CN112572846A - Ignition device test method and system - Google Patents

Ignition device test method and system Download PDF

Info

Publication number
CN112572846A
CN112572846A CN202011317292.3A CN202011317292A CN112572846A CN 112572846 A CN112572846 A CN 112572846A CN 202011317292 A CN202011317292 A CN 202011317292A CN 112572846 A CN112572846 A CN 112572846A
Authority
CN
China
Prior art keywords
ignition
pipeline system
gas cylinder
oxidant
combustion agent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011317292.3A
Other languages
Chinese (zh)
Inventor
党冠华
任守彬
刘雅剑
朱刘成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lanjian Spaceflight Technology Co ltd
Landspace Technology Co Ltd
Original Assignee
Lanjian Spaceflight Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lanjian Spaceflight Technology Co ltd filed Critical Lanjian Spaceflight Technology Co ltd
Priority to CN202011317292.3A priority Critical patent/CN112572846A/en
Publication of CN112572846A publication Critical patent/CN112572846A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B64AIRCRAFT; AVIATION; COSMONAUTICS
    • B64GCOSMONAUTICS; VEHICLES OR EQUIPMENT THEREFOR
    • B64G7/00Simulating cosmonautic conditions, e.g. for conditioning crews
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01MTESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
    • G01M3/00Investigating fluid-tightness of structures
    • G01M3/02Investigating fluid-tightness of structures by using fluid or vacuum

Abstract

The invention provides a test method of an ignition device, which comprises the following steps: and (3) air tightness checking: opening at least one gas cylinder of the oxidant gas cylinder group and at least one gas cylinder of the combustion agent gas cylinder group, carrying out gas tightness inspection on a pipeline system leading to the ignition device, and carrying out blowing replacement on the pipeline system after the inspection is finished; ignition test steps: and opening at least two gas cylinders of the oxidant gas cylinder group and the combustion agent gas cylinder group, adjusting the pressure of the pipeline system to reach an ignition required pressure value, opening a pneumatic valve on the pipeline system to control oxidant and combustion agent to enter the ignition device, starting an ignition oxidant switch and an ignition combustion agent switch simultaneously, and discharging the pipeline system after the test is finished. The method improves the test efficiency of the ignition device and ensures the safety of the test process.

Description

Ignition device test method and system
Technical Field
The invention relates to the field of gas supply of ignition devices, in particular to a method and a system for testing an ignition device.
Background
In recent years, in the launch ignition of an aerospace vehicle, a powder ignition system has been generally used. However, the costs of gunpowder, such as manufacturing cost, storage cost, transportation cost, and the like, are high, and gunpowder belongs to national control products, and causes certain environmental pollution after use, thereby limiting the application of the gunpowder in the field of commercial aerospace.
In view of the above, it is desirable to design a testing method and system which is highly safe and suitable for a gas ignition device.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provides a testing method and a testing system for an ignition device.
The invention provides a test method of an ignition device, which comprises the following steps: and (3) air tightness checking: opening at least one gas cylinder of the oxidant gas cylinder group and at least one gas cylinder of the combustion agent gas cylinder group, carrying out gas tightness inspection on a pipeline system leading to the ignition device, and carrying out blowing replacement on the pipeline system after the inspection is finished; ignition test steps: and opening at least two gas cylinders of the oxidant gas cylinder group and the combustion agent gas cylinder group, adjusting the pressure of the pipeline system to reach an ignition required pressure value, opening a pneumatic valve on the pipeline system to control oxidant and combustion agent to enter the ignition device, starting an ignition oxidant switch and an ignition combustion agent switch simultaneously, and discharging the pipeline system after the test is finished.
According to one embodiment of the invention, before the step of checking the airtightness comprises: a zero position acquisition step: starting ignition oxidant and ignition combustion agent switches, starting zero acquisition, checking whether each measuring point is normal, and closing the ignition oxidant and ignition combustion agent switches after the zero acquisition is finished.
According to one embodiment of the invention, the step of checking for tightness is preceded by: a system debugging step: and checking whether pneumatic valves of the pipeline system are closed or not, starting measurement of a pressure detection unit, starting an ignition oxidant switch, stopping pressure acquisition and performing blowing replacement on the pipeline system after the program is finished.
According to an embodiment of the present invention, the system debugging step further comprises: and checking whether pneumatic valves of the pipeline system are closed or not, starting measurement of a pressure detection unit, starting an ignition combustion agent switch, stopping pressure acquisition and performing blowing replacement on the pipeline system after the program is finished.
According to one embodiment of the invention, the ignition test step further comprises: and when the pressure of the pipeline system does not reach the ignition required pressure value, correspondingly increasing the number of the gas cylinders for opening the oxidant gas cylinder group or the combustion agent gas cylinder group until the pressure of the pipeline system reaches the ignition required pressure value.
In another aspect, the present invention further provides a testing system for an ignition device, comprising: and an air tightness checking module: opening at least one gas cylinder of the oxidant gas cylinder group and at least one gas cylinder of the combustion agent gas cylinder group, carrying out gas tightness inspection on a pipeline system leading to the ignition device, and blowing off and replacing the pipeline system and closing the gas cylinders after the inspection is finished; an ignition test module: and opening at least two gas cylinders of the oxidant gas cylinder group and the combustion agent gas cylinder group, adjusting the pressure of the pipeline system to reach the ignition required pressure value, opening a pneumatic valve on the pipeline system to control the oxidant and the combustion agent to enter the ignition device, and blowing off and replacing the pipeline system after the test is finished.
According to one embodiment of the invention, the testing system further comprises: a zero acquisition module: starting ignition oxidant and ignition combustion agent switches, starting zero acquisition, checking whether each measuring point is normal, and closing the ignition oxidant and ignition combustion agent switches after the zero acquisition is finished.
According to one embodiment of the invention, the testing system further comprises: a system debugging module: and checking whether pneumatic valves of the pipeline system are closed or not, starting measurement of a pressure detection unit, starting an ignition oxidant switch, stopping pressure acquisition and performing blowing replacement on the pipeline system after the program is finished.
According to an embodiment of the present invention, the system debugging module further includes: and checking whether pneumatic valves of the pipeline system are closed or not, starting measurement of a pressure detection unit, starting an ignition combustion agent switch, stopping pressure acquisition and performing blowing replacement on the pipeline system after the program is finished.
According to one embodiment of the invention, the ignition test module further comprises: and when the pressure of the pipeline system does not reach the ignition required pressure value, correspondingly increasing the number of the gas cylinders for opening the oxidant gas cylinder group or the combustion agent gas cylinder group until the pressure of the pipeline system reaches the ignition required pressure value.
The testing method of the ignition device not only solves the pressure detection function required by the ignition device, but also improves the testing efficiency of the ignition device and ensures the safety of the testing process through the steps of air tightness inspection and ignition test.
It is to be understood that both the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the invention, as claimed.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate exemplary embodiments of the invention and together with the description, serve to explain the principles of the invention.
FIG. 1 is a schematic illustration of a method of testing an ignition device according to one embodiment of the present invention;
FIG. 2 is a schematic view of a piping system of an ignition device according to an embodiment of the present invention;
fig. 3 is a schematic view of a piping system of an ignition device according to still another embodiment of the present invention.
Description of reference numerals:
100-oxidant gas cylinder group, 110-first pipeline, 120-first control unit, 121-first pneumatic valve, 122-first one-way valve, 123-first throttling ring, 130-first filtering unit, 140-first pressure detection unit, 150-first bleeding valve, 200-combustion agent gas cylinder group, 210-second pipeline, 220-second control unit, 221-second pneumatic valve, 222-second one-way valve, 223-second throttling ring, 230-second filtering unit, 240-second pressure detection unit, 250-second bleeding valve.
Detailed Description
Features and exemplary embodiments of various aspects of the present invention will be described in detail below, and in order to make objects, technical solutions and advantages of the present invention more apparent, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments. It is to be understood that the specific embodiments described herein are merely illustrative of the invention and are not to be construed as limiting the invention, for the purposes of illustrating the principles of the invention. Additionally, the components in the drawings are not necessarily to scale. For example, the dimensions of some of the elements or regions in the figures may be exaggerated relative to other elements or regions to help improve understanding of embodiments of the present invention.
The directional terms used in the following description are used in the illustrated directions, and do not limit the specific configurations of the embodiments of the present invention. In the description of the present invention, it should be noted that, unless otherwise specified, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning fixedly connected, detachably connected, or integrally connected; may be directly connected or indirectly connected through an intermediate. The specific meaning of the above terms in the present invention can be understood as appropriate to those of ordinary skill in the art.
Furthermore, the terms "comprises," "comprising," "includes," "including," "has," "having" or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a structure or component comprising a list of elements does not include only those elements but may include other mechanical components not expressly listed or inherent to such structure or component. Without further limitation, an element defined by the phrase "comprising … …" does not exclude the presence of additional like elements in the article or device comprising the element.
Spatially relative terms such as "below," "… below," "lower," "above," "… above," "upper," and the like are used for convenience in describing the positioning of one element relative to a second element and are intended to encompass different orientations of the device in addition to different orientations than those illustrated in the figures. Further, for example, the phrase "one element is over/under another element" may mean that the two elements are in direct contact, or that there is another element between the two elements. Furthermore, terms such as "first", "second", and the like, are also used to describe various elements, regions, sections, etc. and should not be taken as limiting. Like terms refer to like elements throughout the description.
It will be apparent to one skilled in the art that the present invention may be practiced without some of these specific details. The following description of the embodiments is merely intended to provide a better understanding of the present invention by illustrating examples of the present invention.
FIG. 1 is a schematic illustration of a method of testing an ignition device according to one embodiment of the present invention; FIG. 2 is a schematic view of a piping system of an ignition device according to an embodiment of the present invention; fig. 3 is a schematic view of a piping system of an ignition device according to still another embodiment of the present invention.
As shown in fig. 2, the present invention provides a piping system of an ignition device, comprising: an oxidant gas cylinder group 100, at least two oxidant gas cylinders for outputting oxidant to a first pipeline 110; a combustion agent gas cylinder group 200, at least two combustion agent gas cylinders for outputting combustion agent to the second pipeline 210; the oxidant gas cylinder group 100 is connected to the ignition device 300 through the first control unit 120, and the combustion agent gas cylinder group 200 is connected to the ignition device 300 through the second control unit 220.
Specifically, the oxidant cylinder group 100 and the combustion agent cylinder group 200 in the pipeline system of the ignition device are used for providing gas source media for the ignition device 300, at least two oxidant cylinders are used for outputting oxidant to the first pipeline 110, at least two combustion agent cylinders are used for outputting combustion agent to the second pipeline 210, and the first pipeline 110 and the second pipeline 210 are used for conveying ignition media (oxidant and combustion agent) to the ignition device 300. The first pipeline 110 is provided with a first control unit 120 for controlling and discharging the oxidant in the oxidant gas cylinder group 100, and the second pipeline 210 is provided with a second control unit 220 for controlling and discharging the combustion agent in the combustion agent gas cylinder group 200, so that the oxidant and the combustion agent are jointly output to the ignition device 300 to complete the ignition operation.
As shown in fig. 3, according to an embodiment of the present invention, the piping system of the ignition device further includes: and a filtering unit 130, 230 disposed at an upstream position of the first and second pipes 110 and 210, for filtering impurities of the oxidant and the combustion agent.
Specifically, the first filtering unit 130 and the second filtering unit 230 are respectively disposed at upstream positions of the first pipeline 110 and the second pipeline 210, and are used for ensuring that the oxidant and the combustion agent entering the ignition device 300 are clean gases, so that the normal use of the ignition device 300 can be ensured, and the design requirements of the ignition device 300 can be met.
According to one embodiment of the invention, the pipe system of the ignition device further comprises: and pressure detecting units 140 and 240 disposed at upstream positions of the first and second pipes 110 and 210 for monitoring supply pressures of the oxidizer gas cylinder group 100 and the burner gas cylinder group 200.
Specifically, the first pressure detection unit 140 and the second pressure detection unit 240 are respectively disposed at upstream positions of the first pipeline 110 and the second pipeline 210, and as one of the modes in this embodiment, the pressure detection units may employ pressure sensors for detecting the supply pressures of the oxidant gas cylinder group 100 and the combustion agent gas cylinder group 200, so as to conveniently monitor the pressure data of the first pipeline 110 and the second pipeline 210 in real time, and an operator may find and make a judgment and an operation in time when the pressure exceeds or does not reach the standard.
According to one embodiment of the invention, the control unit 120, 220 comprises: pneumatic valves 121, 221, disposed at a location downstream of the first and second conduits 110, 210, are used to control the timing of the oxidant and the fuel entering the ignition device 300.
Specifically, a first pneumatic valve 121 and a second pneumatic valve 221 are provided at positions downstream of the first line 110 and the second line 210, respectively, for controlling the timing of the entry of the two gases, oxidizer and burner, into the ignition device 300, while being able to be used to cut off the gas supply in time at risk.
According to an embodiment of the invention, the control unit 120, 220 further comprises: and check valves 122, 222 disposed downstream of the pneumatic valves 121, 221 for preventing backfiring when the ignition device 300 is turned off.
Specifically, the first check valve 122 and the second check valve 222 are respectively arranged on the first pneumatic valve 121 and the second pneumatic valve 221, and are used for preventing the ignition device 300 from being burnt back into the pipeline due to overlarge pipeline back pressure at the ignition device 300 when the test is finished, and the first check valve 122 and the second check valve 222 can prevent the backfire caused by the shutdown of the ignition device 300, so that the safety of the pipeline system is greatly improved.
According to an embodiment of the invention, the control unit 120, 220 further comprises: and a throttle 123, 223 disposed downstream of the one- way valve 122, 222 for controlling the flow of the medium into the ignition device 300.
Specifically, a first choke 123 and a second choke 223 are provided downstream of the first check valve 122 and the second check valve 222, respectively, for controlling the flow of the oxidant and the combustion agent into the ignition device 300, enabling a constant flow rate to be maintained.
According to one embodiment of the invention, the pipe system of the ignition device further comprises: and the gas release valves 150 and 250 are arranged at the gas cylinder outlet pipelines at the upstream in the oxidant gas cylinder group 100 and the combustion agent gas cylinder group 200 and are used for discharging residual gas in the pipelines after ignition is finished.
Specifically, a first bleed valve 150 and a second bleed valve 250 are respectively disposed at the gas cylinder outlet pipelines at the upstream of the oxidant gas cylinder group 100 and the combustion agent gas cylinder group 200, and are used for discharging a small amount of residual gas in the first pipeline 110 and the second pipeline 210 after the ignition is finished or after the test is finished, so as to avoid impurities in the pipeline system during the next test or ignition.
According to one embodiment of the invention, the oxidant gas cylinder group is an oxygen gas cylinder group.
According to one embodiment of the invention, the set of fuel gas cylinders is a set of methane gas cylinders.
In one embodiment of this embodiment, the oxidant used in the ignition device is oxygen, and the combustion agent used in the ignition device is methane gas, that is, the oxidant gas cylinder group is an oxygen gas cylinder group, and the combustion agent gas cylinder group is a methane gas cylinder group.
As shown in fig. 1, the present invention provides a method of testing an ignition device, comprising:
s101, air tightness checking: opening at least one gas cylinder of the oxidant gas cylinder group and at least one gas cylinder of the combustion agent gas cylinder group, carrying out gas tightness inspection on a pipeline system leading to the ignition device, and carrying out blowing replacement on the pipeline system after the inspection is finished;
s102, an ignition test step: opening at least two gas cylinders of the oxidant gas cylinder group and the combustion agent gas cylinder group, adjusting the pressure of the pipeline system to reach the ignition required pressure value, opening a pneumatic valve on the pipeline system to control the oxidant and the combustion agent to enter an ignition device, starting an ignition oxidant switch and an ignition combustion agent switch simultaneously, and discharging the pipeline system after the test is finished.
Specifically, in the air tightness checking step, because the ignition device needs to check whether the air tightness of a pipeline system leading to the ignition device meets the requirement before providing the oxidant and the combustion agent, at least one air cylinder of the oxidant gas cylinder group and at least one air cylinder of the combustion agent gas cylinder group are opened first, a pressure value required by the air tightness checking is set, the pipeline system is checked for air tightness by using the gas in the air cylinders, and after the air tightness checking is finished, the pipeline system is blown and replaced by using two gases so as to remove air and water vapor in the pipeline system.
In the ignition test step, in order to provide an oxidant and a combustion agent with sufficient pressure, at least two gas cylinders of an oxidant gas cylinder group and a combustion agent gas cylinder group need to be opened, a pressure detection unit such as a pressure sensor is arranged on a pipeline system to perform real-time monitoring on the pressure value of the pipeline system, and the pressure of the pipeline system is adjusted to reach the pressure value required by the ignition test of the ignition device. The downstream position of the pipeline system is provided with a pneumatic valve, the pneumatic valve is opened so as to control the oxidant and the combustion agent to enter the ignition device, the ignition oxidant and the ignition combustion agent switch are required to be started simultaneously when the ignition device ignites, the pneumatic valve is closed after the experiment is finished, the residual gas in the pipeline system is discharged through the gas discharge valve, and the gas discharge valve is closed after the discharge is finished.
Besides the pressure detection unit, the pneumatic valve and the air release valve, the filtering unit, the one-way valve and the throttle ring are arranged in the pipeline system, the filtering unit is arranged at the upstream position of the pipeline system, and the one-way valve and the throttle ring are arranged at the downstream position of the pipeline system.
In the ignition test step, at least two oxidant gas cylinders are opened by the oxidant gas cylinder group, and before the oxidant reaches the inlet of the first pneumatic valve through the first filtering unit and the first pressure detection unit by the first pipeline, the first pneumatic valve is in a closed state; and at least two combustion agent gas cylinders are opened by the combustion agent gas cylinder group, the combustion agent passes through the second filtering unit and the second pressure detection unit through the second pipeline and reaches the inlet of the second pneumatic valve, and the second pneumatic valve is in a closed state. Before the ignition device ignites, the pressure values of the first pressure detection unit and the second pressure detection unit reaching the ignition requirement are determined.
In the ignition test step, a first pneumatic valve and a second pneumatic valve are respectively opened, wherein the first throttling ring and the second throttling ring play a throttling role, so that the flow rates of an oxidant and a combustion agent entering the ignition device reach required values. If the ignition test goes wrong, the first one-way valve and the second one-way valve act to prevent the high-temperature fuel gas from returning to the gas cylinder to cause dangerous events.
According to one embodiment of the invention, before the step of checking the airtightness comprises: a zero position acquisition step: starting ignition oxidant and ignition combustion agent switches, starting zero acquisition, checking whether each measuring point is normal, and closing the ignition oxidant and ignition combustion agent switches after the zero acquisition is finished.
Specifically, before the step of checking the air tightness, in order to make the data measured in the test more accurate, a zero position acquisition step needs to be performed, the ignition oxidant and ignition combustion agent switches are started, and the zero position acquisition is started. As another embodiment, if the system uses the temperature detection unit to detect the temperature of the pipeline system, it is necessary to check whether the measurement point of each temperature detection unit is normal. And after the zero position collection is finished, turning off ignition oxidant and ignition combustion agent switches.
According to one embodiment of the invention, the step of checking for tightness is preceded by: a system debugging step: and checking whether pneumatic valves of the pipeline system are closed or not, starting the measurement of the pressure detection unit, starting an ignition oxidant switch, stopping pressure acquisition and blowing and replacing the pipeline system after the program is finished.
Specifically, in the system debugging step, the system debugging of the first pipeline oxidizer may be performed first, and whether pneumatic valves of the pipeline system are all closed or not may be checked, as one of the embodiments, the video recording function may be turned on, the measurement of the pressure detection unit and the measurement of the temperature detection unit are started, and the ignition oxidizer switch is started, and after the program is finished, the pressure acquisition and the temperature acquisition are stopped, and the pipeline system is blown down and replaced.
According to an embodiment of the invention, the system debugging step further comprises: and checking whether pneumatic valves of the pipeline system are closed or not, starting the measurement of the pressure sensor, starting an ignition combustion agent switch, stopping pressure acquisition after the program is finished, and blowing and replacing the pipeline system.
Specifically, in the system debugging step, the system debugging of the second pipeline combustion agent can be performed again, whether pneumatic valves of the pipeline system are all closed or not is checked, as one of the embodiments, the video recording function can be started, the measurement of the pressure detection unit and the measurement of the temperature detection unit are started, the ignition combustion agent switch is started, and after the program is finished, the pressure acquisition and the temperature acquisition are stopped, and the pipeline system is blown off and replaced.
According to one embodiment of the invention, the ignition test step further comprises: and when the pressure of the pipeline system does not reach the ignition required pressure value, correspondingly increasing the number of the gas cylinders for opening the oxidant gas cylinder group or the combustion agent gas cylinder group until the pressure of the pipeline system reaches the ignition required pressure value.
Specifically, in the ignition test step, if the pressure of the first pipeline does not reach the ignition pressure value required by the ignition device, the number of the gas cylinders of the oxidant gas cylinder group is correspondingly increased and started until the pressure of the first pipeline reaches the ignition pressure value required by the ignition; and if the pressure of the second pipeline does not reach the ignition pressure value required by the ignition device, correspondingly increasing and starting the number of the gas cylinders of the combustion agent gas cylinder group until the pressure of the second pipeline reaches the ignition pressure value.
The testing method of the ignition device not only solves the pressure detection function required by the ignition device, but also improves the testing efficiency of the ignition device, and the adoption of oxygen and methane can save the testing cost and protect the environment.
In another aspect, the present invention further provides a testing system for an ignition device, comprising: and an air tightness checking module: opening at least one gas cylinder of the oxidant gas cylinder group and at least one gas cylinder of the combustion agent gas cylinder group, carrying out gas tightness inspection on a pipeline system leading to the ignition device, blowing off and replacing the pipeline system after the inspection is finished, and closing the gas cylinders; an ignition test module: and opening at least two gas cylinders of the oxidant gas cylinder group and the combustion agent gas cylinder group, adjusting the pressure of the pipeline system to reach the ignition required pressure value, opening a pneumatic valve on the pipeline system to control the oxidant and the combustion agent to enter an ignition device, and blowing and replacing the pipeline system after the test is finished.
According to one embodiment of the invention, the testing system further comprises: a zero acquisition module: starting ignition oxidant and ignition combustion agent switches, starting zero acquisition, checking whether each measuring point is normal, and closing the ignition oxidant and ignition combustion agent switches after the zero acquisition is finished.
According to one embodiment of the invention, the testing system further comprises: a system debugging module: and checking whether pneumatic valves of the pipeline system are closed or not, starting the measurement of the pressure detection unit, starting an ignition oxidant switch, stopping pressure acquisition and blowing and replacing the pipeline system after the program is finished.
According to an embodiment of the present invention, the system debugging module further includes: and checking whether pneumatic valves of the pipeline system are closed or not, starting the measurement of the pressure sensor, starting an ignition combustion agent switch, stopping pressure acquisition after the program is finished, and blowing and replacing the pipeline system.
According to one embodiment of the invention, the ignition test module further comprises: and when the pressure of the pipeline system does not reach the ignition required pressure value, correspondingly increasing the number of the gas cylinders for opening the oxidant gas cylinder group or the combustion agent gas cylinder group until the pressure of the pipeline system reaches the ignition required pressure value.
The technical scheme and the technical effect of the test system of the ignition device in the invention are basically consistent with those of the test method of the ignition device, and are not repeated here. The above-described embodiments of the present invention may be combined with each other with corresponding technical effects.
The present invention is not limited to the above preferred embodiments, and any modifications, equivalent substitutions, improvements, etc. within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (10)

1. A method of testing an ignition device, comprising:
and (3) air tightness checking: opening at least one gas cylinder of the oxidant gas cylinder group and at least one gas cylinder of the combustion agent gas cylinder group, carrying out gas tightness inspection on a pipeline system leading to the ignition device, and carrying out blowing replacement on the pipeline system after the inspection is finished;
ignition test steps: and opening at least two gas cylinders of the oxidant gas cylinder group and the combustion agent gas cylinder group, adjusting the pressure of the pipeline system to reach an ignition required pressure value, opening a pneumatic valve on the pipeline system to control oxidant and combustion agent to enter the ignition device, starting an ignition oxidant switch and an ignition combustion agent switch simultaneously, and discharging the pipeline system after the test is finished.
2. The method for testing an ignition device according to claim 1, characterized by comprising, before the step of checking airtightness:
a zero position acquisition step: starting ignition oxidant and ignition combustion agent switches, starting zero acquisition, checking whether each measuring point is normal, and closing the ignition oxidant and ignition combustion agent switches after the zero acquisition is finished.
3. The method for testing an ignition device according to claim 1, wherein the step of checking airtightness is preceded by:
a system debugging step: and checking whether pneumatic valves of the pipeline system are closed or not, starting measurement of a pressure detection unit, starting an ignition oxidant switch, stopping pressure acquisition and performing blowing replacement on the pipeline system after the program is finished.
4. The method for testing an ignition device of claim 3, wherein the system commissioning step further comprises:
and checking whether pneumatic valves of the pipeline system are closed or not, starting measurement of a pressure detection unit, starting an ignition combustion agent switch, stopping pressure acquisition and performing blowing replacement on the pipeline system after the program is finished.
5. The method of testing an ignition device of claim 1, wherein the ignition testing step further comprises:
and when the pressure of the pipeline system does not reach the ignition required pressure value, correspondingly increasing the number of the gas cylinders for opening the oxidant gas cylinder group or the combustion agent gas cylinder group until the pressure of the pipeline system reaches the ignition required pressure value.
6. A testing system for an ignition device, comprising:
and an air tightness checking module: opening at least one gas cylinder of the oxidant gas cylinder group and at least one gas cylinder of the combustion agent gas cylinder group, carrying out gas tightness inspection on a pipeline system leading to the ignition device, and blowing off and replacing the pipeline system and closing the gas cylinders after the inspection is finished;
an ignition test module: and opening at least two gas cylinders of the oxidant gas cylinder group and the combustion agent gas cylinder group, adjusting the pressure of the pipeline system to reach the ignition required pressure value, opening a pneumatic valve on the pipeline system to control the oxidant and the combustion agent to enter the ignition device, and blowing off and replacing the pipeline system after the test is finished.
7. The testing system for an ignition device of claim 6, further comprising:
a zero acquisition module: starting ignition oxidant and ignition combustion agent switches, starting zero acquisition, checking whether each measuring point is normal, and closing the ignition oxidant and ignition combustion agent switches after the zero acquisition is finished.
8. The testing system for an ignition device of claim 6, further comprising:
a system debugging module: and checking whether pneumatic valves of the pipeline system are closed or not, starting measurement of a pressure detection unit, starting an ignition oxidant switch, stopping pressure acquisition and performing blowing replacement on the pipeline system after the program is finished.
9. The testing system for an ignition device of claim 8, wherein the system commissioning module further comprises:
and checking whether pneumatic valves of the pipeline system are closed or not, starting measurement of a pressure detection unit, starting an ignition combustion agent switch, stopping pressure acquisition and performing blowing replacement on the pipeline system after the program is finished.
10. The ignition testing system of claim 6, wherein the ignition testing module further comprises:
and when the pressure of the pipeline system does not reach the ignition required pressure value, correspondingly increasing the number of the gas cylinders for opening the oxidant gas cylinder group or the combustion agent gas cylinder group until the pressure of the pipeline system reaches the ignition required pressure value.
CN202011317292.3A 2020-11-23 2020-11-23 Ignition device test method and system Pending CN112572846A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011317292.3A CN112572846A (en) 2020-11-23 2020-11-23 Ignition device test method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011317292.3A CN112572846A (en) 2020-11-23 2020-11-23 Ignition device test method and system

Publications (1)

Publication Number Publication Date
CN112572846A true CN112572846A (en) 2021-03-30

Family

ID=75123524

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011317292.3A Pending CN112572846A (en) 2020-11-23 2020-11-23 Ignition device test method and system

Country Status (1)

Country Link
CN (1) CN112572846A (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1071520A1 (en) * 1998-04-08 2001-01-31 Lockheed Martin Corporation System and method for inhibiting corrosion of metal containers and components
US20030056573A1 (en) * 2001-09-11 2003-03-27 Makoto Miwa Leak check for fuel vapor purge system
US20060068081A1 (en) * 2000-04-28 2006-03-30 Canon Kabushiki Kaisha Leak judgment method, and computer-readable recording medium with recorded leak-judgment-executable program
US20080052051A1 (en) * 2006-08-22 2008-02-28 Maccallum Taber K Variable-altitude testing systems
EP2451712A1 (en) * 2009-07-10 2012-05-16 Astrium Sas System and method for testing devices using powders
CN103454396A (en) * 2013-09-06 2013-12-18 中国科学技术大学 Test device for high-pressure combustible gas leakage spontaneous combustion and shock wave induction ignition
US20160061685A1 (en) * 2013-03-29 2016-03-03 Mitsubishi Heavy Industries, Ltd. Gas internal combustion engine gas leak checking device and method for same
CN106404834A (en) * 2016-08-29 2017-02-15 中煤科工集团重庆研究院有限公司 Test method for explosion suppression and fire retardant performance of structured packing
US20180087995A1 (en) * 2016-09-27 2018-03-29 Agency For Defense Development Device for testing performance of pyro device using high-pressure air
CN109654375A (en) * 2019-01-30 2019-04-19 中国科学技术大学 A kind of safe feeding device and its air supply method of high pressure combustibility experimental gas
CN209469513U (en) * 2019-01-04 2019-10-08 蓝箭航天空间科技股份有限公司 High thrust liquid rocket engine thrust chamber experimental rig

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1071520A1 (en) * 1998-04-08 2001-01-31 Lockheed Martin Corporation System and method for inhibiting corrosion of metal containers and components
US20060068081A1 (en) * 2000-04-28 2006-03-30 Canon Kabushiki Kaisha Leak judgment method, and computer-readable recording medium with recorded leak-judgment-executable program
US20030056573A1 (en) * 2001-09-11 2003-03-27 Makoto Miwa Leak check for fuel vapor purge system
US20080052051A1 (en) * 2006-08-22 2008-02-28 Maccallum Taber K Variable-altitude testing systems
EP2451712A1 (en) * 2009-07-10 2012-05-16 Astrium Sas System and method for testing devices using powders
US20160061685A1 (en) * 2013-03-29 2016-03-03 Mitsubishi Heavy Industries, Ltd. Gas internal combustion engine gas leak checking device and method for same
CN103454396A (en) * 2013-09-06 2013-12-18 中国科学技术大学 Test device for high-pressure combustible gas leakage spontaneous combustion and shock wave induction ignition
CN106404834A (en) * 2016-08-29 2017-02-15 中煤科工集团重庆研究院有限公司 Test method for explosion suppression and fire retardant performance of structured packing
US20180087995A1 (en) * 2016-09-27 2018-03-29 Agency For Defense Development Device for testing performance of pyro device using high-pressure air
CN209469513U (en) * 2019-01-04 2019-10-08 蓝箭航天空间科技股份有限公司 High thrust liquid rocket engine thrust chamber experimental rig
CN109654375A (en) * 2019-01-30 2019-04-19 中国科学技术大学 A kind of safe feeding device and its air supply method of high pressure combustibility experimental gas

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘瑞敏等: "新一代运载火箭动力系统试车总体试验技术研究", 《火箭推进》 *
薛方凝等: "氢氧发动机试验过程关键数据控制方法探究", 《军民两用技术与产品》 *
陈春富: "大推力氢氧发动机试验推进剂供应技术研究", 《中国优秀博硕士学位论文全文数据库(硕士)工程科技Ⅱ辑》 *

Similar Documents

Publication Publication Date Title
CN107420230B (en) Carbon tank high-load desorption pipeline desorption flow diagnosis method
CN202720101U (en) Pipeline gas tightness detection apparatus
US8261595B2 (en) Method and system for fluid valve leak detection
CN106840532A (en) The method for detecting the leakage in the fuel circuit of gas turbine fuel supply system
US9816891B2 (en) Gas internal combustion engine gas leak checking device and method for same
WO2021250171A3 (en) Valve device, intank valve and gas pressure accumulator system, in particular for fuel cell systems, and method for detecting a leakage
US10288015B2 (en) Method for checking the functionality of a differential pressure measuring unit of a motor vehicle exhaust gas recirculation system
CN111928111A (en) Modularization hydrogenation station and hydrogen sensitive tracing leakage monitoring system thereof
CN112389277A (en) Fuel cell vehicle and hydrogen safety control method, device and system thereof
EP2291627B1 (en) Method and system for diagnosis of gas leakage in a gas-powered vehicle
CN101266187A (en) Gas pressure regulator test device
JP2005257340A (en) Gas leak detection device for high-pressure tank system
CN214196501U (en) Pipeline system of ignition device and ignition system
CN112572846A (en) Ignition device test method and system
CN104215408A (en) Valve air tightness detection system
CN113847143A (en) System and method for detecting excess flow in a fluid system
CN207962117U (en) Gas leakage detection device
CN113154435B (en) Fuel gas pipeline structure and interlocking protection system of open fire heating furnace
CN201902264U (en) Fuel regulation system of heavy combustion engine
CN212204008U (en) 70MPa hydrogenation machine injection system
CN203811371U (en) Natural gas line bleeding valve on-line testing device
CN107519594B (en) A kind of multichannel fire arrester and its working method
CN112903206A (en) Air tightness detection system and air tightness detection method
CN205785652U (en) A kind of device of detected air pressure
CN216433429U (en) Test pipeline system of hydrogen pressure reducer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20210330

WD01 Invention patent application deemed withdrawn after publication