一种基于bim技术的建筑机电管线综合优化方法 Download PDFInfo
- Publication number
- CN112733230A CN112733230A CN202011636052.XA CN202011636052A CN112733230A CN 112733230 A CN112733230 A CN 112733230A CN 202011636052 A CN202011636052 A CN 202011636052A CN 112733230 A CN112733230 A CN 112733230A
- Authority
- CN
- China
- Prior art keywords
- collision
- bim
- plug
- model
- professional
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000005457 optimization Methods 0.000 title claims abstract description 25
- 238000000034 method Methods 0.000 title claims abstract description 22
- 238000005516 engineering process Methods 0.000 title claims abstract description 15
- 238000001514 detection method Methods 0.000 claims abstract description 8
- 238000010276 construction Methods 0.000 claims abstract description 7
- 239000003086 colorant Substances 0.000 claims abstract description 4
- 238000009434 installation Methods 0.000 claims abstract description 4
- 239000000463 material Substances 0.000 claims abstract description 4
- 238000007689 inspection Methods 0.000 claims description 6
- 238000010586 diagram Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/12—Geometric CAD characterised by design entry means specially adapted for CAD, e.g. graphical user interfaces [GUI] specially adapted for CAD
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Geometry (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Computer Hardware Design (AREA)
- Evolutionary Computation (AREA)
- Computational Mathematics (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- General Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Human Computer Interaction (AREA)
- Computer Graphics (AREA)
- Software Systems (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
本发明涉及一种基于BIM技术的建筑机电管线综合优化方法,包括以下步骤:在Revit软件上建立项目样板,包含建筑、结构专业的相关构件,机电设备专业的系统材质、颜色等项目信息;利用Revit软件二次开发的插件快速创建各专业BIM模型,确定机电各专业初始高度;利用Revit软件二次开发的插件进行各专业BIM模型自动碰撞检测,生成碰撞节点报告,包含碰撞构件信息以及在项目中的定位,可通过定位快速切换至碰撞节点;利用Revit软件二次开发的插件与碰撞报告对BIM模型进行优化调整,并记录;根据综合优化后的BIM模型指定管线装配方案,导出模型制作深化图纸;现场根据BIM模型与深化图纸进行安装施工。
Description
技术领域
本发明涉及建筑技术领域,尤其一种基于BIM技术的建筑机电管线综合优化方法。
背景技术
随着我国经济持续发展,建筑规模越来越大,建筑功能越来越多样化,建筑内部机电集成系统错综复杂,使用传统的二维软件进行机电管线综合深化设计,很难进行全局管线碰撞检测。因此利用BIM技术进行管线综合布置可以快速完善施工图,在未施工前根据施工图进行预装配。
发明内容
本发明目的在于解决上述问题,提出一种基于BIM技术的建筑机电管线综合优化方法,具体由以下技术方案实现:
一种基于BIM技术的建筑机电管线综合优化方法,包括以下步骤:
(1)在Revit软件上建立项目样板,包含建筑、结构专业的相关构件,机电设备专业的系统材质、颜色等项目信息。
(2)利用Revit软件二次开发的插件快速创建各专业BIM模型,确定机电各专业初始高度。
(3)利用Revit软件二次开发的插件进行各专业BIM模型自动碰撞检测,生成碰撞节点报告,包含碰撞构件信息以及在项目中的定位,可通过定位快速切换至碰撞节点。
(4)利用Revit软件二次开发的插件与步骤(3)中生成的碰撞报告对BIM模型进行优化调整,并记录。
(5)根据综合优化后的BIM模型指定管线装配方案,导出模型制作深化图纸。
(6)现场根据BIM模型与深化图纸进行安装施工。
所述的一种基于BIM技术的建筑机电管线综合优化方法,其进一步设计在于:步骤(2)中利用二次开发的插件快速创建模型是指:通过拾取CAD文件中的线条、图块等构件,识别其中的图层、块参数等信息,快速转化为Revit文件中的梁、板、柱、墙以及机电设备各专业的管线模型,减少设计人员手动建模的时间,提高建模效率。
所述的一种基于BIM技术的建筑机电管线综合优化方法,其进一步设计在于:步骤(3)中利用二次开发的插件进行自动碰撞检测是指:将模型构件截面分类,分为点、矩形截面与圆形截面三种,对截面边缘绘制其法线并将其强转成定位线,如果不同构件的定位线之间有交叉则判定构件间有碰撞发生,将此碰撞信息传入到收集器中,随后将碰撞检查结果通过列表输出并以表格的形式显示出来,表格中包含碰撞构件的ID、类型和轴网位置信息。
所述的一种基于BIM技术的建筑机电管线综合优化方法,其进一步设计在于:步骤(4)中利用二次开发的插件优化调整模型是指:利用插件可以快速的对机电设备专业的管线模型构件进行移动,对齐,偏移,上下翻弯等快捷操作,相较于原始软件中“打断-连接-设置高度-拉伸-设置高度-连接”的操作大大的减少了优化调整的时间,提高了效率。
本发明具有以下优点:
通过本方法进行管线综合优化既避免了因碰撞造成返工浪费,在设计阶段选出最有管线综合布置方案,最终优化的三维模型可以用于后期运维,实现建筑信息模型的有效利用。
附图说明
图1为本发明基于Revit二次开发的建筑机电管线综合优化方法的流程图。
图 2为快速建模转化界面。
图3为快速优化调整管线界面。
具体实施方式:
以下结合说明书附图以及实施例对本实用新型进行进一步说明:
如图所示的一种基于BIM技术的建筑机电管线综合优化方法,包括以下步骤:
(1)在Revit软件上建立项目样板,包含建筑、结构专业的相关构件,机电设备专业的系统材质、颜色等项目信息。
(2)利用Revit软件二次开发的插件快速创建各专业BIM模型,确定机电各专业初始高度。
(3)利用Revit软件二次开发的插件进行各专业BIM模型自动碰撞检测,生成碰撞节点报告,包含碰撞构件信息以及在项目中的定位,可通过定位快速切换至碰撞节点。
(4)利用Revit软件二次开发的插件与步骤(3)中生成的碰撞报告对BIM模型进行优化调整,并记录。
(5)根据综合优化后的BIM模型指定管线装配方案,导出模型制作深化图纸。
(6)现场根据BIM模型与深化图纸进行安装施工。
步骤(2)中利用二次开发的插件快速创建模型是指:通过拾取CAD文件中的线条、图块等构件,识别其中的图层、块参数等信息,快速转化为Revit文件中的梁、板、柱、墙以及机电设备各专业的管线模型,减少设计人员手动建模的时间,提高建模效率。
步骤(3)中利用二次开发的插件进行自动碰撞检测是指:将模型构件截面分类,分为点、矩形截面与圆形截面三种,对截面边缘绘制其法线并将其强转成定位线,如果不同构件的定位线之间有交叉则判定构件间有碰撞发生,将此碰撞信息传入到收集器中,随后将碰撞检查结果通过列表输出并以表格的形式显示出来,表格中包含碰撞构件的ID、类型和轴网位置信息。
步骤(4)中利用二次开发的插件优化调整模型是指:利用插件可以快速的对机电设备专业的管线模型构件进行移动,对齐,偏移,上下翻弯等快捷操作,相较于原始软件中“打断-连接-设置高度-拉伸-设置高度-连接”的操作大大的减少了优化调整的时间,提高了效率。
Claims (4)
1.一种基于BIM技术的建筑机电管线综合优化方法,包括以下步骤:
在Revit软件上建立项目样板,包含建筑、结构专业的相关构件,机电设备专业的系统材质、颜色等项目信息;
利用Revit软件二次开发的插件创建各专业BIM模型,确定机电各专业初始高度;
利用Revit软件二次开发的插件进行各专业BIM模型自动碰撞检测,生成碰撞节点报告,包含碰撞构件信息以及在项目中的定位,可通过定位快速切换至碰撞节点;
利用Revit软件二次开发的插件与步骤(3)中生成的碰撞报告对BIM模型进行优化调整,并记录;
根据综合优化后的BIM模型指定管线装配方案,导出模型制作深化图纸;
现场根据BIM模型与深化图纸进行安装施工。
2.根据权利要求1所述的基于BIM技术的建筑机电管线综合优化方法,其特征在于,步骤(2)中利用二次开发的插件创建模型方法如下:通过拾取CAD文件中的线条、图块等构件,识别其中的图层、块参数等信息,转化为Revit文件中的梁、板、柱、墙以及机电设备各专业的管线模型。
3.根据权利要求1所述的基于BIM技术的建筑机电管线综合优化方法,其特征在于,步骤(3)中利用二次开发的插件进行自动碰撞检测方法如下:将模型构件截面分类,分为点、矩形截面与圆形截面三种,对截面边缘绘制其法线并将其强转成定位线,如果不同构件的定位线之间有交叉则判定构件间有碰撞发生,将此碰撞信息传入到收集器中,随后将碰撞检查结果通过列表输出并以表格的形式显示出来,表格中包含碰撞构件的ID、类型和轴网位置信息。
4.根据权利要求1所述的基于BIM技术的建筑机电管线综合优化方法,其特征在于,步骤(4)中利用二次开发的插件优化调整模型方法如下:利用插件可以快速的对机电设备专业的管线模型构件进行移动、对齐、偏移、上下翻弯等操作。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011636052.XA CN112733230A (zh) | 2020-12-31 | 2020-12-31 | 一种基于bim技术的建筑机电管线综合优化方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011636052.XA CN112733230A (zh) | 2020-12-31 | 2020-12-31 | 一种基于bim技术的建筑机电管线综合优化方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112733230A true CN112733230A (zh) | 2021-04-30 |
Family
ID=75608636
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011636052.XA Pending CN112733230A (zh) | 2020-12-31 | 2020-12-31 | 一种基于bim技术的建筑机电管线综合优化方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112733230A (zh) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113283225A (zh) * | 2021-05-07 | 2021-08-20 | 中国电建集团华东勘测设计研究院有限公司 | 一种可定制模板的bim可视化碰撞检查报告的自动生成方法、装置、存储介质及设备 |
CN113808258A (zh) * | 2021-09-18 | 2021-12-17 | 广东博意建筑设计院有限公司 | 叠合板内电气导管系统精细化敷设协同设计方法及系统 |
CN114925417A (zh) * | 2022-05-05 | 2022-08-19 | 上海宝冶集团有限公司 | 基于Rhino和Revit的管线碰撞优化方法 |
CN116341074A (zh) * | 2023-03-28 | 2023-06-27 | 山东方杰建工集团有限公司金乡二十分公司 | 基于bim的装配式建筑碰撞检测方法及系统 |
CN116484654A (zh) * | 2023-06-21 | 2023-07-25 | 北京市第三建筑工程有限公司 | 一种基于Revit的弧形结构内管线的定位方法 |
CN117272490A (zh) * | 2023-11-21 | 2023-12-22 | 江西少科智能建造科技有限公司 | 一种bim模型处理方法、系统、计算机及可读存储介质 |
CN117494356A (zh) * | 2023-10-31 | 2024-02-02 | 成都建工第九建筑工程有限公司 | 一种基于bim技术的装配式施工方法 |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108108543A (zh) * | 2017-12-14 | 2018-06-01 | 中交公局海威工程建设有限公司 | 一种鲁班bim技术的二次结构深化设计应用方法 |
CN108563851A (zh) * | 2018-03-29 | 2018-09-21 | 同济大学 | 一种快速精细化的山岭隧道bim建模方法 |
CN108733863A (zh) * | 2017-04-25 | 2018-11-02 | 中国二十冶集团有限公司 | 基于bim的大型城市综合体机电系统安装方法 |
CN110046364A (zh) * | 2018-01-16 | 2019-07-23 | 中国建筑第八工程局有限公司 | 一种基于bim技术的工程量计算方法 |
KR20190094788A (ko) * | 2018-02-06 | 2019-08-14 | 대림산업 주식회사 | Bim 시스템을 활용한 수배관 설계 방법 |
CN110765515A (zh) * | 2019-09-27 | 2020-02-07 | 贵州百胜工程建设咨询有限公司 | 一种基于bim的管综优化方法 |
CN110929326A (zh) * | 2019-11-30 | 2020-03-27 | 四川鸥鹏建筑工程公司 | 一种基于bim的地下室机电建模方法 |
CN111680412A (zh) * | 2020-05-29 | 2020-09-18 | 南京理工大学 | 一种基于Revit的BIM机电和结构碰撞检查方法 |
CN111767632A (zh) * | 2020-04-17 | 2020-10-13 | 中铁建工集团有限公司 | 一种采用Dynamo实现钢支撑自动配节的BIM建模方法 |
-
2020
- 2020-12-31 CN CN202011636052.XA patent/CN112733230A/zh active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108733863A (zh) * | 2017-04-25 | 2018-11-02 | 中国二十冶集团有限公司 | 基于bim的大型城市综合体机电系统安装方法 |
CN108108543A (zh) * | 2017-12-14 | 2018-06-01 | 中交公局海威工程建设有限公司 | 一种鲁班bim技术的二次结构深化设计应用方法 |
CN110046364A (zh) * | 2018-01-16 | 2019-07-23 | 中国建筑第八工程局有限公司 | 一种基于bim技术的工程量计算方法 |
KR20190094788A (ko) * | 2018-02-06 | 2019-08-14 | 대림산업 주식회사 | Bim 시스템을 활용한 수배관 설계 방법 |
CN108563851A (zh) * | 2018-03-29 | 2018-09-21 | 同济大学 | 一种快速精细化的山岭隧道bim建模方法 |
CN110765515A (zh) * | 2019-09-27 | 2020-02-07 | 贵州百胜工程建设咨询有限公司 | 一种基于bim的管综优化方法 |
CN110929326A (zh) * | 2019-11-30 | 2020-03-27 | 四川鸥鹏建筑工程公司 | 一种基于bim的地下室机电建模方法 |
CN111767632A (zh) * | 2020-04-17 | 2020-10-13 | 中铁建工集团有限公司 | 一种采用Dynamo实现钢支撑自动配节的BIM建模方法 |
CN111680412A (zh) * | 2020-05-29 | 2020-09-18 | 南京理工大学 | 一种基于Revit的BIM机电和结构碰撞检查方法 |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113283225A (zh) * | 2021-05-07 | 2021-08-20 | 中国电建集团华东勘测设计研究院有限公司 | 一种可定制模板的bim可视化碰撞检查报告的自动生成方法、装置、存储介质及设备 |
CN113808258A (zh) * | 2021-09-18 | 2021-12-17 | 广东博意建筑设计院有限公司 | 叠合板内电气导管系统精细化敷设协同设计方法及系统 |
CN114925417A (zh) * | 2022-05-05 | 2022-08-19 | 上海宝冶集团有限公司 | 基于Rhino和Revit的管线碰撞优化方法 |
CN114925417B (zh) * | 2022-05-05 | 2024-06-07 | 上海宝冶集团有限公司 | 基于Rhino和Revit的管线碰撞优化方法 |
CN116341074A (zh) * | 2023-03-28 | 2023-06-27 | 山东方杰建工集团有限公司金乡二十分公司 | 基于bim的装配式建筑碰撞检测方法及系统 |
CN116341074B (zh) * | 2023-03-28 | 2023-10-13 | 山东方杰建工集团有限公司金乡二十分公司 | 基于bim的装配式建筑碰撞检测方法及系统 |
CN116484654A (zh) * | 2023-06-21 | 2023-07-25 | 北京市第三建筑工程有限公司 | 一种基于Revit的弧形结构内管线的定位方法 |
CN116484654B (zh) * | 2023-06-21 | 2023-12-08 | 北京市第三建筑工程有限公司 | 一种基于Revit的弧形结构内管线的定位方法 |
CN117494356A (zh) * | 2023-10-31 | 2024-02-02 | 成都建工第九建筑工程有限公司 | 一种基于bim技术的装配式施工方法 |
CN117272490A (zh) * | 2023-11-21 | 2023-12-22 | 江西少科智能建造科技有限公司 | 一种bim模型处理方法、系统、计算机及可读存储介质 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112733230A (zh) | 一种基于bim技术的建筑机电管线综合优化方法 | |
CN110929328A (zh) | 基于bim的混凝土装配式建筑施工方法 | |
CN104281729B (zh) | 一种应用于钢结构建筑数字化加工制造的bim方法 | |
CN112257160B (zh) | 一种基于bim的垃圾焚烧发电厂标准化正向设计方法 | |
CN109885966B (zh) | 基于bim技术的滑槽管片冲突及优化布置的方法 | |
CN104631826A (zh) | 一种基于bim模型的施工总平面布置方法 | |
CN110889160A (zh) | 一种基于bim技术的市政管道施工方法 | |
CN110837670A (zh) | Bim双向深化设计的方法 | |
CN110502834A (zh) | 基于bim的城市轨道交通车辆基地设计方法 | |
CN112765701A (zh) | 一种农民新村设计施工一体化建设方法 | |
CN116070311B (zh) | 一种长大桥梁bim正向设计方法 | |
CN112765711A (zh) | 一种绿色建筑模拟计算的bim建模方法 | |
CN111597625A (zh) | 一种基于bim的基坑支护开挖质量控制方法 | |
CN111581700A (zh) | 基于catia模型添加bim属性并输出bim属性表的方法 | |
KR20020011677A (ko) | 2차원 배관엔지니어링 도면을 3차원 캐드데이타로자동변환 및 모델제작하는 프로그램에 의한 설계방법 | |
CN113642079B (zh) | 一种基于三维技术的工厂设计方法 | |
CN103425844A (zh) | 基于数据流通信平台的cad/cae系统及集成方法 | |
CN112214815B (zh) | 基于图形拓扑的机电综合设计方法 | |
Hsu et al. | Employing simulated annealing algorithms to automatically resolve MEP clashes in building information modeling models | |
CN116204962B (zh) | 一种基于bim的结构设计方法 | |
CN108549765B (zh) | 在Civil3D中利用要素线进行道路纵断设计的方法 | |
CN104298792A (zh) | 基于核电站的模块设计方法和系统 | |
CN112926105B (zh) | 一种利用bim市政管网快速精细化建模方法 | |
CN111080771B (zh) | 一种应用于三维智能辅助设计的信息模型构建方法 | |
CN113821858A (zh) | 基于Revit的任意混凝土浇筑块内机电埋件拆分方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20210430 |