CN112878698A - Construction method for separately installing pipe truss and steel casting and sliding for aligning - Google Patents
Construction method for separately installing pipe truss and steel casting and sliding for aligning Download PDFInfo
- Publication number
- CN112878698A CN112878698A CN201911204631.4A CN201911204631A CN112878698A CN 112878698 A CN112878698 A CN 112878698A CN 201911204631 A CN201911204631 A CN 201911204631A CN 112878698 A CN112878698 A CN 112878698A
- Authority
- CN
- China
- Prior art keywords
- pipe
- truss
- steel casting
- pipe truss
- hoisting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/162—Handles to carry construction blocks
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/19—Three-dimensional framework structures
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/165—Tools or apparatus specially adapted for in situ prefabricated building elements to be tilted up in position
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention particularly relates to a construction method for installing a pipe truss and a steel casting separately and sliding and aligning the pipe truss and the steel casting; the method is characterized in that: firstly, mounting a steel casting on the top of a structural column, then hoisting a pipe truss to a high altitude by a crane, and placing the pipe truss between the installed pipe truss and the steel casting; adjusting the high-altitude posture of the lifting pipe truss and the position of the steel casting on the top of the column by respectively arranging the chain blocks; until the rabbet edge of the steel casting rabbet branch pipe is completely inserted into the inner wall of the lower chord pipe of the hoisting pipe truss, and pipe orifice butt joint is completed; the hoisting pipe truss is butted with the upper chord pipe and the lower chord pipe of the installed pipe truss, and pipe orifice butting is synchronously completed in the process of adjusting the high altitude attitude of the hoisting pipe truss; and then, arranging a horse board at the butt joint for fixing, and completing the in-place installation. According to the construction method, the pipe truss and the steel casting are quickly positioned through traction control of the chain block, and meanwhile, the plurality of pipe orifices are smoothly butted at the same time, so that the construction efficiency is improved, the mechanical shift is saved, and the safety risk is reduced.
Description
Technical Field
The invention relates to the field of steel structure construction, in particular to a construction method for separately installing a pipe truss and a steel casting and sliding and aligning.
Background
The large-scale cultural and tourism project stadium roof is mostly a large-span space circular tube truss structure, and a plurality of steel tubes in the truss structure are concentrated and penetrate through a complex node which is generally replaced by a finished steel casting, so that the size precision and the installation quality of the node are ensured. As shown in figures 1 and 2, the pipe orifices of the branch pipes (4.1), (4.2) and (4.3) of the steel casting (4) are grooves, after the lower chord (3.3) and the web members (3.4) and (3.4) of the hanging pipe truss (3) are butted with the branch pipes (4.1), (4.2) and (4.3) of the steel casting (4), the groove edges play a role of welding a liner plate so as to ensure the root penetration of a welding joint and the back forming of a welding seam. Under the influence of environmental conditions, under the condition that large-scale hoisting machinery cannot be selected, the hoisting pipe truss (3) and the steel casting (4) are hoisted separately and are butted at high altitude, due to the fact that the hoisting weight and the size are large, high altitude fine adjustment is not easy to control, labor and time are consumed for butting of upper and lower chord pipe orifices, and construction is very difficult.
Disclosure of Invention
The invention aims to overcome the defects and provide a construction method which is convenient to operate and can quickly realize the butt joint operation.
In order to achieve the above object, the present invention is realized by:
a pipe truss and steel casting are separately installed and slide to the construction method of the mouth; comprises that
Step 1, mounting a steel casting on the top of a structural column, wherein the mounting position temporarily deviates from the design position by 200 mm; then, hoisting the pipe truss to the high altitude by a crane, and placing the pipe truss between the installed pipe truss and the steel casting;
step 4, tightening the chain block, pulling the steel casting to slide leftwards, and inserting the rabbet edge of the rabbet branch pipe into the inner wall of the lower chord pipe of the lifting pipe truss; at the moment, the center lines of the lower chord tube and the rabbet branch tube are not completely superposed, and the rabbet edge cannot be completely inserted into the inner wall of the lower chord tube;
and 7, installing the web pipes of the hoisting pipe truss, additionally arranging a horse board for fixing, and finishing the opposite installation work of all the rod pieces.
The construction method aims at the limitation of selection of a large crane, provides a construction method for separately installing the pipe truss and the steel casting and sliding and aligning the pipe truss and the steel casting, enables the pipe truss and the steel casting to be in place quickly and enables a plurality of pipe orifices to be in butt joint smoothly at the same time through the traction control of a chain block, improves the construction efficiency, saves mechanical shifts and reduces the safety risk.
Drawings
FIG. 1 shows the steel castings in place with the pipe trusses installed separately from the steel castings and slid into place, with the pipe trusses suspended.
FIG. 2 is a schematic view of the pipe truss and the steel casting separately installed and sliding for alignment, showing the length of the slow release inverted chain, the posture of the truss being adjusted, the lower chord branch pipe being lifted up and facing the tongue-and-groove branch pipe of the steel casting.
FIG. 3 is a schematic view showing that the pipe truss and the steel casting are installed separately and slide to be aligned, and the pipe truss is lifted to move leftwards by tightening the chain block, and the upper chord pipe orifice of the pipe truss is close to the upper chord pipe orifice of the installed pipe truss.
FIG. 4 is a schematic view showing that the pipe truss and the steel casting are installed separately and are in sliding alignment, the steel casting is pulled to slide by tightening the chain block, and the rabbet edge of the rabbet branch pipe begins to be inserted into the lower chord pipe orifice of the hoisting pipe truss.
FIG. 5 is a schematic view showing that the inverted chain is continuously tightened, the pipe truss and the steel casting are separately installed and slide to match, the lifting pipe truss gradually returns, the steel casting continues to slide, and the rabbet edge of the rabbet branch pipe is further inserted into the lower chord pipe orifice of the lifting pipe truss.
FIG. 6 is a schematic view showing the complete alignment of the pipe truss and the steel casting, with the steel casting slid into place and the tongue-and-groove branch pipes completely abutting the lower chord pipes of the lifting pipe truss.
FIG. 7 is a schematic view of the pipe truss and the steel casting separately installed and sliding and aligning to another diagonal web member to complete the aligning installation of all the steel casting branch pipes.
Fig. 8 is a schematic diagram of a conventional method.
In the figure: 1-installed pipe truss, 1.1-installed pipe truss upper chord pipe, 1.2-installed pipe truss lower chord pipe, 2-supporting jig, 3-hoisting pipe truss, 3.1-hoisting pipe truss upper chord pipe, 3.2-hoisting pipe truss lower chord pipe a, 3.3-hoisting pipe truss lower chord pipe b, 3.4-hoisting pipe truss web pipe a, 3.5-hoisting pipe truss b, 4-manifold steel casting, 4.1-steel casting mouth branch pipe a, 4.2-steel casting mouth branch pipe b, 4.3-steel casting mouth branch pipe c, 5-structural column, 6.1-auxiliary lifting lug related to steel casting sliding, 6.2-auxiliary lifting lug related to upper line pipe butt joint, 6.3-lifting, 6.4-auxiliary lifting lug related to hoisting pipe truss adjusting posture, 7.1-overhead pipe truss upper chord adjusting posture, 7.2-overhead boom chain butt joint related to hoisting chain and 7.2-truss butt joint, 7.3-chain block, 8-hoisting wire rope, 9-lifting hook of the crane, 10-horse board, which are related to the sliding of the steel casting.
Detailed Description
The invention is further illustrated by the following specific examples.
As shown in fig. 1 to 7, a construction method for installing a pipe truss and a steel casting separately and sliding for opening; comprises that
Step 1, mounting a steel casting 4 on the top of a structural column 5, wherein the mounting position temporarily deviates from a design position by 200 mm; then, the hoisting machine hoists the pipe truss 3 to the high altitude and places the pipe truss between the installed pipe truss 1 and the steel casting 4;
step 4, tightening the chain block 7.3, pulling the steel casting 4 to slide leftwards, and inserting the rabbet edge of the rabbet branch pipe 4.1 into the inner wall of the lower chord pipe 3.3 of the lifting pipe truss 3; at this time, the center lines of the lower chord tube 3.3 and the rabbet branch tube 4.1 are not completely superposed, and the rabbet edge cannot be completely inserted into the inner wall of the lower chord tube 3.3;
and 7, installing the web pipes 3.4 and 3.5 of the hoisting pipe truss 3, and additionally arranging a horse board 10 for fixing to finish the opposite installation work of all the rod pieces.
The construction method aims at the limitation of selection of a large crane, provides a construction method for separately installing the pipe truss and the steel casting and sliding and aligning the pipe truss and the steel casting, enables the pipe truss and the steel casting to be in place quickly and enables a plurality of pipe orifices to be in butt joint smoothly at the same time through the traction control of a chain block, improves the construction efficiency, saves mechanical shifts and reduces the safety risk.
Claims (1)
1. A pipe truss and steel casting are separately installed and slide to the construction method of the mouth; the method is characterized in that: comprises that
Step 1, mounting a steel casting (4) on the top of a structural column (5), wherein the mounting position temporarily deviates 200mm from the design position; then, the hoisting machine hoists the pipe truss (3) to the high altitude and places the pipe truss (1) and the steel casting (4) between;
step 2, adjusting the high-altitude posture of the hoisting pipe truss (3) by slowly releasing the length of the chain block (7.1), so that the pipe orifice of the lower chord pipe b (3.3) is slightly lifted;
step 3, tightening the chain block (7.2), enabling the hoisting pipe truss (3) to translate leftwards, and enabling the upper opening of the upper chord pipe (3.1) to contact the upper opening of the upper chord pipe (1.1) of the installed pipe truss (1);
step 4, tightening the chain block (7.3), pulling the steel casting (4) to slide leftwards, and inserting the rabbet edge of the rabbet branch pipe (4.1) into the inner wall of the lower chord pipe (3.3) of the hoisting pipe truss (3); at the moment, the center lines of the lower chord tube (3.3) and the rabbet branch tube (4.1) are not completely superposed, and the rabbet edge cannot be completely inserted into the inner wall of the lower chord tube (3.3);
step 5, adjusting the height of the hoisting pipe truss (3) to return to normal by tightening the length of the inverted chain (7.1), so that the pipe orifice of the lower chord pipe b (3.3) of the hoisting pipe truss slightly descends, simultaneously continuously tightening the inverted chain (7.3), slowly pulling the steel casting (4) to slide leftwards, and further inserting the rabbet edge into the inner wall of the lower chord pipe (3.3);
step 6, adjusting the high-altitude posture of the lifting pipe truss (3) through the chain block (7.1), and pulling the steel casting (4) to slide leftwards through the chain block (7.3) until the rabbet edge of the rabbet branch pipe (4.1) is completely inserted into the inner wall of the lower chord pipe (3.3) to complete pipe orifice butt joint; the pipe orifice butt joint is synchronously completed in the process of adjusting the high altitude attitude of the hoisting pipe truss (3) by the hoisting pipe truss (3) and the upper chord pipe (3.1) and the upper chord pipe (1.1), the lower chord pipe (3.2) and the lower chord pipe (1.2) of the installed pipe truss (1); then, a horse board (10) is arranged at the butt joint for fixing, the installation in place is completed, and the hook (9) can be hooked loosely;
and 7, installing the abdominal pipes (3.4) and (3.5) of the hoisting pipe truss (3), and additionally arranging a horse board (10) for fixing to finish the opposite installation work of all the rod pieces.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911204631.4A CN112878698B (en) | 2019-11-29 | 2019-11-29 | Construction method for separately installing pipe truss and steel casting and sliding for aligning |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911204631.4A CN112878698B (en) | 2019-11-29 | 2019-11-29 | Construction method for separately installing pipe truss and steel casting and sliding for aligning |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112878698A true CN112878698A (en) | 2021-06-01 |
CN112878698B CN112878698B (en) | 2022-12-09 |
Family
ID=76038929
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911204631.4A Active CN112878698B (en) | 2019-11-29 | 2019-11-29 | Construction method for separately installing pipe truss and steel casting and sliding for aligning |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112878698B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115288287A (en) * | 2022-06-29 | 2022-11-04 | 上海宝冶集团有限公司 | Inclined installation system and installation method of ultra-large shuttle-shaped column |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102953553A (en) * | 2012-11-14 | 2013-03-06 | 中冶天工集团有限公司 | Method for installing large-span pipe truss by utilizing boom luffing mechanism |
CN104631837A (en) * | 2014-12-08 | 2015-05-20 | 永升建设集团有限公司 | Method for installing and constructing special-shaped large-tonnage steel castings |
WO2017121315A1 (en) * | 2016-01-12 | 2017-07-20 | 广州机施建设集团有限公司 | Construction method for building truss and floor slab |
CN107989380A (en) * | 2016-10-27 | 2018-05-04 | 中交三航局第三工程有限公司 | Steel truss gallery hydraulic synchronizing lifting construction technique |
CN108894329A (en) * | 2018-06-19 | 2018-11-27 | 中国冶集团有限公司 | A kind of installation method of overhanging type tubular truss and its support rod |
CN109441128A (en) * | 2018-12-21 | 2019-03-08 | 贵州建工集团第八建筑工程有限责任公司 | A kind of list Pin tubular truss overhead connection construction |
-
2019
- 2019-11-29 CN CN201911204631.4A patent/CN112878698B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102953553A (en) * | 2012-11-14 | 2013-03-06 | 中冶天工集团有限公司 | Method for installing large-span pipe truss by utilizing boom luffing mechanism |
CN104631837A (en) * | 2014-12-08 | 2015-05-20 | 永升建设集团有限公司 | Method for installing and constructing special-shaped large-tonnage steel castings |
WO2017121315A1 (en) * | 2016-01-12 | 2017-07-20 | 广州机施建设集团有限公司 | Construction method for building truss and floor slab |
CN107989380A (en) * | 2016-10-27 | 2018-05-04 | 中交三航局第三工程有限公司 | Steel truss gallery hydraulic synchronizing lifting construction technique |
CN108894329A (en) * | 2018-06-19 | 2018-11-27 | 中国冶集团有限公司 | A kind of installation method of overhanging type tubular truss and its support rod |
CN109441128A (en) * | 2018-12-21 | 2019-03-08 | 贵州建工集团第八建筑工程有限责任公司 | A kind of list Pin tubular truss overhead connection construction |
Non-Patent Citations (2)
Title |
---|
刘佩衡: "《塔式起重机驾驶》", 31 May 1988, 中国建筑工业出版社 * |
徐至钧: "《管道工程设计与施工手册》", 31 March 2005, 中国石化出版社 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115288287A (en) * | 2022-06-29 | 2022-11-04 | 上海宝冶集团有限公司 | Inclined installation system and installation method of ultra-large shuttle-shaped column |
CN115288287B (en) * | 2022-06-29 | 2024-01-30 | 上海宝冶集团有限公司 | Inclined installation system and installation method for oversized fusiform column |
Also Published As
Publication number | Publication date |
---|---|
CN112878698B (en) | 2022-12-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100557168C (en) | A kind of method for high altitude installation of large span steel truss | |
CN103410322B (en) | The parallel Truss Steel corridor construction method of large span | |
CN104153587B (en) | A kind of built with ribbed bricks body of wall assembly construction method | |
CN110230262A (en) | Basket type steel pipe arch bridge main arch rib semi-monolithic hoisting structure and interconnection method | |
CN108265628A (en) | One kind rides cable-styled erection crane lifting cable-stayed bridge girder steel and bridge floor board construction method | |
CN108582466A (en) | A kind of steel reinforcement cage of prefabricated box girder mould | |
CN112878698B (en) | Construction method for separately installing pipe truss and steel casting and sliding for aligning | |
CN106042173A (en) | Bridge production system | |
CN108842954A (en) | A kind of huge different section Honeycomb Beam structural system construction method of installation of aerofoil profile roofing | |
CN102226497B (en) | Manufacturing method of large rubber rolling curtain sealed dry-type gas holder | |
CN113123612A (en) | Steel structure hoisting method for greenhouse engineering | |
CN205875740U (en) | Standardized batter brace system of structure of encorbelmenting greatly construction die carrier | |
CN108952207B (en) | Steel structure building storey adding structure and storey adding method | |
CN110980500A (en) | Balanced stress auxiliary hanging beam and roof structure integral hoisting method | |
CN116497706A (en) | Device and method for transporting box girder steel bar parts for bridge deck | |
CN112878699A (en) | Construction method for butting pipe truss with steel casting tongue-and-groove branch pipe during hoisting of pipe truss | |
CN107881926B (en) | Combined hanging basket with full-rotation crane and construction method thereof | |
CN215854574U (en) | Quick mounting and dismounting fixture for box girder template | |
CN211664537U (en) | Balanced stress auxiliary hanging beam | |
JPH08134845A (en) | Erection method of bridge | |
CN208392315U (en) | A kind of steel reinforcement cage of prefabricated box girder mould | |
CN111877169A (en) | Construction method for erecting land heavy end cross beam without support and large crane | |
CN215249037U (en) | Assembled outer wall hoist and mount and fixed establishment | |
CN216072688U (en) | Integral hoisting tool for bottom web top steel bar framework of hollow slab beam | |
CN115976980B (en) | Installation method of continuous beam segment reinforcement cage |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |