CN112697103A - Method for monitoring ground surface settlement around foundation pit in urban rail transit construction period - Google Patents

Method for monitoring ground surface settlement around foundation pit in urban rail transit construction period Download PDF

Info

Publication number
CN112697103A
CN112697103A CN202011462127.7A CN202011462127A CN112697103A CN 112697103 A CN112697103 A CN 112697103A CN 202011462127 A CN202011462127 A CN 202011462127A CN 112697103 A CN112697103 A CN 112697103A
Authority
CN
China
Prior art keywords
monitoring
leveling
settlement
points
foundation pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011462127.7A
Other languages
Chinese (zh)
Inventor
史磊
杨正午
王伟
郭奇
刘宁
吕俊哲
张国华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Information Industry Technology Research Institute Co ltd
Original Assignee
Shanxi Information Industry Technology Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Information Industry Technology Research Institute Co ltd filed Critical Shanxi Information Industry Technology Research Institute Co ltd
Priority to CN202011462127.7A priority Critical patent/CN112697103A/en
Publication of CN112697103A publication Critical patent/CN112697103A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Testing Or Calibration Of Command Recording Devices (AREA)

Abstract

The invention belongs to the technical field of construction project monitoring, and particularly relates to a method for monitoring ground surface settlement around a foundation pit in an urban rail transit construction period, which comprises the following steps: s1, burying at least 2 leveling points 1 month before settlement monitoring, wherein the leveling points are arranged near a site and form a leveling control network; s2, before observation, the level gauge and the indium steel ruler used by each measuring point are checked, and records are made, and the leveling gauges and the indium steel ruler are not randomly replaced in the subsequent use process; s3, carrying out measuring point burying on a measuring point to be monitored; s4, observing for the first time, properly increasing the number of measured returns, and generally taking 2-3 times of data as an initial value; s5, determining a settlement monitoring control standard value as comparison data during monitoring data analysis, and feeding back information in time when the measured data exceeds an allowable value; and S6, recording weather conditions, construction progress and site conditions measured every day for reference during monitoring data analysis. The method solves the problem that the existing foundation pit settlement monitoring cannot be completed completely.

Description

Method for monitoring ground surface settlement around foundation pit in urban rail transit construction period
Technical Field
The invention belongs to the technical field of construction project monitoring, and particularly relates to a method for monitoring ground surface settlement around a foundation pit in an urban rail transit construction period.
Background
China is a country with multiple landslides and foundation pit collapse disasters since ancient times. The resulting harmful consequences are direct and indirect disasters, and sometimes cause disasters accompanied by earthquakes and floods or debris flow disasters. With the rapid development of electronic information technology, particularly internet of things technology, automatic monitoring technology for foundation pits and side slopes is also becoming popular and mature.
During excavation of a foundation pit, with the deepening of soil taking, a supporting structure can generate obvious deformation under the action of soil pressure and road dynamic load, and if the deformation exceeds a certain range, instability even occurs, so that damages to surrounding roads and buildings are caused. Therefore, a high-precision construction monitoring team is equipped to provide deformation data in time to guide the smooth construction, and the guarantee of the construction safety is particularly important.
At present, the foundation pit settlement monitoring is mostly carried out by depending on the experience of workers, a lot of factors are not considered comprehensively enough, and the problem discovery is not timely enough.
Therefore, there is a need to improve upon the above problems.
Disclosure of Invention
In order to overcome the defects in the prior art, the invention provides a method for monitoring the settlement of the ground surface around a foundation pit in the urban rail transit construction period, which can solve the problem that the existing foundation pit settlement monitoring cannot be completed completely.
The technical scheme adopted by the invention is as follows:
the method for monitoring the settlement of the ground surface around the foundation pit in the construction period of urban rail transit comprises the following steps:
s1, burying at least 2 leveling points 1 month before settlement monitoring, wherein the leveling points are arranged near a site and form a leveling control network;
s2, before observation, the level gauge and the indium steel ruler used by each measuring point are checked, and records are made, and the leveling gauges and the indium steel ruler are not randomly replaced in the subsequent use process;
s3, carrying out measuring point burying on a measuring point to be monitored;
s4, observing for the first time, properly increasing the number of measured returns, and generally taking 2-3 times of data as an initial value;
s5, determining a settlement monitoring control standard value as comparison data during monitoring data analysis, and feeding back information in time when the measured data exceeds an allowable value;
and S6, recording weather conditions, construction progress and site conditions measured every day for reference during monitoring data analysis.
In step S1, the distance between the measurement points required for embedding the leveling points is not more than 100m, and the leveling points should be formed with little influence on the outside during embedding, so as to be not easy to disturb or vibrate and have good visibility.
In step S2, the leveling point needs to be checked, measured point checked, and instrument checked periodically to ensure the accuracy and continuity of the measured data.
In the step S3, the concrete step of embedding the measuring points is that the measuring points are arranged in the direction parallel to the main building envelope of the station at intervals of 15-20 m from the edge of the building envelope, a drilling machine is used for drilling the ground hardened layer thoroughly, and reinforcing steel bars serving as monitoring points are driven immediately, so that the reinforcing steel bars and the soil body are integrated, and the reinforcing steel bars can sink along with the sinking of the soil body.
The model of the drilling machine is phi 108mm, the driven steel bars are 5-10 cm lower than the road surface, a PVC protection pipe is arranged on the outer side of the measuring point, and a cover plate covers the PVC protection pipe.
Compared with the prior art, the invention has the following beneficial effects:
according to the invention, the protection pipe is arranged on the outer side of the measuring point, the cover plate covers the protection pipe, and the driven steel bar is 5-10 cm lower than the road surface, so that the measuring point is protected in all directions; the checking of the level points, the checking of the measuring points and the checking of the instruments are constantly kept, special instruments for the special points are guaranteed, and the accuracy and the continuity of the measured data are guaranteed; the network measuring points are not known and are measured in an all-around mode, so that when the monitoring result exceeds the warning value, the reason can be found out quickly, and corresponding remedial measures can be carried out.
Drawings
FIG. 1 is a schematic view of the cross-sectional structure of a settlement point of the present invention.
Wherein: 1 is a measuring point, 2 is a cover plate and 3 is a protective tube.
Detailed Description
The technical solutions in the embodiments of the present invention are clearly and completely described below, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
As shown in fig. 1, the method for monitoring the settlement of the ground surface around the foundation pit in the construction period of urban rail transit comprises the following steps:
s1, burying at least 2 leveling points 1 month before settlement monitoring, wherein the leveling points are arranged near a site and form a leveling control network;
s2, before observation, the level gauge and the indium steel ruler used by each measuring point 1 are checked, and records are made, and the level gauge and the indium steel ruler are not randomly replaced in the subsequent use process;
s3, embedding the measuring point 1 to be monitored;
s4, observing for the first time, properly increasing the number of measured returns, and generally taking 2-3 times of data as an initial value;
s5, determining a settlement monitoring control standard value as comparison data during monitoring data analysis, and feeding back information in time when the measured data exceeds an allowable value;
and S6, recording weather conditions, construction progress and site conditions measured every day for reference during monitoring data analysis.
In step S1, the distance between the measuring points 1 required for embedding the leveling points is not more than 100m, and the leveling points have little influence on the outside during embedding, so that the leveling points are not easy to disturb or vibrate and have good visibility, and the measuring points are generally arranged within 65 meters outside the foundation pit.
In step S2, the leveling point needs to be checked, checked at the measuring point 1, and checked with an instrument regularly, so as to ensure the accuracy and continuity of the measured data.
In the step S3, the concrete step of embedding the measuring points 1 is to arrange the measuring points 1 at intervals of 15-20 m from the edges of the building enclosure in the direction parallel to the building enclosure of the main body of the station, drill the hardened layer on the ground through a drilling machine, and then drive in the reinforcing steel bars serving as monitoring points to integrate the reinforcing steel bars with the soil body, so that the reinforcing steel bars can sink along with the sinking of the soil body.
The model of the drilling machine is phi 108mm, the driven steel bars are 5-10 cm lower than the road surface, a PVC protection pipe 3 is arranged on the outer side of the measuring point 1, and a cover plate 2 covers the outer side of the measuring point.
The invention needs to comprehensively analyze the parameters such as the property of the monitored object, the allowable sedimentation value, the sedimentation rate, instruments and equipment, determine the measurement precision and monitor in real time. And when the monitoring result exceeds the warning value, finding out the reason, and adopting measures of changing an excavation scheme, reinforcing the stratum, strengthening the support and the like to ensure the construction safety. By combining on-site observation and monitoring, when the monitoring result exceeds a large range of an alarm value, reporting in time, stopping construction, immediately taking emergency measures such as supporting, plugging and the like, and making corresponding countermeasures together with related units, wherein the ground surface settlement should not exceed 30mm under the general condition.
The settlement observation points and the surface settlement observation points are controlled by reference points, and the arrangement of the settlement observation points and the surface settlement observation points is determined according to the building deformation weight measurement regulation and the common negotiation of the actual situation of the site and related methods such as construction, supervision design and the like. In the laying process, points in some places are too densely laid, and proper selection is carried out in the actual observation process, so that the density of the points is moderate, and the points are uniformly distributed.
The method for monitoring the surface settlement can also be used for monitoring the settlement of the building and monitoring the vertical displacement. Meanwhile, the monitoring discovery of the invention can be combined with a safety monitoring and early warning system in the rail transit construction period, and plays a role in the collection and monitoring of tragedy.
Although only the preferred embodiments of the present invention have been described in detail, the present invention is not limited to the above embodiments, and various changes can be made without departing from the spirit of the present invention within the knowledge of those skilled in the art, and all changes are encompassed in the scope of the present invention.

Claims (5)

1. The method for monitoring the settlement of the ground surface around the foundation pit in the urban rail transit construction period is characterized by comprising the following steps of: the method comprises the following steps:
s1, burying at least 2 leveling points 1 month before settlement monitoring, wherein the leveling points are arranged near a site and form a leveling control network;
s2, before observation, the leveling instrument and the indium steel ruler used by each measuring point (1) are checked, and records are made, and the leveling instrument and the indium steel ruler are not randomly replaced in the subsequent use process;
s3, embedding the measuring point (1) to be monitored into the measuring point (1);
s4, observing for the first time, properly increasing the number of measured returns, and generally taking 2-3 times of data as an initial value;
s5, determining a settlement monitoring control standard value as comparison data during monitoring data analysis, and feeding back information in time when the measured data exceeds an allowable value;
and S6, recording weather conditions, construction progress and site conditions measured every day for reference during monitoring data analysis.
2. The method for monitoring the settlement of the ground surface around the foundation pit in the construction period of the urban rail transit according to claim 1, wherein the method comprises the following steps: in step S1, the distance between the required measuring points (1) for embedding the leveling points is not more than 100m, and the leveling points have little influence on the outside during embedding, so that the leveling points are not easy to disturb or vibrate and have good visibility.
3. The method for monitoring the settlement of the ground surface around the foundation pit in the construction period of the urban rail transit according to claim 1, wherein the method comprises the following steps: in step S2, the leveling point needs to be checked, the measurement point (1) needs to be checked, and the instrument needs to be checked periodically, so as to ensure the accuracy and continuity of the measurement data.
4. The method for monitoring the settlement of the ground surface around the foundation pit in the construction period of the urban rail transit according to claim 1, wherein the method comprises the following steps: in the step S3, the concrete step of burying the measuring points (1) is to arrange the measuring points (1) at intervals of 15-20 m from the edge of the building enclosure in the direction parallel to the building main body building enclosure, drill the ground hardened layer through a drilling machine, and then drive in the reinforcing steel bars serving as monitoring points, so that the reinforcing steel bars and the soil body are integrated, and the reinforcing steel bars can sink along with the sinking of the soil body.
5. The method for monitoring the settlement of the ground surface around the foundation pit in the construction period of the urban rail transit as claimed in claim 4, wherein: the type of the drilling machine is phi 108mm, the driven steel bars are 5-10 cm lower than the road surface, a PVC protection pipe (3) is arranged on the outer side of the measuring point (1), and a cover plate (2) covers the PVC protection pipe.
CN202011462127.7A 2020-12-11 2020-12-11 Method for monitoring ground surface settlement around foundation pit in urban rail transit construction period Pending CN112697103A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011462127.7A CN112697103A (en) 2020-12-11 2020-12-11 Method for monitoring ground surface settlement around foundation pit in urban rail transit construction period

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011462127.7A CN112697103A (en) 2020-12-11 2020-12-11 Method for monitoring ground surface settlement around foundation pit in urban rail transit construction period

Publications (1)

Publication Number Publication Date
CN112697103A true CN112697103A (en) 2021-04-23

Family

ID=75509108

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011462127.7A Pending CN112697103A (en) 2020-12-11 2020-12-11 Method for monitoring ground surface settlement around foundation pit in urban rail transit construction period

Country Status (1)

Country Link
CN (1) CN112697103A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115993107A (en) * 2023-02-22 2023-04-21 南京禄口国际机场空港科技有限公司 Airport runway pavement settlement monitoring system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101691764A (en) * 2009-10-26 2010-04-07 西南交通大学 On-site monitoring and evaluation method for settlement of pile foundations
CN204228155U (en) * 2014-12-10 2015-03-25 中铁二十局集团第一工程有限公司 A kind of shallow-depth-excavation tunnel construction land tenure table settlement monitoring point buries structure underground
CN104655099A (en) * 2013-11-25 2015-05-27 天津城建隧道股份有限公司 Safe settlement observing method
CN110631560A (en) * 2019-08-13 2019-12-31 中铁上海工程局集团有限公司 Underground excavation interval monitoring and measuring method for subway station in dense building area
CN111156009A (en) * 2020-01-10 2020-05-15 中铁二十二局集团轨道工程有限公司 Construction and monitoring method for tunnel shield underpass viaduct
CN210689599U (en) * 2019-12-05 2020-06-05 中铁二十局集团市政工程有限公司 A earth's surface settlement point buries structure underground for subsiding monitoring
CN111623747A (en) * 2020-04-22 2020-09-04 山东交通学院 Ground settlement monitoring system and monitoring method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101691764A (en) * 2009-10-26 2010-04-07 西南交通大学 On-site monitoring and evaluation method for settlement of pile foundations
CN104655099A (en) * 2013-11-25 2015-05-27 天津城建隧道股份有限公司 Safe settlement observing method
CN204228155U (en) * 2014-12-10 2015-03-25 中铁二十局集团第一工程有限公司 A kind of shallow-depth-excavation tunnel construction land tenure table settlement monitoring point buries structure underground
CN110631560A (en) * 2019-08-13 2019-12-31 中铁上海工程局集团有限公司 Underground excavation interval monitoring and measuring method for subway station in dense building area
CN210689599U (en) * 2019-12-05 2020-06-05 中铁二十局集团市政工程有限公司 A earth's surface settlement point buries structure underground for subsiding monitoring
CN111156009A (en) * 2020-01-10 2020-05-15 中铁二十二局集团轨道工程有限公司 Construction and monitoring method for tunnel shield underpass viaduct
CN111623747A (en) * 2020-04-22 2020-09-04 山东交通学院 Ground settlement monitoring system and monitoring method thereof

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
刘元国: ""某大型基坑安全监测设计与数据分析"", 《黑龙江科技信息》 *
刘元国: ""某大型基坑安全监测设计与数据分析"", 《黑龙江科技信息》, no. 24, 31 December 2016 (2016-12-31), pages 3 *
庄铁钢 等: ""双塔宾馆基坑围护工程设计与施工"", 《水利技术监督》 *
庄铁钢 等: ""双塔宾馆基坑围护工程设计与施工"", 《水利技术监督》, no. 6, 31 December 2011 (2011-12-31), pages 3 *
李新锋: ""地铁车站基坑监测方法研究"", 《无线互联科技》 *
李新锋: ""地铁车站基坑监测方法研究"", 《无线互联科技》, no. 5, 31 December 2016 (2016-12-31), pages 2 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115993107A (en) * 2023-02-22 2023-04-21 南京禄口国际机场空港科技有限公司 Airport runway pavement settlement monitoring system

Similar Documents

Publication Publication Date Title
Kovtun et al. Improving the reliability of calculations of bases and soil massifs based on geotechnical control methods
CN108280969B (en) High-slope surface deformation monitoring and early warning system and early warning method thereof
CN106894821B (en) It is a kind of originate, the monitoring method of received well and jacking construction
CN110631560B (en) Underground excavation interval monitoring and measuring method for subway station in dense building area
CN113802622A (en) Method for monitoring construction safety of deep foundation pit near railway
CN105606066A (en) Foundation pit supporting structure deep level displacement monitoring system and method
CN107023043A (en) A kind of deep foundation pit supporting construction monitoring and pre-alarming method
CN113236260A (en) Construction monitoring method for all-dimensional shield underpass of existing subway station
CN106988754A (en) Narrow space shield launching method
CN108999612A (en) A kind of constructing metro tunnel safety monitoring system Internet-based
CN110207655A (en) Subgrade settlement monitoring settlement gauge and monitoring method
CN112836270A (en) Method for predicting influence of diving precipitation on building settlement
CN115637743A (en) Method for intelligently monitoring deformation during construction of deep and large foundation pit
CN112033355A (en) Method for monitoring settlement of pier stud in underpinning of bridge pile foundation
CN107100213A (en) Soil disturbance monitoring system and monitoring method of the bridge construction of pile groups to adjacent piles
CN112697103A (en) Method for monitoring ground surface settlement around foundation pit in urban rail transit construction period
CN113431016A (en) Soft rock large deformation section tunnel shallow-buried underground surface-penetrating building surface monitoring method
CN109184802A (en) A kind of more pilot tunnel tunnel informations monitoring construction methods of big cross section
CN108088632A (en) The monitoring of leakage device and method of water storage structure
CN109765260B (en) Flexible non-contact frost heaving monomer for detecting soil, detection device and detection method thereof
CN207277308U (en) Bridge construction of pile groups monitors system to the soil disturbance of adjacent piles
CN205449046U (en) Deep horizontal displacement monitoring system of foundation pit retaining structure
CN115478567A (en) Tunnel open excavation construction monitoring method with underground track penetrating upwards and adjacent to peripheral buildings
CN105445177B (en) The monitoring method of bank erosion amount and erosion rate
CN218293664U (en) Four-line parallel long-span subway tunnel excavation construction monitoring structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210423