CN112968441B - Power grid planning method applied to large-scale wind power base - Google Patents
Power grid planning method applied to large-scale wind power base Download PDFInfo
- Publication number
- CN112968441B CN112968441B CN202110269583.8A CN202110269583A CN112968441B CN 112968441 B CN112968441 B CN 112968441B CN 202110269583 A CN202110269583 A CN 202110269583A CN 112968441 B CN112968441 B CN 112968441B
- Authority
- CN
- China
- Prior art keywords
- power
- wind
- wind power
- cost
- capacity
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/38—Arrangements for parallely feeding a single network by two or more generators, converters or transformers
- H02J3/381—Dispersed generators
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2203/00—Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
- H02J2203/20—Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2300/00—Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
- H02J2300/20—The dispersed energy generation being of renewable origin
- H02J2300/28—The renewable source being wind energy
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/76—Power conversion electric or electronic aspects
Abstract
The invention discloses a power grid planning method applied to a large-scale wind power base, which comprises the following steps of: carrying out gridding processing on a single wind power cluster region, establishing an optimization model by considering the cost of a wind field outlet substation, the cost of a collection station and the cost of a line, converting the model into a mixed integer linear optimization model by including the constraint condition of an actual grid-connected project, and calling cplex by using Matlab to solve; for the whole area, giving wind resource data of each point, converting wind measurement data into output data of an unfinished wind power plant, establishing a constraint condition including wind power admission level, wherein the constraint condition is the sum of investment cost and scheduling cost of a power grid in a planning period as an optimization target, and solving the optimization model by using a neural network to obtain a medium-term and long-term planning model of a large-scale wind power base; the invention can be used for planning the large-scale wind power base to be connected into a large power grid, and provides a more scientific and reasonable planning method for safely and economically connecting the output of the large-scale wind power base into the power grid.
Description
Technical Field
The invention relates to the technical field of wind power plant planning, in particular to a power grid planning method applied to a large-scale wind power base.
Background
The planning design of the power grid comprising the wind power plant is used as an important work in the early decision-making stage of the power grid development, and is directly related to the safe and stable operation level of the power grid and the economic level of energy utilization and power grid investment. The power grid planning is divided into three phases of long-term, medium-term and short-term.
In order to integrate resources and reasonably adjust the energy supply ratio, a plurality of large-scale wind power bases are planned in each country. Except for the existing developed mode of more centralized wind power resources. There are also areas where large-scale wind resources are abundant that have not yet been developed. The main mode of the wind power base is not on-site consumption, but the generated electric energy is basically sent out. In the development process, the traditional scheme is that planning and later scheduling operation and maintenance are considered separately.
As shown by a large number of studies at present. And analyzing the uncertainty of the wind power resource. There is a correlation of output among wind farms in a certain area. The wind power output in the large-scale region has certain output complementarity, and the fluctuation of the regional wind power generation output can be reduced. In the early planning design, if the coupling characteristic between the wind power plant and the wind power electric field is added, the wind power plant with complementary wind resources is reasonably matched, and different wind resource regions are reasonably developed sequentially, so that the large-scale wind power output power grid or the cost of the later scheduling of the high-permeability power grid and the power line fluctuation of the output power can be greatly saved. When a large-scale external power transmission wind power base is designed and planned in the early period, if the time-space correlation characteristics of wind resources are reasonably considered, the sequential order of wind resource development is considered on the basis of the existing power grid planning. The operation cost can be reduced in the full life cycle of the power grid, so that the full life cycle cost is reduced. Therefore, how to integrate the power grid and the operation and maintenance scheduling becomes a topic with practical research value.
Disclosure of Invention
In order to solve the technical problems, the invention provides a power grid planning method applied to a large-scale wind power base, which can be used for constructing a cluster wind power planning model considering the cost of a transformer substation and the cost of a power transmission line and a medium-long term planning model of the large-scale wind power base comprehensively considering the planning cost and the scheduling operation cost by considering the actual problems of actual power transmission and transformation projects, and determining the site selection and the sequential development sequence of wind power clusters in a planning area.
A power grid planning method applied to a large-scale wind power base is characterized by comprising the following steps:
acquiring data of an existing power grid, load requirements in a planning period, wind resource evaluation results in a planning area, wind resource data in the planning area, planning cost parameters of each site, typical construction cost of a power transmission project, and rasterizing a research area;
and selecting the area of the wind power cluster according to the wind resource distribution condition of the research area, and then establishing an optimization model considering the cost of the transformer substation and the cost of the power transmission line for each wind power cluster area to obtain the site selection of the transformer substation, thereby obtaining the grid structure of the wind power cluster. Establishing a power grid optimization model considering planning cost and scheduling operation cost for the areas of the clusters, and ensuring that constraint conditions of actual grid connection are met;
and converting a mathematical optimization model of site selection of the transformer substation of the wind power cluster into a mixed integer linear model, solving by adopting a Matlab + Yalmip + CPLEX solver to obtain a final site selection of the transformer substation, and determining a grid structure. Solving a mathematical model of the sequential development of the electric field in the whole area through a neural network algorithm to obtain a final planning scheme of 4 periods, wherein each period is 5 years;
the target function expression of the site selection of the transformer substation is as follows:
in the formula (I), the compound is shown in the specification,the construction and operation cost of the grid-connected process is reduced, the construction time of the grid-connected power transmission process is neglected,can be further defined as:
wherein, the first and the second end of the pipe are connected with each other,to representThe construction cost of the wind farm outlet substation of (1),to representThe construction cost of the power transmission line at the outlet of the power station,of the representationThe construction cost of the collection station of the wind farm group,represents the construction cost of the collection station grid-connected transmission line,as is the number of wind farm power stations,to be the number of the aggregation stations,incorporating collection stations for wind-farm power stationsThe number of the lines is set to be,for wind power plant to pass through node directlyA 110kV line to be connected to the grid,passing nodes for sink stationsA grid-connected line;
in actual engineering, the construction cost of a transformer substation of a wind power base is a function of the transformation capacity; therefore, the first and second electrodes are formed on the substrate,can be written as:
in order to correspond to the variable capacitance of the element,is thatFirst, theSegment ofThe construction cost of (a) is a fixed parameter.To judgeWhether or not in the interval0-1 decision variable withinWhen the temperature of the water is higher than the set temperature,the constraint of (2) is established in the following way,;a sufficiently large positive number, K is taken in this application as 1000;
and the construction cost of the unit grid-connected line of the wind power plant and the transmission capacity of the line present a functional relationship. Therefore, it is not only easy to useCan be written as:
substation being a wind farmWhether to sort to a collection station of a group of wind farmsThe 0-1 decision variable of (a),is to judgeWhether or not in the intervalOf decision variables ofRepresentAndthe product of (a), linearizes the equation,representing wind-farm power stationsTo a collection stationThe distance of (a);
further, the constraint conditions of the optimization objective function of the substation site selection are as follows:
(1) Determining the variable of the division of the wind power plant group for ensuring that each wind power plant can be operated in a grid-connected modeVariables for direct grid connection of wind farm power station to main grid nodeSatisfy the requirements of
(2) In order to ensure grid-connected operation of the wind power station group, variables of a collection station grid-connected to a main network node are determinedAnd satisfies the following conditions:
(3) The capacity constraint of the grid-connected transmission project of the wind power plant generation base mainly comprises that the capacity of an outlet substation of a wind power plant power station is not less than the capacity of an outlet line of the wind power plant power station, the transformation capacity of a collection station of a wind power plant power station group is not less than the sum of the capacities of all outlet lines of the wind power plant power stations collected to the collection station, and the capacity of a grid-connected transmission line of the collection station is not more than the capacity of the collection station:
(4) For the site selection range of the collection station of the wind power plant group, limiting a site selection feasible domain R:
(5) The number of the collection station seats required to be built by planning is determined by the actual grid-connected requirement of the new energy power station, and two extreme conditions are considered, wherein each wind power station is directly connected with the grid, and each wind power station is matched with one collection station to build a collection station grid. Thus, the number of convergent stations required to be constructed is plannedThe constraints are as follows:
cluster planning for the entire area: firstly, converting wind speed data into output data according to parameters of a fan and a wind speed-power formula, wherein the design capacity of each wind power cluster is 500MW, selecting the number N of the wind power clusters needing to be built according to the load requirement of a planning period, adding every N power of selected points to obtain total output power, and utilizing a relative standard deviationTo measure the fluctuation of the output, wherein
The functional expression of the mathematical model developed sequentially of the electric field within the region is:
in the formula (I), the compound is shown in the specification,the investment and construction cost of the unit can be further defined as follows:
t is the planning age, r is the discount rate,for the investment cost of the newly invested wind power cluster in the t year,in order to invest cost (yuan/MW) at the point i, the cost also includes the construction cost of the power transmission line caused by different distances between the wind power base and the load center at different points.The total installed capacity of the unit which needs to be newly input in the t year within the point i;
in the economics, the characteristic that funds have time value for discount rate means that the current purchasing power of one unit of currency is different from the purchasing power of one unit of currency in the future, and the currency will increase in value over time. In economics, the discount rate, which is the rate at which future limited-term expected revenue is discounted to a realized value, is introduced to measure this time-value property of capital. Due to the time value attribute of the currency, the investment values of the wind power cluster in different years are different, and in order to evaluate the planning scheme more accurately, the investment costs in different years need to be converted to the same period for comparison. The discount rate is introduced, and all the expenses can be converted to be calculated at the beginning of the first year;
a cost in actual operation is included, and the cost comprises the fuel expense of the thermal power generating unit, the system load shedding penalty cost and the wind abandoning cost. Namely:
the cost of fuel consumed by the thermal power unit mainly refers to the cost of fuel generated by the operation of the thermal power unit, and the operation of the thermal power unitAnd meanwhile, the fuel cost generated by the power generation unit is related to the power generation amount of the unit, and the fuel cost generated by the power generation amount in different scenes is calculated by adopting a linear programming method.The number of the scenes is referred to as the number,the consumed fuel coefficient is generated for the unit generating capacity of the thermal power generating unit,refers to the probability of each scene occurring,representing the length of time that the scene s is generating,represents the power generation time of thermal power under each scene in a year,representing the output power of the thermoelectric generator set in the s scene in the t year;
in a power system containing wind power, due to the time sequence fluctuation and the incomplete prediction accuracy of the wind power, the situation that the system is forced to cut load can possibly occur in some extreme scenes, the system load cutting penalty cost is added into a model, and the load cutting amount of the system is reduced as much as possible;for cutting loadThe penalty factor of (2) is determined,the load shedding amount of the system in a t-year scene s;
in order to improve the permeability of the wind power in the power system, the wind abandoning cost is added into the model.To curtail the cost of wind, it can be further defined as:
cost coefficient for wind power abandonment;the method is characterized in that the method is the abandoned wind power of the system in a scene of t years s;
further, the constraint conditions of the optimization objective function are as follows:
(1) Total installed capacity equation:
the total installed capacity is a discrete variable, and in order to simplify calculation, a plurality of wind power plants can be built at the position with each point location as the center according to planning requirements, namely the total installed capacity in the position with each point location as the center can only be an integral multiple of the installed capacity of the optional wind power plants. In the equationRepresenting the total installed capacity of point i in year t.Is a variable 0-1, which is used for selecting whether a unit is put into operation at the point, assuming that a plurality of capacity-level wind power clusters can be selected during planning, when the capacity of the first-level wind power cluster is selected to be built at the point i,on the contrary。A set of alternative construction capacities of the unit is represented,indicating the alternative capacity of the l-th unit (specifying the value of the expression for 1 for l as 0, i.e.)。
The total installed capacity expression restricts that each point location can only be selected by one capacity level at most, and the capacity level determines the total installed capacity which can be built by the point location. For example, if an alternate construction capacity of 500MW level is selected, thenAnd so on.
(2) Active power balance constraint
N is a node number, and k is a line number; s is a scene number;、 respectively representing the output power (MW) of the thermal power generating unit and the wind power generating unit at the t moment of the scene s, respectively representing incidence matrixes of the node-thermal power generating unit and the node-wind power generating unit, and representing the contact between the node and the wind power generating unit by using the matrixes;representing the load demand (MW) at node n at time t,representing the power flow on line k in scene s;is a node-branch incidence matrix;representing a set of power lines.
(3) Constraint of DC power flow equation
In the formula (I), the compound is shown in the specification,represents the admittance of line k;representing the phase angle at node n in scene s;for node-branch offA joint matrix;represented as a set of nodes;
(4) Existing thermal power generating unit output constraint
Actual output (MW) of the generator set i in a scene s for the generator set in the t year;respectively representing the upper and lower output limits of the thermal power generating unit i,indicating that the thermal generator set is available.
(5) Newly-built wind power cluster output restraint:
in the formulaRepresents the actual contribution ((MW) of the wind power cluster i in the scene in year t,the wind intensity coefficient at the point i in the scene s is represented, the size of the wind intensity coefficient is related to the distribution condition of wind resources, and the point with the richest wind resources in the planning area is takenThe value is 1, and the coefficients of other point locations are determined according to the proportion of the wind intensity of the point location to the wind intensity of the point location with the most abundant wind resources。
(6) Line transmission capacity constraints
(7) Constraint of phase angle:
in the formulaRepresenting the phase angle at the balancing node, the phase angle at the balancing node is 0, and the phase angles at other nodes are free variables.
The invention has the beneficial effects of disclosing a power grid planning method applied to a large-scale wind power base and a sequential development method of the large-scale wind power base. Aiming at a single wind power cluster, the cost of a transformer substation and the cost of a power transmission line are considered, an optimization model for addressing of the transformer substation is established, the complementarity between large-scale wind power bases is considered, the optimization model comprehensively considering the planning cost and the scheduling operation cost is established, the sequential development sequence of large-scale wind power base planning is obtained, the development direction of a power grid is determined, and the accurate investment of the power grid is realized. The method can be used for power grid planning and sequential development under large-scale wind power integration.
Drawings
Fig. 1 is a grid diagram of a research area according to the present invention.
Fig. 2 is a schematic diagram of a power grid planning result of the wind power base.
FIG. 3 is a schematic diagram of the system of the present invention.
FIG. 4 is a flow chart of the present invention.
FIG. 5 is a wind resource analysis display for a region of the present invention.
Fig. 6 is a schematic diagram of the wind farm cluster access grid of the research case.
Detailed Description
Referring to fig. 1-6, the present invention designs a power grid planning method applied to a large-scale wind power base, which mainly comprises the following steps:
1. grid planning for the cluster:
(1) Parameter setting
The planning region is defined as a two-dimensional spaceTo characterize the geographical range, the grid is numbered using a two-dimensional coordinate system, as shown in fig. 1; each grid isGrid, obtaining 32 grids in total;
assuming that a 50MW wind power plant can be built in each grid area, wherein the total number of the wind power plants is 32, and the transformer substation of each wind power plant is assumed to be built in the center of a grid; specifically, as shown in table 1, the power grid of the wind power base is planned by using a mathematical optimization model for site selection of the substation in the specification, and the voltage levels of the substations at the outlet of the wind power plant are all 110kV.
TABLE 1 research area wind farm essential information
The wind power base is provided with a 500kV/750kV cluster central station which is used for collecting the output of all wind power plants in the base; in this way, the cluster central station is used as a common connection point for grid connection of the wind power plant or the wind power plant group and is directly connected with the extra-high voltage backbone network frame in the grid connection area. Assume cluster hub location is 11 (45, 45); typical construction cost tables of the power transmission project involved in the method are shown in table 2;
note: the optimization of the planning scheme in the application is to build an MILP model of a wind power grid planning model on Matlab, call a CPLEX12.5 solver to solve the scheme, and configure a used calculator as an Intel (R) Core (TM) i5-4200H @3.40 GHz,8GB RAM.
TABLE 2 typical cost of transmission projects
(2) Scheme analysis for power grid planning
In the power grid planning scheme, 32 wind power plants are directly connected with a cluster central station through 110kV lines. Meanwhile, the capacity configuration of the outlet transformer substation and the outlet line of each wind power plant is carried out in the manner mentioned in the scheme; according to the planning method of the wind power generation base access system, a planning scheme of the wind power generation base access system can be obtained, and simulation results show that:
according to the planning method for the access system of the wind power generation base, the planning scheme for the access system of the wind power generation base can be obtained, and simulation results show that:
the 32 wind power plants are divided into 3 groups for access, and the total cost is lowest. Grouping condition: 1. 2, 3, 7, 8,9, 13, 14, 15 and 19 are the wind farm group 1, and the site selection of the collection station 1 is (16.52, 43.87); 20. 21, 22 and 24-32 are a wind farm group 2, and the site selection of a gathering station 2 is (37.32, 14.58); 4.5, 6, 10, 11, 12, 16, 17, 18 and 23 are wind power plants 3 which are directly connected with a central substation; the line optimization configuration results are shown in table 3; the specific wiring form is shown in fig. 2.
TABLE 3 line configuration optimization results
In addition, fig. 2 also shows that the site of the collection station is located at the middle position of each wind farm inside the wind farm group (the total length of 110k lines is shorter, and 220kV grid-connected lines are longer), but not at the middle position of the public connection point outside the wind farm group (the total length of 110kV lines is longer, and the 220kV lines are shorter). The construction cost of the unit capacity of the 220kV power transmission line is lower than that of the unit capacity of the 110kV power transmission line, and from the economical point of view, if a plurality of wind power plants need to be connected to the power grid through a collecting station, the length of the power transmission line with a lower voltage level is reduced as much as possible by the access system scheme, so that the total cost of the power transmission project is reduced, for example, each cost of the planning scheme of the wind power cluster access system is shown in table 4. Wind power plants with similar geographic positions are divided into the same wind power plant group, a gathering station of the wind power plant group is located in the middle of an area surrounded by the wind power plants, and a main network node closest to the gathering station is selected as a public connection point to be connected to the grid.
TABLE 4 costs of wind power cluster access system planning scheme
2. And (3) medium-long term planning aiming at the large-area wind power cluster:
(1) Setting parameters:
the calculation example adopts the sales electricity quantity of a certain region in China as a load, the average sales electricity quantity growth rate of nearly five years as a load growth rate, actual measurement data of wind speed as calculation example basic data, sampling intervals are one hour, the load data of the first year is used as a reference year, the planning process is carried out by taking a period as a unit, the load growth rate is 9 percent per year, if the planning period is set to be 20 years in 4 periods, the planning internal load growth condition is shown in a table 5, a system standby unit is a 600MW thermal power unit, and the coal consumption is reduced,=800 yuan/MW,=500 yuan/MW;
TABLE 5 schematic diagram of system load change during planning period
In order to verify the feasibility of the model accessing to the power grid, a system with 5 nodes is adopted as a test system, a system diagram is shown in fig. 3, thermal power generating units are respectively installed on the nodes 1 and 2, and the nodes 3,4 and 5 are respectively accessed to two wind power plant groups.
(2) Simulation result
First applying the relative standard deviationThe combination with the least volatility was chosen at the selection points 3,4,6,8,9,11, and a mathematical model was developed according to the sequence described above, resulting in a phase 4 planning scheme as shown in table 6:
TABLE 6 planning scheme Table
As can be seen from the planning results, the wind power clusters are invested in each planning period to meet the load demand of the system, wherein as the load increases year by year, 2 wind power clusters need to be built in 3,4 th period to meet the load demand.
Claims (2)
1. A power grid planning method applied to a large-scale wind power base is characterized by comprising the following steps:
for a single wind power cluster center, constructing a mathematical optimization model, wherein the optimization model takes the sum of the cost of a wind power plant transformer substation, the cost of a collection station and the cost of lines among all stages of transformer substations as the optimal target and contains engineering constraints in a power transmission project, converting the optimization model into a mixed integer linear programming model, and solving the model by using a mixed integer linear programming solver to obtain a grid structure of the single wind power cluster;
the optimization model is as follows:
an objective function:
in the formula (I), the compound is shown in the specification,the construction and operation cost in the grid-connected process is reduced, the construction time in the grid-connected power transmission process is ignored,can be further defined as:
wherein the content of the first and second substances,to representThe construction cost of the wind farm outlet substation of (a),to representThe construction cost of the power transmission line at the outlet of the power station,of the representationThe construction cost of the collection station of the wind farm group,power transmission line for indicating collection station and connecting to power gridThe construction cost of the road is reduced,as is the number of wind farm power stations,to be the number of the aggregation stations,incorporating collection stations for wind-farm power stationsThe number of the lines is set to be,for wind power plant to pass through node directlyA grid-connected 110kV line,passing nodes for sink stationsA grid-connected line;
in actual engineering, the construction cost of a transformer substation of a wind power base is a function of the transformation capacity; therefore, the first and second electrodes are formed on the substrate,can be written as:
in order to correspond to the variable capacitance of the element,is thatFirst, theSegment ofThe construction cost of (a) is a fixed parameter;to judgeWhether or not in the interval0-1 decision variable withinWhen the temperature of the water is higher than the set temperature,the constraint of (2) is established in the following way,;a positive number large enough, K is 1000;
the construction cost of a unit grid-connected line of the wind power plant and the transmission capacity of the line present a functional relationship; therefore, it is not only easy to useCan be written as:
substation being a wind farmWhether to sort to a collection station of a group of wind farmsThe 0-1 decision variable of (a),is to judgeWhether or not in the intervalOf decision variables ofRepresentsAndthe product of (a) and (b), linearizes the equation,representing wind-farm power stationsTo a collection stationThe distance of (d);
the constraint conditions of the objective function of the site selection of the transformer substation are as follows:
(1) Determining the variable of the division of the wind power plant group for ensuring that each wind power plant can be operated in a grid-connected modeVariable directly connected to main network node by new energy power stationIt must satisfy:
(2) In order to ensure the grid-connected operation of the new energy power station group, a variable from a collection station to a main network node is determinedIt must satisfy:
(3) The capacity constraint of the grid-connected power transmission project of the wind power generation base mainly comprises that the capacity of an outlet transformer substation of a wind power station is not less than the capacity of an outlet line of a new energy power station; the transformation capacity of a collection station of a wind power station group cannot be smaller than the sum of the capacities of outlet lines of all wind power stations collected to the collection station; the capacity of the collection station grid-connected power transmission line is not greater than the capacity of the collection station:
(4) For the site selection range of the collection station of the wind power plant group, limiting a site selection feasible domain R:
(5) The number of the collection stations required to be built by planning is determined by the actual grid-connected requirement of the wind power plant power stations, and two extreme conditions are considered, wherein each wind power plant power station is directly connected with the grid; thus, the number of convergent stations required to be constructed is plannedThe constraints are as follows:
planning the wind power bases in the whole area, considering the space-time complementary characteristics and load requirements of each field group, establishing a medium-long term planning optimization model comprehensively considering planning cost and scheduling cost, and solving through a neural network to obtain a sequential development sequence of electric fields in the area;
firstly, converting wind speed data into output data according to parameters of a fan and a wind speed-power formula, wherein the design capacity of each wind power cluster is 500MW, selecting the number N of the wind power clusters needing to be built according to the load requirement of a planning period, adding every N power of selected points to obtain total output power, and utilizing a relative standard deviationTo measure the fluctuation of the output, wherein
By the relative standard deviation obtainedClustering the wind power output data through k-means to obtain a typical output scene; establishing an optimization model comprehensively considering planning cost and scheduling operation cost to obtain a sequential development sequence of the wind power clusters;
the sequential development model of the electric field in the region is as follows:
an objective function:
in the formula (I), the compound is shown in the specification,the unit investment and construction cost can be further defined as:
t is the planning age, r is the discount rate,for the investment cost of the newly invested wind power cluster in the t year,the investment cost is on the point i, the unit is yuan/MW, and the cost also comprises the construction cost of the power transmission line caused by different distances between the wind power base and the load center on different points;the total installed capacity of the unit which needs to be newly input in the t year within the point i;
in the economics, the capital has the characteristic of time value, namely the purchasing power of one unit of currency in the present time is different from that of one unit of currency in the future, and the currency is increased with the time; in economics, discount rate, which is the rate of converting future limited-term expected revenue to realized value, is introduced to measure this time-value property of capital; due to the time value attribute of the currency, the investment values of the wind power cluster in different years are different, and in order to more accurately evaluate the planning scheme, the investment costs in different years need to be converted to the same period for comparison; the discount rate is introduced, and all the expenses can be converted to be calculated at the beginning of the first year;
including a cost at actual runtime, includingFuel cost of a thermal power generating unit, system load shedding penalty cost and wind abandoning cost are reduced; namely:
the cost of fuel consumption of the thermal power unit mainly refers to the fuel cost generated by the operation of the thermal power unit, when the thermal power unit operates, the fuel cost generated by the thermal power unit is related to the generated energy of the thermal power unit, and the fuel cost generated by the generated energy of different scenes is calculated by adopting a linear programming method;the number of the scenes is referred to as the number,the consumed fuel coefficient is generated for the unit power generation amount of the thermal power generating unit,means the probability of occurrence of each scene, T S Representing the length of time that the scene s is generating,represents the power generation time of thermal power under each scene in a year,representing the output power of the thermoelectric generator set in the s scene in the t year;
in a power system containing wind power, due to the time sequence fluctuation and the incomplete prediction accuracy of the wind power, the situation that the system is forced to cut load can possibly occur in some extreme scenes, the system load cutting penalty cost is added into a model, and the load cutting amount of the system is reduced as much as possible;in order to make the penalty factor of load shedding,= 800-membered/MWh,the load shedding amount of the system in a t-year scene s;
in order to improve the permeability of the wind power in the power system, the wind abandoning cost is added into the model;to curtail the cost of wind, it can be further defined as:
in order to abandon the cost coefficient of the wind power,=500 yuan/MWh;the method is characterized in that the method is the abandoned wind power of the system in a scene of t years s;
the constraint conditions of the objective function are as follows:
(1) Total installed capacity equation:
the total installed capacity is a discrete variable, and in order to simplify calculation, a plurality of wind power plants can be built at the position with each point location as the center according to planning requirements, namely the total installed capacity in the position with each point location as the center can only be an integral multiple of the installed capacity of the selectable wind power plants; in the equationRepresenting the total installed capacity of the t year point position i;is a variable 0-1, which is used for selecting whether a unit is put into operation at the point, assuming that a plurality of capacity-level wind power clusters can be selected during planning, when the capacity of the first-level wind power cluster is selected to be built at the point i,on the contrary;Representing a set of unit alternative construction capacity,representing the alternative capacity of the l-th unit, specifying the value of the expression for 1, i.e. 0;
The total installed capacity expression restricts that each point location can only have one capacity level at most to be selected, and the capacity level determines the total installed capacity which can be built by the point location; if an alternative construction capacity of the 500MW level is selected, thenAnd so on;
(2) Active power balance constraint
N is a node number, and k is a line number; s is a scene number;、respectively representing the output power of the thermal power generating unit and the wind power generating unit at the moment t of the scene s, the unit is MW,respectively representing incidence matrixes of the node-thermal power generating unit and the node-wind power generating unit, and representing the contact between the node and the wind power generating unit by using the matrixes;representing the load demand at node n at time t, in MW,representing the power flow on line k in scene s;is a node-branch incidence matrix;representing a set of power lines;
(3) Constraint of DC power flow equation
In the formula (I), the compound is shown in the specification,represents the admittance of line k;representing the phase angle at node n in scene s;is a node-branch incidence matrix;represented as a set of nodes;
(4) Existing thermal power generating unit output constraint
The actual output of the generator set i in the scene s in the t year of the generator set is MW;respectively representing the upper and lower output limits of the thermal power generating unit i,representing the existing thermal generator set;
(5) Newly-built wind power cluster output restraint:
in the formulaThe actual output of the wind power cluster i in the scene in the t year is expressed in MW,representing the wind intensity coefficient at the point i in the scene s, the size of the coefficient is related to the distribution condition of the wind resources, and the point with the richest wind resources in the planning area is takenThe value is 1, and the coefficients of other point locations are determined according to the proportion between the wind intensity of the point location and the wind intensity of the point location with the most abundant wind resources;
(6) Line transmission capacity constraints
(7) Constraint of phase angle:
2. The power grid planning method applied to the large-scale wind power base according to claim 1, wherein: the method comprises the steps of obtaining or planning data of a power grid of a given area in advance, typical construction cost data of a power transmission project of the planned area, unit cost data of the planned area, space-time complementary characteristics of the planned area, wind resource data of the planned area and load prediction data of the planned area.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110269583.8A CN112968441B (en) | 2021-03-12 | 2021-03-12 | Power grid planning method applied to large-scale wind power base |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110269583.8A CN112968441B (en) | 2021-03-12 | 2021-03-12 | Power grid planning method applied to large-scale wind power base |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112968441A CN112968441A (en) | 2021-06-15 |
CN112968441B true CN112968441B (en) | 2023-03-24 |
Family
ID=76277713
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110269583.8A Active CN112968441B (en) | 2021-03-12 | 2021-03-12 | Power grid planning method applied to large-scale wind power base |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112968441B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113642788A (en) * | 2021-08-10 | 2021-11-12 | 陕西四季春清洁热源股份有限公司 | Diversified heat source optimization planning method suitable for large-scale medium-deep geothermal region |
CN113675940B (en) * | 2021-08-17 | 2024-04-16 | 中国华能集团清洁能源技术研究院有限公司 | Plant factory power supply system and plant factory power supply method |
CN116436020A (en) * | 2023-05-05 | 2023-07-14 | 国网湖南省电力有限公司 | Demand judging method and system for new energy Internet surfing aggregation station |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104124707A (en) * | 2014-07-23 | 2014-10-29 | 北京四方继保自动化股份有限公司 | Hydropower station power quick adjustment system and implementation method based on intensive small hydropower station groups |
CN108365610A (en) * | 2018-01-16 | 2018-08-03 | 华北电力大学 | A kind of reactive voltage control method coordinated based on source net |
CN109728605A (en) * | 2019-03-01 | 2019-05-07 | 西安交通大学 | Planing method is combined in wind power plant-power transmission network based on chance constraint IGDT-energy storage |
Family Cites Families (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103746389B (en) * | 2014-01-21 | 2016-08-17 | 国家电网公司 | Wind-powered electricity generation 500kV based on reactive voltage characteristic collects Substation Reactive-power Compensation collocation method |
CN105375513B (en) * | 2015-11-06 | 2017-08-25 | 国家电网公司 | A kind of 110 kilovolts of wind power field automatic voltage controls based on real-time on-line equivalent |
CN107294130B (en) * | 2017-06-28 | 2020-01-17 | 东北电力大学 | Wind storage power generation black start system and energy storage configuration method thereof |
CN108683197A (en) * | 2018-06-15 | 2018-10-19 | 北京清大高科系统控制有限公司 | It reduces large-scale wind electricity and the dynamic reactive power configuration method of wind problem is abandoned in barrier |
US11165254B2 (en) * | 2018-09-18 | 2021-11-02 | Sinewatts, Inc. | Systems and methods for electricity generation, storage, distribution, and dispatch |
CN109524988B (en) * | 2018-11-26 | 2021-12-03 | 国网河北省电力有限公司 | Wind power collection station voltage control method based on total active power trend prediction |
US20200203951A1 (en) * | 2018-12-19 | 2020-06-25 | Battelle Memorial Institute | Transactive mechanism to engage inverters for reactive power support |
CN111082466B (en) * | 2019-12-27 | 2021-03-02 | 国网宁夏电力有限公司经济技术研究院 | New energy access and grid frame extension optimization method considering wind power uncertainty |
CN111799777A (en) * | 2020-06-11 | 2020-10-20 | 国网山东省电力公司经济技术研究院 | Comprehensive energy planning method considering coupling of natural gas and electric power |
-
2021
- 2021-03-12 CN CN202110269583.8A patent/CN112968441B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104124707A (en) * | 2014-07-23 | 2014-10-29 | 北京四方继保自动化股份有限公司 | Hydropower station power quick adjustment system and implementation method based on intensive small hydropower station groups |
CN108365610A (en) * | 2018-01-16 | 2018-08-03 | 华北电力大学 | A kind of reactive voltage control method coordinated based on source net |
CN109728605A (en) * | 2019-03-01 | 2019-05-07 | 西安交通大学 | Planing method is combined in wind power plant-power transmission network based on chance constraint IGDT-energy storage |
Also Published As
Publication number | Publication date |
---|---|
CN112968441A (en) | 2021-06-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112968441B (en) | Power grid planning method applied to large-scale wind power base | |
CN106874630B (en) | Electric quantity consumption-based regional power grid new energy development potential evaluation method | |
CN113746144B (en) | Source-grid-load real-time interaction electric carbon control method and intelligent management system thereof | |
CN105356492B (en) | A kind of energy management analogue system and method suitable for micro-capacitance sensor | |
CN109103926A (en) | Photovoltaic power generation based on more Radiation Characteristics year meteorology scenes receives capacity calculation method | |
CN102063563B (en) | Network-province-local integrative bus load predicting method | |
CN112178756B (en) | Intelligent heat supply management system and working method thereof | |
CN103577901A (en) | Method of intertidal zone wind power for accessing power grid | |
CN103138256A (en) | New energy electric power reduction panorama analytic system and method | |
CN109978242A (en) | The photovoltaic power generation cluster power forecasting method and device of scale are risen based on statistics | |
CN109740808A (en) | A kind of scene water complemental power-generation plan calculation method and system | |
Weinand et al. | Identification of potential off-grid municipalities with 100% renewable energy supply for future design of power grids | |
CN114243709A (en) | Scheduling operation method capable of adjusting resource layering and grading at demand side | |
CN115081902B (en) | Comprehensive planning method, device, equipment and medium based on source network load storage cooperation | |
CN105654224A (en) | Provincial power-grid monthly electricity purchasing risk management method considering wind power uncertainty | |
CN108695859A (en) | A kind of capacitor group addressing constant volume method of access active distribution network | |
CN107769268A (en) | Scope is adjusted to predict that province supplies load method a few days ago in a kind of ground containing small power station | |
CN114066315A (en) | Power distribution network planning system suitable for multi-source load access | |
CN105610199A (en) | Method and device for determining wind-solar ratio considering grid constraints | |
Zhang et al. | Multi–objective Cluster Partition Method for Distribution Network Considering Uncertainties of Distributed Generations and Loads | |
CN116167644A (en) | Evaluation index method for novel zero-carbon power system at distribution network side | |
CN114925962A (en) | Active power distribution network operation flexibility quantitative analysis method based on node marginal electricity price | |
CN113890029A (en) | Multi-objective optimization method for power distribution network with openable capacity improvement | |
CN114266471A (en) | Energy efficiency evaluation method for multi-energy flow coupling comprehensive energy of cold, heat and electricity | |
Maochun et al. | Typical scenario construction for fast assessment of renewable energy absorption capacity |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |