CN112832583B - Rail guard is used in construction is built in room - Google Patents

Rail guard is used in construction is built in room Download PDF

Info

Publication number
CN112832583B
CN112832583B CN202110069563.6A CN202110069563A CN112832583B CN 112832583 B CN112832583 B CN 112832583B CN 202110069563 A CN202110069563 A CN 202110069563A CN 112832583 B CN112832583 B CN 112832583B
Authority
CN
China
Prior art keywords
bottom beam
pushing blocks
transmission
top beam
pushing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110069563.6A
Other languages
Chinese (zh)
Other versions
CN112832583A (en
Inventor
赵忠爱
张一�
张彦强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202110069563.6A priority Critical patent/CN112832583B/en
Publication of CN112832583A publication Critical patent/CN112832583A/en
Application granted granted Critical
Publication of CN112832583B publication Critical patent/CN112832583B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H17/00Fencing, e.g. fences, enclosures, corrals
    • E04H17/14Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
    • E04H17/1413Post-and-rail fences, e.g. without vertical cross-members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H17/00Fencing, e.g. fences, enclosures, corrals
    • E04H17/14Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
    • E04H17/20Posts therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The invention relates to a protective guard for building construction, which belongs to the technical field of house construction and comprises two upright posts, a top beam, a guardrail and a bottom beam, wherein the upright posts are used for being connected with the ground; the guardrail is of a scissor-fork structure and is connected between the top beam and the bottom beam. By adopting the technical scheme, the protective height of the protective guard can be effectively adjusted, the protective guard is convenient to install and detach, and vehicles and personnel can conveniently enter a construction site from different positions.

Description

Rail guard is used in construction in room
Technical Field
The invention belongs to the technical field of house building construction, and particularly relates to a protective fence for house building construction.
Background
The guard rail is generally arranged at the periphery of a building construction site, plays a role in reminding, avoids danger caused by the fact that non-construction personnel enter a construction area by mistake and avoids troubles of damaging the construction site caused by the fact that vehicles enter the construction area by mistake, is usually applied to places with long construction periods such as a building site and the like, and is immovable guard rail is usually adopted, a plurality of foundation bolts are usually used for fixing upright columns on a concrete floor, cross bars are connected between adjacent upright columns through bolts, the cross bars are enclosed into a circle to surround the construction site, and then a valve is arranged at one place of the upright columns for the construction workers and vehicles to pass in and out. However, with the guard rail in the form, people and vehicles can only pass through a gate, and need to be bent when people and vehicles need to enter and exit a construction site from other positions, which is very inconvenient; in addition, the height of the guard rail in the form of the guard rail cannot be adjusted, and the guard rail is possibly too low or too high when the guard rail is used.
Disclosure of Invention
In view of the above, the present invention provides a protective fence for building construction, so as to solve the technical problems that the height of the protective fence for building construction in the prior art cannot be adjusted and people and vehicles cannot conveniently enter a construction site from different positions.
In order to achieve the purpose, the technical scheme adopted by the invention is as follows:
a rail guard is used in construction in room, includes:
the two upright columns comprise column bodies and connecting plates connected to the bottoms of the column bodies, and the connecting plates are used for being connected with the ground;
the bottom beam is arranged between the two columns, the extending direction of the bottom beam is defined as the left and right direction, and the left end and the right end of the bottom beam are respectively connected with the columns in a hooking manner;
the top beam is arranged above the bottom beam, the left end and the right end of the top beam are respectively in sliding fit with the corresponding cylinders in the vertical direction, the top beam comprises a beam body, two pushing blocks arranged in the beam body and a transmission assembly connected with the two pushing blocks, a pushing spring is arranged between the pushing blocks and the beam body, the transmission assembly comprises two transmission rods and a transmission plate hinged with the two transmission rods simultaneously, the two transmission rods are respectively hinged with the corresponding pushing blocks, the transmission plate can move in the vertical direction to drive the two pushing blocks to move back to back or towards each other relative to the beam body in the horizontal direction simultaneously through the transmission rods, and one end, far away from the transmission rods, of the pushing block is provided with an external thread section;
the guardrail is arranged between the bottom beam and the top beam and is connected with the bottom beam and the top beam at the same time, and is of a scissor-fork structure which can be unfolded and retracted along the up-down direction;
the two pushing blocks penetrate through the corresponding cylinders when moving back to the set position, are detachably connected with the corresponding cylinders through threaded fasteners, and are separated from the corresponding cylinders when moving to the set position in opposite directions.
The beneficial effects of the above technical scheme are: when the protective guard for building construction is installed, the bottom beam and the two columns are hooked together, the protective height of the protective guard is adjusted by lifting or lowering the top beam, after the adjustment is finished, the moving strokes of the two pushing blocks are adjusted by controlling the up-and-down movement of the driving plate until the pushing blocks penetrate through the columns, and then the top beam and the columns are connected through the threaded fasteners, so that the rapid installation of the protective guard for building construction can be realized; when a vehicle or a person needs to enter a construction site, the threaded fastener is screwed off, the transmission plate is lifted up to enable the ejector pad to retreat from the column body, and the bottom beam is removed from the column body, so that the top beam, the bottom beam and the guardrail can be quickly detached from the column body, and the vehicle or the person can conveniently enter and exit. When the protective guard is used, the protective guard for building construction can be arranged on the periphery of a construction site, an access door is not needed, and vehicles or personnel can get in and out by quickly detaching the top beam, the protective guard and the bottom beam, so that the protective guard is convenient.
Furthermore, the beam body is internally provided with a guide rod extending along the left-right direction, and the two pushing blocks are sleeved on the guide rod.
Has the advantages that: the guide rod is arranged to prevent the pushing block from shifting during movement, so that the pushing block can smoothly pass through the column body to be connected with the column body.
Furthermore, be equipped with the hickey on the driving plate, be equipped with the opening corresponding with the hickey on the back timber, the hickey is used for being connected with the screw to reciprocate through screw pulling driving plate.
Has the advantages that: during the in-service use, the accessible alternates the screw on the back timber and realizes reciprocating of driving plate, need not to set up screw isotructure on the back timber.
Furthermore, the cylinder body is provided with a sliding groove extending along the up-down direction, and is also provided with a plurality of through holes arranged at intervals along the up-down direction, the through holes are communicated with the sliding groove, and the through holes are used for the pushing block to pass through.
Has the advantages that: simple structure, and is convenient for realizing the assembly between the top beam and the column body.
Further, the guardrail is provided with more than two sets of side by side along left right direction, and adjacent two sets of guardrails support each other and lean on.
Has the advantages that: the protection length of the protective guard for house building construction is improved, and then the protection effect of the protective guard for house building construction is improved.
Furthermore, a connecting spring extending along the left-right direction is arranged in the cylinder body, a hook is arranged on the connecting spring, a hanging ring matched with the hook of the hook is arranged at the end part of the bottom beam, and the connecting spring is in a tightening state when the bottom beam is matched with the hook of the connecting spring.
Has the advantages that: not only ensures the reliable connection between the bottom beam and the column body, but also facilitates the installation and the disassembly between the bottom beam and the column body.
Drawings
Fig. 1 is an overall schematic view of a guard rail for building construction according to the present invention;
fig. 2 is a schematic view showing an assembly relationship between a cap and a post in the guard rail for building construction according to the present invention.
Reference numerals: 1-upright column, 2-top beam, 3-bottom beam, 4-connecting spring, 5-top pressure spring, 6-transmission rod, 7-transmission plate, 8-top pushing block, 9-column, 10-connecting plate, 11-beam body, 12-guide rod, 13-sliding groove, 14-perforation, 15-screw, 16-guardrail, 17-hook, 18-hanging ring, 19-stopping step, 20-mounting groove, 21-screw fastener, 22-upper seat and 23-lower seat.
Detailed Description
The invention is described in further detail below with reference to the drawings and the detailed description.
The invention relates to a concrete embodiment of a protective fence for building construction, which comprises the following steps:
as shown in fig. 1 and 2, the guard rail for building construction includes a vertical column 1, a top beam 2, a bottom beam 3, and a guard rail 16, and in this embodiment, the extending direction of the bottom beam is defined as a left-right direction.
Specifically, stand 1 is equipped with two, and two stand 1 are arranged side by side interval, and every stand 1 all includes cylinder 9 and connects the connecting plate 10 in cylinder 9 bottom. When installed, the connection plate 10 is connected to the ground by means of anchor bolts to stably fix the whole guard rail for house construction to the ground. The two opposite side surfaces of the two column bodies 9 are provided with sliding grooves 13 extending along the vertical direction, the two column bodies 9 are further provided with a plurality of through holes 14 arranged at intervals along the vertical direction, and the axes of the through holes 14 extend along the left-right direction.
The bottom beam 3 is arranged between the two columns 9, and the left end and the right end of the bottom beam 3 are respectively connected with the columns 9 in a hooking way. As shown in fig. 1, a mounting groove 20 extending in the left-right direction is provided at a position of the column 9 close to the connecting plate 10, a connecting spring 4 capable of contracting and stretching in the left-right direction is fixedly connected to the bottom of the mounting groove 20, a hook 17 is fixed to one end of the connecting spring 4 far away from the mounting groove 20, and a hanging ring 18 hooked and matched with the hook 17 is fixed to each of the left and right ends of the bottom beam 3. When the bottom beam 3 is hooked and matched with the connecting spring 4, the connecting spring 4 is in a tightening state, so that the stability of connection between the bottom beam 3 and the upright post 1 is ensured.
As shown in fig. 2, the top beam 2 is disposed above the bottom beam 3, and left and right ends of the top beam 2 are slidably fitted with the corresponding columns 9 in the up-down direction, respectively. Specifically, the top beam 2 comprises a beam body 11, two pushing blocks 8 arranged in the beam body 11, and a transmission assembly connected with the two pushing blocks 8. The top push block 8 is a T-shaped structure and comprises a vertical part extending in the vertical direction and a horizontal part extending in the left-right direction, a stop step 19 is arranged in the beam body 11, a top press spring 5 is sleeved on the vertical part, one end of the top press spring 5 presses the horizontal part, and the other end of the top press spring presses the stop step 19. The transmission assembly comprises two transmission rods 6 and a transmission plate 7 which is hinged with the two transmission rods 6 at the same time, the two transmission rods 6 are respectively hinged with corresponding pushing blocks 8, and the transmission plate 7 can move in the up-down direction to drive the two pushing blocks 8 to move back to back or in opposite directions relative to the beam body 11 in the left-right direction through the transmission rods 6. The transmission plate 7 is provided with a threaded interface, the top beam 2 is provided with an opening corresponding to the threaded interface, and the threaded interface is used for being connected with a threaded piece 15 so as to pull the transmission plate 7 to move up and down through the threaded piece 15. In order to improve the motion stability of the pushing block 8, a guide rod 12 extending along the left-right direction is arranged in the beam body 11, the guide rod 12 is located below the transmission plate 7 and coaxially penetrates through the pushing block 8, namely the pushing block 8 is sleeved outside the guide rod 12 and moves along the axial direction of the guide rod 12. One end of each pushing block 8, which is far away from the transmission rod 6, is provided with an external thread section, and the two pushing blocks 8 simultaneously penetrate through the through holes 14 on the corresponding cylinders when moving back to the set positions and are detachably connected with the corresponding cylinders 18 through threaded fasteners 21; the two pushing blocks are separated from the corresponding column bodies when moving to the set position in opposite directions.
The guard rail 16 is provided between the bottom girder 3 and the top girder 2 and is coupled to both the bottom girder 3 and the top girder 2. In this embodiment, the guard rail 16 is a scissor-type structure that can be deployed and retracted in the up-down direction, and three sets are arranged side by side in the left-right direction. As shown in fig. 2, the guard rail 16 includes two upper seats 22 in the top beam 2, two lower seats 23 in the bottom beam 3, and extendable and retractable scissor arms connected between the upper seats and the lower seats, wherein the upper seats 22 are movably fitted to the top beam 2 in the left-right direction, and the lower seats 23 are movably fitted to the bottom beam in the left-right direction. When the three groups of guardrails are installed, the upper seats 23 of the two adjacent groups of guardrails are abutted against the upper seats, and the lower seats 23 are abutted against the lower seats; the upper seats in the two groups of the guardrails positioned on the outermost side are abutted to the top beam 2, and the lower seats are abutted to the bottom beam 3, so that the three groups of the guardrails are stably connected with the top beam and the bottom beam.
When the guard rail for building construction is installed, the guard rail is installed on the periphery of a construction site, the height of the guard rail is adjusted according to the height required to be protected, when the height needs to be adjusted, the threaded fastener is unscrewed, the pushing block is withdrawn from the through hole under the action of the elastic force of the pushing spring, the threaded part is held by a hand to press the transmission plate downwards, the pushing block extends into the sliding groove and keeps the current position of the threaded part, the top beam moves upwards along the sliding groove, the top beam drives the scissor arms to expand upwards, when the guard rail is adjusted to a set position, the threaded part continues to be pressed downwards, the transmission plate moves downwards at the moment, the pushing block is driven to continue to move outwards until the pushing block penetrates through the through hole in the column body, and the pushing block is fixedly connected with the column body through the threaded fastener. When the lower end of the cylinder needs to be adjusted, the threaded fastener is unscrewed, the pushing block is made to withdraw from the through hole under the elastic action of the pushing spring, the threaded part is held by a hand at the moment, the driving plate is pressed downwards, the pushing block extends into the sliding groove, the current position of the threaded part is kept, the top beam moves downwards along the sliding groove, the top beam drives the scissor fork arm to withdraw downwards, when the lower end of the scissor fork is adjusted to the set position, the threaded part continues to be pressed downwards, the driving plate moves downwards at the moment, the pushing block is driven to continue to move outwards until the pushing block penetrates through the through hole in the cylinder, and the pushing block is fixedly connected with the cylinder through the threaded fastener.
When a vehicle or a person needs to enter a construction site, the threaded fastener is screwed off, the transmission plate is lifted through the threaded fastener to enable the ejector pad to retreat from the column body, the bottom beam is separated from the connecting spring, the bottom beam can be removed, and the top beam, the bottom beam and the guardrail can be quickly detached from the column body, so that the vehicle or the person can conveniently enter and exit. When the protective guard is used, the protective guard for building construction can be arranged on the periphery of a construction site, an access door is not needed, and vehicles or people can conveniently pass in and out by quickly detaching the top beam, the protective guard and the bottom beam.
The protective guard for building construction is convenient to mount and dismount, and facilitates vehicles and personnel to enter and exit from different positions; meanwhile, the protective guard for building construction can flexibly adjust the protective height of the protective guard according to the requirement, and is practical.
In other embodiments, the guide rod may not be provided, and at this time, a group of transmission assemblies may be additionally provided, and the two groups of transmission assemblies are arranged in the beam body in an up-down symmetrical manner, so as to ensure the linear motion of the ejector pad.
In other embodiments, the upper seats and the lower seats of the guardrails can also be respectively and correspondingly fixed on the top beam and the bottom beam, as long as an overlarge gap is not formed between the lower seats and the upper seats of the two adjacent groups of guardrails.
In other embodiments, a hanging ring may be directly welded to the side surface of the column without providing a connecting spring, and a hook may be connected to the left and right ends of the bottom beam.
The above-described embodiments of the present invention do not limit the scope of the present invention. Any modification, equivalent replacement, and improvement made within the spirit and principle of the present invention should be included in the scope of the claims of the present invention.

Claims (1)

1. The utility model provides a rail guard is used in construction in room which characterized in that includes:
the two upright columns comprise column bodies and connecting plates connected to the bottoms of the column bodies, the connecting plates are used for being connected with the ground, sliding grooves extending in the vertical direction are formed in the column bodies, and a plurality of through holes are formed in the vertical direction at intervals and communicated with the sliding grooves;
the bottom beam is arranged between the two columns, the extending direction of the bottom beam is defined as the left and right direction, and the left end and the right end of the bottom beam are respectively connected with the columns in a hooking manner; the connecting spring extending along the left and right direction is arranged in the cylinder body, the connecting spring is provided with a hook, the end part of the bottom beam is provided with a hanging ring matched with the hook of the hook, and when the bottom beam is matched with the hook of the connecting spring, the connecting spring is in a tightening state;
the top beam is arranged above the bottom beam, the left end and the right end of the top beam are respectively in sliding fit with the corresponding cylinders in the vertical direction, the top beam comprises a beam body, two pushing blocks arranged in the beam body and a transmission assembly connected with the two pushing blocks, a pushing spring is arranged between the pushing blocks and the beam body, a through hole is used for the pushing blocks to penetrate through, the transmission assembly comprises two transmission rods and a transmission plate hinged with the two transmission rods, the two transmission rods are respectively hinged with the corresponding pushing blocks, the transmission plate can move in the vertical direction to drive the two pushing blocks to move back and forth or opposite to each other in the horizontal direction through the transmission rods, and one end, far away from the transmission rods, of the pushing block is provided with an external thread section; the transmission plate is provided with a threaded interface, the top beam is provided with an opening corresponding to the threaded interface, and the threaded interface is used for being connected with a threaded piece so as to pull the transmission plate to move up and down through the threaded piece; the beam body is internally provided with a guide rod extending along the left-right direction, and the two pushing blocks are sleeved on the guide rod;
the guardrail is arranged between the bottom beam and the top beam and is simultaneously connected with the bottom beam and the top beam, the guardrail is of a scissor-fork type structure which can be unfolded and retracted along the up-down direction, more than two groups of guardrails are arranged side by side along the left-right direction, and two adjacent groups of guardrails are mutually abutted;
the two pushing blocks penetrate through the corresponding cylinders when moving back to the set position, are detachably connected with the corresponding cylinders through threaded fasteners, and are separated from the corresponding cylinders when moving to the set position in opposite directions.
CN202110069563.6A 2021-01-19 2021-01-19 Rail guard is used in construction is built in room Active CN112832583B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110069563.6A CN112832583B (en) 2021-01-19 2021-01-19 Rail guard is used in construction is built in room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110069563.6A CN112832583B (en) 2021-01-19 2021-01-19 Rail guard is used in construction is built in room

Publications (2)

Publication Number Publication Date
CN112832583A CN112832583A (en) 2021-05-25
CN112832583B true CN112832583B (en) 2022-06-21

Family

ID=75928791

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110069563.6A Active CN112832583B (en) 2021-01-19 2021-01-19 Rail guard is used in construction is built in room

Country Status (1)

Country Link
CN (1) CN112832583B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB209836A (en) * 1922-10-19 1924-01-21 Claude William Scott Saberton Improvements in or relating to anti-splash devices for the wheels of motor or other road vehicles
WO2005103418A1 (en) * 2004-04-22 2005-11-03 Everglade Farm Limited Fencing system
CN108678309A (en) * 2018-06-19 2018-10-19 安吉柏森塑木材料有限公司 A kind of modeling wooden rails connection structure
CN109056590A (en) * 2018-09-17 2018-12-21 孙江花 A kind of convenient operation type traffic guardrail
CN211173377U (en) * 2019-10-25 2020-08-04 刘国聪 Building construction protective fence
CN212105388U (en) * 2019-11-04 2020-12-08 王芹 Accomodate convenient guardrail for construction
CN112065142A (en) * 2020-09-21 2020-12-11 陈大宽 Power transmission power grid conveying frame

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10266150A (en) * 1997-03-27 1998-10-06 Sekisui Jushi Co Ltd Protection fence

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB209836A (en) * 1922-10-19 1924-01-21 Claude William Scott Saberton Improvements in or relating to anti-splash devices for the wheels of motor or other road vehicles
WO2005103418A1 (en) * 2004-04-22 2005-11-03 Everglade Farm Limited Fencing system
CN108678309A (en) * 2018-06-19 2018-10-19 安吉柏森塑木材料有限公司 A kind of modeling wooden rails connection structure
CN109056590A (en) * 2018-09-17 2018-12-21 孙江花 A kind of convenient operation type traffic guardrail
CN211173377U (en) * 2019-10-25 2020-08-04 刘国聪 Building construction protective fence
CN212105388U (en) * 2019-11-04 2020-12-08 王芹 Accomodate convenient guardrail for construction
CN112065142A (en) * 2020-09-21 2020-12-11 陈大宽 Power transmission power grid conveying frame

Also Published As

Publication number Publication date
CN112832583A (en) 2021-05-25

Similar Documents

Publication Publication Date Title
CN112832583B (en) Rail guard is used in construction is built in room
CN2457268Y (en) Climbing scaffold with lifting mechanism
CN110306777B (en) Construction method applied to elevator shaft lifting platform in building engineering
CN214658688U (en) Efficient creeping formwork equipment for variable cross-section creeping formwork construction
CN212612046U (en) Novel ultra-wide overhanging combined guy rope hanging basket
CN209742351U (en) Guardrail device with lifting function
CN213623191U (en) Supporting platform for oil pipeline anticorrosion and heat preservation construction operation
CN213475232U (en) Automatic installation equipment of construction protection network
CN213330363U (en) Stainless steel protective barrier with adjustable height
CN112252202A (en) Hanging basket for bridge building
CN210003009U (en) construction adjustable rail guard is built in room
CN211173071U (en) Light climbing formwork steel frame system
CN218234269U (en) Lifting type construction stand frame
CN220267160U (en) Safety belt tying rack
CN213979835U (en) Scaffold convenient to remove
CN219974097U (en) Safety fence
CN211922419U (en) Buffer stop is used in municipal construction
CN215976854U (en) Cast-in-place bridge bailey brace demolishs equipment
CN211949712U (en) Double-layer safety net for assembly type building construction
CN220580603U (en) Protective net for building engineering
CN220747581U (en) Construction safety device
CN219620816U (en) Safety protection device
CN220889406U (en) Safety device is built by laying bricks or stones to high-rise building exterior wall
CN221052470U (en) Protective fence
CN212714695U (en) Traffic guardrail convenient to installation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant