考虑移相变压器接入输电线路距离保护测量阻抗计算方法 Download PDFInfo
- Publication number
- CN112763806A CN112763806A CN202110233649.8A CN202110233649A CN112763806A CN 112763806 A CN112763806 A CN 112763806A CN 202110233649 A CN202110233649 A CN 202110233649A CN 112763806 A CN112763806 A CN 112763806A
- Authority
- CN
- China
- Prior art keywords
- phase
- impedance
- shifting transformer
- calculating
- distance protection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000005540 biological transmission Effects 0.000 title claims abstract description 20
- 238000005259 measurement Methods 0.000 title claims abstract description 13
- 238000000034 method Methods 0.000 title claims description 15
- 238000004364 calculation method Methods 0.000 claims abstract description 13
- 230000010363 phase shift Effects 0.000 claims abstract description 6
- 150000001875 compounds Chemical class 0.000 claims description 3
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000002847 impedance measurement Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R27/00—Arrangements for measuring resistance, reactance, impedance, or electric characteristics derived therefrom
- G01R27/02—Measuring real or complex resistance, reactance, impedance, or other two-pole characteristics derived therefrom, e.g. time constant
- G01R27/08—Measuring resistance by measuring both voltage and current
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R25/00—Arrangements for measuring phase angle between a voltage and a current or between voltages or currents
Abstract
本发明公开了一种考虑移相变压器接入输电线路距离保护测量阻抗计算方法,它包括:采集移相变压器输入端电压、负荷电流为和移相变压器输出端电压、负荷电流;计算输入电压与输出电压之间向量对应移相角;计算移相变压器阻抗;计算线路首端对应负荷阻抗;测量移相变压器接入线路出口外发生故障时首端故障电流和输出端电流;计算移相变压器接入线路出口外发生故障的测量阻抗;将测量阻抗的减去对应档位等效阻抗绝对值作为距离保护用测量阻抗;解决了现有技术仅仅关注移相变压本身作为潮流控制理想模型,尚未考虑由于移相变压器本身阻抗及其变化对线路保护的影响;导致移相变压器接入输电线路造成距离保护范围小,无法实现线路保护等问题。
Description
技术领域
本发明属于输电线路距离保护整定领域,尤其涉及一种考虑移相变压器接入输电线路距离保护测量阻抗计算方法。
背景技术
随着电网规模的不断扩大,电网中不可避免出现并行线路、环网线路等结构。在不采取各种措施的前提条件下,线路的潮流分布往往按照线路阻抗进行自然分布,进而影响线路的经济性和系统本身安全性。
随着装备制造业水平的提高、移相变压器等作为线路潮流调节的设备近年来成为电力系统专家关注的重点,并提出了将其作为线路潮流控制设想。然而在传统的电力系统中,仅仅关注了移相变压本身作为潮流控制理想模型,尚未考虑由于移相变压器本身阻抗及其变化对线路保护的影响。导致移相变压器接入输电线路造成距离保护范围小,无法实现线路保护的问题。
发明内容
本发明要解决的问题是提供一种考虑移相变压器接入输电线路距离保护测量阻抗计算方法,以解决现有技术仅仅关注移相变压本身作为潮流控制理想模型,尚未考虑由于移相变压器本身阻抗及其变化对线路保护的影响;导致移相变压器接入输电线路造成距离保护范围小,无法实现线路保护等问题。
本发明采用技术方案如下:
一种考虑移相变压器接入输电线路距离保护测量阻抗计算方法,它包括:
步骤3、计算移相变压器阻抗Zeq;
步骤4、计算线路首端对应负荷阻抗Z1;
步骤6、计算移相变压器接入线路出口外发生故障的测量阻抗Z1s;
步骤7、将测量阻抗的减去对应档位等效阻抗Zeq绝对值作为距离保护用测量阻抗Zm。
它还包括:步骤8、根据可靠系数krel乘以线路总阻抗得到距离保护整定阻抗计算值。
步骤3所述移相变压器阻抗Zeq的计算公式为:
线路首端对应负荷阻抗Z1的计算方法为:
步骤6所述计算移相变压器接入线路出口外发生故障的测量阻抗Z1s的公式为:
步骤7所述距离保护用测量阻抗Zm的计算公式为:
Zm=|Z1s-Zeq|。
所述根据可靠系数krel乘以线路总阻抗得到距离保护整定阻抗计算值的公式为:
Zset=krel·Z。
本发明的有益效果:
本发明为新型潮流控制设备--移相变压器的接入系统进行潮流控制过程的距离保护提供了理论计算方法,解决了现有技术仅仅关注移相变压本身作为潮流控制理想模型,尚未考虑由于移相变压器本身阻抗及其变化对线路保护的影响;导致移相变压器接入输电线路造成距离保护范围小,无法实现线路保护等问题。
附图说明
图1为本发明的计算流程图。
具体实施方式
本发明提供一种考虑移相变压器接入输电线路距离保护的测量阻抗计算方法的具体步骤包括:
3)计算移相变压器阻抗Zeq:
4)计算线路首端对应负荷阻抗Z1:
6)计算移相变压器接入线路出口外发生故障的测量阻抗方法测量阻抗Z1s为:
7)为避免移相变压器在不同档位下阻抗Zeq对测量阻抗幅值变化影响,在距离保护中将测量阻抗的减去对应档位等效阻抗Zeq绝对值作为距离保护用测量阻抗Zm:
Zm=|Z1s-Zeq|。
8)确定移相变压器线路距离保护整定阻抗:根据可靠系数krel(取值范围0.8~0.85)乘以线路总阻抗得到距离保护整定阻抗计算值Zset=krel·Z。
Claims (8)
2.根据权利要求1所述的一种考虑移相变压器接入输电线路距离保护测量阻抗计算方法,其特征在于:它还包括:步骤8、根据可靠系数krel乘以线路总阻抗得到距离保护整定阻抗计算值。
7.根据权利要求1所述的一种考虑移相变压器接入输电线路距离保护测量阻抗计算方法,其特征在于:步骤7所述距离保护用测量阻抗Zm的计算公式为:Zm=|Z1s-Zeq|。
8.根据权利要求2所述的一种考虑移相变压器接入输电线路距离保护测量阻抗计算方法,其特征在于:所述根据可靠系数krel乘以线路总阻抗得到距离保护整定阻抗计算值的公式为:
Zset=krel·Z。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110233649.8A CN112763806A (zh) | 2021-03-03 | 2021-03-03 | 考虑移相变压器接入输电线路距离保护测量阻抗计算方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110233649.8A CN112763806A (zh) | 2021-03-03 | 2021-03-03 | 考虑移相变压器接入输电线路距离保护测量阻抗计算方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112763806A true CN112763806A (zh) | 2021-05-07 |
Family
ID=75690806
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110233649.8A Pending CN112763806A (zh) | 2021-03-03 | 2021-03-03 | 考虑移相变压器接入输电线路距离保护测量阻抗计算方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112763806A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113378500A (zh) * | 2021-06-04 | 2021-09-10 | 广东电网有限责任公司 | 一种移相变压器输出电压和电流的计算方法及装置 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4476578A (en) * | 1981-11-27 | 1984-10-09 | Thomson-Csf | Device for detecting the optimum anode load impedance of a tube transmitter in a high frequency transmission chain |
CN101036302A (zh) * | 2004-10-06 | 2007-09-12 | 皇家飞利浦电子股份有限公司 | 阻抗检测器 |
CN103107524A (zh) * | 2013-01-31 | 2013-05-15 | 福建省电力有限公司 | 一种输电线路相间故障继电保护方法 |
CN110058084A (zh) * | 2019-04-15 | 2019-07-26 | 南方电网科学研究院有限责任公司 | 一种换流变压器的谐波阻抗测量系统及方法 |
CN110082596A (zh) * | 2019-03-08 | 2019-08-02 | 国网浙江省电力有限公司杭州供电公司 | 基于高频暂态量的距离保护故障阻抗计算方法及系统 |
-
2021
- 2021-03-03 CN CN202110233649.8A patent/CN112763806A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4476578A (en) * | 1981-11-27 | 1984-10-09 | Thomson-Csf | Device for detecting the optimum anode load impedance of a tube transmitter in a high frequency transmission chain |
CN101036302A (zh) * | 2004-10-06 | 2007-09-12 | 皇家飞利浦电子股份有限公司 | 阻抗检测器 |
CN103107524A (zh) * | 2013-01-31 | 2013-05-15 | 福建省电力有限公司 | 一种输电线路相间故障继电保护方法 |
CN110082596A (zh) * | 2019-03-08 | 2019-08-02 | 国网浙江省电力有限公司杭州供电公司 | 基于高频暂态量的距离保护故障阻抗计算方法及系统 |
CN110058084A (zh) * | 2019-04-15 | 2019-07-26 | 南方电网科学研究院有限责任公司 | 一种换流变压器的谐波阻抗测量系统及方法 |
Non-Patent Citations (3)
Title |
---|
DASH, PK 等: "Apparent impedance calculations for distance-protected transmission lines employing series-connected FACTS devices", ELECTRIC POWER COMPONENTS AND SYSTEMS * |
刘青, 王增平: "FACTS元件对距离保护产生的影响分析", 中国电力, no. 10 * |
张仲驰;童伟林;王建全;: "移相变压器在特高压直流双极闭锁故障中的应用", 机电工程, no. 12 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113378500A (zh) * | 2021-06-04 | 2021-09-10 | 广东电网有限责任公司 | 一种移相变压器输出电压和电流的计算方法及装置 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107181281B (zh) | 一种孤岛微网并联逆变器间环流抑制方法 | |
CN103235280B (zh) | 基于比例变换器的电流互感器磁饱和裕度直接测量方法 | |
CN109802419A (zh) | 多直流馈入系统受端电网暂态过电压评估计算方法 | |
US9847647B2 (en) | Solar power conversion system and method | |
CN107658909A (zh) | 一种含光伏接入的中低压配电网电压抬升抑制方法 | |
CN101320908B (zh) | 并联电抗器的匝间启动方法 | |
CN112763806A (zh) | 考虑移相变压器接入输电线路距离保护测量阻抗计算方法 | |
CN107069718A (zh) | 基于三相不平衡对线路损耗影响的低压配网线损计算方法 | |
CN103809010A (zh) | 用于确定中压网络的每相的电压和功率的装置及方法 | |
CN212209198U (zh) | 一种无源零磁通的宽量程计量用电流互感器 | |
Singh et al. | Power Quality Issues of Electric Arc Furnace and their Mitigations-A Review | |
CN108565892A (zh) | 一种故障穿越方法、装置和光伏发电系统 | |
CN108574276A (zh) | 一种基于频率注入的直流微电网功率均分控制方法及系统 | |
CN103424622A (zh) | 一种分数谐波源的检测和判断方法 | |
CN104237668B (zh) | 用于确定调节点处的电特性的方法和装置 | |
CN112202182B (zh) | 考虑换流站电压无功控制的交直流协调二级电压控制方法 | |
CN109901096A (zh) | 一种电容式电压互感器计量精度在线监测系统和方法 | |
Kocewiak et al. | Harmonic mitigation methods in large offshore wind power plants | |
CN107860994B (zh) | 海上全功率水冷变流器测试平台 | |
CN114142474B (zh) | 一种提高新能源装备暂态稳定的阻尼控制方法及系统 | |
CN109599858B (zh) | 交直流系统预防控制和紧急控制的协调优化方法 | |
CN107167641A (zh) | 一种移动式分段计量器 | |
CN203608079U (zh) | 单元机组协调控制系统 | |
CN107785914A (zh) | 一种前端供电多电平有源补偿装置及控制方法 | |
CN109698510A (zh) | 抑制电力系统低频振荡的控制方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |