CN112989465B - Design method of slope deep-buried shear pile supporting structure based on plane sliding method - Google Patents
Design method of slope deep-buried shear pile supporting structure based on plane sliding method Download PDFInfo
- Publication number
- CN112989465B CN112989465B CN202110254791.0A CN202110254791A CN112989465B CN 112989465 B CN112989465 B CN 112989465B CN 202110254791 A CN202110254791 A CN 202110254791A CN 112989465 B CN112989465 B CN 112989465B
- Authority
- CN
- China
- Prior art keywords
- shear
- sliding
- pile
- piles
- length
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
- E02D17/207—Securing of slopes or inclines with means incorporating sheet piles or piles
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/17—Mechanical parametric or variational design
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F2119/00—Details relating to the type or aim of the analysis or the optimisation
- G06F2119/14—Force analysis or force optimisation, e.g. static or dynamic forces
Abstract
The invention discloses a design method of a side slope deep-buried shear pile supporting structure based on a plane sliding method, which comprises the following implementation processes of: preliminarily determining the diameter D of the deeply buried shear pile and the arrangement position and the arrangement distance s of the deeply buried shear pile on a side slope; selecting a longitudinal row of shear piles and a side slope within a calculation width range as a calculation unit, and setting the number of the shear piles to be m rows and the horizontal projection length of a bar block containing the piles to be s according to a sliding surface form. The force of the computing unit is analyzed by adopting a plane sliding method, the anti-sliding force provided by the shearing resistance of the steel bar is considered, and the safety coefficient of the slope is calculated to be F s Cross section area A of reinforcing bar bundle needed by each shear-resistant pile s Thereby performing the arrangement of the tendons. And finally, calculating the length of the anchoring section of the shear-resistant pile foundation rock and the length of the embedded section of the sliding body according to the checking calculation of the uplift bearing capacity of the anchoring body. The method has better operability, gives consideration to the economy on the premise of ensuring the safety, is favorable for saving the construction period and reducing the possibility of disaster occurrence.
Description
Technical Field
The invention relates to a design method of a side slope supporting structure, in particular to a design method of a side slope deep-buried shear pile supporting structure based on a plane sliding method.
Background
Along with the expansion of various construction scales, the frequent occurrence of geological disasters such as slope instability, landslide and the like, the construction of a supporting structure is required to be convenient and rapid, the disturbance to a landslide body is small, the operation is economic and reasonable in landslide prevention and particularly landslide emergency rescue, the requirements of existing treatment means such as load reduction, back pressure, anchor cables, anti-slide piles and other retaining forms on site conditions are high, the construction period is generally long, and the application has certain limitation. The invention provides a design method of a side slope deeply-buried shear pile supporting structure based on a plane sliding method, wherein a shear pile poured by a reinforcing bar bundle and cement mortar is adopted for supporting, and the shear resistance of the cross section of the reinforcing bar bundle is utilized to provide the anti-sliding force; and calculating the residual sliding force according to a plane sliding method, distributing the residual sliding force to each row of piles, determining the sectional area of the tendon of each row of shear piles required by meeting the limit balance state of the side slope, determining the arrangement of the tendons of the shear piles, and checking the anti-pulling stability to obtain the lengths of the shear piles embedded into the bedrock and the sliding body. This stake of shearing has better maneuverability, and the site operation is convenient, can effectively provide the cling compound power to the sliding surface, compromises economic nature under the prerequisite of guaranteeing safety, avoids unnecessary extravagant, helps saving the time limit for a project, reduces the possibility that the calamity took place.
Disclosure of Invention
Aiming at the problems, the technical problems to be solved by the invention are as follows: the design method of the side slope deep-buried shear pile supporting structure based on the plane sliding method is provided, and aims to solve the problems that the existing landslide supporting means is long in construction time, large in landslide disturbance and poor in economical efficiency when used for landslide emergency rescue.
The technical method adopted by the invention is as follows: a design method of a side slope deep-buried shear pile supporting structure based on a plane sliding method comprises the following steps:
the method comprises the following steps: preliminarily determining the diameter D of each row of deeply buried shear piles, and the arrangement positions and the transverse and longitudinal arrangement spacing s of the deeply buried shear piles on the side slope;
step two: selecting a row of longitudinal shear piles and a side slope within the range of the calculation width (namely the pile spacing s) of the shear piles as a calculation unit, and setting the number of the shear piles to be m rows and the horizontal projection length of a bar block containing the piles to be s according to the form of a sliding surface. (ii) a
Step three: the stress analysis is carried out on the calculation unit by adopting a plane sliding method, and the slope is calculated according to the following formulaAt a safety factor of F s Cross section area A of reinforcing bar bundle needed by each shear-resistant pile s Thereby performing the tendon deployment;
P=R-T
T=W sinθ
in the formula, F s The safety coefficient of the side slope is set; n is the gliding force which each shear pile should bear; f. of v The design value of the shear strength of the steel bar is obtained; p is the residual sliding force of the sliding mass; t is the gliding force caused by gravity and other external forces in the width calculated by the gliding body; r is the anti-sliding force caused by gravity and other external forces in the calculated width of the sliding body; c is the cohesive force of the sliding surface;is the internal friction angle of the sliding surface; l is the length of the sliding surface; theta is the inclination angle of the sliding surface; w is the self weight of the slider.
Step four: and calculating the length of the anchoring section of the shear-resistant pile foundation rock and the length of the embedded section of the sliding body according to the following formula by checking the uplift bearing capacity of the anchoring body.
In the formula, l a The length of the anchoring section of the shear pile; k is the anti-pulling safety coefficient of the anchoring body; f. of y As reinforcing barsDesign value of tensile strength; d is the drilling diameter of the shear pile; f. of rbk The ultimate bonding strength standard value between the rock-soil layer and the anchoring body is adopted, the ultimate bonding strength between the bedrock and the anchoring body is adopted when the embedded section length of the shear pile in the bedrock is calculated, and the ultimate bonding strength between the sliding body and the anchoring body is adopted when the embedded section length of the shear pile in the sliding body is calculated; n is the number of the steel bars contained in the steel bar bundle; d is a radical of s The diameter of the steel bar; f. of b The design value of the bonding strength between the steel bar and the anchoring mortar is obtained; alpha is the reduction coefficient of the bonding strength when 2 or more than 2 steel bars are adopted and bound into the steel bar bundles.
Drawings
FIG. 1 is a diagram illustrating force analysis of a slider according to an embodiment of the present invention;
fig. 2 is a schematic plan view of a shear pile according to an embodiment of the present invention;
fig. 3 is a large cross-sectional view of a shear pile according to an embodiment of the present invention.
Detailed Description
The following will clearly and completely describe the specific embodiments of the technical solution of the present invention.
A design method of a side slope deep-buried shear pile supporting structure based on a plane sliding method comprises the following specific implementation processes: in a slope sliding along a plane, m rows of shear-resistant piles are arranged at appropriate positions, the pile diameter of each row of shear-resistant piles is D, the transverse and longitudinal spacing of the piles is s, and a longitudinal row of shear-resistant piles and a slope sliding body within the range of the calculation width (i.e. the pile spacing s) of the shear-resistant piles are taken as a calculation unit for analysis, as shown in fig. 1 and 2.
According to the plane sliding method, the safety coefficient of the side slope is F s When in use, the remaining sliding force of the sliding body is as follows:
P=R-T (1)
T=W sinθ
after a plurality of rows of shear piles are arranged, the slip body is distributed to each row of piles in an average manner of the remaining slip force, and the slip force born by each shear pile can be obtained according to a formula (1):
from the formula (2), the cross-sectional area of the tendon of each shear pile is:
in the formula, N is the gliding force to be borne by each shear pile, A s The cross-sectional area of each shear pile tendon.
The shear piles are formed by pouring reinforcing steel bar bundles and cement mortar, as shown in fig. 3, the length of the embedded sliding body and the length of the embedded bedrock of each row of shear piles can be calculated according to the requirement of the shear pile on the pulling resistance bearing capacity, namely, the bonding strength of the grouting body and the soil body of the hole wall in the anchoring section and the bonding strength of the reinforcing steel bar and the grouting body in the anchoring section meet the requirement, the shear piles can be obtained according to the following formula, and the larger value is selected.
The invention provides a design method of a deep-buried shear pile supporting structure for a plane sliding side slope, which considers the anti-sliding force provided by the shearing resistance of steel bars, calculates the residual sliding force by a plane sliding method, uniformly distributes the residual sliding force to each row of piles, determines the section area of each shear pile tendon required by the limit balance state of the side slope, and calculates the length of the shear pile embedded in bedrock and a sliding body determined by the pulling resistance stability. The design method of the supporting structure is rapid in construction, economical and reasonable and provides for landslide emergency engineering.
The above description is only an embodiment of the present invention, but the scope of the present invention is not limited thereto, and any changes or substitutions without creative efforts should be covered within the scope of the present invention.
Claims (1)
1. A design method of a side slope deep-buried shear pile supporting structure based on a plane sliding method is characterized by comprising the following steps: the method comprises the following steps:
the method comprises the following steps: preliminarily determining the diameter D of each row of deeply buried shear piles, and the arrangement positions and the transverse and longitudinal arrangement spacing s of the deeply buried shear piles on the side slope;
step two: selecting a longitudinal row of shear piles and the calculated width thereof, namely a side slope within the pile spacing s as a calculation unit, and setting the number of the shear piles as m rows and the horizontal projection length of a bar block containing the piles as s according to the form of a sliding surface;
step three: the stress analysis is carried out on the calculation unit by adopting a plane sliding method, and the safety coefficient of the slope F is calculated according to the following formula s Cross section area A of reinforcing bar bundle needed by each shear-resistant pile s Thereby performing the tendon deployment;
P=R-T
T=Wsinθ
in the formula, F s The safety coefficient of the side slope is set; n is the gliding force which each shear pile should bear; f. of v The design value of the shear strength of the steel bar is obtained; p is the residual sliding force of the sliding mass; t is the gliding force caused by gravity and other external forces in the width calculated by the gliding body; r is the anti-sliding force caused by gravity and other external forces in the calculated width of the sliding body; c is the cohesive force of the sliding surface;is the internal friction angle of the sliding surface; l is the length of the sliding surface; theta is the inclination angle of the sliding surface; w is the self weight of the sliding body;
step four: calculating the length of the anchoring section of the shear-resistant pile foundation rock and the length of the embedded sliding body section according to the following formula by checking the uplift bearing capacity of the anchoring body;
in the formula, l a The length of the anchoring section of the shear pile; k is the anti-pulling safety coefficient of the anchoring body; f. of y The design value of the tensile strength of the steel bar is; d is the drilling diameter of the shear pile; f. of rbk The ultimate bonding strength standard value between the rock-soil layer and the anchoring body is adopted, the ultimate bonding strength between the bedrock and the anchoring body is adopted when the embedded section length of the shear-resistant pile in the bedrock is calculated, and the ultimate bonding strength between the sliding body and the anchoring body is adopted when the embedded section length of the shear-resistant pile in the sliding body is calculated; n is the number of the steel bars contained in the steel bar bundle; d s The diameter of the steel bar; f. of b The design value of the bonding strength between the steel bar and the anchoring mortar is obtained; alpha is the reduction coefficient of the bonding strength when 2 or more than 2 steel bars are adopted and bound into the steel bar bundles.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110254791.0A CN112989465B (en) | 2021-03-09 | 2021-03-09 | Design method of slope deep-buried shear pile supporting structure based on plane sliding method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110254791.0A CN112989465B (en) | 2021-03-09 | 2021-03-09 | Design method of slope deep-buried shear pile supporting structure based on plane sliding method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112989465A CN112989465A (en) | 2021-06-18 |
CN112989465B true CN112989465B (en) | 2022-12-06 |
Family
ID=76336093
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110254791.0A Active CN112989465B (en) | 2021-03-09 | 2021-03-09 | Design method of slope deep-buried shear pile supporting structure based on plane sliding method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112989465B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114892688B (en) * | 2022-05-13 | 2023-03-21 | 中铁二院工程集团有限责任公司 | Three-dimensional design method and system for side slope anchor rod frame beam |
CN115506383A (en) * | 2022-10-23 | 2022-12-23 | 重庆敏思岩土工程有限公司 | Rotary spraying replacement method for soil band rib of sliding band |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103225310A (en) * | 2013-05-21 | 2013-07-31 | 中南大学 | Structural design method for load-bearing section of miniature anti-slip compound pile |
CN107419628A (en) * | 2017-04-14 | 2017-12-01 | 中交天津港湾工程研究院有限公司 | A kind of construction method of the rapid build road on reclaimed ground |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN205776276U (en) * | 2016-06-28 | 2016-12-07 | 贵州正业工程技术投资有限公司 | A kind of large-scale buried friction pile of side slope two-part props up mark structure |
CN106777520A (en) * | 2016-11-24 | 2017-05-31 | 中国人民解放军后勤工程学院 | A kind of method for designing of Anti-slide Pile |
CN107217679B (en) * | 2017-08-02 | 2018-07-06 | 中国地质环境监测院 | A kind of megalith mixture landslide micro combination pile group buttress reinforcement means |
-
2021
- 2021-03-09 CN CN202110254791.0A patent/CN112989465B/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103225310A (en) * | 2013-05-21 | 2013-07-31 | 中南大学 | Structural design method for load-bearing section of miniature anti-slip compound pile |
CN107419628A (en) * | 2017-04-14 | 2017-12-01 | 中交天津港湾工程研究院有限公司 | A kind of construction method of the rapid build road on reclaimed ground |
Also Published As
Publication number | Publication date |
---|---|
CN112989465A (en) | 2021-06-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3827133B1 (en) | Method for stabilizing deep excavations or earth slope instability near existing civil objects | |
CN112989465B (en) | Design method of slope deep-buried shear pile supporting structure based on plane sliding method | |
CN103452147B (en) | Self-balancing anchor counterweight broken pile forced-landing tilt correcting method | |
CN100535263C (en) | Construction method for vertical prestressed anchor rope friction pile slope-sliding prevention and treatment | |
CN111021376A (en) | Three-dimensional frame pile body structure for deep landslide treatment and construction process thereof | |
CN112989467B (en) | Simplified Bischot-based soil slope deep-buried shear pile support structure design method | |
CN113204828A (en) | Integral reinforcement design method considering landslide bottom building stability | |
CN107893428A (en) | A kind of vertical anchor retaining wall design method | |
CN112989466B (en) | Design method of slope deep-buried shear pile supporting structure based on simple distribution method | |
CN203080470U (en) | Pile-bearing platform-barricade combined supporting and retaining structure | |
CN110565657A (en) | Supporting structure for reinforcing landslide and construction method | |
CN101126241A (en) | Scattered row piles-brad wall combination supporting method | |
CN201610546U (en) | Prestress anchoring frame plat | |
CN104652455A (en) | Soil landslide raft type lattice-anchor rod-anchor cable combined anti-skid structure and soil landslide raft type lattice-anchor rod-anchor cable combined anti-skid method | |
US6745421B2 (en) | Abutment with seismic restraints | |
CN204738304U (en) | An anchor rope framed bent friction pile combination fender structure | |
CN206418509U (en) | A kind of anchored pile supporting of high gradient slope | |
CN108755745A (en) | A kind of Novel section steel cantilever retaining structure and its design and calculation method | |
CN113158294B (en) | Design method of slowly-inclined fold line sliding surface side slope deep-buried shear pile supporting structure | |
CN203270588U (en) | Mini-pile antiskid structure | |
CN211713987U (en) | Three-dimensional frame pile body structure for deep landslide treatment | |
CN212001250U (en) | Triangular frame reinforced concrete retaining wall | |
CN114032932A (en) | Construction method of mixed retaining structure | |
CN107130617A (en) | A kind of flat pressure dispersing anchorage cable wall retaining structure of rock matter cut slope | |
CN217027038U (en) | Pile anchor structure capable of adapting to soil filling, consolidation and settlement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |