CN112681304A - Anchor cable construction method in high-water-pressure soil layer supporting engineering in loess area - Google Patents

Anchor cable construction method in high-water-pressure soil layer supporting engineering in loess area Download PDF

Info

Publication number
CN112681304A
CN112681304A CN202011483999.1A CN202011483999A CN112681304A CN 112681304 A CN112681304 A CN 112681304A CN 202011483999 A CN202011483999 A CN 202011483999A CN 112681304 A CN112681304 A CN 112681304A
Authority
CN
China
Prior art keywords
anchor
hole
anchor cable
soil layer
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011483999.1A
Other languages
Chinese (zh)
Other versions
CN112681304B (en
Inventor
丁新建
高鹏
马勇峰
张旗
石岩
程江博
杨平
毛舵
宋鑫龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SCEGC No 6 Construction Engineering Group Co Ltd
Original Assignee
SCEGC No 6 Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SCEGC No 6 Construction Engineering Group Co Ltd filed Critical SCEGC No 6 Construction Engineering Group Co Ltd
Priority to CN202011483999.1A priority Critical patent/CN112681304B/en
Publication of CN112681304A publication Critical patent/CN112681304A/en
Application granted granted Critical
Publication of CN112681304B publication Critical patent/CN112681304B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses an anchor cable construction method in high water pressure soil layer supporting engineering in a loess area, which comprises the following steps: s1: preparation for construction, S2: primary drilling, S3: preliminary grouting, S4: re-drilling, S5: anchor cable installation, S6: anchor hole grouting and S7: waist rail construction, this anchor rope construction method in loess area high water pressure soil layer supporting engineering, mode through drilling many times and grout many times, fix the anchor rope in high water pressure soil layer, fastness when can strengthening the anchor rope and fix, and the thick liquid is at the in-process that fills, can follow earlier from outside again and cooperate the setting of separating the sheathed tube, can make the concrete thick liquid of inlayer, the effect of solidification is better, and form inside and outside separation, make between the mutual noninterference, the in-process of filling in inside, the effect of solidification is fine, the effectual protective effect who improves the anchor rope and use, increase the factor of safety of supporting engineering simultaneously, and the quality when having guaranteed follow-up anchor rope installation, and to the inside support effect.

Description

Anchor cable construction method in high-water-pressure soil layer supporting engineering in loess area
Technical Field
The invention belongs to the technical field of foundation pit support, and particularly relates to an anchor cable construction method in high-water-pressure soil layer support engineering in a loess area.
Background
In recent years, with the rapid development of infrastructure construction in China, more and more slope projects are involved in projects such as expressways, industrial and civil buildings, urban rail transit, large-scale public facilities, stadiums and the like, wherein slope support becomes a serious difficulty in engineering quality and safety. In deep foundation pit slope support engineering, a support form of piles with prestressed anchor cables or composite soil nailing walls containing prestressed anchor cables is often adopted.
The anchor cable support has the characteristics of large anchoring radius, strong anchoring force, wide reinforcing range and the like, and plays an important role in the process of supporting the side slope of foundation pit excavation engineering. The anchor cable support is that an anchor cable is installed in a soil layer and is grouted to form an anchoring body, and the anchoring force of the anchoring body is transmitted to a foundation pit support structure through a steel strand, so that the stability of the support structure is guaranteed. At present, in the anchor cable technology for high-water-pressure soil layer supporting engineering in loess areas, a hole is generally drilled to form an anchor cable hole before an anchor cable is installed, and the anchor cable is arranged in the anchor cable hole.
Disclosure of Invention
The invention aims to provide an anchor cable construction method in high-water-pressure soil layer supporting engineering in a loess area, and aims to solve the problems in the background art.
In order to achieve the purpose, the invention provides the following technical scheme:
an anchor cable construction method in high water pressure soil layer supporting engineering in a loess area comprises the following steps:
s1: the construction is prepared for the construction of the concrete,
firstly, preparing equipment, tools and auxiliary materials required by construction for standby, and selecting anchor cable positioning holes in a rectangular array on the side wall of an excavated foundation pit;
s2: the hole is initially drilled,
installing a preliminary drilling head on the drilling machine, and drilling a preliminary hole at the selected anchor cable positioning hole;
s3: the slurry is primarily grouted into the slurry,
firstly, absorbing seepage water in a primary drilled hole by using a water absorbing material and a water absorbing pump, filling a separation sleeve in the middle of the formed hole after absorption, filling a water absorbing auxiliary material between the outer side of the separation sleeve and the hole wall, and grouting between the separation sleeve and the hole wall by using a grouting pump after the water absorbing auxiliary material is filled, so that the water absorbing auxiliary material is wrapped by slurry, and the outer side of the separation sleeve at the opening of the hole is sealed by using a sealing ring;
s4: then the hole is drilled again, and the hole is drilled,
installing a multi-hole anchor disc at a drill bit of the drilling machine, installing a drill rod penetrating through the anchor disc at the drill bit, respectively penetrating a plurality of anchor holes of the anchor disc through the drill rod, placing the anchor disc at an internal opening of the separation sleeve, and drilling the drilled hole again to form an anchor cable placing hole;
s5: the anchor cable is installed, and the anchor cable is installed,
sequentially placing the prepared anchor cables into the drilled anchor cable placing holes;
s6: the anchor hole is grouted with slurry,
grouting the outer side of the drill rod inside the separation sleeve from inside to outside by using a grouting pump, gradually taking out the hollow drill rod in the grouting process until the drill rod is completely taken out, and completing the complete grouting on the outer side of the anchor cable;
s7: the construction of the waist rail is carried out,
and mounting a waist beam at the position of the anchor cable close to the orifice of the anchor cable hole, filling concrete between the waist beam and the pile to be compact, and performing tension locking test after construction is finished.
Preferably, in S1, the drilling preparation equipment at least comprises a jet grouting machine, a grouting pump, a suction pump, a construction tool at least comprises a hollow drill pipe, a hollow separation sleeve, an anchor cable, an anchor disc, a waist beam and an annular sealing ring, and the auxiliary materials at least comprise absorbent cotton, absorbent stone and mixed soil slurry.
Preferably, in S2, the depth of the preliminary drilling is one half to one third of the depth of the secondary drilling in S4.
Preferably, in S3, the cement slurry is required to be prepared at the time of grouting, and the prepared cement slurry is PO42.5R cement slurry, and the water-cement ratio is 1: 1.
Preferably, in S4, the anchor disc has the same size as the inner diameter of the separation sleeve, and a through hole through which the grouting pipe passes is formed in the middle of the anchor disc.
Preferably, in S5, the number of the anchor cables is at least three, the anchor cables are arranged in an annular array, and the anchor cables are made of steel strands.
The invention has the technical effects and advantages that:
1. according to the anchor cable construction method in the high-water-pressure soil layer supporting engineering in the loess area, the anchor cable is fixed in the high-water-pressure soil layer in a mode of multiple drilling and multiple grouting, the firmness of the anchor cable in the fixing process can be enhanced, in the grouting process, the slurry can be firstly discharged from the outside and then discharged from the outside and matched with the arrangement of the separation sleeve, so that the concrete slurry in the inner layer can be better in solidification effect, the inside and outside separation is formed, the mutual interference between the inside and the outside separation is avoided, the solidification effect is good in the internal filling process, and the use protection effect of the anchor cable is effectively improved;
2. according to the anchor cable construction method in the high-water-pressure soil layer support engineering in the loess area, in addition, the hole depth of the first drilled hole is smaller than the hole depth of the subsequent anchor cable during positioning, and the auxiliary materials and the water absorbing materials are filled into the first drilled hole for adsorption treatment, so that the slurry can be quickly solidified when the slurry is poured, the construction speed is increased, the safety factor of the support engineering is increased, the quality of the subsequent anchor cable during installation is ensured, and the support effect on the inside is achieved.
Detailed Description
The technical solutions in the present invention will be described clearly and completely with reference to the contents of the present invention, and it is obvious that the described contents are only a part of the contents of the present invention, and not all of the contents. All other matters which can be obtained by a person skilled in the art without making creative efforts based on the contents of the present invention belong to the protection scope of the present invention.
The invention provides an anchor cable construction method in high water pressure soil layer supporting engineering in a loess area, which comprises the following steps:
s1: the construction is prepared for the construction of the concrete,
firstly, preparing equipment, tools and auxiliary materials required by construction for standby, and selecting anchor cable positioning holes in a rectangular array on the side wall of an excavated foundation pit;
s2: the hole is initially drilled,
installing a preliminary drilling head on the drilling machine, and drilling a preliminary hole at the selected anchor cable positioning hole;
s3: the slurry is primarily grouted into the slurry,
firstly, absorbing seepage water in a primary drilled hole by using a water absorbing material and a water absorbing pump, filling a separation sleeve in the middle of the formed hole after absorption, filling a water absorbing auxiliary material between the outer side of the separation sleeve and the hole wall, and grouting between the separation sleeve and the hole wall by using a grouting pump after the water absorbing auxiliary material is filled, so that the water absorbing auxiliary material is wrapped by slurry, and the outer side of the separation sleeve at the opening of the hole is sealed by using a sealing ring;
s4: then the hole is drilled again, and the hole is drilled,
installing a multi-hole anchor disc at a drill bit of the drilling machine, installing a drill rod penetrating through the anchor disc at the drill bit, respectively penetrating a plurality of anchor holes of the anchor disc through the drill rod, placing the anchor disc at an internal opening of the separation sleeve, and drilling the drilled hole again to form an anchor cable placing hole;
s5: the anchor cable is installed, and the anchor cable is installed,
sequentially placing the prepared anchor cables into the drilled anchor cable placing holes;
s6: the anchor hole is grouted with slurry,
grouting the outer side of the drill rod inside the separation sleeve from inside to outside by using a grouting pump, gradually taking out the hollow drill rod in the grouting process until the drill rod is completely taken out, and completing the complete grouting on the outer side of the anchor cable;
s7: the construction of the waist rail is carried out,
and mounting a waist beam at the position of the anchor cable close to the orifice of the anchor cable hole, filling concrete between the waist beam and the pile to be compact, and performing tension locking test after construction is finished.
Specifically, in S1, the drilling preparation equipment at least includes a jet grouting machine, a grouting pump, a suction pump, and a construction tool at least includes a hollow drill pipe, a hollow separation sleeve, an anchor cable, an anchor disc, a waist beam, and an annular seal ring, and the auxiliary material at least includes absorbent cotton, absorbent stone, and mixed soil slurry.
Specifically, in S2, the depth of the preliminary drilling is one-half to one-third of the depth of the secondary drilling in S4.
Specifically, in S3, the cement slurry is required to be mixed during grouting, and the prepared cement slurry is PO42.5R cement slurry, and the water-cement ratio is 1: 1.
Specifically, in S4, the size of the anchor disc is the same as the inner diameter of the separation sleeve, and a through hole through which the grouting pipe passes is formed in the middle of the anchor disc.
Specifically, in S5, there are at least three groups of anchor cables arranged in an annular array, and the anchor cables are made of steel strands.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.

Claims (6)

1. An anchor cable construction method in high water pressure soil layer supporting engineering in a loess area is characterized by comprising the following steps:
s1: the construction is prepared for the construction of the concrete,
firstly, preparing equipment, tools and auxiliary materials required by construction for standby, and selecting anchor cable positioning holes in a rectangular array on the side wall of an excavated foundation pit;
s2: the hole is initially drilled,
installing a preliminary drilling head on the drilling machine, and drilling a preliminary hole at the selected anchor cable positioning hole;
s3: the slurry is primarily grouted into the slurry,
firstly, absorbing seepage water in a primary drilled hole by using a water absorbing material and a water absorbing pump, filling a separation sleeve in the middle of the formed hole after absorption, filling a water absorbing auxiliary material between the outer side of the separation sleeve and the hole wall, and grouting between the separation sleeve and the hole wall by using a grouting pump after the water absorbing auxiliary material is filled, so that the water absorbing auxiliary material is wrapped by slurry, and the outer side of the separation sleeve at the opening of the hole is sealed by using a sealing ring;
s4: then the hole is drilled again, and the hole is drilled,
installing a multi-hole anchor disc at a drill bit of the drilling machine, installing a drill rod penetrating through the anchor disc at the drill bit, respectively penetrating a plurality of anchor holes of the anchor disc through the drill rod, placing the anchor disc at an internal opening of the separation sleeve, and drilling the drilled hole again to form an anchor cable placing hole;
s5: the anchor cable is installed, and the anchor cable is installed,
sequentially placing the prepared anchor cables into the drilled anchor cable placing holes;
s6: the anchor hole is grouted with slurry,
grouting the outer side of the drill rod inside the separation sleeve from inside to outside by using a grouting pump, gradually taking out the hollow drill rod in the grouting process until the drill rod is completely taken out, and completing the complete grouting on the outer side of the anchor cable;
s7: the construction of the waist rail is carried out,
and mounting a waist beam at the position of the anchor cable close to the orifice of the anchor cable hole, filling concrete between the waist beam and the pile to be compact, and performing tension locking test after construction is finished.
2. The anchor cable construction method in the high water pressure soil layer supporting engineering of the loess area according to claim 1, wherein: s1, the drilling preparation equipment at least comprises a rotary jet drilling machine, an injection pump, a water suction pump and a construction tool, wherein the construction tool at least comprises a hollow drill rod, a hollow separation sleeve, an anchor cable, an anchor disc, a waist beam and an annular sealing ring, and auxiliary materials at least comprise water-absorbing cotton, water-absorbing stone and mixed soil slurry.
3. The anchor cable construction method in the high water pressure soil layer supporting engineering of the loess area according to claim 1, wherein: in S2, the depth of the preliminary drilling is one-half to one-third of the depth of the secondary drilling in S4.
4. The anchor cable construction method in the high water pressure soil layer supporting engineering of the loess area according to claim 1, wherein: in S3, during grouting, cement slurry needs to be prepared, wherein the prepared cement slurry is PO42.5R cement slurry, and the water-cement ratio is 1: 1.
5. The anchor cable construction method in the high water pressure soil layer supporting engineering of the loess area according to claim 1, wherein: in S4, the size of the anchor disc is the same as the inner diameter of the separation sleeve, and a through hole through which a grouting pipe passes is formed in the middle of the anchor disc.
6. The anchor cable construction method in the high water pressure soil layer supporting engineering of the loess area according to claim 1, wherein: in S5, the number of the anchor cables is at least three, the anchor cables are arranged in a ring array, and the anchor cables are made of steel strands.
CN202011483999.1A 2020-12-16 2020-12-16 Anchor cable construction method in high-water-pressure soil layer supporting engineering in yellow land area Active CN112681304B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011483999.1A CN112681304B (en) 2020-12-16 2020-12-16 Anchor cable construction method in high-water-pressure soil layer supporting engineering in yellow land area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011483999.1A CN112681304B (en) 2020-12-16 2020-12-16 Anchor cable construction method in high-water-pressure soil layer supporting engineering in yellow land area

Publications (2)

Publication Number Publication Date
CN112681304A true CN112681304A (en) 2021-04-20
CN112681304B CN112681304B (en) 2022-07-22

Family

ID=75448134

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011483999.1A Active CN112681304B (en) 2020-12-16 2020-12-16 Anchor cable construction method in high-water-pressure soil layer supporting engineering in yellow land area

Country Status (1)

Country Link
CN (1) CN112681304B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE202008016537U1 (en) * 2007-12-21 2009-03-19 Grund & Boden Geotechnik Gmbh Arrangement for securing loose rock slopes
CN201746840U (en) * 2010-07-29 2011-02-16 林华国 Foundation pit support system equipped with a plurality of inclined rear anchors capable of recycling
CN103615011A (en) * 2013-11-29 2014-03-05 上海强劲地基工程股份有限公司 Construction method for anchoring support in high-water-pressure soil layer
EP3042998A1 (en) * 2014-12-04 2016-07-13 Gebr. Strab GmbH + Co. Method for introducing a soil foundation and soil foundation which is produced by said method
CN108252737A (en) * 2017-12-22 2018-07-06 神华宁夏煤业集团有限责任公司 The abandoned well sorting technique of bank
CN108755676A (en) * 2018-05-05 2018-11-06 深圳市蛇口招商港湾工程有限公司 Anchor cable construction method under the conditions of rich aquifer sand layer
CN111794221A (en) * 2020-06-28 2020-10-20 中国水利水电第四工程局有限公司 Prestressed anchor cable construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE202008016537U1 (en) * 2007-12-21 2009-03-19 Grund & Boden Geotechnik Gmbh Arrangement for securing loose rock slopes
CN201746840U (en) * 2010-07-29 2011-02-16 林华国 Foundation pit support system equipped with a plurality of inclined rear anchors capable of recycling
CN103615011A (en) * 2013-11-29 2014-03-05 上海强劲地基工程股份有限公司 Construction method for anchoring support in high-water-pressure soil layer
EP3042998A1 (en) * 2014-12-04 2016-07-13 Gebr. Strab GmbH + Co. Method for introducing a soil foundation and soil foundation which is produced by said method
CN108252737A (en) * 2017-12-22 2018-07-06 神华宁夏煤业集团有限责任公司 The abandoned well sorting technique of bank
CN108755676A (en) * 2018-05-05 2018-11-06 深圳市蛇口招商港湾工程有限公司 Anchor cable construction method under the conditions of rich aquifer sand layer
CN111794221A (en) * 2020-06-28 2020-10-20 中国水利水电第四工程局有限公司 Prestressed anchor cable construction method

Also Published As

Publication number Publication date
CN112681304B (en) 2022-07-22

Similar Documents

Publication Publication Date Title
CN111594181B (en) Construction method for communicating and connecting newly-added underground excavation channel and existing station hall layer
US11840820B2 (en) Method for strengthening and lifting high-rise building having raft foundation
CN112647498B (en) Construction method for anti-floating anchor cable penetrating through water-rich layer
CN105386435B (en) It is a kind of to be used for the double-liquid grouting system and its construction technology of cement and water glass solution
CN112253162B (en) Water-rich sand layer large-diameter jacking pipe group entrance and exit reinforcing structure and construction method
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN106498943A (en) Disposable high-pressure rotary-spray type enlarged footing Prestressed Soil anchor pole construction method
CN107513995A (en) A kind of bridge struction pile post grouting construction method
CN107503362A (en) A kind of compound antiskid piling wall retaining structure and construction method suitable for reservoir stability
CN106638643A (en) Water-stopping-curtain construction device and method
CN112112654A (en) Isolation plate structure in upper soft and lower hard stratum and construction method thereof
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN104074197B (en) The construction method of large diameter thin wall cylinder stake compound anchor rod-type foundation pit enclosure structure
CN207659986U (en) A kind of building or structures foundation stabilization underpin pier
CN102174818A (en) Controlled impermeable leaking stoppage grout-extruding water-stopping technology of strong water permeable stratum of quaternary system
CN112681304B (en) Anchor cable construction method in high-water-pressure soil layer supporting engineering in yellow land area
CN105672329B (en) The large size prefabricated building enclosure of deep basal pit and construction method
CN105714832A (en) Deep-foundation-pit large-sized precast building envelope and construction method
CN114541408B (en) Front upper part wind-containing well structure of underground station end well and underpass construction method thereof
CN111519647A (en) Novel foundation suitable for marine soft foundation treatment and reinforcement and construction method
CN113464150A (en) Shield end reinforcing structure and reinforcing construction method
CN112411526A (en) Mortar consolidation construction method for rotary drilling collapse hole in high backfill region
Autuori et al. Effects of construction and demolition of a TBM excavated tunnel inside existing diaphragm walls
CN219992437U (en) Anchor rope grouting stop plug structure
CN215718763U (en) Shield constructs end reinforced structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant