用恒功率控制的储能电站控制策略及工作特性,建立储能电站等效模型为:According to the control strategy and working characteristics of the energy storage power station using constant power control, the equivalent model of the energy storage power station is established as follows:

Figure BDA0002342845540000051
Figure BDA0002342845540000051

式中,SN为储能电站额定功率,EG为储能电站出口相电压,IG为储能电站输出 相电流,IN为储能电站额定相电流。In the formula, SN is the rated power of the energy storage station, EG is the outlet phase voltage of the energy storage station, IG is the output phase current of the energy storage station, and I N is the rated phase current of the energy storage station.

进一步地,步骤1中所述的定义临界电流、最远短路电流、达标电流,具体如下:Further, the definition of critical current, farthest short-circuit current, and up-to-standard current described in step 1 is as follows:

临界电流的定义为:设定IN为储能电站额定电流,则储能电站输出电流恰好达到最 大电流限制时,即2倍额定电流2IN时流过储能电站接入点上游线路保护的电流,其计算式为:The definition of critical current is: set I N as the rated current of the energy storage power station, when the output current of the energy storage power station just reaches the maximum current limit, that is, when twice the rated current 2IN flows through the protection of the upstream line of the access point of the energy storage power station. current, which is calculated as:

Figure BDA0002342845540000052
Figure BDA0002342845540000052

式中,I1'为临界电流,E为储能电站额定相电压,ZS为系统电源阻抗,Z1为储能 电站接入点上游线路阻抗;In the formula, I 1 ' is the critical current, E is the rated phase voltage of the energy storage power station, Z S is the system power supply impedance, and Z 1 is the upstream line impedance of the energy storage power station access point;

最远短路电流的定义为:储能电站接入点上游线路的限时电流速断保护的保护范围 末端发生短路故障时,流过储能电站接入点上游线路保护的电流;The farthest short-circuit current is defined as: the protection range of the time-limited current quick-break protection of the upstream line of the energy storage power station access point When a short-circuit fault occurs at the end, the current flowing through the protection of the upstream line of the energy storage power station access point;

达标电流的定义为:限时电流速断保护灵敏度恰好满足要求时,储能电站接入点上 游线路限时电流速断保护的定值,其计算式为:The definition of up-to-standard current is: when the sensitivity of the time-limited current quick-break protection just meets the requirements, the fixed value of the time-limited current quick-break protection of the upstream line of the access point of the energy storage power station, and its calculation formula is:

Figure BDA0002342845540000053
Figure BDA0002342845540000053

式中,ID为达标电流,I1m为储能电站接入点上游线路末端两相短路时流过储能电站接入点上游线路保护的电流,Ksen为满足要求的灵敏度,取值为1.3。In the formula, I D is the current that reaches the standard, I 1m is the current flowing through the protection of the upstream line of the access point of the energy storage power station when the two-phase short-circuit at the end of the upstream line of the energy storage power station access point, K sen is the sensitivity that meets the requirements, and the value is 1.3.

进一步地,步骤2所述的比较临界电流与最远短路电流的大小关系,判断储能电站输出短路电流是否达到最大电流限制,具体如下:Further, comparing the magnitude relationship between the critical current and the farthest short-circuit current described in step 2, to determine whether the output short-circuit current of the energy storage power station reaches the maximum current limit, the details are as follows:

步骤2.1、定义k点为临界电流对应短路点,k点与储能电站接入点下游线路首端之间的阻抗计算式为:Step 2.1. Define point k as the short-circuit point corresponding to the critical current. The impedance calculation formula between point k and the head end of the downstream line of the access point of the energy storage power station is:

Figure BDA0002342845540000061
Figure BDA0002342845540000061

式中,Z2为储能电站接入点下游线路阻抗,β'为常数;In the formula, Z 2 is the downstream line impedance of the access point of the energy storage power station, and β' is a constant;

根据上式计算出β',若β'≥1,则储能电站输出电流必定达限;若β'<1,则进入步骤2.2;Calculate β' according to the above formula. If β'≥1, the output current of the energy storage power station must reach the limit; if β'<1, go to step 2.2;

步骤2.2、设定最远短路电流小于临界电流,则最远短路电流的计算式为:Step 2.2. Set the farthest short-circuit current to be less than the critical current, then the calculation formula of the farthest short-circuit current is:

Figure BDA0002342845540000062
Figure BDA0002342845540000062

式中,I″1为最远短路电流,β为常数;In the formula, I″ 1 is the farthest short-circuit current, and β is a constant;

将β'作为β代入上式计算出最远短路电流I″1,然后将最远短路电流I″1与临界电流I1' 进行比较,若仍满足I″1<I1',则储能电站输出电流未达限;若I″1≥I1',则储能电站输出 电流达限。Substitute β' as β into the above formula to calculate the farthest short-circuit current I″ 1 , and then compare the farthest short-circuit current I″ 1 with the critical current I 1 ′, if I″ 1 <I 1 ' is still satisfied, the energy storage The output current of the power station has not reached the limit; if I″ 1 ≥ I 1 ', the output current of the energy storage power station has reached the limit.

进一步地,步骤3所述的根据储能电站输出短路电流是否达限,确定优化因子α,对储能电站接入点上游线路的限时电流速断保护定值进行优化,具体如下:Further, according to step 3, according to whether the output short-circuit current of the energy storage power station reaches the limit, the optimization factor α is determined, and the time-limited current quick-break protection setting value of the upstream line of the access point of the energy storage power station is optimized, as follows:

步骤3.1、定义h点为达标电流对应短路点,则h点与储能电站接入点下游线路首端之间的阻抗计算式为:Step 3.1. Define point h as the short-circuit point corresponding to the up-to-standard current, then the impedance calculation formula between point h and the head end of the downstream line of the access point of the energy storage power station is:

Figure BDA0002342845540000063
Figure BDA0002342845540000063

式中,SN为储能电站额定容量,βD为常数;In the formula, S N is the rated capacity of the energy storage power station, and β D is a constant;

步骤3.2、根据储能电站输出电流是否达限,确定优化因子α,计算出储能电站接入点下游线路的电流速断保护定值:Step 3.2, according to whether the output current of the energy storage power station reaches the limit, determine the optimization factor α, and calculate the current quick-break protection setting value of the downstream line of the access point of the energy storage power station:

Figure BDA0002342845540000071
Figure BDA0002342845540000071

式中,

Figure BDA0002342845540000072
为储能电站接入点下游线路的电流速断保护定值,
Figure BDA0002342845540000073
为电流速断保护可靠系数,取值为1.2;
Figure BDA0002342845540000074
为限时电流速断保护可靠系数,取值为1.25;In the formula,
Figure BDA0002342845540000072
It is the setting value for the current quick-break protection of the downstream line of the access point of the energy storage power station.
Figure BDA0002342845540000073
is the reliability factor of the current quick-break protection, and the value is 1.2;
Figure BDA0002342845540000074
is the reliability factor of time-limited current quick-break protection, the value is 1.25;

步骤3.3、对储能电站接入点上游线路的限时电流速断保护定值进行优化,公式为:Step 3.3, optimize the time-limited current quick-break protection setting of the upstream line of the access point of the energy storage power station, the formula is:

Figure BDA0002342845540000075
Figure BDA0002342845540000075

式中,

Figure BDA0002342845540000076
为储能电站接入点上游线路的限时电流速断保护定值。In the formula,
Figure BDA0002342845540000076
It is a fixed value for the time-limited current quick-break protection of the upstream line of the access point of the energy storage power station.

下面结合附图和具体实施例对本发明作进一步的详细说明。The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

实施例Example

结合图1,本发明一种储能电站接入配电网的限时电流速断保护定值优化方法,包括以下步骤:With reference to Fig. 1, a method for optimizing the setting value of time-limited current quick-break protection for an energy storage power station connected to a distribution network of the present invention includes the following steps:

步骤1、构建储能电站等效模型,定义临界电流、最远短路电流、达标电流,根据 配电网参数及储能电站输出电流的最大限制值计算临界电流,具体如下:Step 1. Build the equivalent model of the energy storage power station, define the critical current, the farthest short-circuit current, and the up-to-standard current, and calculate the critical current according to the distribution network parameters and the maximum limit value of the output current of the energy storage power station, as follows:

储能电站的故障特性取决于其逆变器的控制策略,一般采用的控制策略是恒功率控制(PQ控制),PQ控制的储能电站的整体结构图如图2所示。PQ控制下的储能电 站可以看作一个恒功率输出电源,其有功功率和和无功功率可以实时跟踪参考信号, 其实质为将有功功率与无功功率解耦控制,对电流采用PI控制,保持输出恒定。将电 网中的abc坐标系下的电压、电流经abc/dq转换得到d轴、q轴分量,利用dq坐标系 下的电压、电流分量计算得到有功功率P和无功功率Q的测量值。将有功功率和无功功 率参考值Pref、Qref与有功功率、无功功率实际测量值进行比较,得到有功无功偏差, 经过PI控制器产生电流dq坐标系下的电流参考值IL.ref与经过实际测量值进行比较,产 生dq坐标系下经PI环节得到的电压参考值uref,用来控制SPWM(正弦脉宽调制器) 产生触发脉冲,得到逆变器的驱动信号,从而实现控制逆变器输出恒定功率的目的。 储能电站的输出电流受逆变器输出电流限制在额定电流的2倍以下,当输出电流未达最 大输出电流时,储能电站维持输出功率S不变,出口电压下降时,输出电流将增大。 当储能电站输出电流达到最大电流限制之后,随着出口的电压的降低,输出功率也随 之下降。储能电站的工作状态一般分为三种:充电、放电和备用。充电状态下其工作 特性相当于一个负载,根据以上特性,建立放电状态的储能电站等效模型为:The fault characteristics of the energy storage power station depend on the control strategy of its inverter. The control strategy generally used is constant power control (PQ control). The overall structure of the energy storage power station under PQ control is shown in Figure 2. The energy storage power station under PQ control can be regarded as a constant power output power supply, and its active power and reactive power can track the reference signal in real time. keep the output constant. The voltage and current in the abc coordinate system in the power grid are converted by abc/dq to obtain the d-axis and q-axis components, and the measured values of active power P and reactive power Q are calculated by using the voltage and current components in the dq coordinate system. The active and reactive power reference values P ref and Q ref are compared with the actual measured values of active power and reactive power to obtain the active and reactive power deviation, and the current reference value IL in the current dq coordinate system is generated through the PI controller . The ref is compared with the actual measured value to generate the voltage reference value u ref obtained by the PI link in the dq coordinate system, which is used to control the SPWM (sinusoidal pulse width modulator) to generate the trigger pulse and obtain the drive signal of the inverter, so as to realize The purpose of controlling the inverter to output constant power. The output current of the energy storage power station is limited by the inverter output current to be less than 2 times the rated current. When the output current does not reach the maximum output current, the energy storage power station maintains the output power S unchanged. When the outlet voltage drops, the output current will increase. big. When the output current of the energy storage power station reaches the maximum current limit, as the voltage at the outlet decreases, the output power also decreases. The working state of the energy storage power station is generally divided into three types: charging, discharging and standby. Its working characteristics in the charging state are equivalent to a load. According to the above characteristics, the equivalent model of the energy storage power station in the discharging state is established as follows:

Figure BDA0002342845540000081
Figure BDA0002342845540000081

式中,SN为储能电站额定功率,EG为储能电站出口相电压,IG为储能电站输出 相电流,IN为储能电站额定相电流。In the formula, SN is the rated power of the energy storage station, EG is the outlet phase voltage of the energy storage station, IG is the output phase current of the energy storage station, and I N is the rated phase current of the energy storage station.

进一步地,构建了典型的含储能电站的配电网拓扑图如图3所示,由于配电网的辐射状结构,任意配电网络均可通过阻抗串并联原理(将线路等效为等值阻抗)等效为典 型配电网拓扑。对于储能电站接入点上游线路的限时电流速断保护而言,其整定原则 为躲过下级线路的电流速断保护定值,即Further, a typical topology of the distribution network with energy storage power stations is constructed, as shown in Figure 3. Due to the radial structure of the distribution network, any distribution network can pass the impedance series-parallel principle (equivalent lines to equal value impedance) is equivalent to a typical distribution network topology. For the time-limited current quick-break protection of the upstream line of the access point of the energy storage power station, the setting principle is to avoid the current quick-break protection setting of the lower line, that is,

Figure BDA0002342845540000082
Figure BDA0002342845540000082

式中,

Figure BDA0002342845540000083
为储能电站接入点上游线路的限时电流速断保护定值,
Figure BDA0002342845540000084
为储能电站接入点下游线路的电流速断保护定值,
Figure BDA0002342845540000085
为电流保护Ⅱ段可靠系数,取值为1.25。In the formula,
Figure BDA0002342845540000083
It is the setting value for the time-limited current quick-break protection of the upstream line of the access point of the energy storage power station.
Figure BDA0002342845540000084
It is the setting value for the current quick-break protection of the downstream line of the access point of the energy storage power station.
Figure BDA0002342845540000085
It is the reliability factor of the current protection section II, and the value is 1.25.

由于储能电站接入后配电网变为多源网络,储能电站接入点上游线路保护处测得的电流值小于储能电站接入点下游线路保护处测得的电流值,如果仍沿用此整定方 式,会使储能电站接入点上游线路的限时电流速断保护灵敏度减小,出现拒动情况。Since the distribution network becomes a multi-source network after the energy storage power station is connected, the current value measured at the upstream line protection point of the energy storage power station access point is smaller than the current value measured at the downstream line protection point of the energy storage power station access point. Continuing this setting method will reduce the sensitivity of the time-limited current quick-break protection of the upstream line of the access point of the energy storage power station, resulting in a refusal to operate.

进一步地,根据图3所示的典型拓扑图,可得故障发生在储能电站接入点下游线路时的等值电路图,如图4所示,图中β为短路点与储能电站接入点下游线路首端之间的 阻抗占储能电站接入点下游线路总阻抗的百分比值,后文算式推导均从图4所示等值电 路而得。Further, according to the typical topology diagram shown in Figure 3, the equivalent circuit diagram when the fault occurs in the downstream line of the access point of the energy storage power station can be obtained, as shown in Figure 4, in the figure β is the short-circuit point and the access point of the energy storage power station. The impedance between the head ends of the downstream line at the point accounts for the percentage value of the total impedance of the downstream line at the access point of the energy storage power station. The following formulas are derived from the equivalent circuit shown in Figure 4.

进一步地,定义临界电流、最远短路电流、达标电流,具体如下:Further, define the critical current, the farthest short-circuit current, and the up-to-standard current, as follows:

临界电流的定义为:设定IN为储能电站额定电流,则储能电站输出电流恰好达到最 大电流限制时,即2倍额定电流2IN时流过储能电站接入点上游线路保护的电流,其计算式为:The definition of critical current is: set I N as the rated current of the energy storage power station, when the output current of the energy storage power station just reaches the maximum current limit, that is, when twice the rated current 2IN flows through the protection of the upstream line of the access point of the energy storage power station. current, which is calculated as:

Figure BDA0002342845540000091
Figure BDA0002342845540000091

式中,I1'为临界电流,E为储能电站额定相电压,ZS为系统电源阻抗,Z1为储能 电站接入点上游线路阻抗;定义k点为临界电流对应短路点,显然,短路点位于临界短 路点k下游时,储能电站提供的短路电流小于2IN;短路点位于临界短路点k上游时, 储能电站提高的短路电流等于2INIn the formula, I 1 ' is the critical current, E is the rated phase voltage of the energy storage power station, Z S is the system power supply impedance, and Z 1 is the upstream line impedance of the access point of the energy storage power station; point k is defined as the short-circuit point corresponding to the critical current, obviously , when the short-circuit point is downstream of the critical short-circuit point k, the short-circuit current provided by the energy storage power station is less than 2IN; when the short - circuit point is upstream of the critical short-circuit point k, the short-circuit current increased by the energy storage station is equal to 2IN .

最远短路电流的定义为:储能电站接入点上游线路的限时电流速断保护的保护范围 末端发生短路故障时,流过储能电站接入点上游线路保护的电流;定义j点为最远短路电流对应短路点,当最远短路电流小于临界电流时,保护范围末端j点在临界短路点k 下游,储能电站所提供的短路电流小于2IN;当最远短路电流大于临界电流时,保护范 围末端j点在临界短路点k上游,储能电站提高的短路电流等于2IN,据此分为两种情 况进行优化。The farthest short-circuit current is defined as: when a short-circuit fault occurs at the end of the protection range of the time-limited current quick-break protection of the upstream line of the energy storage power station access point, the current flowing through the protection of the upstream line of the energy storage power station access point; point j is defined as the farthest The short-circuit current corresponds to the short-circuit point. When the farthest short-circuit current is less than the critical current, point j at the end of the protection range is downstream of the critical short-circuit point k, and the short-circuit current provided by the energy storage power station is less than 2IN; when the farthest short - circuit current is greater than the critical current, The point j at the end of the protection range is upstream of the critical short-circuit point k, and the short-circuit current increased by the energy storage power station is equal to 2IN , which is divided into two cases for optimization.

达标电流的定义为:限时电流速断保护灵敏度恰好满足要求时,储能电站接入点上 游线路限时电流速断保护的定值,其计算式为:The definition of up-to-standard current is: when the sensitivity of the time-limited current quick-break protection just meets the requirements, the fixed value of the time-limited current quick-break protection of the upstream line of the access point of the energy storage power station, and its calculation formula is:

Figure BDA0002342845540000092
Figure BDA0002342845540000092

式中,ID为达标电流,I1m为储能电站接入点上游线路末端两相短路时流过储能电站接入点上游线路保护的电流,Ksen为满足要求的灵敏度,取值为1.3。In the formula, I D is the current that reaches the standard, I 1m is the current flowing through the protection of the upstream line of the access point of the energy storage power station when the two-phase short-circuit at the end of the upstream line of the energy storage power station access point, K sen is the sensitivity that meets the requirements, and the value is 1.3.

步骤2、比较临界电流与最远短路电流的大小关系,判断储能电站输出短路电流是否达到最大电流限制,具体如下:Step 2. Compare the magnitude relationship between the critical current and the farthest short-circuit current, and determine whether the output short-circuit current of the energy storage power station reaches the maximum current limit, as follows:

步骤2.1、定义k点为临界电流对应短路点,k点与储能电站接入点下游线路首端之间的阻抗计算式为:Step 2.1. Define point k as the short-circuit point corresponding to the critical current. The impedance calculation formula between point k and the head end of the downstream line of the access point of the energy storage power station is:

Figure BDA0002342845540000093
Figure BDA0002342845540000093

式中,Z2为储能电站接入点下游线路阻抗,β'为常数;In the formula, Z 2 is the downstream line impedance of the access point of the energy storage power station, and β' is a constant;

根据上式计算出β',若β'≥1,则储能电站输出电流必定达限;若β'<1,则进入步骤2.2;Calculate β' according to the above formula. If β'≥1, the output current of the energy storage power station must reach the limit; if β'<1, go to step 2.2;

步骤2.2、设定最远短路电流小于临界电流,则最远短路电流的计算式为:Step 2.2. Set the farthest short-circuit current to be less than the critical current, then the calculation formula of the farthest short-circuit current is:

Figure BDA0002342845540000101
Figure BDA0002342845540000101

式中,I″1为最远短路电流,β为常数;In the formula, I″ 1 is the farthest short-circuit current, and β is a constant;

将β'作为β代入上式计算出最远短路电流I″1,然后将最远短路电流I″1与临界电流I1' 进行比较,若仍满足I″1<I1',则储能电站输出电流未达限;若I″1≥I1',则储能电站输出 电流达限。Substitute β' as β into the above formula to calculate the farthest short-circuit current I″ 1 , and then compare the farthest short-circuit current I″ 1 with the critical current I 1 ′, if I″ 1 <I 1 ' is still satisfied, the energy storage The output current of the power station has not reached the limit; if I″ 1 ≥ I 1 ', the output current of the energy storage power station has reached the limit.

步骤3、根据储能电站输出短路电流是否达限,确定优化因子α,对储能电站接入点上游线路的限时电流速断保护定值进行优化,结合图5,具体如下:Step 3. Determine the optimization factor α according to whether the output short-circuit current of the energy storage power station reaches the limit, and optimize the time-limited current quick-break protection setting of the upstream line of the access point of the energy storage power station, as shown in Figure 5, as follows:

步骤3.1、定义h点为达标电流对应短路点,则h点与储能电站接入点下游线路首端之间的阻抗计算式为:Step 3.1. Define point h as the short-circuit point corresponding to the up-to-standard current, then the impedance calculation formula between point h and the head end of the downstream line of the access point of the energy storage power station is:

Figure BDA0002342845540000102
Figure BDA0002342845540000102

式中,SN为储能电站额定容量,βD为常数,根据上式可解得βDIn the formula, S N is the rated capacity of the energy storage power station, β D is a constant, and β D can be solved according to the above formula;

步骤3.2、根据储能电站输出电流是否达限,确定优化因子α,计算出储能电站接入点下游线路的电流速断保护定值:Step 3.2, according to whether the output current of the energy storage power station reaches the limit, determine the optimization factor α, and calculate the current quick-break protection setting value of the downstream line of the access point of the energy storage power station:

在储能电站输出电流未达限时,根据式:When the output current of the energy storage power station does not reach the limit, according to the formula:

Figure BDA0002342845540000103
Figure BDA0002342845540000103

得βD对应的最远短路电流,利用此最远短路电流求解得的优化因子α上限会偏小,有利于增加保护灵敏度,由于最远短路电流对应储能电站接入点上游线路限时电 流速断保护的保护范围末端,其值与实际整定值相等,为保证灵敏度要求,优化过后 的定值需小于此时βD所对应的最远短路电流值,引入优化因子α后的整定式为:To obtain the farthest short-circuit current corresponding to β D , the upper limit of the optimization factor α obtained by using this farthest short-circuit current will be small, which is beneficial to increase the protection sensitivity. Because the farthest short-circuit current corresponds to the time-limited current fast break of the upstream line of the energy storage power station access point At the end of the protection range of protection, its value is equal to the actual setting value. In order to ensure the sensitivity requirements, the optimized setting value should be smaller than the farthest short-circuit current value corresponding to β D at this time. The setting formula after introducing the optimization factor α is:

Figure BDA0002342845540000111
Figure BDA0002342845540000111

此时有:At this point there are:

Figure BDA0002342845540000112
Figure BDA0002342845540000112

当储能电站处于充电或备用状态时,储能电站接入点下游线路发生故障,储能电站提供的短路电流为0,储能电站接入点上游线路限时电流速断保护定值根据上述过程 修改过,此情况下其保护范围可能会超过储能电站接入点下游线路电流速断保护,导 致误动作。储能电站处于充电或备用状态时的储能电站接入点下游线路电流速断保护 保护整定值为:When the energy storage power station is in the charging or standby state, the downstream line of the energy storage power station access point fails, the short-circuit current provided by the energy storage power station is 0, and the time-limited current quick-break protection setting of the upstream line of the energy storage power station access point is modified according to the above process. However, in this case, its protection range may exceed the current quick-break protection of the downstream line of the access point of the energy storage power station, resulting in malfunction. When the energy storage power station is in the charging or standby state, the current quick-break protection of the downstream line of the energy storage power station access point. The protection setting value is:

Figure BDA0002342845540000113
Figure BDA0002342845540000113

因此保护1处电流Ⅱ段的保护整定值必须不小于储能电站处于充电或备用状态时保 护2处电流Ⅰ段的保护整定值,即

Figure BDA0002342845540000114
则有:Therefore, the protection setting value of the current stage II of the protection 1 must not be less than the protection setting value of the current stage I of the protection two places when the energy storage power station is in the charging or standby state, that is
Figure BDA0002342845540000114
Then there are:

Figure BDA0002342845540000115
Figure BDA0002342845540000115

为同时保证灵敏度与选择性,优化因子取上下限的中间值,即:In order to ensure the sensitivity and selectivity at the same time, the optimization factor takes the middle value of the upper and lower limits, namely:

Figure BDA0002342845540000116
Figure BDA0002342845540000116

结合储能电站输出电流未达限时储能电站接入点下游线路的电流速断保护定值整定 式:Combined with the current quick-break protection setting formula of the downstream line of the access point of the energy storage power station when the output current of the energy storage power station does not reach the limit:

Figure BDA0002342845540000117
Figure BDA0002342845540000117

上式中

Figure BDA0002342845540000118
为电流速断保护可靠系数,取值为1.2;In the above formula
Figure BDA0002342845540000118
is the reliability factor of the current quick-break protection, and the value is 1.2;

步骤3.3、对储能电站接入点上游线路的限时电流速断保护定值进行优化,公式为:Step 3.3, optimize the time-limited current quick-break protection setting of the upstream line of the access point of the energy storage power station, the formula is:

Figure BDA0002342845540000121
Figure BDA0002342845540000121

在储能电站输出电流达限时,根据式:When the output current of the energy storage power station reaches the limit, according to the formula:

Figure BDA0002342845540000122
Figure BDA0002342845540000122

得βD对应的最远短路电流,类似储能电站输出电流未达限情况,可得优化因子α上限:The farthest short-circuit current corresponding to β D can be obtained. Similar to the case where the output current of the energy storage power station does not reach the limit, the upper limit of the optimization factor α can be obtained:

Figure BDA0002342845540000123
Figure BDA0002342845540000123

为保证保护的选择性,需要考虑储能电站处于备用或充电状态时的防止误动,此处的整定原则亦与储能电站输出电流未达限情况类似,有:In order to ensure the selectivity of protection, it is necessary to consider the prevention of misoperation when the energy storage power station is in standby or charging state. The setting principle here is also similar to the case where the output current of the energy storage power station does not reach the limit, as follows:

Figure BDA0002342845540000124
Figure BDA0002342845540000124

为同时保证灵敏度与选择性,优化因子取上下限的中间值,即:In order to ensure the sensitivity and selectivity at the same time, the optimization factor takes the middle value of the upper and lower limits, namely:

Figure BDA0002342845540000125
Figure BDA0002342845540000125

结合储能电站输出电流未达限时储能电站接入点下游线路的电流速断保护定值整定 式:Combined with the current quick-break protection setting formula of the downstream line of the access point of the energy storage power station when the output current of the energy storage power station does not reach the limit:

Figure BDA0002342845540000126
Figure BDA0002342845540000126

可通过式:Passable:

Figure BDA0002342845540000127
Figure BDA0002342845540000127

求得储能电站输出电流达限时的优化整定值。Obtain the optimal setting value when the output current of the energy storage power station reaches the limit.

经定值优化过后的储能电站接入点上游线路限时电流速断保护可保证在储能电站 的各个工作状态下不会发生误动、拒动,能够可靠动作。The time-limited current quick-break protection of the upstream line of the access point of the energy storage power station after the optimization of the fixed value can ensure that there will be no malfunction or refusal to operate under each working state of the energy storage power station, and it can operate reliably.

以两个实际配电网参数为例,采用上述流程对其保护定值进行优化,配电网参数如下表1所示:Taking two actual distribution network parameters as an example, the above process is used to optimize their protection settings. The distribution network parameters are shown in Table 1 below:

表1Table 1

Figure BDA0002342845540000131
Figure BDA0002342845540000131

优化结果如下表2所示:The optimization results are shown in Table 2 below:

表2Table 2

Figure BDA0002342845540000132
Figure BDA0002342845540000132

由优化结果可见,对于2个配电网络而言,储能电站接入后,按原有整定方式所得的储能电站接入点上游线路限时电流速断保护灵敏度均不能满足要求,采用本发明所 述方法进行优化后,灵敏度均达到了要求,并且在储能电站由放电状态切换至充电或 备用状态时,储能电站接入点上游线路限时电流速断保护不会超越保护范围越级跳 闸,优化后的储能电站接入点上游线路限时电流速断保护在储能电站的各种工作状态 下均不会发生误动、拒动,能够可靠动作。It can be seen from the optimization results that for the two power distribution networks, after the energy storage power station is connected, the time-limited current quick-break protection sensitivity of the upstream line of the energy storage power station access point obtained by the original setting method cannot meet the requirements. After the optimization of the above method, the sensitivity all meet the requirements, and when the energy storage power station is switched from the discharge state to the charging or standby state, the time-limited current quick-break protection of the upstream line of the energy storage power station access point will not exceed the protection range. The time-limited current quick-break protection of the upstream line of the energy storage power station access point will not malfunction or refuse to operate under various working conditions of the energy storage power station, and can operate reliably.

Claims (2)

1. A time-limited current quick-break protection fixed value optimization method for an energy storage power station to be connected to a power distribution network is characterized by comprising the following steps:
step 1, constructing an equivalent model of an energy storage power station, defining critical current, farthest short-circuit current and standard current, and calculating the critical current according to parameters of a power distribution network and the maximum limit value of output current of the energy storage power station;
step 2, comparing the magnitude relation between the critical current and the farthest short-circuit current, and judging whether the output short-circuit current of the energy storage power station reaches the maximum current limit or not;
step 3, determining an optimization factor alpha according to whether the output short-circuit current of the energy storage power station reaches a limit, and optimizing a time-limited current quick-break protection fixed value of an upstream line of an access point of the energy storage power station;
the construction of the equivalent model of the energy storage power station in the step 1 specifically comprises the following steps:
according to the control strategy and the working characteristics of the energy storage power station adopting constant power control, the establishment of an energy storage power station equivalent model is as follows:
Figure FDA0003690889050000011
in the formula, S N Rated power for energy storage power stations, E G For the outlet phase voltage of the energy storage station, I G For the output phase current of the energy-storing power station, I N Rated current for the energy storage power station;
defining critical current, farthest short circuit current and standard current in the step 1, specifically as follows:
the critical current is defined as: setting I N The rated current of the energy storage power station is the rated current of the energy storage power station, and when the output current of the energy storage power station just reaches the maximum current limit, namely 2 times of the rated current 2I N The current flowing through the upstream line protection of the access point of the energy storage power station is calculated by the following formula:
Figure FDA0003690889050000012
in formula (II)' 1 Is critical current, E is rated phase voltage of energy storage power station, Z S Is the system supply impedance, Z 1 The impedance of an upstream line of an access point of the energy storage power station;
the definition of the farthest short-circuit current is: when the short-circuit fault occurs at the end of the protection range of the time-limited current quick-break protection of the upstream line of the access point of the energy storage power station, the current flows through the protection of the upstream line of the access point of the energy storage power station;
the current to standard is defined as: when the sensitivity of the time-limited current quick-break protection just meets the requirement, the fixed value of the time-limited current quick-break protection of the upstream line of the access point of the energy storage power station is calculated by the following formula:
Figure FDA0003690889050000013
in the formula I D To meet the current standard, I 1m For the current, K, flowing through the protection of the upstream line of the access point of the energy storage station in the event of a two-phase short circuit at the end of the upstream line of the access point of the energy storage station sen To meet the required sensitivity;
comparing the magnitude relation between the critical current and the farthest short-circuit current, and judging whether the short-circuit current output by the energy storage power station reaches the maximum current limit, wherein the method specifically comprises the following steps:
step 2.1, defining k point as a critical current corresponding short circuit point, and impedance beta' Z between the k point and the head end of the downstream line of the access point of the energy storage power station 2 The calculation formula is as follows:
Figure FDA0003690889050000014
in the formula, Z 2 The impedance of a downstream line of an access point of the energy storage power station is beta' which is a constant;
calculating beta 'according to the formula, wherein if the beta' is more than or equal to 1, the output current of the energy storage power station must reach the limit; if beta' is less than 1, entering a step 2.2;
step 2.2, setting the farthest short-circuit current to be smaller than the critical current, and then calculating the farthest short-circuit current according to the following formula:
Figure FDA0003690889050000021
in the formula, I 1 β is a constant for the farthest short circuit current;
substituting beta' as beta into the formula to calculate the farthest short circuit current I ″) 1 Then the farthest short-circuit current I ″, is measured 1 And critical current I' 1 Comparing, if I ″' is still satisfied 1 <I′ 1 If the output current of the energy storage power station does not reach the limit; if I ″) 1 ≥I′ 1 And the output current of the energy storage power station reaches the limit.
2. The method for optimizing the time-limited current quick-break protection fixed value of the energy storage power station to be connected to the power distribution network according to claim 1, wherein an optimization factor alpha is determined according to whether the short-circuit current output by the energy storage power station reaches a limit or not, and the time-limited current quick-break protection fixed value of an upstream line of an access point of the energy storage power station is optimized, specifically as follows:
step 3.1, defining the h point as a short-circuit point corresponding to the standard current, and then impedance beta between the h point and the head end of the downstream line of the access point of the energy storage power station D Z 2 The calculation formula is as follows:
Figure FDA0003690889050000022
in the formula, S N For rated capacity, beta, of energy-storage power stations D Is a constant;
step 3.2, determining an optimization factor alpha according to whether the output current of the energy storage power station reaches the limit, and calculating a current quick-break protection fixed value of a downstream line of an access point of the energy storage power station:
Figure FDA0003690889050000023
in the formula (I), the compound is shown in the specification,
Figure FDA0003690889050000031
the current quick-break protection constant value is set for the current of the downstream line of the access point of the energy storage power station,
Figure FDA0003690889050000032
the current quick-break protection reliability coefficient is obtained;
Figure FDA0003690889050000033
the current is a time-limited current quick-break protection reliable coefficient;
step 3.3, optimizing a time-limited current quick-break protection fixed value of an upstream line of an access point of the energy storage power station, wherein the formula is as follows:
Figure FDA0003690889050000034
in the formula (I), the compound is shown in the specification,
Figure FDA0003690889050000035
and the fixed value is protected for the time-limited current quick-break of the upstream line of the access point of the energy storage power station.
CN201911383387.2A 2019-12-27 2019-12-27 Time-limited current quick-break protection fixed value optimization method for power distribution network access of energy storage power station Active CN113054633B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911383387.2A CN113054633B (en) 2019-12-27 2019-12-27 Time-limited current quick-break protection fixed value optimization method for power distribution network access of energy storage power station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911383387.2A CN113054633B (en) 2019-12-27 2019-12-27 Time-limited current quick-break protection fixed value optimization method for power distribution network access of energy storage power station

Publications (2)

Publication Number Publication Date
CN113054633A CN113054633A (en) 2021-06-29
CN113054633B true CN113054633B (en) 2022-09-16

Family

ID=76507395

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911383387.2A Active CN113054633B (en) 2019-12-27 2019-12-27 Time-limited current quick-break protection fixed value optimization method for power distribution network access of energy storage power station

Country Status (1)

Country Link
CN (1) CN113054633B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106684834A (en) * 2015-11-10 2017-05-17 中国电力科学研究院 A distribution network adaptive current protection system and method
CN107706893A (en) * 2017-10-31 2018-02-16 广东电网有限责任公司惠州供电局 A kind of computational methods of DG accesses distribution optimum capacity
WO2018129842A1 (en) * 2017-01-10 2018-07-19 华北电力大学 Pilot protection method for transmission line of new energy station based on current waveform similarity
WO2018167306A1 (en) * 2017-03-16 2018-09-20 Naval Group System for supplying electrical energy to an on-board network of a submarine

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106684834A (en) * 2015-11-10 2017-05-17 中国电力科学研究院 A distribution network adaptive current protection system and method
WO2018129842A1 (en) * 2017-01-10 2018-07-19 华北电力大学 Pilot protection method for transmission line of new energy station based on current waveform similarity
WO2018167306A1 (en) * 2017-03-16 2018-09-20 Naval Group System for supplying electrical energy to an on-board network of a submarine
CN107706893A (en) * 2017-10-31 2018-02-16 广东电网有限责任公司惠州供电局 A kind of computational methods of DG accesses distribution optimum capacity

Also Published As

Publication number Publication date
CN113054633A (en) 2021-06-29

Similar Documents

Publication Publication Date Title
CN110376483B (en) A DC islanding detection method based on positive feedback of specific frequency bus voltage
WO2021253368A1 (en) Coordinated control system and method of wind turbine and statcom for suppressing unbalanced voltage in dispersed wind farm
Xie et al. Adaptive master-slave control strategy for medium voltage DC distribution systems based on a novel nonlinear droop controller
CN110233490A (en) Avoid the direct current transportation fault recovery control method and system of continuous commutation failure
CN107732951A (en) Direct current locking failure impacts the multiple resource control method for coordinating and device of communication channel
CN108923461B (en) A grid-connected optimization method for distributed inverter power supply considering relay protection constraints
CN108964043A (en) Grid control system and method based on the storage of source net lotus
WO2022099825A1 (en) Parameter optimization method for low-voltage current limiting controller in multi-infeed direct current system
CN114447984A (en) Low Voltage Ride-Through Control Method and Application for Offshore Wind Power Convergence Line Faults
CN109004671B (en) Modal switching method, modal switching device and back-to-back equipment
CN107171334B (en) Event driven cutting load and corrective route switching control method for coordinating and system
CN110768285A (en) Method for obtaining strength of alternating current-direct current hybrid direct current multi-feed-in receiving-end power grid
CN111987732A (en) Electric energy exchanger and method suitable for flexible interconnection of feeder lines of power distribution network
CN113054633B (en) Time-limited current quick-break protection fixed value optimization method for power distribution network access of energy storage power station
CN108197788B (en) Microgrid voltage frequency deviation estimation method under peer-to-peer control mode
CN110957744B (en) Frequency and voltage safety and stability emergency regulation and control online pre-decision method
CN109066762A (en) A kind of flexible DC transmission exchangeization operation method
Ye et al. Improved droop control strategy for an MMC-MTDC connected to offshore wind farms with dynamic correction of the actual operating point
Jia et al. An optimal control strategy for lv distribution network with pv and energy storage units
CN117578453A (en) A hybrid converter cluster independent power grid stability analysis and active control method
CN105790295A (en) Double-end flexible direct-current transmission system power grid fault non-communication ride-through control method
CN104638621B (en) Reclosing and emergent control comprehensive optimization method under a kind of power network based on DSR
CN106918754A (en) A kind of direct-current micro-grid island detection method based on additional impedance
CN116373677A (en) Cooperative control method for multiple direct-current charging pile systems
CN111682584B (en) Power distribution network voltage management method based on voltage regulator and multi-photovoltaic system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Wang Baohua

Inventor after: Deng Yujie

Inventor after: Jiang Haifeng

Inventor before: Deng Yujie

Inventor before: Jiang Haifeng

Inventor before: Wang Baohua

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant