CN112609903A CN202011502808.1A CN202011502808A CN112609903A CN 112609903 A CN112609903 A CN 112609903A CN 202011502808 A CN202011502808 A CN 202011502808A CN 112609903 A CN112609903 A CN 112609903A
Authority
CN
China
Prior art keywords
bolt holes
component
bolt
connecting plate
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011502808.1A
Other languages
Chinese (zh)
Inventor
徐春丽
张文
唐林
吴天河
张贵文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN202011502808.1A priority Critical patent/CN112609903A/en
Publication of CN112609903A publication Critical patent/CN112609903A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/162Connectors or means for connecting parts for reinforcements
    • E04C5/163Connectors or means for connecting parts for reinforcements the reinforcements running in one single direction
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/18Spacers of metal or substantially of metal

Abstract

The invention provides a steel bar connecting assembly and a construction method by utilizing a PC (personal computer) component. The two ends of the connecting plates are provided with first bolt holes, and the middle part of at least one of the two connecting plates is provided with a through hole for the exposed steel bar of the PC component to pass through. And second bolt holes corresponding to the first bolt holes are formed in flanges at two ends of the groove-shaped connecting piece, and the bolts are used for penetrating through the first bolt holes and the second bolt holes. The steel bar connecting component provided by the invention has the advantage of convenience in operation, and is beneficial to shortening the construction period and improving the connection quality of PC members.

Description

Steel bar connecting assembly and method for building by utilizing PC (polycarbonate) component
Technical Field
The invention relates to the technical field of buildings, in particular to a steel bar connecting assembly and a method for constructing by utilizing a PC (personal computer) component.
Background
In recent years, the prefabricated concrete structure is developed rapidly in China, has the advantages of being fast in construction, saving materials, low in labor cost, easy to control the quality of prefabricated parts, small in field operation pollution and the like, meets the future development requirements of the building industry in China, and is the direction of novel building industrial development.
In the construction site of the fabricated concrete structure, PC members (precast concrete) need to be connected, wherein the PC members are fixedly connected with exposed steel bars, and in the current construction method, most of the connection modes of the exposed steel bars have the problem of inconvenient operation, which affects the construction progress, so how to provide a steel bar connection mode with convenient construction becomes a technical problem to be solved urgently by technical personnel in the field.
Disclosure of Invention
In view of the above, the present invention provides a rebar connecting assembly and a method for constructing a PC member, in which the rebar connecting assembly is used to connect PC members, and the method has the advantages of convenient operation and reliable quality, and is beneficial to shortening the construction period.
In order to achieve the purpose, the invention provides the following technical scheme:
a rebar junction assembly, comprising:
the two ends of the connecting plate are provided with first bolt holes, and the middle part of at least one of the two connecting plates is provided with a through hole for an exposed steel bar of the PC component to pass through;
the flanges at the two ends of the groove-shaped connecting piece are provided with second bolt holes corresponding to the first bolt holes;
the first nut is used for being in threaded connection with the exposed steel bar of the PC component;
bolts for passing through the first bolt holes and the second bolt holes; and
and the second nut is connected with the bolt in a matched manner.
Optionally, in the above-mentioned reinforcing bar connecting assembly, a threaded hole for threaded connection with an exposed reinforcing bar of the PC member is formed in a middle portion of one of the two connecting plates, where the through hole is not formed.
Optionally, in the above reinforcing bar connecting assembly, a backing ring is further included for being disposed between the first nut and the connecting plate.
Optionally, in the above-mentioned reinforcing bar connecting assembly, the second bolt hole is a long hole.
Optionally, in the reinforcing bar connecting assembly, a distance between flanges at two ends of the channel-type connecting member is 10cm to 30 cm.
Optionally, in the reinforcing bar connecting assembly, a distance between the first bolt holes at two ends of the connecting plate is 3cm to 10 cm.
A method of constructing PC structures using a rebar junction assembly as disclosed in any one of the above, comprising the steps of:
after two PC components to be connected are hoisted in place in a construction site, the two connecting plates are respectively installed on exposed reinforcing steel bars of the two PC components, and the exposed reinforcing steel bars are fixedly connected with the middle parts of the connecting plates;
buckling the two groove-shaped connecting pieces to two ends of the connecting plate respectively, wherein the groove-shaped connecting pieces and the connecting plate are enclosed into a square shape, and the second bolt holes at two ends of the groove-shaped connecting pieces are aligned to the first bolt holes of the two connecting plates respectively;
and after the bolt sequentially penetrates through the first bolt hole and the second bolt hole, the second nut and the bolt are screwed and fixed.
Alternatively, in the above method of constructing using PC members, one of the two PC members to be connected is pre-installed on a PC member production line with one of the two connection plates, in which the through-hole is not provided, and the other of the two connection plates is clamped and fixed on the exposed reinforcing bars of the PC members by the two first nuts at a construction site.
Alternatively, in the above method of constructing using a PC component, the connection plate previously installed in the PC component manufacturing line is welded to the exposed steel bars of the PC component.
According to the technical scheme, the two connecting plates are respectively provided with the first bolt holes at two ends, the flanges at two ends of the groove-shaped connecting piece are provided with the second bolt holes corresponding to the first bolt holes, when the connecting rod connecting assembly is used, the two connecting plates are respectively installed on exposed steel bars of a PC component to be connected, the two connecting plates are approximately parallel to each other, then the two groove-shaped connecting pieces are respectively buckled at two ends of the connecting plates and form a square with the two connecting plates, and finally bolts sequentially penetrate through the first bolt holes of the connecting plates and the second bolt holes of the groove-shaped connecting pieces and tighten nuts matched with the bolts. According to the use process, when the PC components are connected, the reinforcing steel bar connecting component provided by the invention can be completely installed through simple operation steps, so that the work efficiency is improved, the construction period is shortened, the space utilization rate of the square-shaped structure formed by the reinforcing steel bar connecting component in the pouring connecting band between the PC components can be improved, the integral strength of the pouring connecting band is improved, and the connection quality between the PC components is more reliable.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the provided drawings without creative efforts.
Fig. 1 is a perspective view illustrating a use state of a reinforcing bar coupler assembly according to an embodiment of the present invention;
FIG. 2 is a front view of FIG. 1;
fig. 3 is a schematic view of the upper reinforcement bar 1 of fig. 1;
FIG. 4 is a schematic view of the upper connecting plate 2 of FIG. 1;
fig. 5 is a schematic view of the lower reinforcement bar 7 of fig. 1;
FIG. 6 is a schematic view of the lower connecting plate 8 of FIG. 1;
FIG. 7 is a schematic view of the channel connector 9 of FIG. 1;
fig. 8 is a schematic view of the nut 3 and bolt 4 of fig. 1.
Labeled as:
1. reinforcing steel bars are arranged; 2. an upper connecting plate; 21. a convex ring part; 22. bolt holes; 23. a threaded hole; 3. a nut; 4. a bolt; 5. a nut; 6. a backing ring; 7. arranging steel bars; 8. a lower connecting plate; 81. a through hole; 82. bolt holes; 9. a slot-type connecting piece; 91. bolt holes.
Detailed Description
For the purpose of facilitating understanding, the present invention will be further described with reference to the accompanying drawings.
Referring to fig. 1 and 2, taking an upper steel bar 1 and a lower steel bar 7 to be connected as an example, the upper steel bar 1 and the lower steel bar 7 are exposed steel bars of a PC component to be connected, and the steel bar connecting assembly comprises an upper connecting plate 2, a lower connecting plate 8 and two groove-shaped connecting pieces 9, wherein as shown in fig. 4, a threaded hole 23 in threaded connection with the upper steel bar 1 is formed in the middle of the upper connecting plate 2, and bolt holes 22 are formed in two ends of the upper connecting plate 2; as shown in fig. 6, the middle of the lower connecting plate 8 is provided with a through hole 81 for the lower steel bar 7 to pass through, and two ends of the lower connecting plate 8 are provided with bolt holes 82; as shown in fig. 7, the groove-shaped connecting member 9 is C-shaped, and bolt holes 91 are formed in flanges at both ends of the groove-shaped connecting member 9. In addition, the reinforcing bar connecting assembly further comprises a nut 5, and a bolt 4 and a nut 3 which are matched with each other.
The method of using the rebar junction assembly is as follows: firstly, the upper connecting plate 2 is installed on the upper reinforcing steel bar 1, the lower connecting plate 8 is installed on the lower reinforcing steel bar 7, the external thread (see fig. 3) of the upper reinforcing steel bar 1 is connected with the threaded hole 23 of the upper connecting plate 2, the external thread (see fig. 5) of the lower reinforcing steel bar 7 is connected with the nut 5, and the two nuts 5 clamp and fix the lower connecting plate 8 (in order to improve stability, a backing ring 6 can be arranged between the lower connecting plate 8 and the nut 5). After the upper connecting plate 2 and the lower connecting plate 8 are installed, the upper connecting plate 2 and the lower connecting plate 8 are approximately parallel to each other, then the groove-shaped connecting pieces 9 are buckled at the two ends of the upper connecting plate 2 and the lower connecting plate 8, when the groove-shaped connecting pieces 9 are installed, the distance between the upper connecting plate 2 and the lower connecting plate 8 can be finely adjusted by adjusting the positions of the nuts 5, and two flanges of the groove-shaped connecting pieces 9 can be respectively buckled on the upper connecting plate 2 and the lower connecting plate 8. After the groove-shaped connecting piece 9 is fastened, a bolt hole 91 at the upper end of the groove-shaped connecting piece 9 is aligned to a bolt hole 22 of the upper connecting plate 2, a bolt hole 91 at the lower end of the groove-shaped connecting piece 9 is aligned to a bolt hole 82 of the lower connecting plate 8, finally, two bolts 4 sequentially penetrate through the bolt holes 22 and the bolt holes 91 and are screwed with nuts 3 to fix the upper connecting plate 2 with the groove-shaped connecting piece 9, the other two bolts 4 sequentially penetrate through the bolt holes 82 and the bolt holes 91 and are screwed with nuts 3 to fix the lower connecting plate 8 with the groove-shaped connecting piece 9, and therefore.
As shown in fig. 1 and 2, in order to make the screw hole 23 of the upper connecting plate 2 have a long length, a convex ring portion 21 may be provided at a middle portion of the upper connecting plate 2, and the screw hole 23 extends to an inner wall of the convex ring portion 21. In a specific practical application, the protruding ring part 21 may be a structure integrally formed with the connecting plate 2, or may be a part welded to the connecting plate 2.
It can be seen from the above-mentioned method of use that the distance between the upper connecting plate 2 and the lower connecting plate 8 can be finely adjusted by adjusting the position of the nut 5, so as to ensure that the groove-shaped connecting member 9 can be smoothly fastened, which is to say, the position of the lower connecting plate 8 is adjusted, it is easy to understand that the connection between the upper connecting plate 2 and the upper steel bar 1 can be changed into the connection between the lower connecting plate 8 and the lower steel bar 7, so that the positions of the upper connecting plate 2 and the lower connecting plate 8 can be adjusted, that is, at least one of the two connecting plates needs to have a through hole in the middle for the exposed steel bar of the PC member to pass through.
If only one of the two connecting plates is provided with a through hole in the middle like the lower connecting plate 8, the other connecting plate can be connected with the steel bar in other ways such as welding and the like besides being connected with the steel bar thread like the upper connecting plate 2, as long as the connecting plate can be fixed on the exposed steel bar of the PC component, and the connecting plates without adjusting the positions are usually pre-installed on the PC component production line in consideration of the field situation of construction, for example, when the upper steel bar 1 is still on the PC component production line, the upper connecting plate 2 is connected with the upper steel bar 1, and when the construction site is reached, other parts left by the steel bar connecting assembly are connected.
After the two PC components are hoisted in place at the construction site, if there is a large coaxiality deviation between the upper steel bar 1 and the lower steel bar 7, the bolt holes 91 of the groove-type connecting member 9 are difficult to align with the bolt holes on the connecting plate, which may affect the normal installation of the bolts 4, and for this reason, the bolt holes 91 may be designed as long holes to ensure that the bolts 4 can smoothly pass through the bolt holes on the connecting plate and the bolt holes 91 on the groove-type connecting member 9 in sequence.
In a specific practical application, the distance between the flanges at the two ends of the groove-shaped connecting member 9 may be 10cm to 30cm, for example 20cm, and the distance between the two bolt holes 22 and the distance between the two bolt holes 82 may be 3cm to 10cm, for example 5cm or 8 cm.
Based on the reinforcing steel bar connecting component provided by the invention, the invention also provides a method for building by utilizing the PC component, which comprises the following steps:
and S1, after the two PC components to be connected are hoisted in place in a construction site, the two connecting plates are respectively installed on the exposed steel bars of the two PC components, so that the exposed steel bars are fixedly connected with the middle parts of the connecting plates.
Taking fig. 1 and 2 as an example, the purpose of step S1 is to fixedly connect the upper connecting plate 2 with the upper reinforcement bar 1, and the lower connecting plate 8 with the lower reinforcement bar 7.
S2, buckling the two groove-shaped connecting pieces 9 to two ends of the connecting plate respectively, wherein the groove-shaped connecting pieces 9 and the connecting plate are enclosed into a square shape, and bolt holes 91 at two ends of each groove-shaped connecting piece 9 are aligned to bolt holes of the two connecting plates respectively.
Taking fig. 1 and 2 as an example, the purpose of step S2 is to make the groove-shaped connecting members 9 snap onto the upper connecting plate 2 and the lower connecting plate 8 so that the upper connecting plate 2, the lower connecting plate 8 and the two groove-shaped connecting members 9 enclose a square shape, the bolt holes 91 at the upper ends of the groove-shaped connecting members 9 are aligned with the bolt holes 22 of the upper connecting plate 2, and the bolt holes 91 at the lower ends of the groove-shaped connecting members 9 are aligned with the bolt holes 82 of the lower connecting plate 8, ready for the installation of the bolts 4.
And S3, sequentially penetrating the bolt 4 through the bolt hole of the connecting plate and the bolt hole 91 of the groove-shaped connecting piece 9, and then screwing and fixing the nut 3 and the bolt 4.
Taking fig. 1 and 2 as an example, the step S3 is to fix the upper connecting plate 2 to the channel-shaped connecting member 9 and the lower connecting plate 8 to the channel-shaped connecting member 9, thereby completing the connection of the upper reinforcement 1 to the lower reinforcement 7.
In practical applications, if one of the two tie plates is not provided with a through hole in the middle as the lower tie plate 8, then this tie plate can be used in the PC component production line in advance, so that the aforementioned step S1 only operates the other tie plate, and as shown in fig. 1 and 2, in the PC component production line, the PC component where the upper reinforcement bar 1 is located uses the upper tie plate 2, i.e., the upper tie plate 2 is pre-installed before the PC component is transported to the construction site, so that the step S1 only installs the lower tie plate 8 on the lower reinforcement bar 7, and specifically, the lower tie plate 8 is clamped and fixed on the lower reinforcement bar 7 by the two nuts 5 at the construction site.
When the PC member is used for construction, the region where the exposed steel bars are located is poured after the step S3 to form the pouring connecting strip, as can be seen from fig. 2, the steel bar connecting assembly provided by the present invention can improve the space utilization rate in the pouring connecting strip, and improve the overall strength of the pouring connecting strip.
It should be noted that the present invention is described above with respect to the reinforcing bars 1 and the lower reinforcing bars 7 by way of example, but the use of the reinforcing bar connecting assembly is not limited by the form of the positions of the reinforcing bars, and for example, the reinforcing bar connecting assembly of the present invention can be used with two reinforcing bars to be connected arranged side by side.
The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to the embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (9)

1. A rebar junction assembly, comprising:
the two ends of the connecting plate are provided with first bolt holes, and the middle part of at least one of the two connecting plates is provided with a through hole for an exposed steel bar of the PC component to pass through;
the flanges at the two ends of the groove-shaped connecting piece are provided with second bolt holes corresponding to the first bolt holes;
the first nut is used for being in threaded connection with the exposed steel bar of the PC component;
bolts for passing through the first bolt holes and the second bolt holes; and
and the second nut is connected with the bolt in a matched manner.
2. The reinforcing bar connecting assembly according to claim 1, wherein one of the two coupling plates, in which the through hole is not provided, is provided at a middle portion thereof with a screw hole to be screw-coupled with an exposed reinforcing bar of the PC member.
3. The rebar junction assembly of claim 1, further comprising a grommet for disposing between the first nut and the junction plate.
4. The rebar connecting assembly according to claim 1, wherein the second bolt hole is an elongated hole.
5. A reinforcing bar connecting assembly according to any one of claims 1 to 4, wherein the distance between flanges at both ends of the channel-type connecting member is 10cm to 30 cm.
6. The reinforcing bar connecting assembly according to claim 5, wherein the distance between the first bolt holes at both ends of the connecting plate is 3cm to 10 cm.
7. A method for constructing a PC member, wherein the PC member is connected by using the reinforcing bar connecting assembly according to any one of claims 1 to 6, comprising the following steps:
after two PC components to be connected are hoisted in place in a construction site, the two connecting plates are respectively installed on exposed reinforcing steel bars of the two PC components, and the exposed reinforcing steel bars are fixedly connected with the middle parts of the connecting plates;
buckling the two groove-shaped connecting pieces to two ends of the connecting plate respectively, wherein the groove-shaped connecting pieces and the connecting plate are enclosed into a square shape, and the second bolt holes at two ends of the groove-shaped connecting pieces are aligned to the first bolt holes of the two connecting plates respectively;
and after the bolt sequentially penetrates through the first bolt hole and the second bolt hole, the second nut and the bolt are screwed and fixed.
8. The method for building with PC components according to claim 7, wherein any one of the two PC components to be connected is pre-installed with one of the two connection plates, in which the through hole is not provided, on a PC component production line, and the other of the two connection plates is clamped and fixed on the exposed reinforcement of the PC component by the two first nuts at a construction site.
9. The method of constructing a PC component of claim 8, wherein the pre-installed connector plate is welded to exposed rebar of the PC component in a PC component manufacturing line.
CN202011502808.1A 2020-12-17 2020-12-17 Steel bar connecting assembly and method for building by utilizing PC (polycarbonate) component Pending CN112609903A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011502808.1A CN112609903A (en) 2020-12-17 2020-12-17 Steel bar connecting assembly and method for building by utilizing PC (polycarbonate) component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011502808.1A CN112609903A (en) 2020-12-17 2020-12-17 Steel bar connecting assembly and method for building by utilizing PC (polycarbonate) component

Publications (1)

Publication Number Publication Date
CN112609903A true CN112609903A (en) 2021-04-06

Family

ID=75241031

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011502808.1A Pending CN112609903A (en) 2020-12-17 2020-12-17 Steel bar connecting assembly and method for building by utilizing PC (polycarbonate) component

Country Status (1)

Country Link
CN (1) CN112609903A (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0842064A (en) * 1994-07-27 1996-02-13 Tokyo Tekko Co Ltd Building method of reinforced cage for column and building jig
CN203201023U (en) * 2013-02-19 2013-09-18 东南大学 Steel bar connection structure for prefabricated assembling structure
CN203320813U (en) * 2013-06-03 2013-12-04 徐曼 Reinforcement connecting piece for prefabricated concrete component
KR20150139350A (en) * 2014-06-03 2015-12-11 주식회사 태명실업 Precast box using bended angle connection plate and construction method therefor
CN105155781A (en) * 2015-09-09 2015-12-16 北京建筑大学 Reinforced connecting structure and method between precast reinforced concrete components
CN206581502U (en) * 2017-02-13 2017-10-24 李聪 A kind of reinforcing bar couples fastener
CN107338871A (en) * 2016-11-22 2017-11-10 湖南远大工程设计有限公司 Precast concrete box connection component
CN206737271U (en) * 2017-04-27 2017-12-12 李聪 A kind of a chain of bar connecting of bolt is buckled
CN108412132A (en) * 2017-02-10 2018-08-17 李聪 A kind of dual U-shaped is welded to connect button and attaching method thereof
KR101922534B1 (en) * 2018-06-07 2018-11-27 정택동 Composite type steel temporary construction and construction method thereof
CN109267701A (en) * 2018-10-12 2019-01-25 天津城建大学 A kind of new reinforcing steel bar connection structure convenient for reinforcing bar connection
KR102079674B1 (en) * 2019-03-14 2020-02-20 동서 피, 씨, 씨 주식회사 Precast concrete column for used by continuous construction method

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0842064A (en) * 1994-07-27 1996-02-13 Tokyo Tekko Co Ltd Building method of reinforced cage for column and building jig
CN203201023U (en) * 2013-02-19 2013-09-18 东南大学 Steel bar connection structure for prefabricated assembling structure
CN203320813U (en) * 2013-06-03 2013-12-04 徐曼 Reinforcement connecting piece for prefabricated concrete component
KR20150139350A (en) * 2014-06-03 2015-12-11 주식회사 태명실업 Precast box using bended angle connection plate and construction method therefor
CN105155781A (en) * 2015-09-09 2015-12-16 北京建筑大学 Reinforced connecting structure and method between precast reinforced concrete components
CN107338871A (en) * 2016-11-22 2017-11-10 湖南远大工程设计有限公司 Precast concrete box connection component
CN108412132A (en) * 2017-02-10 2018-08-17 李聪 A kind of dual U-shaped is welded to connect button and attaching method thereof
CN206581502U (en) * 2017-02-13 2017-10-24 李聪 A kind of reinforcing bar couples fastener
CN206737271U (en) * 2017-04-27 2017-12-12 李聪 A kind of a chain of bar connecting of bolt is buckled
KR101922534B1 (en) * 2018-06-07 2018-11-27 정택동 Composite type steel temporary construction and construction method thereof
CN109267701A (en) * 2018-10-12 2019-01-25 天津城建大学 A kind of new reinforcing steel bar connection structure convenient for reinforcing bar connection
KR102079674B1 (en) * 2019-03-14 2020-02-20 동서 피, 씨, 씨 주식회사 Precast concrete column for used by continuous construction method

Similar Documents

Publication Publication Date Title
CN111877547B (en) Assembled concrete beam column trunk type connecting joint
CN212613183U (en) Assembled steel sheet compound shear wall structure
CN204804062U (en) Steel sheet - concrete compound shear wall and concrete shear force wall quadrature connected node
KR100401671B1 (en) Composite beam with prestressed precast concrete panel
CN112609903A (en) Steel bar connecting assembly and method for building by utilizing PC (polycarbonate) component
CN210395642U (en) Detachable assembly type steel structure building connecting node
CN114753489A (en) Prefabricated beam column node and novel assembled reinforced concrete building thereof
CN112609831A (en) Steel pipe constraint section steel recycled concrete column-beam assembled node and installation method
CN212224320U (en) Arc-shaped shear wall with steel tube bundle with ear plates and toothed steel plates
CN210086553U (en) Dry-type connected precast concrete wall and foundation connection node
CN209011313U (en) A kind of novel prefabricated primary and secondary beam composite joint node
KR100695491B1 (en) A fixing device, a pre-fabricating forms for concrete-structure and the construction method thereof
CN210797914U (en) Connection structure of buckled plate is assembled to inside
CN209891418U (en) Pre-buried connecting piece and concrete member
CN111749343A (en) Mounting method of detachable assembled steel structure house
CN211369547U (en) Assembly type disassembly-free framework assembly for template
CN217711149U (en) Assembled roof beam-wall connection structure
CN211369546U (en) Assembly type steel skeleton disassembly-free template
CN114144558A (en) Steel bar joint, steel bar assembly and prefabricated reinforced concrete body
CN215330474U (en) Steel pipe restraint shaped steel regeneration concrete column-roof beam assembled node
CN108978890A (en) Novel prefabricated primary and secondary beam composite joint node of one kind and attaching method thereof
KR102271112B1 (en) Twin leg bolt, steel bar spacing maintenance fixed structure and method using the same
CN219508818U (en) Prefabricated girder component with secondary girder connection node
CN214994658U (en) Assembled steel structure component
CN219825640U (en) Assembled steel connection hybrid frame column foot structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210406