CN112700086A - Refinery berth scheduling method and device based on hierarchical constraint conditions - Google Patents

Refinery berth scheduling method and device based on hierarchical constraint conditions Download PDF

Info

Publication number
CN112700086A
CN112700086A CN202011447997.7A CN202011447997A CN112700086A CN 112700086 A CN112700086 A CN 112700086A CN 202011447997 A CN202011447997 A CN 202011447997A CN 112700086 A CN112700086 A CN 112700086A
Authority
CN
China
Prior art keywords
berth
tanker
oil
data
refinery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011447997.7A
Other languages
Chinese (zh)
Inventor
虞景露
娄海川
林雪茹
刘聪
陈亮
栾吴建
孔倩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Supcon Software Co ltd
Zhejiang Supcon Technology Co Ltd
Original Assignee
Zhejiang Supcon Software Co ltd
Zhejiang Supcon Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Supcon Software Co ltd, Zhejiang Supcon Technology Co Ltd filed Critical Zhejiang Supcon Software Co ltd
Priority to CN202011447997.7A priority Critical patent/CN112700086A/en
Publication of CN112700086A publication Critical patent/CN112700086A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2111/00Details relating to CAD techniques
    • G06F2111/04Constraint-based CAD
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2111/00Details relating to CAD techniques
    • G06F2111/06Multi-objective optimisation, e.g. Pareto optimisation using simulated annealing [SA], ant colony algorithms or genetic algorithms [GA]

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • Educational Administration (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a refinery berth scheduling method and a device based on hierarchical constraint conditions, which comprises the following steps: acquiring oil tanker data and berth data, and distributing priority to the oil tanker according to the oil tanker data; establishing an objective function by taking the minimum total delay cost as a target, and establishing a constraint condition comprising a priority and a preset oil tanker berth matching rule; and inputting the oil tanker data and the berth data into an objective function, and solving the objective function under the constraint condition to obtain a berth scheduling result. The berth scheduling method provided by the invention does not take the benefit of a berth scheduling system as a unique optimization point under the condition that a refinery has special requirements on crude oil, so that required oil products can be provided according to the actual requirements of the refinery on the premise of ensuring the minimum total lag cost as far as possible, the scientificity of a berth scheduling sequence is improved, and the production requirements of the refinery are met.

Description

Refinery berth scheduling method and device based on hierarchical constraint conditions
Technical Field
The invention belongs to the field of industrial berth scheduling, and particularly relates to a refinery berth scheduling method and device based on a hierarchical constraint condition.
Background
The crude oil scheduling and scheduling process mainly comprises product scheduling in the petrochemical oil refining process, and is used as the most important working link of petrochemical oil refining enterprises, and the high-efficiency rationality of the crude oil scheduling and scheduling process can greatly influence the operation condition and the economic benefit of the whole refinery.
At present, the traditional refinery berth scheduling is generally arranged through manual calculation and is only scheduled from a single angle of reducing the lag time cost, the scheduling strategy has the defects of large influence of subjective factors and complicated flow, the requirements of the refinery on oil products are neglected, the overall arrangement can only be carried out by focusing on short-term local scheduling but not for a long time, the condition that the oil products which are most needed for current processing cannot be provided for the refinery can occur, and the subsequent processing flow of the refinery is influenced.
Disclosure of Invention
In order to solve the defects in the prior art, the invention provides a refinery berth scheduling method based on a hierarchical constraint condition, which comprises the following steps:
acquiring preset layered constraint conditions, wherein the layered constraint conditions comprise a first constraint condition used for determining a berth matched with a tanker and a second constraint condition used for determining a berthing sequence of the tanker in the same berth;
establishing an objective function by taking the minimum total delay cost as a target;
acquiring oil tanker data and berth data, inputting the oil tanker data and the berth data into an objective function, and solving the objective function under the hierarchical constraint condition to obtain a berth scheduling result.
Optionally, the first constraint condition includes:
the length of the tanker does not exceed the maximum accommodation length of the berth, and the width of the tanker does not exceed the maximum accommodation width of the berth;
the draft of the tanker does not exceed the expected draft of the berth;
the loading capacity of the tanker does not exceed the maximum loading capacity of the berth;
the oil seeds loaded on the oil tanker are the oil seeds which are allowed to operate in the berth;
the waiting time of the tanker does not exceed the preset time.
Optionally, the second constraint condition includes:
acquiring the data of the oil tanker distributed to the same berth, wherein the data comprises the oil grade, the delay charge coefficient, the loading capacity and the estimated arrival time of the oil tanker;
if the oil product grade is higher than the preset grade, determining the mooring sequence of the oil tanker according to the sequence from high to low of the oil product grade within the allowable waiting time range of the oil tanker, and if the oil product grade is not higher than the preset grade, judging whether the estimated arrival time of the oil tanker conflicts with other oil tankers;
and if the conflict exists, weighting and summing the delay charge coefficient and the loading capacity based on the preset weight, determining the mooring sequence of the oil tanker with the conflict according to the sequence from high to low of the summed value, and if the conflict does not exist, determining the mooring sequence of the oil tanker according to the sequence from small to large of the loading capacity.
Optionally, the establishing an objective function with the minimum total hysteresis cost as a target includes:
establishing a target function totalmeurage based on a formula I;
Figure BDA0002825492340000021
wherein totalmeurage represents the minimum value of the total lag, ship, waitiIndicating the waiting time, ship, of tanker iiThe free working time of the tanker i is represented, the ship _ demurrage represents the lag cost coefficient of the tanker, and m is the total number of the tankers; totalmeurage, ship, waiti、ship,freehouriThe value range of the ship _ demarreage is positive number, and the value range of the m is positive integer.
Optionally, the obtaining of the tanker data and the berth data, inputting the tanker data and the berth data into an objective function, and solving the objective function under a hierarchical constraint condition to obtain a berth scheduling result includes:
acquiring oil tanker data of a predicted arrival port oil tanker and berth data of a refinery port;
inputting the oil tanker data and the berth data into an objective function, solving the minimum value of the objective function on the premise of meeting the hierarchical constraint condition, and obtaining a berth scheduling result through the solving result;
and outputting a berth scheduling result in a Gantt chart form, wherein the berth scheduling result comprises a berth number, the starting operation time of the oil tanker at the berth and the berthing time.
Optionally, the refinery berth scheduling method further includes an optimization process of the berth scheduling result, specifically including:
and acquiring weather data and tide height data in real time, delaying the operation starting time of the oil tanker influenced by weather and tide, updating the berth scheduling result, and determining the delayed time length according to the weather data and the tide height data.
The invention also provides a refinery berth scheduling device based on the layered constraint condition based on the same idea, which comprises the following components:
a restraint unit: the method comprises the steps of acquiring preset hierarchical constraint conditions, wherein the hierarchical constraint conditions comprise a first constraint condition for determining a berth matched with a tanker and a second constraint condition for determining a berthing sequence of the tanker in the same berth;
a modeling unit: the method comprises the steps of establishing an objective function by taking the minimum total delay cost as a target;
a scheduling unit: the method is used for acquiring the oil tanker data and the berth data, inputting the oil tanker data and the berth data into an objective function, and solving the objective function under the hierarchical constraint condition to obtain a berth scheduling result.
Optionally, the constraint unit is configured to determine a first constraint condition, and includes:
the length of the tanker does not exceed the maximum accommodation length of the berth, and the width of the tanker does not exceed the maximum accommodation width of the berth;
the draft of the tanker does not exceed the expected draft of the berth;
the loading capacity of the tanker does not exceed the maximum loading capacity of the berth;
the oil seeds loaded on the oil tanker are the oil seeds which are allowed to operate in the berth;
the waiting time of the tanker does not exceed the preset time.
Optionally, the constraint unit is further configured to determine a second constraint condition, including:
acquiring the data of the oil tanker distributed to the same berth, wherein the data comprises the oil grade, the delay charge coefficient, the loading capacity and the estimated arrival time of the oil tanker;
if the oil product grade is higher than the preset grade, determining the mooring sequence of the oil tanker according to the sequence from high to low of the oil product grade within the allowable waiting time range of the oil tanker, and if the oil product grade is not higher than the preset grade, judging whether the estimated arrival time of the oil tanker conflicts with other oil tankers;
and if the conflict exists, weighting and summing the delay charge coefficient and the loading capacity based on the preset weight, determining the mooring sequence of the oil tanker with the conflict according to the sequence from high to low of the summed value, and if the conflict does not exist, determining the mooring sequence of the oil tanker according to the sequence from small to large of the loading capacity.
Optionally, the scheduling unit is specifically configured to:
acquiring oil tanker data of a predicted arrival port oil tanker and berth data of a refinery port;
inputting the oil tanker data and the berth data into an objective function, solving the minimum value of the objective function on the premise of meeting the hierarchical constraint condition, and obtaining a berth scheduling result through the solving result;
and outputting a berth scheduling result in a Gantt chart form, wherein the berth scheduling result comprises a berth number, the starting operation time of the oil tanker at the berth and the berthing time.
The technical scheme provided by the invention has the beneficial effects that:
compared with the traditional method for carrying out berth scheduling only from the perspective of the lag time fee, the berth scheduling method provided by the invention does not take the benefits of a berth scheduling system as a unique optimization point, so that the required oil product can be provided according to the actual requirements of a refinery on the premise of ensuring the minimum total lag time fee as far as possible. The priority in the invention is a hierarchical priority, the scientificity of the berth scheduling sequence can be improved by setting the first-level priority and the second-level priority, the production requirement of a refinery is further met, meanwhile, the optimal berth scheduling result is obtained by combining the oil tanker and the berth matching rule, and the influence of subjective factors is overcome to the maximum extent. In addition, the technical scheme provided by the invention displays the berthing scheduling result in a Gantt chart mode, and can more intuitively display the berthing condition of the tanker in a period of time in the future.
Drawings
In order to more clearly illustrate the technical solution of the present invention, the drawings needed to be used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings based on the drawings without creative efforts.
FIG. 1 is a schematic flow chart of a refinery berth scheduling method based on hierarchical constraint conditions according to the present invention;
FIG. 2 is a schematic illustration showing a Gantt chart of a result of berthing scheduling;
fig. 3 is a block diagram of a refinery berth scheduling apparatus based on hierarchical constraint conditions according to the present invention.
Detailed Description
To make the structure and advantages of the present invention clearer, the structure of the present invention will be further described with reference to the accompanying drawings.
As shown in fig. 1, the present invention provides a refinery berth scheduling method based on hierarchical constraint conditions, including:
s100: and acquiring preset hierarchical constraint conditions, wherein the hierarchical constraint conditions comprise a first constraint condition for determining the berth matched with the tanker and a second constraint condition for determining the berthing sequence of the tanker in the same berth.
The hierarchical constraint conditions comprise a first constraint condition and a second constraint condition, when the oil tanker is subjected to berth scheduling, a proper berth is allocated to each oil tanker arriving at the port according to the first constraint condition, and then the berthing sequence of the oil tanker in the same berth is determined according to the second constraint condition.
The first constraint includes:
(1) and (3) space constraint: the length of the tanker does not exceed the maximum accommodation length of the berth, and the width of the tanker does not exceed the maximum accommodation width of the berth;
(2) draft depth restraint: the draft of the tanker does not exceed the expected draft of the berth;
(3) and (3) load capacity constraint: the loading capacity of the tanker does not exceed the maximum loading capacity of the berth;
(4) oil seed restraint: the oil seeds loaded on the oil tanker are the oil seeds which are allowed to operate in the berth;
(5) and (3) latency constraint: the waiting time of the oil tanker does not exceed the preset time;
in addition to this, it is necessary to ensure that each tanker must be and can only be serviced once, namely:
Figure BDA0002825492340000051
wherein x isijIndicating whether the ith tanker is assigned to the jth berth, xijThe value range of (1) is 0 or 1, and a value of 0 indicates that the signal is not assigned to the jth parking space, and a value of 1 indicates that the signal is assigned to the jth parking space. m represents the total number of tanker ships, n represents the total number of berths; the value ranges of m, n, i and j are all positive integers.
The second constraint includes:
(1) the oil grade is set according to the production requirement and the inventory condition of the refinery, and the lower the inventory of oil required by the refinery production, the higher the oil grade.
(2) If the oil product grade is higher than the preset grade, determining the mooring sequence of the oil tanker according to the sequence from high to low of the oil product grade within the allowable waiting time range of the oil tanker, and if the oil product grade is not higher than the preset grade, judging whether the estimated arrival time of the oil tanker conflicts with other oil tankers;
(3) and if the conflict exists, weighting and summing the delay charge coefficient and the loading capacity based on the preset weight, determining the mooring sequence of the oil tanker with the conflict according to the sequence from high to low of the summed value, and if the conflict does not exist, determining the mooring sequence of the oil tanker according to the sequence from small to large of the loading capacity.
The berth scheduling method is divided into two stages by using the layering constraint condition, so that the sequential berth scheduling is facilitated, the requirement of the oil tanker on the berth is met, and the production requirement of a refinery plant is met as far as possible. The berth is preferentially distributed to the oil tanker loading the specified oil products according to the level of the oil product grade, the required oil products can be timely unloaded, the production progress of a refinery cannot be influenced due to unreasonable scheduling of the berth, and meanwhile, the berth is distributed to the oil tanker loading the oil products with the lower grade according to the loading capacity and the delay cost coefficient by combining the estimated arrival time due to the fact that the oil product with the lower grade of the refinery is not high in demand degree. The method and the device realize simultaneous consideration of the lag time and the oil product condition, timely allocate the berth according to the production requirement of the refinery, and improve the rationality and scientificity of berth scheduling.
S200: and establishing an objective function by taking the minimum total delay cost as a target.
The method is the same as the traditional berth scheduling method, and the implementation also establishes an objective function by taking the minimum total delay cost as a target, so that the berthing cost of the oil tanker is reduced to the maximum extent. The late fee is a certain penalty paid to the ship side for the time exceeding the time, because the ship renter does not finish the loading and unloading operation within the specified loading and unloading period, so that economic loss is caused to the ship side. The method for calculating the delay fee comprises the following steps: and calculating the difference between the waiting time of the oil tanker and the free working time length, wherein the product of the absolute value of the difference and the delay charge coefficient of the oil tanker is the delay charge of the oil tanker. The method specifically comprises the following steps:
an objective function totalmeurage is established based on the formula one,
Figure BDA0002825492340000061
wherein totalmeurage represents the minimum value of the total lag, ship, waitiIndicating the waiting time, ship, of tanker iiThe free working time of the tanker i is represented, the ship _ demurrage represents the lag cost coefficient of the tanker, and m is the total number of the tankers; totalmeurage, ship, waiti、ship,freehouriThe value range of the ship _ demarreage is positive number, and the value range of the m is positive integer.
Ship, freehour in formula IiBoth the variable ship _ demurrage and the variable ship _ demurrage can be obtained from the tanker dataiCan be calculated based on the estimated time to port in the tanker data. In this embodiment, the minimum time of the objective function, ship, wait, is solvediDetermining a berthage scheduling result.
S300: acquiring oil tanker data and berth data, inputting the oil tanker data and the berth data into an objective function, and solving the objective function under the hierarchical constraint condition to obtain a berth scheduling result.
Acquiring the data of the oil tanker expected to arrive at the port oil tanker and the berth data of the refinery port. The tanker data includes oil grade, lag time coefficient and loading capacity, and also includes tanker code, estimated arrival time, crude oil loading and unloading rate, free working time, tanker width, tanker length and tanker draft. The berth data includes a set of berthable tanker codes, a maximum containment length, a maximum containment width, a projected draft, a maximum payload, a berth-allowable operating oil seed, and historical tide level information.
Inputting the oil tanker data and the berth data into an objective function, and solving the objective function as the minimum time variable ship, wait on the premise of meeting the hierarchical constraint conditioniAccording to the value of ship, waitiThe value of the position number is combined with the estimated arrival time in the oil tanker data to obtain the starting operation time of the oil tanker in the position scheduling result, the berthing time in the position scheduling result is obtained according to the ratio of the loading capacity to the loading and unloading rate of the crude oil, and the position number in the position scheduling result is obtained according to the corresponding position distribution condition when the objective function is the minimum value.
Finally, as shown in fig. 2, the result of the berthage scheduling is output in the form of a gantt chart. The display content of the gantt chart includes a berth number, the starting operation time of the tanker at the berth, and the berthing time. Wherein, the 'berth _ 001' and the 'berth _ 002' respectively represent two berths with berth numbers of 1 and 2, a time axis for representing the date is arranged above the Gantt chart, and the 'A', the 'B', the 'C' and the 'D' all represent the number of the oil tanker parked in the corresponding time period and the loaded oil product. And acquiring the starting operation time and the mooring time of the oil tanker at the berth according to the corresponding relation between the length of the square in the figure and the time axis.
The Gantt chart can visually display the starting operation time, the operation duration, the waiting time, the planned departure time and the planned berthing of the oil tanker, and output the delay cost and the total delay cost of each ship, so that a dispatcher can conveniently check the berthing dispatching result in time, and the manual adjustment is facilitated.
Since the berthing port is often influenced by typhoon and tidal changes, which may cause the possibility that some affected oil tankers may delay arriving at the port, the embodiment further includes an optimization process of the berthing scheduling result, specifically including:
and acquiring weather data and tide height data in real time, delaying the operation starting time of the oil tanker influenced by weather and tide, updating the berth scheduling result, and determining the delayed time length according to the weather data and the tide height data. For example, under the influence of typhoon, the estimated arrival time of the oil tanker is delayed and adjusted for 1 day, and the adjusted estimated arrival time is input into the berth scheduling model for scheduling again, so that the optimized berth scheduling result is obtained.
By the process, optimization processing can be realized according to weather and tide reasons, and the berth scheduling result can adapt to more application scenes.
Example two
As shown in fig. 3, the present invention provides a refinery berth scheduling apparatus 4 based on hierarchical constraint conditions, comprising:
the restricting unit 41: the method comprises the steps of obtaining preset hierarchical constraint conditions, wherein the hierarchical constraint conditions comprise a first constraint condition used for determining the berth matched with the tanker and a second constraint condition used for determining the berthing sequence of the tanker in the same berth.
The hierarchical constraint conditions comprise a first constraint condition and a second constraint condition, when the oil tanker is subjected to berth scheduling, a proper berth is allocated to each oil tanker arriving at the port according to the first constraint condition, and then the berthing sequence of the oil tanker in the same berth is determined according to the second constraint condition.
The constraint unit 41 is configured to determine a first constraint, where the first constraint includes:
(1) and (3) space constraint: the length of the tanker does not exceed the maximum accommodation length of the berth, and the width of the tanker does not exceed the maximum accommodation width of the berth;
(2) draft depth restraint: the draft of the tanker does not exceed the expected draft of the berth;
(3) and (3) load capacity constraint: the loading capacity of the tanker does not exceed the maximum loading capacity of the berth;
(4) oil seed restraint: the oil seeds loaded on the oil tanker are the oil seeds which are allowed to operate in the berth;
(5) and (3) latency constraint: the waiting time of the oil tanker does not exceed the preset time;
in addition to this, it is necessary to ensure that each tanker must be and can only be serviced once, namely:
Figure BDA0002825492340000081
wherein x isijIndicating whether the ith tanker is assigned to the jth berth, xijThe value range of (1) is 0 or 1, and a value of 0 indicates that the signal is not assigned to the jth parking space, and a value of 1 indicates that the signal is assigned to the jth parking space. m represents the total number of tanker ships, n represents the total number of berths; the value ranges of m, n, i and j are all positive integers.
The constraint unit 41 is further configured to determine a second constraint, where the second constraint includes:
(1) the oil grade is set according to the production requirement and the inventory condition of the refinery, and the lower the inventory of oil required by the refinery production, the higher the oil grade.
(2) If the oil product grade is higher than the preset grade, determining the mooring sequence of the oil tanker according to the sequence from high to low of the oil product grade within the allowable waiting time range of the oil tanker, and if the oil product grade is not higher than the preset grade, judging whether the estimated arrival time of the oil tanker conflicts with other oil tankers;
(3) and if the conflict exists, weighting and summing the delay charge coefficient and the loading capacity based on the preset weight, determining the mooring sequence of the oil tanker with the conflict according to the sequence from high to low of the summed value, and if the conflict does not exist, determining the mooring sequence of the oil tanker according to the sequence from small to large of the loading capacity.
The berth scheduling method is divided into two stages by using the layering constraint condition, so that the sequential berth scheduling is facilitated, the requirement of the oil tanker on the berth is met, and the production requirement of a refinery plant is met as far as possible. The berth is preferentially distributed to the oil tanker loading the specified oil products according to the level of the oil product grade, the required oil products can be timely unloaded, the production progress of a refinery cannot be influenced due to unreasonable scheduling of the berth, and meanwhile, the berth is distributed to the oil tanker loading the oil products with the lower grade according to the loading capacity and the delay cost coefficient by combining the estimated arrival time due to the fact that the oil product with the lower grade of the refinery is not high in demand degree. The method and the device realize simultaneous consideration of the lag time and the oil product condition, timely allocate the berth according to the production requirement of the refinery, and improve the rationality and scientificity of berth scheduling.
The modeling unit 42: for establishing an objective function with a minimum total hysteresis.
Like the conventional berth scheduling method, the modeling unit 42 in this embodiment also establishes an objective function with the minimum total delay cost as a target, thereby reducing the berthing cost of the tanker to the maximum extent. The late fee is a certain penalty paid to the ship side for the time exceeding the time, because the ship renter does not finish the loading and unloading operation within the specified loading and unloading period, so that economic loss is caused to the ship side. The method for calculating the delay fee comprises the following steps: and calculating the difference between the waiting time of the oil tanker and the free working time length, wherein the product of the absolute value of the difference and the delay charge coefficient of the oil tanker is the delay charge of the oil tanker. The method specifically comprises the following steps:
an objective function totalmeurage is established based on the formula one,
Figure BDA0002825492340000091
wherein totalmeurage represents the minimum value of the total lag, ship, waitiIndicating the waiting time, ship, of tanker iiThe free working time of the tanker i is represented, the ship _ demurrage represents the lag cost coefficient of the tanker, and m is the total number of the tankers; totalmeurage, ship, waiti、ship,freehouriThe value range of the ship _ demarreage is positive number, and the value range of the m is positive integer.
Ship, freehour in formula IiBoth the variable ship _ demurrage and the variable ship _ demurrage can be obtained from the tanker dataiCan be calculated based on the estimated time to port in the tanker data. In this embodiment, the minimum time of the objective function, ship, wait, is solvediDetermining a berthage scheduling result.
The scheduling unit 43: the method is used for acquiring the oil tanker data and the berth data, inputting the oil tanker data and the berth data into an objective function, and solving the objective function under the hierarchical constraint condition to obtain a berth scheduling result. The method is specifically used for:
acquiring the data of the oil tanker expected to arrive at the port oil tanker and the berth data of the refinery port. The tanker data includes oil grade, lag time coefficient and loading capacity, and also includes tanker code, estimated arrival time, crude oil loading and unloading rate, free working time, tanker width, tanker length and tanker draft. The berth data includes a set of berthable tanker codes, a maximum containment length, a maximum containment width, a projected draft, a maximum payload, a berth-allowable operating oil seed, and historical tide level information.
Inputting the oil tanker data and the berth data into an objective function, and solving the objective function as the minimum time variable ship, wait on the premise of meeting the hierarchical constraint conditioniAccording to the value of ship, waitiThe value of the position number is combined with the estimated arrival time in the oil tanker data to obtain the starting operation time of the oil tanker in the position scheduling result, the berthing time in the position scheduling result is obtained according to the ratio of the loading capacity to the loading and unloading rate of the crude oil, and the position number in the position scheduling result is obtained according to the corresponding position distribution condition when the objective function is the minimum value.
Finally, as shown in fig. 2, the result of the berthage scheduling is output in the form of a gantt chart. The display content of the gantt chart includes a berth number, the starting operation time of the tanker at the berth, and the berthing time. Wherein, the 'berth _ 001' and the 'berth _ 002' respectively represent two berths with berth numbers of 1 and 2, a time axis for representing the date is arranged above the Gantt chart, and the 'A', the 'B', the 'C' and the 'D' all represent the number of the oil tanker parked in the corresponding time period and the loaded oil product. And acquiring the starting operation time and the mooring time of the oil tanker at the berth according to the corresponding relation between the length of the square in the figure and the time axis.
The Gantt chart can visually display the starting operation time, the operation duration, the waiting time, the planned departure time and the planned berthing of the oil tanker, and output the delay cost and the total delay cost of each ship, so that a dispatcher can conveniently check the berthing dispatching result in time, and the manual adjustment is facilitated.
Since mooring ports are often affected by typhoons and tidal variations, which may cause the possibility of delayed arrival of some affected oil tankers, the present embodiment further comprises an optimization unit for optimizing the berth scheduling result, specifically for:
and acquiring weather data and tide height data in real time, delaying the operation starting time of the oil tanker influenced by weather and tide, updating the berth scheduling result, and determining the delayed time length according to the weather data and the tide height data. For example, under the influence of typhoon, the estimated arrival time of the oil tanker is delayed and adjusted for 1 day, and the adjusted estimated arrival time is input into the berth scheduling model for scheduling again, so that the optimized berth scheduling result is obtained.
By the process, optimization processing can be realized according to weather and tide reasons, and the berth scheduling result can adapt to more application scenes.
The sequence numbers in the above embodiments are merely for description, and do not represent the sequence of the assembly or the use of the components.
The above description is only exemplary of the present invention and should not be taken as limiting the invention, as any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (10)

1. A refinery berth scheduling method based on hierarchical constraint conditions is characterized by comprising the following steps:
acquiring preset layered constraint conditions, wherein the layered constraint conditions comprise a first constraint condition used for determining a berth matched with a tanker and a second constraint condition used for determining a berthing sequence of the tanker in the same berth;
establishing an objective function by taking the minimum total delay cost as a target;
acquiring oil tanker data and berth data, inputting the oil tanker data and the berth data into an objective function, and solving the objective function under the hierarchical constraint condition to obtain a berth scheduling result.
2. The method of claim 1, wherein the first constraint comprises:
the length of the tanker does not exceed the maximum accommodation length of the berth, and the width of the tanker does not exceed the maximum accommodation width of the berth;
the draft of the tanker does not exceed the expected draft of the berth;
the loading capacity of the tanker does not exceed the maximum loading capacity of the berth;
the oil seeds loaded on the oil tanker are the oil seeds which are allowed to operate in the berth;
the waiting time of the tanker does not exceed the preset time.
3. The method of claim 1, wherein the second constraint comprises:
setting oil grade according to the production requirement and the inventory condition of a refinery, wherein the lower the inventory of oil required by the production of the refinery, the higher the oil grade;
if the oil product grade is higher than the preset grade, determining the mooring sequence of the oil tanker according to the sequence from high to low of the oil product grade within the allowable waiting time range of the oil tanker, and if the oil product grade is not higher than the preset grade, judging whether the estimated arrival time of the oil tanker conflicts with other oil tankers;
and if the conflict exists, weighting and summing the delay charge coefficient and the loading capacity based on the preset weight, determining the mooring sequence of the oil tanker with the conflict according to the sequence from high to low of the summed value, and if the conflict does not exist, determining the mooring sequence of the oil tanker according to the sequence from small to large of the loading capacity.
4. The method of claim 1, wherein the establishing an objective function with a minimum total hysteresis cost as a target comprises:
establishing a target function totalmeurage based on a formula I;
Figure FDA0002825492330000021
wherein totalmeurage represents the minimum value of the total lag, ship, waitiIndicating the waiting time, ship, of tanker iiThe free working time of the tanker i is represented, the ship _ demurrage represents the lag cost coefficient of the tanker, and m is the total number of the tankers; totalmeurage, ship, waiti、ship,freehouriThe value range of the ship _ demarreage is positive number, and the value range of the m is positive integer.
5. The refinery berth scheduling method based on hierarchical constraint conditions as claimed in claim 1, wherein the obtaining of the tanker data and the berth data, the inputting of the tanker data and the berth data into an objective function, and the solving of the objective function under the hierarchical constraint conditions to obtain the berth scheduling result comprises:
acquiring oil tanker data of a predicted arrival port oil tanker and berth data of a refinery port;
inputting the oil tanker data and the berth data into an objective function, solving the minimum value of the objective function on the premise of meeting the hierarchical constraint condition, and obtaining a berth scheduling result through the solving result;
and outputting a berth scheduling result in a Gantt chart form, wherein the berth scheduling result comprises a berth number, the starting operation time of the oil tanker at the berth and the berthing time.
6. The refinery berth scheduling method based on hierarchical constraint conditions of claim 1, further comprising an optimization process of berth scheduling results, specifically comprising:
and acquiring weather data and tide height data in real time, delaying the operation starting time of the oil tanker influenced by weather and tide, updating the berth scheduling result, and determining the delayed time length according to the weather data and the tide height data.
7. A refinery berth scheduling device based on hierarchical constraint conditions, characterized in that the refinery berth scheduling device comprises:
a restraint unit: the method comprises the steps of acquiring preset hierarchical constraint conditions, wherein the hierarchical constraint conditions comprise a first constraint condition for determining a berth matched with a tanker and a second constraint condition for determining a berthing sequence of the tanker in the same berth;
a modeling unit: the method comprises the steps of establishing an objective function by taking the minimum total delay cost as a target;
a scheduling unit: the method is used for acquiring the oil tanker data and the berth data, inputting the oil tanker data and the berth data into an objective function, and solving the objective function under the hierarchical constraint condition to obtain a berth scheduling result.
8. The layered constraint-based refinery berth scheduling device of claim 7, wherein the constraint unit is configured to determine the first constraint, and comprises:
the length of the tanker does not exceed the maximum accommodation length of the berth, and the width of the tanker does not exceed the maximum accommodation width of the berth;
the draft of the tanker does not exceed the expected draft of the berth;
the loading capacity of the tanker does not exceed the maximum loading capacity of the berth;
the oil seeds loaded on the oil tanker are the oil seeds which are allowed to operate in the berth;
the waiting time of the tanker does not exceed the preset time.
9. The hierarchical constraint based refinery berth scheduling device of claim 7, wherein the constraint unit is further configured to determine a second constraint comprising:
acquiring the data of the oil tanker distributed to the same berth, wherein the data comprises the oil grade, the delay charge coefficient, the loading capacity and the estimated arrival time of the oil tanker;
if the oil product grade is higher than the preset grade, determining the mooring sequence of the oil tanker according to the sequence from high to low of the oil product grade within the allowable waiting time range of the oil tanker, and if the oil product grade is not higher than the preset grade, judging whether the estimated arrival time of the oil tanker conflicts with other oil tankers;
and if the conflict exists, weighting and summing the delay charge coefficient and the loading capacity based on the preset weight, determining the mooring sequence of the oil tanker with the conflict according to the sequence from high to low of the summed value, and if the conflict does not exist, determining the mooring sequence of the oil tanker according to the sequence from small to large of the loading capacity.
10. The refinery berth scheduling device based on hierarchical constraint conditions of claim 7, wherein the scheduling unit is specifically configured to:
acquiring oil tanker data of a predicted arrival port oil tanker and berth data of a refinery port;
inputting the oil tanker data and the berth data into an objective function, solving the minimum value of the objective function on the premise of meeting the hierarchical constraint condition, and obtaining a berth scheduling result through the solving result;
and outputting a berth scheduling result in a Gantt chart form, wherein the berth scheduling result comprises a berth number, the starting operation time of the oil tanker at the berth and the berthing time.
CN202011447997.7A 2020-12-09 2020-12-09 Refinery berth scheduling method and device based on hierarchical constraint conditions Pending CN112700086A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011447997.7A CN112700086A (en) 2020-12-09 2020-12-09 Refinery berth scheduling method and device based on hierarchical constraint conditions

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011447997.7A CN112700086A (en) 2020-12-09 2020-12-09 Refinery berth scheduling method and device based on hierarchical constraint conditions

Publications (1)

Publication Number Publication Date
CN112700086A true CN112700086A (en) 2021-04-23

Family

ID=75507914

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011447997.7A Pending CN112700086A (en) 2020-12-09 2020-12-09 Refinery berth scheduling method and device based on hierarchical constraint conditions

Country Status (1)

Country Link
CN (1) CN112700086A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113593290A (en) * 2021-06-25 2021-11-02 桂林电子科技大学 Parking-position-based perceivable parking conflict avoiding scheduling method, system and storage medium
CN115577859A (en) * 2022-11-21 2023-01-06 南京联云智能系统有限公司 Anchor berth distribution method, system and equipment

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03189702A (en) * 1989-12-20 1991-08-19 Sooteisu:Kk Berth control expert system
CN104281894A (en) * 2014-10-30 2015-01-14 大连海事大学 Ship dispatch optimization method based on channel and berth resources
CN106372753A (en) * 2016-08-31 2017-02-01 湖南大唐先科技有限公司 Coal carrier scheduling method and system
CN111080052A (en) * 2019-10-25 2020-04-28 浙江中控技术股份有限公司 Berth scheduling optimization method and system suitable for refinery plant
CN111754075A (en) * 2020-05-25 2020-10-09 山东浪潮质量链科技有限公司 Block chain-based multi-berth port ship scheduling method, equipment and medium
CN111754041A (en) * 2020-06-27 2020-10-09 华东师范大学 Port berth allocation method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03189702A (en) * 1989-12-20 1991-08-19 Sooteisu:Kk Berth control expert system
CN104281894A (en) * 2014-10-30 2015-01-14 大连海事大学 Ship dispatch optimization method based on channel and berth resources
CN106372753A (en) * 2016-08-31 2017-02-01 湖南大唐先科技有限公司 Coal carrier scheduling method and system
CN111080052A (en) * 2019-10-25 2020-04-28 浙江中控技术股份有限公司 Berth scheduling optimization method and system suitable for refinery plant
CN111754075A (en) * 2020-05-25 2020-10-09 山东浪潮质量链科技有限公司 Block chain-based multi-berth port ship scheduling method, equipment and medium
CN111754041A (en) * 2020-06-27 2020-10-09 华东师范大学 Port berth allocation method

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
BARROS, VICTOR HUGO: "Model and heuristic for berth allocation in tidal bulk ports with stock level constraints", COMPUTERS & INDUSTRIAL ENGINEERING *
杨斌;岳宇菲;: "离散泊位分配装卸量加权延迟最小化策略", 河南科技大学学报(自然科学版), no. 04, 3 June 2014 (2014-06-03) *
禹美凤: "基于柔性靠泊的集装箱港口泊位和岸桥的调度优化", 中国优秀硕士学位论文全文数据库, no. 06 *
郑红星: "考虑潮汐影响的离散型泊位和岸桥集成调度", 运筹与管理 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113593290A (en) * 2021-06-25 2021-11-02 桂林电子科技大学 Parking-position-based perceivable parking conflict avoiding scheduling method, system and storage medium
CN113593290B (en) * 2021-06-25 2022-12-13 桂林电子科技大学 Parking-position-based perceivable parking conflict avoiding scheduling method, system and storage medium
CN115577859A (en) * 2022-11-21 2023-01-06 南京联云智能系统有限公司 Anchor berth distribution method, system and equipment

Similar Documents

Publication Publication Date Title
Raa et al. An enriched model for the integrated berth allocation and quay crane assignment problem
He et al. Modeling berth allocation and quay crane assignment considering QC driver cost and operating efficiency
Brancaccio et al. Geography, search frictions and endogenous trade costs
CN101789093A (en) Distribution method of container quay berths and shore bridges
CN112700086A (en) Refinery berth scheduling method and device based on hierarchical constraint conditions
CN103645705B (en) A kind of LNG multiple spot cargo ship transport power forecast dispatching method
Pjevčević et al. Application of DEA to the analysis of AGV fleet operations in a port container terminal
Theofanis et al. Container terminal berth planning: critical review of research approaches and practical challenges
Štepec et al. Machine learning based system for vessel turnaround time prediction
CN111080052A (en) Berth scheduling optimization method and system suitable for refinery plant
Wang et al. Data-driven intelligent port management based on blockchain
CN112053003B (en) Scheduling method for intermediate storage tank in crude oil conveying process
Feng et al. Space planning considering congestion in container terminal yards
CN104376375B (en) Marine ships oil spill accident emergency resources concocting method based on multi objective fuzzy planning
US20230252395A1 (en) A quay crane operation method
KR102486545B1 (en) Method for predicting demand of requirement man power and material according to new ship contract
CN116957440A (en) Large-scale power generation group-oriented coal transportation planning method and system
CN112668778B (en) Intelligent ship scheduling system and method and computer storage medium
Wang et al. Systematic network design for liner shipping services
CN115545369A (en) Automated quayside container bridge resource planning decision-making method, terminal and medium
WO2017098494A1 (en) Rubust dynamic time scheduling and planning
Zheng et al. Hybrid dynamic modeling and receding horizon speed optimization for liner shipping operations from schedule reliability and energy efficiency perspectives
Yu et al. Automated rail-water intermodal transport container terminal handling equipment cooperative scheduling based on bidirectional hybrid flow-shop scheduling problem
Spasovic et al. Increasing productivity and service quality of the straddle carrier operations at a container port terminal
Hess et al. On transportation system with deterministic service time

Legal Events