CN112818459A - 基于bim和甘特图的工程建设期可视化进度管理方法 - Google Patents

基于bim和甘特图的工程建设期可视化进度管理方法 Download PDF

Info

Publication number
CN112818459A
CN112818459A CN202110270939.XA CN202110270939A CN112818459A CN 112818459 A CN112818459 A CN 112818459A CN 202110270939 A CN202110270939 A CN 202110270939A CN 112818459 A CN112818459 A CN 112818459A
Authority
CN
China
Prior art keywords
progress
bim
analysis
gantt chart
project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110270939.XA
Other languages
English (en)
Inventor
王楠
尤林奇
蔺志刚
王陆
陶玉波
李彦
刘瑾程
王小平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yellow River Engineering Consulting Co Ltd
Original Assignee
Yellow River Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yellow River Engineering Consulting Co Ltd filed Critical Yellow River Engineering Consulting Co Ltd
Priority to CN202110270939.XA priority Critical patent/CN112818459A/zh
Publication of CN112818459A publication Critical patent/CN112818459A/zh
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F8/00Arrangements for software engineering
    • G06F8/30Creation or generation of source code
    • G06F8/34Graphical or visual programming
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F8/00Arrangements for software engineering
    • G06F8/60Software deployment

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Software Systems (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Geometry (AREA)
  • Computer Hardware Design (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明公开了一种基于BIM和甘特图的工程建设期可视化进度管理方法,1,BIM进度模型设计、拆分与编码;2,构建基于BIM的进度管理数据表;3,完成浏览器端甘特图插件的设计;4,完成基于BIM和甘特度的布局与双向联动设计;5,完成基于BIM和进度管理智能分析模块设计,包括进度模拟分析、偏差分析、关键线路分析、进度跟踪分析和趋势分析功能的设计;6,功能模块程序集成与发布:程序开发设计采用BS架构,通过前后端分离的开发形式与其它业务模块、功能系统或平台进行集成与部署,并完成功能发布。本发明优点体现在提供甘特图WEB端的高性能解决方案,无需安装插件;实现进度甘特图数据与BIM模型数据的双向联动,交互性强,可视化程度高。

Description

基于BIM和甘特图的工程建设期可视化进度管理方法
技术领域
本发明涉及工程建设期的现场进度管理,尤其是涉及基于BIM和甘特图的工程建设期可视化进度管理方法。
背景技术
进度管理通常作为一项工程建设期的首要控制目标,当前工程建设管理已逐步采用BIM信息化手段,但依然存在标准化程度低、数据孤岛、可视化程度不高、管理效益不能最大化等问题,主要体现在一下几方面:
第一,多数工程企业工程管理尤其是进度管理仍然不够精细,虽有较成熟的进度管理方法支持,但是无法与BIM技术有效结合形成可视化程度高的精细化进度管理信息系统。
第二,工程进度计划过于刚性,缺少优化;目前工程进度管理主要运用横道图、网络计划技术,结合Project、P3等项目管理软件进行工程进度计划制定、管理;但运用此类进度计划进行进度控制,只是单纯的根据机械效率进行叠加计算工期,没有与BIM数据有效结合,无法直观反应工程实际面貌,更难以进行可视化的进度模拟分析去支撑进度方案的优化。
第三,目前的建设管理系统,普遍存在可视化程度低,数据透视难度高,各模块数据缺乏统一的管理颗粒等问题,进度、质量、成本三大管理目标相互制约,难以平衡。
发明内容
本发明目的在于提供一种基于BIM和甘特图的工程建设期可视化进度管理方法,通过引入BIM技术,实现关键线路分析、偏差分析、进度跟踪和趋势分析等关键业务功能,建立进度管理优化数据模型,改变传统的进度管理方法粒度过粗、很难适应基于BIM的精细化进度管控的问题,明确提出进度、资源、费用、质量之间的数据关系和信息迭代方式,为进度管理提供智能化解决方案。
为实现上述目的,本发明采取下述技术方案:
本发明所述基于BIM和甘特图的工程建设期可视化进度管理方法,包括下述步骤:
步骤1,BIM进度模型设计、拆分与编码:
根据工程建设进度计划完成所述BIM模型设计,按照工程项目划分原则进行BIM模型分块拆解并赋予WBS编码;
步骤2,构建基于BIM的进度管理数据表;
表1 基于BIM的进度管理数据表
Figure DEST_PATH_IMAGE002
步骤3,完成浏览器端甘特图插件的设计:
在浏览器中通过横道图方式直观展现项目进度情况,满足各类型项目对进度管理的要求,且与P3、P6、PROJECT无缝集成,支持快速导入;
步骤4,完成基于BIM和甘特度的布局与双向联动设计:
BIM数据与甘特图数据通过WBS编码建立双向链接,点击BIM模型,即可跳转至甘特图对应的详细进度计划,点击甘特图数据,即可跳转至对应的BIM模型;
步骤5,完成基于BIM和进度管理智能分析模块设计,包括进度模拟分析、偏差分析、关键线路分析、进度跟踪分析和趋势分析功能的设计;
步骤6,功能模块程序集成与发布:程序开发设计采用BS架构,通过前后端分离的开发形式与其它业务模块、功能系统或平台进行集成与部署,并完成功能发布。
步骤5中,所述进度模拟分析是:基于工程BIM模型实现各级进度的可视化数据展现,实施基于BIM的进度计划虚拟模拟,直观呈现现场作业面貌,辅助现场进行施工计划的合理安排;所述偏差分析是:基于计划进度和实际进度数据,以横道图对比、工程模型计划/实际完成色彩对比、工程量计划与实际完成比例对比的可视化方式反馈进度偏差,结合资源配置数据进一步分析,预设允许偏差值;所述关键线路分析是:根据进度计划,自动计算项目关键线路及设置里程碑,并在BIM模型上查询各里程碑节点的形象面貌;针对最近的里程碑进行重点监控,根据进度偏差分析结果,判断截止该里程碑节点是否滞后,对于可能发生的进度滞后问题提前预判并进行预警提示;所述进度跟踪分析是:甘特图预设当前时间线,通过移动时间线,查询任一时间点工程的计划进度面貌与实际面貌;所述趋势分析是:采用柱状图表示,x轴为月份,y轴为每月计划进度与实际进度完成百分比,并增加两条趋势线,即累计完成进度线和偏差趋势线,按标段、项目、单位工程、分部工程进行查看。
本发明优点体现在以下方面:
(1)提供甘特图WEB端的高性能解决方案,无需安装插件。
(2)实现进度甘特图数据与BIM模型数据的双向联动,交互性强,可视化程度高。
(3)实现基于BIM的进度管理智能分析,包括进度模拟分析、偏差分析、关键线路分析、进度跟踪分析和趋势分析。
附图说明
图1是本发明的流程图。
图2是本发明所述基于BIM的进度管理布局设计示意图。
具体实施方式
下面结合附图对本发明的实施例作详细说明,本实施例在以本发明技术方案为前提下进行实施,给出了详细的实施方式和具体的操作过程,但本发明的保护范围不限于下述实施例。
如图1所示,本发明所述基于BIM和甘特图的工程建设期可视化进度管理方法,包括下述步骤:
步骤1,BIM进度模型设计、拆分与编码:
根据工程建设进度计划完成所述BIM模型设计,按照工程项目划分原则进行BIM模型分块拆解并赋予WBS编码;
步骤2,构建基于BIM的进度管理数据表,如表1所示:
表1 基于BIM的进度管理数据表
Figure DEST_PATH_IMAGE004
步骤3,完成浏览器端甘特图插件的设计:
在浏览器中通过横道图方式直观展现项目进度情况,满足各类型项目对进度管理的要求,且与P3、P6、PROJECT无缝集成,支持快速导入;
步骤4,完成基于BIM和甘特度的布局与双向联动设计:
如图2所示,BIM数据与甘特图数据通过WBS编码建立双向链接,点击BIM模型,即可跳转至甘特图对应的详细进度计划,点击甘特图数据,即可跳转至对应的BIM模型;
步骤5,完成基于BIM和进度管理智能分析模块设计,包括进度模拟分析、偏差分析、关键线路分析、进度跟踪分析和趋势分析功能的设计;
所述进度模拟分析:基于工程BIM模型实现各级进度的可视化数据展现,实施基于BIM的进度计划虚拟模拟,直观呈现现场作业面貌,辅助现场进行施工计划的合理安排;
所述偏差分析:基于计划进度和实际进度数据,以横道图对比、工程模型计划/实际完成色彩对比、工程量计划与实际完成比例对比的可视化方式反馈进度偏差,结合资源配置数据进一步分析,预设允许偏差值;
所述关键线路分析:根据进度计划,自动计算项目关键线路及设置里程碑,并在BIM模型上查询各里程碑节点的形象面貌;针对最近的里程碑进行重点监控,根据进度偏差分析结果,判断截止该里程碑节点是否滞后,对于可能发生的进度滞后问题提前预判并进行预警提示;
所述进度跟踪分析:甘特图预设当前时间线,通过移动时间线,查询任一时间点工程的计划进度面貌与实际面貌;
所述趋势分析: 采用柱状图表示,x轴为月份,y轴为每月计划进度与实际进度完成百分比,并增加两条趋势线,即累计完成进度线和偏差趋势线(每个月的实际完成百分比与计划完成百分比的差值),按标段、项目、单位工程、分部工程进行查看;
步骤6,功能模块程序集成与发布:程序开发设计采用BS架构,通过前后端分离的开发形式与其它业务模块、功能系统或平台进行集成与部署,并完成功能发布。

Claims (2)

1.一种基于BIM和甘特图的工程建设期可视化进度管理方法,其特征在于:包括下述步骤:
步骤1,BIM进度模型设计、拆分与编码:
根据工程建设进度计划完成所述BIM模型设计,按照工程项目划分原则进行BIM模型分块拆解并赋予WBS编码;
步骤2,构建基于BIM的进度管理数据表;
表1 基于BIM的进度管理数据表
Figure 345120DEST_PATH_IMAGE002
步骤3,完成浏览器端甘特图插件的设计:
在浏览器中通过横道图方式直观展现项目进度情况,满足各类型项目对进度管理的要求,且与P3、P6、PROJECT无缝集成,支持快速导入;
步骤4,完成基于BIM和甘特度的布局与双向联动设计:
BIM数据与甘特图数据通过WBS编码建立双向链接,点击BIM模型,即可跳转至甘特图对应的详细进度计划,点击甘特图数据,即可跳转至对应的BIM模型;
步骤5,完成基于BIM和进度管理智能分析模块设计,包括进度模拟分析、偏差分析、关键线路分析、进度跟踪分析和趋势分析功能的设计;
步骤6,功能模块程序集成与发布:程序开发设计采用BS架构,通过前后端分离的开发形式与其它业务模块、功能系统或平台进行集成与部署,并完成功能发布。
2.根据权利要求1所述基于BIM和甘特图的工程建设期可视化进度管理方法,其特征在于:步骤5中,所述进度模拟分析是:基于工程BIM模型实现各级进度的可视化数据展现,实施基于BIM的进度计划虚拟模拟,直观呈现现场作业面貌,辅助现场进行施工计划的合理安排;所述偏差分析是:基于计划进度和实际进度数据,以横道图对比、工程模型计划/实际完成色彩对比、工程量计划与实际完成比例对比的可视化方式反馈进度偏差,结合资源配置数据进一步分析,预设允许偏差值;所述关键线路分析是:根据进度计划,自动计算项目关键线路及设置里程碑,并在BIM模型上查询各里程碑节点的形象面貌;针对最近的里程碑进行重点监控,根据进度偏差分析结果,判断截止该里程碑节点是否滞后,对于可能发生的进度滞后问题提前预判并进行预警提示;所述进度跟踪分析是:甘特图预设当前时间线,通过移动时间线,查询任一时间点工程的计划进度面貌与实际面貌;所述趋势分析是: 采用柱状图表示,x轴为月份,y轴为每月计划进度与实际进度完成百分比,并增加两条趋势线,即累计完成进度线和偏差趋势线,按标段、项目、单位工程、分部工程进行查看。
CN202110270939.XA 2021-03-12 2021-03-12 基于bim和甘特图的工程建设期可视化进度管理方法 Pending CN112818459A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110270939.XA CN112818459A (zh) 2021-03-12 2021-03-12 基于bim和甘特图的工程建设期可视化进度管理方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110270939.XA CN112818459A (zh) 2021-03-12 2021-03-12 基于bim和甘特图的工程建设期可视化进度管理方法

Publications (1)

Publication Number Publication Date
CN112818459A true CN112818459A (zh) 2021-05-18

Family

ID=75863169

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110270939.XA Pending CN112818459A (zh) 2021-03-12 2021-03-12 基于bim和甘特图的工程建设期可视化进度管理方法

Country Status (1)

Country Link
CN (1) CN112818459A (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113780729A (zh) * 2021-08-04 2021-12-10 中国二十冶集团有限公司 一种基于工程管控平台的进度预警方法
CN113961998A (zh) * 2021-10-21 2022-01-21 黑龙江省求索科技信息技术有限公司 一种用于bim的建筑施工管理系统及管理方法
CN114003831A (zh) * 2021-10-21 2022-02-01 易协云(杭州)科技有限公司 一种利用网页图形化展示项目进度的方法及系统
CN116205411A (zh) * 2023-04-27 2023-06-02 山东铁路投资控股集团有限公司 一种基于大数据的物资用量核查方法、装置、设备及介质
CN117893075A (zh) * 2024-01-11 2024-04-16 国网安徽省电力有限公司综合服务中心 基于大数据管理的电力工程云平台智慧审计系统

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140032255A1 (en) * 2011-03-21 2014-01-30 Tarek Mohamed Mohamed HEGAZI System and method for schedule optimization
CN105427091A (zh) * 2015-12-03 2016-03-23 国网浙江杭州市萧山区供电公司 一种电力营销高压业扩报装全过程管控系统
CN107273640A (zh) * 2017-07-11 2017-10-20 黄河勘测规划设计有限公司 基于三维数字模型的水利水电工程进度监控方法
CN107622355A (zh) * 2017-09-30 2018-01-23 长江勘测规划设计研究有限责任公司 项目群施工过程数字化管理系统及方法
CN108596423A (zh) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 一种基于bim的轨道工程施工进度信息管理方法
KR101936121B1 (ko) * 2017-12-13 2019-04-03 지에스건설주식회사 기상 데이터와 bim 데이터를 이용한 해상구조물 시공관리 시스템
CN111429097A (zh) * 2020-03-24 2020-07-17 上海捷规建筑工程咨询有限公司 一种基于bim的现场进度与模型自动匹配方法和系统
CN111754138A (zh) * 2020-07-07 2020-10-09 天津水泥工业设计研究院有限公司 一种基于bim模型的工程建设进度计划管控系统及方法
CN112100725A (zh) * 2020-09-18 2020-12-18 中国电建集团华东勘测设计研究院有限公司 基于bim模型和横道图的工程全要素过程信息展示方法
CN112365113A (zh) * 2020-08-20 2021-02-12 中国铁道科学研究院集团有限公司电子计算技术研究所 基于bim的四电施组计划模拟与资源动态调整方法及系统

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140032255A1 (en) * 2011-03-21 2014-01-30 Tarek Mohamed Mohamed HEGAZI System and method for schedule optimization
CN105427091A (zh) * 2015-12-03 2016-03-23 国网浙江杭州市萧山区供电公司 一种电力营销高压业扩报装全过程管控系统
CN107273640A (zh) * 2017-07-11 2017-10-20 黄河勘测规划设计有限公司 基于三维数字模型的水利水电工程进度监控方法
CN107622355A (zh) * 2017-09-30 2018-01-23 长江勘测规划设计研究有限责任公司 项目群施工过程数字化管理系统及方法
KR101936121B1 (ko) * 2017-12-13 2019-04-03 지에스건설주식회사 기상 데이터와 bim 데이터를 이용한 해상구조물 시공관리 시스템
CN108596423A (zh) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 一种基于bim的轨道工程施工进度信息管理方法
CN111429097A (zh) * 2020-03-24 2020-07-17 上海捷规建筑工程咨询有限公司 一种基于bim的现场进度与模型自动匹配方法和系统
CN111754138A (zh) * 2020-07-07 2020-10-09 天津水泥工业设计研究院有限公司 一种基于bim模型的工程建设进度计划管控系统及方法
CN112365113A (zh) * 2020-08-20 2021-02-12 中国铁道科学研究院集团有限公司电子计算技术研究所 基于bim的四电施组计划模拟与资源动态调整方法及系统
CN112100725A (zh) * 2020-09-18 2020-12-18 中国电建集团华东勘测设计研究院有限公司 基于bim模型和横道图的工程全要素过程信息展示方法

Non-Patent Citations (9)

* Cited by examiner, † Cited by third party
Title
HEXU LIU .ETAL: "BIM-based integrated approach for detailed construction scheduling under resource constraints", 《AUTOMATION IN CONSTRUCTION》 *
HEXU LIU .ETAL: "BIM-based integrated approach for detailed construction scheduling under resource constraints", 《AUTOMATION IN CONSTRUCTION》, vol. 53, 31 May 2015 (2015-05-31), pages 29 - 43, XP029583621, DOI: 10.1016/j.autcon.2015.03.008 *
万力: "基于BIM的工程项目进度管理研究", 《合作经济与科技》 *
万力: "基于BIM的工程项目进度管理研究", 《合作经济与科技》, no. 24, 31 December 2017 (2017-12-31), pages 144 - 145 *
井然哲: "《项目管理实验教程》", 上海财经大学出版社 *
刘琳琳: "BIM技术在地下市政管网工程全生命周期中的应用研究", 《中国优秀硕士学位论文全文数据库 (工程科技Ⅱ辑)》, no. 6, 15 June 2017 (2017-06-15), pages 038 - 86 *
周圣栋 等: ""基于BIM 的变电站数字化建设管控平台构建及应用", 《中国电力》 *
周圣栋 等: ""基于BIM 的变电站数字化建设管控平台构建及应用", 《中国电力》, vol. 52, no. 5, 31 May 2019 (2019-05-31), pages 142 - 147 *
郭红兵 编著: "BIM技术在市政工程设计行业中的应用研究与实践", 北京理工大学出版社, pages: 79 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113780729A (zh) * 2021-08-04 2021-12-10 中国二十冶集团有限公司 一种基于工程管控平台的进度预警方法
CN113961998A (zh) * 2021-10-21 2022-01-21 黑龙江省求索科技信息技术有限公司 一种用于bim的建筑施工管理系统及管理方法
CN114003831A (zh) * 2021-10-21 2022-02-01 易协云(杭州)科技有限公司 一种利用网页图形化展示项目进度的方法及系统
CN114003831B (zh) * 2021-10-21 2024-04-30 易协云(杭州)科技有限公司 一种利用网页图形化展示项目进度的方法及系统
CN116205411A (zh) * 2023-04-27 2023-06-02 山东铁路投资控股集团有限公司 一种基于大数据的物资用量核查方法、装置、设备及介质
CN117893075A (zh) * 2024-01-11 2024-04-16 国网安徽省电力有限公司综合服务中心 基于大数据管理的电力工程云平台智慧审计系统
CN117893075B (zh) * 2024-01-11 2024-08-23 国网安徽省电力有限公司综合服务中心 基于大数据管理的电力工程云平台智慧审计系统

Similar Documents

Publication Publication Date Title
CN112818459A (zh) 基于bim和甘特图的工程建设期可视化进度管理方法
Li et al. A blockchain-and IoT-based smart product-service system for the sustainability of prefabricated housing construction
CN111021265B (zh) 一种基于bim技术的铁路大跨度连续梁转体施工管控方法
Barbosa et al. Reinventing construction: A route of higher productivity
CN110334924B (zh) 基于bim的计算机辅助设计、施工一体化管理系统及方法
CN109388902A (zh) 一种应用bim技术的场地布置施工方法
Duffy et al. Linear scheduling model with varying production rates
CN104680320A (zh) 基于bim的工程管理系统和方法
CN106934163A (zh) 基于bim的桥梁三维模型构建方法
CN112258159B (zh) 基于bim+gis的水工结构管理系统及方法
CN105893577B (zh) 路网数据处理方法及装置
CN111383000A (zh) 一种提升建筑工程项目管理的方法
CN112307548A (zh) 基于bim的轨道交通施工可视化进度管理方法及系统
CN111563651A (zh) 一种基于bim技术的沥青路面施工工程量动态追踪管理系统
Suarez et al. Using 5D models and Cba for planning the foundations and concrete structure stages of a complex office building
CN117591079A (zh) 一种企业级一体化经营管理系统的设计构建方法
Saeed et al. Building information modelling (BIM) and knowledge management in implementation for con-struction projects
Busco et al. Globalisation and the international convergence of management accounting
Qiu et al. Application of BIM technology in construction engineering
CN109242550B (zh) 一种钢铁工序成本预测系统
Lyu et al. Research on railway cooperative test platform and key technologies based on digital twin
Li et al. Smart City Construction Visual Simulation Application Based on Intelligent BIM Technology
Yan et al. Application of the BIM Technique in Modern Project Management
George 5G-Enabled Digital Transformation: Mapping the Landscape of Possibilities and Problems
Guo Rethinking construction project management using the VP-based manufacturing management model

Legal Events