CN112854021A - Rotary in-place construction method for crossing bridge - Google Patents

Rotary in-place construction method for crossing bridge Download PDF

Info

Publication number
CN112854021A
CN112854021A CN202110144846.2A CN202110144846A CN112854021A CN 112854021 A CN112854021 A CN 112854021A CN 202110144846 A CN202110144846 A CN 202110144846A CN 112854021 A CN112854021 A CN 112854021A
Authority
CN
China
Prior art keywords
steel box
girder
track
rotary
section steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110144846.2A
Other languages
Chinese (zh)
Inventor
周伟明
马乐乐
严来章
刘宗族
李龙
杨东
王�琦
廖星星
李景丰
王亚坤
侯立君
杨亮
廖志洲
苏红华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 24th Bureau Group Co Ltd
Anhui Engineering Co Ltd of China Railway 24th Bureau Group Co Ltd
Original Assignee
China Railway 24th Bureau Group Co Ltd
Anhui Engineering Co Ltd of China Railway 24th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 24th Bureau Group Co Ltd, Anhui Engineering Co Ltd of China Railway 24th Bureau Group Co Ltd filed Critical China Railway 24th Bureau Group Co Ltd
Priority to CN202110144846.2A priority Critical patent/CN112854021A/en
Publication of CN112854021A publication Critical patent/CN112854021A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/08Methods or apparatus specially adapted for erecting or assembling bridges by rotational movement of the bridge or bridge sections
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a construction method for rotatably positioning a spanning bridge, wherein a span-in bracket and an outer bracket are respectively arranged in the span-in and at two sides of a road to be used as temporary brackets, and a track beam is arranged on each temporary bracket; respectively assembling half-section steel box girders on two sides parallel to a road by taking bridge beam ends of piers and track girders as supporting points; one end of the half-section steel box girder, which is positioned at the pier, is a rotating center end, and one end of the half-section steel box girder, which is positioned at the girder end of the track girder, is a rotating movable end; and pushing the rotary movable ends of the half-section steel box girders to the center of the girder of the track girder from the girder end of the track girder by adopting a pushing mechanism, closing the rotary movable ends of the two half-section steel box girders at the midspan, keeping the rotary central end of the half-section steel box girders on a pier, welding a midspan closure opening, dismantling the temporary support and completing the in-place construction of the steel box girders. The invention has high tooling level and safe and efficient construction process, is suitable for the simple steel box girder to cross the existing road under the complex terrain environment, and greatly reduces the interference of bridge construction on the road traffic.

Description

Rotary in-place construction method for crossing bridge
Technical Field
The invention relates to the technical field of simple-support steel box girder cross road installation construction, in particular to a construction method for a simple-support steel box girder to cross an existing traffic road in a complex terrain environment.
Background
With the continuous perfection of traffic infrastructure and the continuous organization of road networks, it is more and more common to build bridges in environments with complex landforms or crossing existing traffic roads. When a bridge spans an existing traffic road, the traditional method comprises a bridge erecting frame method, a turning method, a support method, a pushing method and the like, but when the bridge is a simple beam and has a large span, the bridge erecting frame method and the turning method cannot meet the construction requirements; if the support method and the pushing method are adopted for construction, an assembling support or a pushing support needs to be erected on an existing passing road, the passing of the existing road is influenced to a certain extent, the passing road can be in a limited passing state for a long time, and the passing function of the road is greatly reduced.
Disclosure of Invention
The invention aims to overcome the defects in the prior art, and provides the rotary positioning construction method for the bridge crossing, which has high tooling level and safe and efficient construction process, is suitable for simply-supported steel box girders crossing the existing traffic roads in complex terrain environments and reduces the interference of bridge construction on road traffic.
The invention adopts the following technical scheme for solving the technical problems:
the rotary in-place construction method for the spanning bridge is characterized by comprising the following steps:
providing a temporary support comprising: a middle support is arranged in the center of the road, and outer supports are respectively arranged at two sides of the road; installing a track beam on the temporary support, enabling the center of the track beam to be positioned on the midspan support, and enabling the beam end of the track beam to be positioned on the outer side supports on two sides;
the steel box girder is segmented into two half-segment steel box girders for splicing, two-side steel box girder splicing frames are respectively constructed on two sides parallel to a road by taking bridge piers and beam ends of track girders as supporting points, and the splicing of the half-segment steel box girders is completed on the steel box girder splicing frames; setting one end of the half-section steel box girder, which is positioned at a pier, as a rotating center end, and setting one end of the half-section steel box girder, which is positioned at a beam end of a track beam, as a rotating movable end;
pushing the rotary movable end of the half-section steel box girder from the girder end of the track girder to the girder center of the track girder by adopting a pushing mechanism; and (3) closing the rotary movable ends of the two half-section steel box girders at the midspan positions on the track girders until the rotary movable ends of the two half-section steel box girders are closed, keeping the rotary central ends of the two half-section steel box girders on the piers, welding midspan closing openings, and then removing the temporary supports to complete the in-place construction of the steel box girders.
The rotary positioning construction method for the spanning bridge is also characterized in that: the pushing mechanism is a horizontal hydraulic jack arranged on the track beam, a rotary roller is arranged at the bottom of the half-section steel box beam, and the horizontal hydraulic jack pushes the rotary roller to enable the rotary movable end of the half-section steel box beam to rotate on the track beam and move forwards along the track beam.
The rotary positioning construction method for the spanning bridge is also characterized in that: the rotary idler wheel is characterized in that an upper rotating body and a lower rolling body are respectively arranged on an idler wheel seat, the lower rolling body is supported on the track beam and can move forwards along the track beam under the pushing of the horizontal hydraulic jack, and the upper rotating body is a rotatable piece arranged at the bottom of the half-section steel box beam.
The rotary positioning construction method for the spanning bridge is also characterized in that: and installing the track beam on the temporary support by adopting a pushing method.
The rotary positioning construction method for the spanning bridge is also characterized in that: and arranging a support frame between the bridge pier and the outer side support on the corresponding side, forming a support of the steel box girder assembling frame by the bridge pier, the outer side support and the support frame together, and assembling the half-section steel box girder on the steel box girder assembling frame by adopting a support method.
Compared with the prior art, the invention has the beneficial effects that:
the method is suitable for erection and installation construction of the simple steel box girder crossing the existing traffic road, and compared with the traditional support method and the pushing method, the method has the advantages of high tooling level, safe and efficient construction process, greatly shortened road traffic interference time caused by bridge construction, suitability for the simple steel box girder crossing the existing traffic road in the complex terrain environment, and greatly reduced road traffic interference caused by bridge construction.
Drawings
FIG. 1 is a schematic plan view of the construction method of the present invention;
FIG. 2 is a schematic view of the construction method of the present invention in an elevation view;
FIG. 3 is a side view of FIG. 2;
reference numbers in the figures: the road comprises a road 1, a middle span support 2a, an outer side support 2b, a track beam 3, a pier 4, a steel box beam 5, a rotary movable end 5a, a rotary center end 5b, rotary rollers 6, a horizontal hydraulic jack 7, a temporary supporting point 8, a steel box beam assembling frame 9 and a pile foundation 10.
Detailed Description
Referring to fig. 1, 2 and 3, the construction method for the cross-bridge rotation positioning in the embodiment is as follows:
firstly, a temporary support is arranged, comprising: a middle support 2a is arranged in the center of the road 1, and outer supports 2b are respectively arranged at two sides of the road 1; the track beam 3 is arranged on the temporary support, the beam center of the track beam 3 is positioned on the midspan support 2a, and the beam end of the track beam 3 is positioned on the outer supports 2b at two sides.
Then, the steel box girder 5 is segmented into two half-segment steel box girders for splicing, two steel box girder splicing frames 9 are respectively constructed on two sides parallel to the road 1 by taking the beam ends of the bridge piers 4 and the track girders 3 as supporting points, and the splicing of the half-segment steel box girders is respectively completed on the steel box girder splicing frames 9 on each side; one end of the half-section steel box girder, which is positioned at the pier 4, is set as a rotating center end 5b, and one end of the half-section steel box girder, which is positioned at the girder end of the track girder 3, is set as a rotating movable end 5 a.
Finally, a pushing mechanism is adopted to push the rotary movable end 5a of each half section of steel box girder from the beam end of the track girder 3 to the center of the track girder 3, and meanwhile, the rotary central end 5b of each half section of steel box girder rotates on the bridge pier 4, and the posture of the steel box girder is adjusted accordingly; until the rotary movable ends 5a of the two half-section steel box girders are closed at the midspan position on the track girder 3, simultaneously, the rotary central ends 5b of the two half-section steel box girders are kept on the piers 4, and the geometric posture of the steel box girders 5 is adjusted to ensure that the steel box girders 5 are superposed with the design line position; and welding the span-in closure opening, and then removing the temporary support to complete the in-place construction of the steel box girder 5.
The pushing mechanism shown in fig. 2 is a horizontal hydraulic jack 7 installed on the track beam 3, the bottom of the half-section steel box beam is provided with a rotating roller 6, and the horizontal hydraulic jack 7 pushes the rotating roller 6 to rotate the rotating movable end 5a of each half-section steel box beam on the track beam 3 and move forward along the track beam 3.
The rotating roller 6 shown in fig. 3 is provided with an upper rotating body 6a and a lower rolling body 6b on a roller seat, wherein the lower rolling body 6b is supported on the track beam 3 and can advance along the track beam 3 under the pushing of a horizontal hydraulic jack 7, and the upper rotating body 6a is a rotatable member arranged at the bottom of a half-section steel box girder.
Fig. 1 shows that a support frame 8 is arranged between a pier 4 and an outer support 2b on the corresponding side, the pier 4, the outer support 2b and the support frame 8 jointly form a support of a steel box girder assembling frame 9 so as to meet assembling requirements, and assembling of a half-section steel box girder on the steel box girder assembling frame 9 is completed by a support method.
In specific implementation, the corresponding technical measures also include:
the middle-span support 2a and the outer side support 2b in the temporary support are both formed by assembling steel pipes and section steel, and the bottom of a steel pipe upright post is arranged on the pile foundation 10.
In order to reduce the interference of construction on road traveling, a track beam 3 is installed on the temporary support by adopting a pushing method, and the track beam is pushed from one side of the road 1 by adopting a walking pushing method, and then pushed again after subsequent track beam sections are hoisted until the operation is finished; then, a rotary roller 6 and a horizontal hydraulic jack 7 are arranged on the track beam 3; the track beam 3 is an I-shaped section steel member composed of steel plates.
The track beam is constructed by adopting a walking jacking method, the simply supported steel box beam is constructed by adopting jacking rotation, the tooling level is high, the construction process is safe and efficient, the track beam is suitable for the situation that the simply supported steel box beam spans the existing traffic road in a complex terrain environment, and the interference of bridge construction on the road traffic is greatly reduced.

Claims (5)

1. A rotary in-place construction method for a spanning bridge is characterized by comprising the following steps:
providing a temporary support comprising: a midspan bracket (2a) is arranged in the center of the road (1), and outer brackets (2b) are respectively arranged at two sides of the road (1); the temporary supports are provided with track beams (3), the beam centers of the track beams (3) are positioned on the midspan supports (2a), and the beam ends of the track beams (3) are positioned on the outer side supports (2b) on two sides;
the steel box girder (5) is segmented into two half-segment steel box girders for splicing, two steel box girder splicing frames (9) are respectively constructed on two sides parallel to a road (1) by taking beam ends of a pier (4) and a track girder (3) as supporting points, and the half-segment steel box girders are spliced on the steel box girder splicing frames (9); setting one end of the half-section steel box girder, which is positioned at a pier (4), as a rotating center end, and setting one end of the half-section steel box girder, which is positioned at a beam end of a track beam (3), as a rotating movable end;
a pushing mechanism is adopted to push the rotary movable end of the half-section steel box girder from the girder end of the track girder (3) to the center of the track girder (3); and (3) closing the rotary movable ends of the two half-section steel box girders at the midspan positions on the track girders (3), keeping the rotary central ends of the two half-section steel box girders on the piers (4), welding midspan closing openings, and then removing the temporary supports to complete the in-place construction of the steel box girders (5).
2. The rotary setting construction method for crossing bridges of claim 1, wherein: the pushing mechanism is a horizontal hydraulic jack (7) installed on the track beam (3), a rotary roller (6) is arranged at the bottom of the half-section steel box beam, and the horizontal hydraulic jack (7) pushes the rotary roller (6) to enable the rotary movable end of the half-section steel box beam to rotate on the track beam (3) and move forwards along the track beam.
3. The bridge spanning rotary in-place construction method according to claim 2, wherein: rotatory gyro wheel (6) set up upper rotor (6a) and lower part rolling element (6b) respectively on the gyro wheel seat, lower part rolling element (6b) support is on track roof beam (3) to can advance along track roof beam (3) under the top of horizontal hydraulic jack (7) top, upper rotor (6a) are the rotatable piece that sets up the bottom at half section steel case roof beam.
4. The bridge spanning rotary in-place construction method according to claim 1, wherein: and installing a track beam (3) on the temporary support by adopting a pushing method.
5. The bridge spanning rotary in-place construction method according to claim 1, wherein: set up support frame (8) between pier (4) and outside support (2b) of corresponding one side to pier (4), outside support (2b) and support frame (8) constitute the support of steel box girder concatenation frame (9) jointly, adopt the support method to accomplish assembling of half section steel box girder on steel box girder concatenation frame (9).
CN202110144846.2A 2021-02-02 2021-02-02 Rotary in-place construction method for crossing bridge Pending CN112854021A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110144846.2A CN112854021A (en) 2021-02-02 2021-02-02 Rotary in-place construction method for crossing bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110144846.2A CN112854021A (en) 2021-02-02 2021-02-02 Rotary in-place construction method for crossing bridge

Publications (1)

Publication Number Publication Date
CN112854021A true CN112854021A (en) 2021-05-28

Family

ID=75986386

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110144846.2A Pending CN112854021A (en) 2021-02-02 2021-02-02 Rotary in-place construction method for crossing bridge

Country Status (1)

Country Link
CN (1) CN112854021A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115404778A (en) * 2022-07-25 2022-11-29 中铁十一局集团有限公司 Long-span steel box girder pushing system for crossing existing road

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11158814A (en) * 1997-11-26 1999-06-15 Nkk Corp Method of constructing portal pier for viaduct
JP2000008329A (en) * 1998-06-26 2000-01-11 Nishimatsu Constr Co Ltd Construction method of bridge
JP2007138514A (en) * 2005-11-17 2007-06-07 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Erection method of girder
CN102733317A (en) * 2012-07-22 2012-10-17 中铁二十局集团第一工程有限公司 Plane rotation construction technique for steel truss girder for existing bridge spanning construction
CN103628421A (en) * 2013-12-11 2014-03-12 中铁第一勘察设计院集团有限公司 Horizontal swivel construction system and method for simply supported steel trussed beam
CN104328745A (en) * 2014-11-04 2015-02-04 中铁第四勘察设计院集团有限公司 Rotating device of small-span bridge across high-speed rail at small angle and construction method of rotating device
CN105648926A (en) * 2015-12-31 2016-06-08 中铁二十局集团有限公司 Swivel construction method for large span continuous beam which spans existing station
CN107938518A (en) * 2017-11-21 2018-04-20 中铁四局集团钢结构建筑有限公司 One kind is first turned across busy railway freely-supported steel truss girder translates erection construction method again
CN109826110A (en) * 2019-02-25 2019-05-31 中铁十九局集团有限公司 Continuous beam swivel system with side-span ground slide
CN110453590A (en) * 2019-08-08 2019-11-15 中国铁路设计集团有限公司 A kind of antisymmetry plane swivel structure and its construction method
CN111926691A (en) * 2020-08-21 2020-11-13 中国铁路设计集团有限公司 Pier top rotating structure with power arranged on side pier and construction method
CN111926714A (en) * 2020-08-19 2020-11-13 中交路桥华南工程有限公司 Installation method of steel truss girder bridge

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11158814A (en) * 1997-11-26 1999-06-15 Nkk Corp Method of constructing portal pier for viaduct
JP2000008329A (en) * 1998-06-26 2000-01-11 Nishimatsu Constr Co Ltd Construction method of bridge
JP2007138514A (en) * 2005-11-17 2007-06-07 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Erection method of girder
CN102733317A (en) * 2012-07-22 2012-10-17 中铁二十局集团第一工程有限公司 Plane rotation construction technique for steel truss girder for existing bridge spanning construction
CN103628421A (en) * 2013-12-11 2014-03-12 中铁第一勘察设计院集团有限公司 Horizontal swivel construction system and method for simply supported steel trussed beam
CN104328745A (en) * 2014-11-04 2015-02-04 中铁第四勘察设计院集团有限公司 Rotating device of small-span bridge across high-speed rail at small angle and construction method of rotating device
CN105648926A (en) * 2015-12-31 2016-06-08 中铁二十局集团有限公司 Swivel construction method for large span continuous beam which spans existing station
CN107938518A (en) * 2017-11-21 2018-04-20 中铁四局集团钢结构建筑有限公司 One kind is first turned across busy railway freely-supported steel truss girder translates erection construction method again
CN109826110A (en) * 2019-02-25 2019-05-31 中铁十九局集团有限公司 Continuous beam swivel system with side-span ground slide
CN110453590A (en) * 2019-08-08 2019-11-15 中国铁路设计集团有限公司 A kind of antisymmetry plane swivel structure and its construction method
CN111926714A (en) * 2020-08-19 2020-11-13 中交路桥华南工程有限公司 Installation method of steel truss girder bridge
CN111926691A (en) * 2020-08-21 2020-11-13 中国铁路设计集团有限公司 Pier top rotating structure with power arranged on side pier and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115404778A (en) * 2022-07-25 2022-11-29 中铁十一局集团有限公司 Long-span steel box girder pushing system for crossing existing road

Similar Documents

Publication Publication Date Title
CN107460830B (en) Scheme for erecting full prefabricated bridge without temporary way with medium and small span
CN103255726B (en) A kind of construction method of continuous beam arch combination bridge
CN103046476A (en) Railway long-span rotator T-shaped bridge construction method
CN107740350B (en) The bridge pier column construction method and its passing method of full precast bridge Bridge Erector
CN102121234A (en) Quick construction method of two-tower five-span steel truss girder cable-stayed bridge
CN110205938B (en) Steel pipe arch installation method of through beam-arch combination bridge
CN111676816B (en) Steel truss girder and frame pier steel beam construction method
JP4671912B2 (en) Bridge replacement method
CN103255693A (en) Assembled type three-dimensional urban road system and rapid installing method
CN112854021A (en) Rotary in-place construction method for crossing bridge
CN114214920B (en) Large-span double-layer built-up steel truss arch bridge and construction method thereof
CN216640288U (en) Tower-passing sliding platform for steel box girder of cable-stayed bridge
CN214401451U (en) Rotatory construction frock of taking one's place of bridge strides
CN115821795A (en) Steel truss girder high-speed railway crossing swivel construction system and method
CN111945572B (en) Multi-connected arch bridge erecting machine and multi-connected arch bridge erecting method
CN211171637U (en) Steel box girder installation system
CN113322814B (en) Construction method of cable-stayed bridge steel box girder spanning multiple obstacles
CN111648246B (en) Construction method for building medium and large steel truss girder
CN113756200A (en) Construction method for hanging and splicing steel beam on existing upper-span route
CN110593117A (en) Steel box girder installation system and construction method thereof
CN219364352U (en) Wheel type self-transportation, rotation and jacking integrated bridging device
CN111535182A (en) Tubular bridge girder erection method
CN220550433U (en) Prefabricated mosaic structure of superelevation pier
CN110578301A (en) Steel box girder longitudinal and transverse sliding construction process
CN113863134B (en) Bridge deck structure capable of adjusting bridge deck elevation and bridge deck elevation adjusting method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210528