CN113047184A - Construction method of connection structure of partially-filled concrete-filled steel tube pier and foundation with self-resetting function - Google Patents

Construction method of connection structure of partially-filled concrete-filled steel tube pier and foundation with self-resetting function Download PDF

Info

Publication number
CN113047184A
CN113047184A CN202110537893.3A CN202110537893A CN113047184A CN 113047184 A CN113047184 A CN 113047184A CN 202110537893 A CN202110537893 A CN 202110537893A CN 113047184 A CN113047184 A CN 113047184A
Authority
CN
China
Prior art keywords
concrete
prestressed
steel
filled
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110537893.3A
Other languages
Chinese (zh)
Inventor
马玥
付明春
刘颖
于丰纶
王占飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian Ocean University
Original Assignee
Dalian Ocean University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dalian Ocean University filed Critical Dalian Ocean University
Priority to CN202110537893.3A priority Critical patent/CN113047184A/en
Publication of CN113047184A publication Critical patent/CN113047184A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to the field of bridge engineering, in particular to a construction method of a connecting structure of a partially-filled concrete-filled steel tube pier and a foundation with a self-resetting function. The technical scheme is as follows: the method comprises the following steps: the method comprises the following steps: pouring a concrete bearing platform; step two: installing a steel pipe and a perforated plate; step three: and tensioning the prestressed steel strands and the prestressed steel bars. The construction method of the connecting structure of the partially filled concrete-filled steel tube pier and the foundation with the self-resetting function, provided by the invention, has enough bearing capacity and self-resetting capability.

Description

Construction method of connection structure of partially-filled concrete-filled steel tube pier and foundation with self-resetting function
Technical Field
The invention relates to the field of bridge engineering, in particular to a construction method of a connecting structure of a partially-filled concrete-filled steel tube pier and a foundation with a self-resetting function.
Background
The traditional ductile bridge pier has high bearing capacity, good ductility and excellent seismic performance, but has poor restorability after earthquake.
The traditional self-resetting bridge pier is composed of a bearing component, a self-resetting component, an energy dissipation component and a joint, and is a novel anti-seismic bridge pier system appearing in recent years. The pier has the advantages of small permanent deformation after earthquake and good restorability, but the pier has small lateral stiffness and low bearing capacity and is not suitable for bridges in heavy-load traffic.
Two kinds of ductility pier and self-resetting pier in the traditional sense have common problems in use: the arrangement mode of the joint component.
(1) For a traditional ductile pier, a pier column is in rigid connection with a bearing platform, and seismic energy is dissipated through ductility of a plastic hinge area of the pier. However, the accumulated deformation of such a pier from elastic deformation to plastic deformation causes a large permanent residual deformation after the earthquake. Minor damage can be repaired, while bridges with severe damage need to be rebuilt, which is time and labor consuming and affects the normal traffic function of the bridge.
(2) For the traditional self-resetting bridge pier, the pier column and the bearing platform adopt hinged joints, the joints of the connecting mode are easy to be damaged by pressure, and the parallel and level butt joint contact joints are not beneficial to the transmission of shearing force and are easy to cause the shearing damage of prestressed reinforcements.
Disclosure of Invention
The invention provides a construction method of a connecting structure of a partially-filled concrete-filled steel tube pier and a foundation with a self-resetting function.
The technical scheme of the invention is as follows:
the construction method of the connecting structure of the partially filled concrete-filled steel tube pier and the foundation with the self-resetting function comprises the following steps:
the method comprises the following steps: cast concrete bearing platform
Embedding a supporting nut in the foundation and anchoring one end of the prestressed steel strand and one end of the prestressed reinforcement; installing a rectangular steel plate on a foundation, pouring a concrete bearing platform above the rectangular steel plate, wherein a preformed hole A is formed in the center of the concrete bearing platform, and a plurality of preformed holes B are formed in the periphery of the concrete bearing platform; penetrating out the prestressed steel strands from the preformed hole A, and penetrating out a plurality of prestressed steel bars from the preformed hole B;
step two: mounting steel pipe and perforated plate
Installing a perforated plate at the top of the concrete bearing platform, installing a steel pipe at the upper part of the perforated plate, and welding the perforated plate and the steel pipe into a whole by using a stiffening rib; pouring filling concrete into the steel pipe, arranging a reserved hole C in the center of the filling concrete, enabling the reserved hole C to be concentric with the reserved hole A, and enabling the prestressed steel strand to penetrate out of the reserved hole C;
step three: stretching prestressed strand and prestressed reinforcement
Tensioning the prestressed steel strand by using a post-tensioning method, and anchoring the upper end of the prestressed steel strand by using a backing plate and a supporting nut; and tensioning the prestressed reinforcement by using a post-tensioning method, and anchoring the upper end of the prestressed reinforcement on the perforated plate by using a supporting nut.
Further, in the construction method of the connection structure of the partially filled concrete-filled steel tube pier and the foundation with the self-resetting function, the cross section of the steel tube is square, rectangular, circular or oval.
Further, according to the construction method of the connection structure of the partially-filled concrete-filled steel tube pier and the foundation with the self-resetting function, the spiral ribs are arranged around the upper end of the prestressed steel strand, and the spiral ribs are arranged in the filled concrete.
The invention has the beneficial effects that:
1. when the connecting structure is used in earthquake, certain bending deformation and then swinging occur, the steel pipe generates a good energy dissipation effect, earthquake damage can be controlled within a certain range to avoid damage of the main body structure, and the connecting structure has good earthquake resistance.
2. After the earthquake, the steel pipe and the filled concrete can be pulled back to the original shape by the prestressed steel strands and the prestressed steel bars, so that the residual deformation is reduced, and the pier is restored to the original position.
3. The invention has simple construction, safe and reliable quality and convenient popularization.
Drawings
FIG. 1 is a schematic view of a connection structure of a partially-filled concrete-filled steel tube rectangular pier and a foundation with a self-resetting function in example 1;
FIG. 2 is a schematic perspective view of a connection structure of a partially-filled concrete-filled steel tube rectangular pier and a foundation with a self-resetting function in example 1;
FIG. 3 is a schematic view of a deformation state of a connection structure of a partially-filled concrete-filled steel tube rectangular pier and a foundation with a self-resetting function;
fig. 4 is a schematic perspective view of a connection structure between a partially-filled concrete-filled steel tube rectangular pier and a foundation having a self-resetting function in example 2.
Detailed Description
Example 1
As shown in fig. 1 and 2, the construction method of the connection structure of the partially filled concrete-filled steel tube pier and the foundation having the self-restoration function includes the following steps:
the method comprises the following steps: cast concrete bearing platform 9
Embedding a support nut 11 in the foundation and anchoring one ends of the prestressed steel strands 6 and the prestressed steel bars 8; installing a rectangular steel plate 14 on a foundation, pouring a concrete bearing platform 9 above the rectangular steel plate 14, arranging a preformed hole A in the center of the concrete bearing platform 9, and arranging a plurality of preformed holes B10 around the concrete bearing platform 9; the prestressed steel strands 6 penetrate out of the preformed holes A, and the plurality of prestressed steel bars 8 penetrate out of the preformed holes B10;
step two: mounting the steel pipe 1 and the perforated plate 12
Installing a perforated plate 12 at the top of a concrete bearing platform 9, installing a steel pipe 1 on the upper part of the perforated plate 12, wherein the section of the steel pipe 1 is rectangular, and welding the perforated plate 12 and the steel pipe 1 into a whole by using a stiffening rib 5; pouring filling concrete 2 into the steel pipe 1, wherein a preformed hole C7 is formed in the center of the filling concrete 2, the preformed hole C7 is concentric with the preformed hole A, and the prestressed steel strand 6 penetrates out of the preformed hole C7; spiral reinforcements 4 are arranged around the upper ends of the prestressed steel strands 6, and the spiral reinforcements 4 are arranged in the filling concrete 2;
step three: stretching prestressed steel strand 6 and prestressed reinforcement 8
Tensioning the prestressed steel strand 6 by using a post-tensioning method, and anchoring the upper end of the prestressed steel strand by using a backing plate 3 and a supporting nut 11; the prestressed reinforcement 8 is tensioned by a post-tensioning method, and the upper end is anchored on a perforated plate 12 by a supporting nut 11.
As shown in fig. 3, in the figure: pPInternal force of prestressed steel strand, LPEffective length of prestressed reinforcement, delta total: total horizontal displacement, θ: opening angle of pier, d is pier column section diameter, hc: height of pier column, Gc: dead weight of pier, Gsup: superstructure load, FEDiTension generated by the ith prestressed reinforcement, e: rotation point, h: distance from the upper structure load point of action to the top of the concrete cap, APArea of the cross section of the prestressed steel strand, dEDi: distance from ith prestressed reinforcement to point e, c: distance from the point of rotation to the edge of the pier.
During earthquake, under the action of horizontal earthquake force, the pier is firstly subjected to bending deformation to consume energy, then a clearance angle theta is formed between the pier and the concrete bearing platform 9, the pier starts to rotate, the clearance angle theta is continuously increased along with the continuous increase of horizontal load, and the tension F of the prestressed reinforcement 8 isEDiAnd 6 tension P of prestressed steel strandPQuickly increased and 6 tension P of prestressed steel strandPThe yield bearing capacity is not reached in the whole stress process of the pier. The total horizontal displacement delta total comprises horizontal displacement generated by bending deformation of the bridge pier and horizontal displacement generated by rotation of the bridge pier. And after the earthquake load is unloaded, the pier is restored to the original position by utilizing the tensile force of the prestressed reinforcement 8 and the prestressed steel strand 6.
Example 2
As shown in fig. 4, the difference from example 1 is that the cross-sectional shape of the steel pipe 1 is circular.

Claims (3)

1. The construction method of the connecting structure of the partially filled concrete-filled steel tube pier and the foundation with the self-resetting function is characterized by comprising the following steps of:
the method comprises the following steps: cast concrete bearing platform
Embedding a supporting nut in the foundation and anchoring one end of the prestressed steel strand and one end of the prestressed reinforcement; installing a rectangular steel plate on a foundation, pouring a concrete bearing platform above the rectangular steel plate, wherein a preformed hole A is formed in the center of the concrete bearing platform, and a plurality of preformed holes B are formed in the periphery of the concrete bearing platform; penetrating out the prestressed steel strands from the preformed hole A, and penetrating out a plurality of prestressed steel bars from the preformed hole B;
step two: mounting steel pipe and perforated plate
Installing a perforated plate at the top of the concrete bearing platform, installing a steel pipe at the upper part of the perforated plate, and welding the perforated plate and the steel pipe into a whole by using a stiffening rib; pouring filling concrete into the steel pipe, arranging a reserved hole C in the center of the filling concrete, enabling the reserved hole C to be concentric with the reserved hole A, and enabling the prestressed steel strand to penetrate out of the reserved hole C;
step three: stretching prestressed strand and prestressed reinforcement
Tensioning the prestressed steel strand by using a post-tensioning method, and anchoring the upper end of the prestressed steel strand by using a backing plate and a supporting nut; and tensioning the prestressed reinforcement by using a post-tensioning method, and anchoring the upper end of the prestressed reinforcement on the perforated plate by using a supporting nut.
2. The construction method of a connection structure of a partially filled concrete filled steel tube pier and foundation having a self-restoration function according to claim 1, wherein the shape of the cross section of the steel tube is square, rectangular, circular or oval.
3. The construction method of the connection structure of the pier and the foundation with the self-restoration function of the partially filled concrete-filled steel tube according to claim 1, wherein a spiral bar is provided around the upper end of the prestressed steel strand, and the spiral bar is provided in the filled concrete.
CN202110537893.3A 2021-05-18 2021-05-18 Construction method of connection structure of partially-filled concrete-filled steel tube pier and foundation with self-resetting function Pending CN113047184A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110537893.3A CN113047184A (en) 2021-05-18 2021-05-18 Construction method of connection structure of partially-filled concrete-filled steel tube pier and foundation with self-resetting function

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110537893.3A CN113047184A (en) 2021-05-18 2021-05-18 Construction method of connection structure of partially-filled concrete-filled steel tube pier and foundation with self-resetting function

Publications (1)

Publication Number Publication Date
CN113047184A true CN113047184A (en) 2021-06-29

Family

ID=76518349

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110537893.3A Pending CN113047184A (en) 2021-05-18 2021-05-18 Construction method of connection structure of partially-filled concrete-filled steel tube pier and foundation with self-resetting function

Country Status (1)

Country Link
CN (1) CN113047184A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114396192A (en) * 2021-12-13 2022-04-26 中国能源建设集团安徽省电力设计院有限公司 Plug-in type concrete-filled steel tube column base for large power transmission tower and construction method thereof
CN117385732A (en) * 2023-11-30 2024-01-12 石家庄铁道大学 Prefabricated assembly type swing pier structure system, installation method and application

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030036572A (en) * 2003-04-21 2003-05-09 주식회사 일승에스티 Construction method and structure of steel foundation for connecting steel pier and steel pipe pile
CN204919987U (en) * 2015-07-22 2015-12-30 北京建筑大学 Prestressing force sways and exposes formula column base
CN205935236U (en) * 2016-07-08 2017-02-08 西安建筑科技大学 From square steel tube concrete frame column base node that restores to throne
CN211973073U (en) * 2019-12-03 2020-11-20 防灾科技学院 Cable-stayed bridge auxiliary pier system free of earthquake damage design

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030036572A (en) * 2003-04-21 2003-05-09 주식회사 일승에스티 Construction method and structure of steel foundation for connecting steel pier and steel pipe pile
CN204919987U (en) * 2015-07-22 2015-12-30 北京建筑大学 Prestressing force sways and exposes formula column base
CN205935236U (en) * 2016-07-08 2017-02-08 西安建筑科技大学 From square steel tube concrete frame column base node that restores to throne
CN211973073U (en) * 2019-12-03 2020-11-20 防灾科技学院 Cable-stayed bridge auxiliary pier system free of earthquake damage design

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
崔京浩: "《第19届全国结构工程学术会议论文集 第2册》", 31 October 2010 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114396192A (en) * 2021-12-13 2022-04-26 中国能源建设集团安徽省电力设计院有限公司 Plug-in type concrete-filled steel tube column base for large power transmission tower and construction method thereof
CN114396192B (en) * 2021-12-13 2024-03-15 中国能源建设集团安徽省电力设计院有限公司 Inserted steel tube concrete column base for large power transmission tower and construction method thereof
CN117385732A (en) * 2023-11-30 2024-01-12 石家庄铁道大学 Prefabricated assembly type swing pier structure system, installation method and application
CN117385732B (en) * 2023-11-30 2024-06-04 石家庄铁道大学 Prefabricated assembly type swing pier structure system, installation method and application

Similar Documents

Publication Publication Date Title
CN105113389B (en) Assembled type bridge pier column member with steel-concrete composite structure
CN109914234B (en) Precast segment shear-resistant spliced concrete pier connected through bolts
CN113585049B (en) Self-resetting prefabricated assembled concrete filled steel tube pier node connecting structure with replaceable plastic hinges and construction method thereof
CN113047184A (en) Construction method of connection structure of partially-filled concrete-filled steel tube pier and foundation with self-resetting function
CN110616733A (en) Integral reinforcing device and method for foundation and component of power transmission tower
CN114622481A (en) Double-column type self-resetting pier structure with buckling-restrained brace and construction method thereof
CN110835974A (en) Tough steel column and construction and installation method thereof
CN214939362U (en) Steel pipe concrete rectangular pier and foundation connecting structure with self-resetting function
CN111236096A (en) Pier column vertical prestressed tendon reinforcing structure and construction method
CN215482258U (en) Multi-damping system for segment-assembled single-column pier separated UHPC swinging bearing platform
CN112049028A (en) Damping and anti-overturning single-column pier bridge reinforcing device and installation method
CN108442238A (en) A kind of transverse direction assembled runback bit-type Antivibration block and its construction method
CN111455834A (en) Self-resetting prefabricated assembled pier and construction method thereof
CN112627016B (en) Assembly type pier with self-resetting and strong energy consumption and construction method thereof
CN209907185U (en) Bolted prefabricated segment shear-resistant assembled concrete pier
CN117026789A (en) Self-resetting bridge pier
CN111155643A (en) Assembly type mixed frame structure and construction method
CN216615473U (en) Take energy consumption damping device's assembled hollow concrete pier
CN213571600U (en) Bridge underpins bearing structure
CN212656105U (en) Self-resetting prefabricated assembled pier
CN214883011U (en) Connection structure capable of realizing accurate positioning of multi-limb concrete-filled steel tube space structure and bearing platform
CN214576115U (en) Assembled antidetonation steel pipe concrete toughness post
CN212104108U (en) Recoverable assembled prestressing force suspension cable foundation ditch support piece
CN210856913U (en) FRP (fiber reinforced plastic) confined concrete hollow self-resetting-mild steel extrusion energy dissipation pier structure
CN211473068U (en) Toughness energy dissipation steel column

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210629