CN112746849A - Shaft water-carrying digging and building method - Google Patents

Shaft water-carrying digging and building method Download PDF

Info

Publication number
CN112746849A
CN112746849A CN202011457446.9A CN202011457446A CN112746849A CN 112746849 A CN112746849 A CN 112746849A CN 202011457446 A CN202011457446 A CN 202011457446A CN 112746849 A CN112746849 A CN 112746849A
Authority
CN
China
Prior art keywords
water
shaft
concrete
rock
well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011457446.9A
Other languages
Chinese (zh)
Other versions
CN112746849B (en
Inventor
钱自卫
孟凡贞
吕文茂
侯俊华
赵迎春
蔡逢华
范宝江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN202011457446.9A priority Critical patent/CN112746849B/en
Publication of CN112746849A publication Critical patent/CN112746849A/en
Application granted granted Critical
Publication of CN112746849B publication Critical patent/CN112746849B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/012Use of fluid-tight or anti-friction material on outside of, or between, lining layers
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/08Sinking shafts while moving the lining downwards
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/10Preparation of the ground
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a shaft water-carrying digging and building method, which comprises the following specific steps: tunneling a water-bearing rock stratum section of a shaft, paving a water-proof drainage plate on the wall surface of surrounding rock bare rock, supporting a formwork of the shaft wall and pouring concrete, and when the total water quantity after the water-proof drainage plate of the shaft reaches a set limit value, constructing a concrete grout stop pad at the bottom of the shaft and filling the concrete grout stop pad after the shaft wall, and repeating the steps to complete the tunneling of the water-bearing stratum section of the shaft with water; the method has simple principle and convenient operation, and can effectively solve the problems of well wall quality assurance and water burst treatment under the condition that the shaft passes through the water-bearing rock stratum to discharge water.

Description

Shaft water-carrying digging and building method
Technical Field
The invention relates to the field of mine construction, in particular to a shaft water-carrying digging and building method.
Background
The well bore is known visually as the throat of an underground mining mine and assumes the important tasks of mine personnel, equipment, material access to the well and ventilation of the well. The current main construction methods of the shaft are divided into a freezing method, a drilling method and a common method, wherein the freezing method and the drilling method are special well drilling methods and are mainly used for special geological condition working conditions such as thick unconsolidated formations and the like. The common method is applied most in the actual shaft sinking process, the drilling and blasting method is mainly adopted for drilling the shaft by the common method, broken stones are cleared and transported by a grab bucket and a bucket, and the well wall is poured by conventional concrete. In the ordinary method sinking process, aiming at the working condition that a well casing penetrates a water-bearing rock stratum, a pre-grouting method and a well wall grouting method are adopted to treat water damage. The pre-grouting can generally achieve an ideal effect aiming at a strong-permeability rock stratum such as limestone and the like with wide and large solution fracture development, and after the pre-grouting, when a well bore is tunneled again and meets a water-bearing rock stratum, a large flow of water outlet phenomenon generally does not exist. However, for the working conditions of micro fractures such as straightly developed sandstone pores and micro fractures of lohezone sandstone in western mining areas and micro fractures of flat-topped mountain sandstone in flat-topped mountain mining areas in China, the pre-grouting effect cannot be completely expected, namely a certain amount of water gushing is still remained in the water-bearing rock interval of the well casing after pre-grouting. And in addition, partial slightly-permeable and weakly-permeable rock strata are usually adopted, a water-bearing rock stratum section is directly excavated and disclosed under the condition of no grouting, and the water-bearing rock stratum section can also show a certain amount of water inrush phenomenon. Such water gushing points often appear to be dispersed, small and dense.
Because of the existence of residual water gushing, in the process of casting the well wall concrete in situ, the residual water gushing of rock strata behind the wall can generate scouring action on the well wall concrete, the cement ingredients in the concrete are taken away by running water, and according to data record, when the water gushing amount is 17m3When the well is built at the time of/h, 30% of cement components in newly poured concrete can be washed away, the well wall strength can be reduced by more than 2/3, and serious phenomena of honeycomb pitted surface, cracking, leakage, strength reduction and the like occur. When the well wall grouting method is adopted to treat the water leakage of the well wall at the later stage, the quality of the well wall is poor, and the grouting pressure must be controlled to prevent the well wall from further breaking, namely the grouting pressure of the well wall cannot be guaranteedThe grouting on the well wall can not achieve the expected effect. The problems of poor well wall quality and over-standard leakage water of a plurality of shafts are caused, such as Ningxia plum blossom well coal mine air shafts, Hongtiansi coal mine shafts, peacekeeping ten mine three-level air shafts, walnut slack coal mine measure wells, Lucun one mine air shafts and the like. How to guarantee the quality of wall of a well concrete pouring under the condition that there is certain gushing water volume at pit shaft water-bearing rock stratum section to it is the technical problem that needs to solve to manage the wall of a well gushing water under the better condition of wall of a well quality.
Disclosure of Invention
Aiming at the technical defects, the invention aims to provide a method for digging and building a shaft with water, which has simple principle and convenient operation and can effectively solve the problems of quality assurance and water burst treatment of a concrete shaft wall under the condition that the shaft passes through an aquifer and is discharged.
In order to solve the technical problems, the invention adopts the following technical scheme:
the invention provides a shaft water-carrying digging and building method, which specifically comprises the following steps:
1) after the pre-grouting treatment, cleaning and transporting broken stones in a rock layer section with larger estimated water inflow or a micro-seepage and weak-seepage rock layer section after rock drilling by adopting a conventional drilling and blasting method;
2) according to the design section height of single-section tunneling, paving a concave-convex anti-drainage plate 6 on the surrounding rock bare rock wall surface 5 tunneled in the water-bearing rock layer section 4, wherein the anti-drainage plate 6 is matched with the uneven surface of the surrounding rock bare rock wall surface 5 to isolate water from gushing, and the gushing water flows downwards from a gap between the anti-drainage plate 6 and the bare rock wall surface 5 and finally flows into the well bottom; then, a well wall template is supported and concrete is poured to form a concrete well wall 2;
3) repeating the step 2), wherein the drainage preventing plates 6 paved and attached in two adjacent single-section tunneling processes need to be abutted and lapped together, so that water between the drainage preventing plates 6 and the wall surface 5 of the surrounding rock bare rock can flow downwards and cannot overflow outwards;
4) when the total amount of water gushing out behind the water-proof and drainage plate 6 in the shaft 1 is close to a threshold value, tunneling a certain distance H to the bottom of the well, and then continuously paving the water-proof and drainage plate 6 downwards along the newly tunneled wall surface 5 of the bare rock of the surrounding rock to the bottom of the well;
5) constructing a water filtering layer 7 at the bottom of the well, vertically installing a water collecting pipeline 3 in the middle of the water filtering layer 7, opening a water through hole at the bottom of the water collecting pipeline 3, installing a water pump in the water collecting pipeline, and finally pouring a concrete grout stop pad 8 on the water filtering layer 7;
6) after the concrete grout stopping pad 8 is fully solidified, a plurality of rows of drill holes 9 are constructed on the concrete well wall 2 which is paved with the waterproof drainage plate 6, the uppermost row of drill holes 9 is arranged at the starting position of the water-carrying tunneling section, the number of each row of drill holes 9 is N and is uniformly arranged, the water collecting pipeline 3 on the concrete grout stopping pad 8 is connected with grouting pipeline equipment and is used for grouting, grout 10 is subjected to seepage diffusion in the space behind the water filtering layer 7 and the concrete well wall 2, and the water-carrying tunneling of the section of the well shaft 1 is finally completed.
Preferably, in the step 1), after the pre-grouting treatment, if a water inrush phenomenon occurs in a water-containing rock stratum section in the tunneling process, the water amount is not too large, and temporary drainage equipment is installed at the tunneling head for drainage.
Preferably, in the step 4), the water volume limit value is determined according to the diameter of the shaft 1 and the temporary drainage capacity of the shaft 1, and the limit water volume is not more than 50m3/h。
Preferably, in step 4), the calculation formula of H is:
Figure BDA0002829857750000031
h is the distance of re-tunneling at the bottom of the well and is the unit m;
P01.5 times of the water pressure of the original water-bearing rock stratum section at the bottom hole position in unit of MPa;
r is the shaft tunneling radius in m;
[ sigma ] is the allowable compressive strength of the concrete for pouring the grout stopping pad, and the unit is Mpa;
preferably, in the step 5), the thickness of the water filtering layer 7 is 0.5m, the casting thickness of the concrete grout stopping pad 8 is H-0.5m, and a pump in the water collecting pipeline 3 continuously pumps and drains water at the bottom of the well to the outside in the solidification process of the concrete grout stopping pad 8.
Preferably, in the step 6), the hole diameter of the drill hole 9 is not more than 42mm, 3 holes are distributed in each row, and the vertical distance between every two rows of drill holes 9 is 30 m.
Preferably, in step 6), after the construction of the drill holes 9 is completed, the hole pipes and the valves are installed, the water collecting pipeline 3 on the concrete grout stop pad 8 is connected with grouting pipeline equipment and grouting is carried out, grout 10 seeps and diffuses in the space behind the water filtering layer 7 and the concrete well wall 2, the valves on the hole pipes of the drill holes 9 are opened during grouting, when the grout return phenomenon of one drill hole 9 is observed, the valves of the drill holes 9 are closed, and grouting is completed until the grout return phenomenon of the top row of drill holes 9 occurs.
The invention has the beneficial effects that: the method has a simple principle, is convenient to operate, can effectively prevent the influence of rock stratum water in the concrete well wall pouring process by adopting a method of firstly isolating water and then controlling water, ensures the well wall pouring quality, and simultaneously realizes the plugging of the rock stratum water by adopting a method of pouring a grout stopping pad and grouting.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without any creative effort.
FIG. 1 is a schematic illustration of a location of a water-bearing formation segment according to an embodiment of the present invention;
fig. 2 is a schematic view of an installation position of a waterproof and drainage plate according to an embodiment of the present invention;
FIG. 3 is a schematic diagram of a concrete well wall casting position provided by an embodiment of the invention;
FIG. 4 is a schematic view of the installation position of a concrete grout stop pad according to an embodiment of the present invention;
fig. 5 is a schematic diagram of a grouting effect provided by an embodiment of the invention.
Description of reference numerals:
1. a wellbore; 2. a concrete well wall; 3. a water collecting pipeline; 4. a hydrous rock interval; 5. wall rock bare rock wall surface; 6. a water-proof and drainage plate; 7. filtering a water layer; 8. concrete grout stopping pads; 9. drilling; 10. and (3) slurry.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
As shown in fig. 1 to 5, a method for digging and building a shaft with water specifically comprises the following steps:
1) after the pre-grouting treatment, cleaning and transporting broken stones in a rock layer section with larger estimated water inflow or a micro-seepage and weak-seepage rock layer section after rock drilling by adopting a conventional drilling and blasting method; after the pre-grouting treatment, if the water burst phenomenon occurs in the water-bearing rock stratum section in the tunneling process, the water quantity is not too large, and temporary drainage equipment is arranged at the head of the tunneling for drainage;
2) according to the design section height of single-section tunneling, paving a concave-convex anti-drainage plate 6 on the surrounding rock bare rock wall surface 5 tunneled in the water-bearing rock layer section 4, wherein the anti-drainage plate 6 is matched with the uneven surface of the surrounding rock bare rock wall surface 5 to isolate water from gushing, and the gushing water flows downwards from a gap between the anti-drainage plate 6 and the bare rock wall surface 5 and finally flows into the well bottom; then, a well wall template is supported and concrete is poured to form a concrete well wall;
3) repeating the step 2), wherein the drainage preventing plates 6 paved and attached in two adjacent single-section tunneling processes need to be abutted and lapped together, so that water between the drainage preventing plates 6 and the wall surface 5 of the surrounding rock bare rock can flow downwards and cannot overflow outwards;
4) when the total amount of water gushing out behind the water-proof and drainage plate 6 in the shaft 1 is close to a threshold value, tunneling a certain distance H to the bottom of the well, and then continuously paving the water-proof and drainage plate 6 downwards along the newly tunneled wall surface 5 of the bare rock of the surrounding rock to the bottom of the well; the limit value of water quantity is determined according to the diameter of the shaft 1 and the temporary drainage capacity of the shaft 1, and the limit water quantity is not more than 50m3H; the formula for H is:
Figure BDA0002829857750000051
h is the distance of re-tunneling at the bottom of the well and is the unit m;
P01.5 times of the water pressure of the original water-bearing rock stratum section at the bottom hole position in unit of MPa;
r is the shaft tunneling radius in m;
[ sigma ] is the allowable compressive strength of the concrete for pouring the grout stopping pad, and the unit is Mpa;
5) constructing a water filtering layer 7 at the bottom of the well, vertically installing a water collecting pipeline 3 in the middle of the water filtering layer 7, opening a water through hole at the bottom of the water collecting pipeline 3, installing a water pump in the water collecting pipeline, and finally pouring a concrete grout stop pad 8 on the water filtering layer 7; the thickness of the water filtering layer 7 is 0.5m, the pouring thickness of the concrete grout stopping pad 8 is H-0.5m, and a pump in the water collecting pipeline 3 continuously pumps and drains water at the bottom of the well to the outside in the solidification process of the concrete grout stopping pad 8;
6) after the concrete grout stopping pad 8 is fully solidified, a plurality of rows of drill holes 9 are constructed on the concrete well wall 2 on which the waterproof drainage plate 6 is paved, the uppermost row of drill holes 9 is arranged at the starting position of the water-carrying tunneling section, the aperture of each drill hole 9 is not more than 42mm, 3 holes are distributed in each row, the vertical distance between every two rows of drill holes 9 is 30m, the water collecting pipeline 3 on the concrete grout stopping pad 8 is connected with grouting pipeline equipment and performs grouting, grout 10 diffuses in the space behind the water filtering layer 7 and the concrete well wall 2 in a seepage manner, a valve on a grout conveying pipe of each drill hole 9 is opened during grouting, when the grout returning phenomenon of a certain drill hole 9 is observed, the valve of the drill hole 9 is closed, the grouting is completed until the grout returning phenomenon of the uppermost row of drill holes 9 occurs, and the water-carrying of the section of well shaft 1 is finally completed.
It will be apparent to those skilled in the art that various changes and modifications may be made in the present invention without departing from the spirit and scope of the invention. Thus, if such modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is intended to include such modifications and variations.

Claims (7)

1. A shaft water-carrying digging and building method is characterized by comprising the following steps:
1) after the pre-grouting treatment, cleaning and transporting broken stones after rock drilling by adopting a conventional drilling and blasting method in a rock stratum section with larger estimated water inflow or a micro-seepage and weak-seepage rock stratum section;
2) according to the design section height of single-section tunneling, paving a concave-convex anti-drainage plate 6 on the surrounding rock bare rock wall surface 5 tunneled in the water-bearing rock layer section 4, wherein the anti-drainage plate 6 is matched with the uneven surface of the surrounding rock bare rock wall surface 5 to isolate water from gushing, and the gushing water flows downwards from a gap between the anti-drainage plate 6 and the bare rock wall surface 5 and finally flows into the bottom of the well; then, a well wall template is supported and concrete is poured to form a concrete well wall 2;
3) repeating the step 2), wherein the drainage preventing plates 6 paved and attached in two adjacent single-section tunneling processes need to be abutted and lapped together, so that water between the drainage preventing plates 6 and the wall surface 5 of the surrounding rock bare rock is ensured to flow downwards and not to overflow outwards;
4) when the total amount of water gushing out behind the water-proof and drainage plate 6 in the shaft 1 is close to a threshold value, tunneling a certain distance H to the bottom of the well, and then continuously paving the water-proof and drainage plate 6 downwards along the newly tunneled wall surface 5 of the bare rock of the surrounding rock to the bottom of the well;
5) constructing a water filtering layer 7 at the bottom of the well, vertically installing a water collecting pipeline 3 in the middle of the water filtering layer 7, opening a water through hole at the bottom of the water collecting pipeline 3, installing a water pump in the water collecting pipeline, and finally pouring a concrete grout stop pad 8 on the water filtering layer 7;
6) after the concrete grout stopping pad 8 is fully solidified, a plurality of rows of drill holes 9 are constructed on the concrete well wall 2 which is paved with the waterproof drainage plate 6, the top row of drill holes 9 is arranged at the starting position of the water-carrying tunneling section, the number of each row of drill holes 9 is N and is uniformly arranged, the water collecting pipeline 3 on the concrete grout stopping pad 8 is connected with grouting pipeline equipment and is used for grouting, grout 10 is subjected to seepage diffusion in the space behind the water filtering layer 7 and the concrete well wall 2, and finally the water-carrying tunneling of the section of the well shaft 1 is completed.
2. The method for digging and building a shaft with water according to claim 1, wherein in the step 1), after the pre-grouting treatment, if the water gushing phenomenon occurs in the water-bearing rock stratum section during the driving process, the water quantity is not too large, and temporary drainage equipment is arranged at the head of the driving for drainage.
3. As claimed in claim 1The method for digging and building the shaft with water is characterized in that in the step 4), a water volume limit value is determined according to the diameter of the shaft 1 and the temporary drainage capacity of the shaft 1, and the limit water volume is not more than 50m3/h。
4. The method for digging and laying a shaft with water according to claim 1, wherein in the step 4), the calculation formula of H is as follows:
Figure FDA0002829857740000021
h is the distance of re-tunneling at the bottom of the well and is the unit m;
P01.5 times of the water pressure of the original water-bearing rock stratum section at the bottom hole position in unit of MPa;
r is the shaft tunneling radius in m;
[ sigma ] is the allowable compressive strength of the concrete for pouring the grout stop pad, and the unit is Mpa.
5. A method for digging and building a shaft with water according to claim 1, wherein in the step 5), the thickness of the drainage layer 7 is 0.5m, the pouring thickness of the concrete grout stop 8 is H-0.5m, and a pump in the water collecting pipeline 3 continuously pumps and drains water at the bottom of the shaft outwards during the solidification process of the concrete grout stop 8.
6. A method for digging and laying a shaft with water according to claim 1, wherein in step 6), the bore diameter of the drill hole 9 is not more than 42mm, 3 holes are distributed in each row, and the vertical distance between the drill holes 9 in each row is 30 m.
7. A shaft water digging and building method according to claim 1, characterized in that in step 6), after the construction of the drill hole 9 is completed, the hole pipes and the valves are installed, the water collecting pipeline 3 on the concrete grout stop pad 8 is connected with grouting pipeline equipment and grouting is carried out, grout 10 seeps and spreads in the space behind the drainage layer 7 and the concrete well wall 2, the valves on the hole pipes of the drill holes 9 are opened during grouting, when the grout return phenomenon of one drill hole 9 is observed, the valve of the drill hole 9 is closed, and the grouting is completed until the grout return phenomenon of the top row of drill holes 9 occurs.
CN202011457446.9A 2020-12-11 2020-12-11 Shaft water-carrying digging and building method Active CN112746849B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011457446.9A CN112746849B (en) 2020-12-11 2020-12-11 Shaft water-carrying digging and building method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011457446.9A CN112746849B (en) 2020-12-11 2020-12-11 Shaft water-carrying digging and building method

Publications (2)

Publication Number Publication Date
CN112746849A true CN112746849A (en) 2021-05-04
CN112746849B CN112746849B (en) 2022-02-18

Family

ID=75648367

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011457446.9A Active CN112746849B (en) 2020-12-11 2020-12-11 Shaft water-carrying digging and building method

Country Status (1)

Country Link
CN (1) CN112746849B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113309522A (en) * 2021-06-19 2021-08-27 莱州汇金矿业投资有限公司 Construction method for pre-grouting water plugging concrete grout stop pad on working surface of kilometer vertical shaft
CN114607386A (en) * 2022-04-18 2022-06-10 中国矿业大学 Single-layer well wall with connecting and water stopping structure and grouting system and construction method thereof
WO2023160471A1 (en) * 2022-02-25 2023-08-31 中国矿业大学 Pre-grouting treatment method for water hazards in shaft construction

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10266765A (en) * 1997-03-21 1998-10-06 Matsunaga Kiso:Kk Construction method of shaft
CN202370524U (en) * 2011-12-28 2012-08-08 陕西煤业化工建设(集团)有限公司 Water control construction structure for working face of shaft body of air return vertical shaft
CN103046932A (en) * 2012-12-22 2013-04-17 中冶集团武汉勘察研究院有限公司 Pre-grouting and water plugging method for permeable layer in vertical shaft
CN203383822U (en) * 2013-06-16 2014-01-08 钱自卫 Seepage-proofing well wall
CN104453913A (en) * 2014-12-19 2015-03-25 玉溪大红山矿业有限公司 Vertical shaft working face ahead pre-grouting method
CN206957765U (en) * 2017-07-31 2018-02-02 河北钢铁集团矿业有限公司 Water outburst treatment structure is built in a kind of vertical shaft pick
CN108661650A (en) * 2018-04-23 2018-10-16 中铁隧道局集团有限公司 A kind of rich water magmatic body area depth pozo shaft construction method
CN109026012A (en) * 2018-07-25 2018-12-18 中国电建集团华东勘测设计研究院有限公司 Vertical shaft surrounding rock supporting structure and its excavation supporting method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10266765A (en) * 1997-03-21 1998-10-06 Matsunaga Kiso:Kk Construction method of shaft
CN202370524U (en) * 2011-12-28 2012-08-08 陕西煤业化工建设(集团)有限公司 Water control construction structure for working face of shaft body of air return vertical shaft
CN103046932A (en) * 2012-12-22 2013-04-17 中冶集团武汉勘察研究院有限公司 Pre-grouting and water plugging method for permeable layer in vertical shaft
CN203383822U (en) * 2013-06-16 2014-01-08 钱自卫 Seepage-proofing well wall
CN104453913A (en) * 2014-12-19 2015-03-25 玉溪大红山矿业有限公司 Vertical shaft working face ahead pre-grouting method
CN206957765U (en) * 2017-07-31 2018-02-02 河北钢铁集团矿业有限公司 Water outburst treatment structure is built in a kind of vertical shaft pick
CN108661650A (en) * 2018-04-23 2018-10-16 中铁隧道局集团有限公司 A kind of rich water magmatic body area depth pozo shaft construction method
CN109026012A (en) * 2018-07-25 2018-12-18 中国电建集团华东勘测设计研究院有限公司 Vertical shaft surrounding rock supporting structure and its excavation supporting method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王洪理: "地面注浆封堵井筒淋、渗水的施工实践", 《建井技术》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113309522A (en) * 2021-06-19 2021-08-27 莱州汇金矿业投资有限公司 Construction method for pre-grouting water plugging concrete grout stop pad on working surface of kilometer vertical shaft
CN113309522B (en) * 2021-06-19 2022-11-04 莱州汇金矿业投资有限公司 Construction method for pre-grouting water plugging concrete grout stop pad on working surface of kilometer vertical shaft
WO2023160471A1 (en) * 2022-02-25 2023-08-31 中国矿业大学 Pre-grouting treatment method for water hazards in shaft construction
CN114607386A (en) * 2022-04-18 2022-06-10 中国矿业大学 Single-layer well wall with connecting and water stopping structure and grouting system and construction method thereof

Also Published As

Publication number Publication date
CN112746849B (en) 2022-02-18

Similar Documents

Publication Publication Date Title
CN112746849B (en) Shaft water-carrying digging and building method
CN104453913B (en) A kind of Shaft Stopes front pre-grouting method
CN107237650B (en) Drilling siphon negative pressure drainage system and method for treating water seepage of tunnel wall
WO2019000776A1 (en) Side slope underground water drilling self-starting negative pressure drainage system and method
CN207260136U (en) Ultra-deep bored pile borehole cleaning system
CN109184754B (en) Tunnel water drainage disease prevention treatment method and system
CN107816051B (en) Pressure-bearing property phreatic aquifer deep basal pit combination well dewatering construction method
CN205387712U (en) Quick treatment device of foundation pit piping
CN113374440B (en) Rapid plugging method and construction method for water burst channel of hidden collapse column
CN108590716A (en) A kind of tunnel crosses rich water tomography tree root type and dredges water blockoff integral construction method
CN103343690B (en) Construction method of shaft antiseep structure used when large section of inclined shaft passes through aquifer
JP2022553449A (en) External expansion pipe construction method for drilling in the mining zone
CN106638606B (en) A kind of quick grouting method of deep covering layer
CN104294806A (en) Excavation, diversion and drainage method for inter-pile water above water-resisting layer of deep foundation pit
CN107218010B (en) Water plugging bridge plug for damaged drilling sleeve and double-bridge plug type water plugging method
CN114382073B (en) Underground continuous wall system for protecting spring vein or underground water and construction method thereof
CN114991774A (en) Ground subsection descending type grouting method for crushed andesite basalt stratum
CN104060964A (en) Pit grouting and water blocking method for protecting groundwater environment
CN104060636B (en) Pressure release anti-float method during high water level regional architecture foundation construction and device
CN111441775B (en) Rapid grouting arching reinforcement method before excavation of tunnel in stratum with poor groutability and difficult self-stabilization
CN207194952U (en) A kind of flood mine working bottom plate is harnessed the river structure
CN208949889U (en) Deep basal pit karst base lime rock stratum groundwater treatment system
CN112664207A (en) Advanced pre-reinforcement method for tillite layer tunnel
CN206052746U (en) A kind of deep basal pit explosion discharge structure
CN203834529U (en) Pressure-relieving anti-floating device for building foundation construction in high-water-level district

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant