CN112560227B - A method for simulation preview of power grid dispatching day-ahead planning - Google Patents

A method for simulation preview of power grid dispatching day-ahead planning Download PDF

Info

Publication number
CN112560227B
CN112560227B CN202011341454.7A CN202011341454A CN112560227B CN 112560227 B CN112560227 B CN 112560227B CN 202011341454 A CN202011341454 A CN 202011341454A CN 112560227 B CN112560227 B CN 112560227B
Authority
CN
China
Prior art keywords
power grid
simulation
power
plan
load
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202011341454.7A
Other languages
Chinese (zh)
Other versions
CN112560227A (en
Inventor
王亚军
王鹏
马斌
汤磊
李均强
崔波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Beijing King Star Hi Tech System Control Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Beijing King Star Hi Tech System Control Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Hebei Electric Power Co Ltd, Beijing King Star Hi Tech System Control Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN202011341454.7A priority Critical patent/CN112560227B/en
Publication of CN112560227A publication Critical patent/CN112560227A/en
Application granted granted Critical
Publication of CN112560227B publication Critical patent/CN112560227B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Development Economics (AREA)
  • Geometry (AREA)
  • Evolutionary Computation (AREA)
  • Computer Hardware Design (AREA)
  • General Engineering & Computer Science (AREA)
  • Educational Administration (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention relates to a power grid dispatching day-ahead plan simulation rehearsal method, which comprises the following steps of 1) generating a power generation curve, a load curve and a maintenance operation event table for power grid simulation; generating a power grid simulation expected fault event table; generating a day-ahead plan simulation teaching plan; 2) starting a power grid training simulation system according to the day-ahead plan simulation teaching plan, setting power grid operation mode changes according to a power grid simulation overhaul operation event table, and completing simulation load flow calculation according to power grid power generation and load values set by a power grid simulation unit output table and a power grid simulation load tidal current table; triggering simulation faults according to a power grid simulation expected fault event table, simulating the power grid fault condition, and completing simulation load flow calculation after fault setting; 3) and saving the simulation power flow sections according to a set period, and calling power flow calculation and N-1 scanning functions to give the power grid operation risk of each simulation preview section. The invention improves the safety of scheduling operation.

Description

一种电网调度日前计划仿真预演方法A method for simulation preview of power grid scheduling day-ahead planning

技术领域technical field

本发明属于电力系统调度自动化领域,特别涉及一种电网调度日前计划仿真预演方法。The invention belongs to the field of power system dispatch automation, and in particular relates to a method for simulation and rehearsal of a day-ahead scheduling plan of a power grid.

背景技术Background technique

我国电力系统的调度通常需要制定日前调度计划,包括日前发电计划和检修计划等。在实时运行时,则通过执行日前计划来保证电网的正常运行。日前计划在制定的过程中已经完成了电网安全校核等工作,但是缺乏电网调度日前计划的仿真预演功能,无法模拟执行日前调度计划过程中出现电网突发故障的状况,辨识可能存在的运行风险。电网培训仿真系统(DTS)已经在广泛应用于调度运行人员的日常培训和演练。如何将电网培训仿真系统(DTS)应用于日前调度计划的仿真预演,并能模拟电网紧急状态,提示电网运行风险成为互联大电网调度仿真中迫切需要解决的问题。The dispatch of my country's power system usually requires the formulation of a day-ahead dispatch plan, including a day-ahead power generation plan and a maintenance plan. In real-time operation, the normal operation of the grid is guaranteed by executing the day-ahead plan. The power grid security check and other work have been completed in the process of formulating the previous plan, but it lacks the simulation and rehearsal function of the power grid dispatching plan, so it is impossible to simulate the sudden failure of the power grid during the execution of the daily dispatch plan, and identify the possible operation risks. . The power grid training simulation system (DTS) has been widely used in the daily training and exercise of dispatching operators. How to apply the power grid training simulation system (DTS) to the simulation rehearsal of the dispatch plan a few days ago, and to simulate the emergency state of the power grid, prompting the risk of power grid operation has become an urgent problem to be solved in the dispatch simulation of interconnected large power grids.

发明内容SUMMARY OF THE INVENTION

本发明所要解决的技术问题在于提供一种电网调度日前计划仿真预演方法,提高了调度运行的安全性。The technical problem to be solved by the present invention is to provide a method for the simulation and preview of the grid scheduling day-ahead plan, which improves the security of the scheduling operation.

为实现上述目的,本发明的技术方案包括以下步骤:To achieve the above object, the technical scheme of the present invention comprises the following steps:

其包括以下步骤,It includes the following steps,

1)生成用于电网仿真的发电曲线、负荷曲线及检修操作事件表;生成电网仿真预想故障事件表;生成日前计划仿真教案;1) Generate power generation curve, load curve and maintenance operation event table for power grid simulation; generate power grid simulation expected fault event table; generate a day-ahead planning simulation lesson plan;

2)根据所述日前计划仿真教案启动电网培训仿真系统,根据电网仿真检修操作事件表设置电网运行方式变化,按照电网仿真机组出力表和电网仿真负荷潮流表设置的电网发电、负荷数值完成仿真潮流计算;按照电网仿真预想故障事件表触发仿真故障,模拟电网故障情况,完成故障设置后的仿真潮流计算;2) Start the power grid training simulation system according to the previously planned simulation teaching plan, set the power grid operation mode change according to the power grid simulation maintenance operation event table, and complete the simulated power flow according to the power grid generation and load values set by the power grid simulation unit output table and the power grid simulation load flow table. Calculation; trigger simulation faults according to the power grid simulation expected fault event table, simulate power grid fault conditions, and complete the simulation power flow calculation after fault setting;

3)按照设定周期保存仿真潮流断面,调用电网潮流计算和N-1扫描功能给出每个仿真潮流断面的电网运行风险。3) Save the simulated power flow section according to the set period, and call the power flow calculation and N-1 scanning functions to give the power grid operation risk of each simulated power flow section.

进一步地,步骤1)中,根据初始电网运行断面,按照电网调度日前发电计划、检修计划和负荷预测数据,生成用于电网仿真的发电曲线、负荷曲线及检修操作事件表;根据用户设定的预想事故,设定电网仿真的预想故障类型及时间,生成电网仿真预想故障事件表。Further, in step 1), according to the initial power grid operation section, according to the power generation plan, the maintenance plan and the load forecast data before the grid dispatching, the power generation curve, the load curve and the maintenance operation event table for power grid simulation are generated; Anticipate the accident, set the predicted fault type and time of the power grid simulation, and generate the power grid simulation predicted fault event table.

进一步地,步骤1)中,所述电网调度日前发电计划、检修计划和负荷预测数据的获取方式为:从电网调度自动化系统中获取电网调度日前发电计划、检修计划和负荷预测数据;Further, in step 1), the acquisition method of the power generation plan, maintenance plan and load forecast data before the grid dispatching is: obtaining the grid dispatching power generation plan, maintenance plan and load forecast data before the grid dispatching automation system;

所述日前发电计划包括电网中所有发电机组的96点有功计划;The day-ahead power generation plan includes a 96-point active power plan for all generating units in the power grid;

所述检修计划包括开关刀闸动作的时间计划;The maintenance plan includes the time plan of the switch knife action;

所述负荷预测数据包括电网中所有母线负荷的96点有功预测数据。The load forecast data includes 96-point active power forecast data of all busbar loads in the power grid.

进一步地,步骤1)中,通过生成某时刻的电网仿真断面生成所述发电曲线和负荷曲线。Further, in step 1), the power generation curve and the load curve are generated by generating a power grid simulation section at a certain time.

进一步地,某时刻的电网仿真断面的生成方式为根据初始电网运行断面,逐个获取以15分钟为周期的计划数据,生成该时刻的电网仿真潮流断面。Further, the generation method of the power grid simulation section at a certain moment is to obtain plan data with a period of 15 minutes one by one according to the initial power grid operation section, and generate the power grid simulation power flow section at that moment.

进一步地,某时刻的电网仿真断面的生成包括以下步骤,Further, the generation of the power grid simulation section at a certain moment includes the following steps:

S1:以在初始电网运行断面为基础,将所有机组有功设置为该时刻的计划有功值,将所有负荷有功设置为该时刻的有功预测值;调用潮流计算程序完成该时刻计划断面的潮流计算,从而得到出力潮流有功值;S1: Based on the initial power grid operation section, set the active power of all units to the planned active power value at this moment, and set the active power of all loads to the active power prediction value of this moment; call the power flow calculation program to complete the power flow calculation of the planned section at this moment, Thereby, the active value of the output current can be obtained;

S2:计算该计划断面内网机组出力潮流有功值与计划有功值的偏差Pw-acc,Pw-acc的计算过程如式(1)所示:S2: Calculate the deviation P w-acc between the output power flow active power value of the internal grid unit in the planned section and the planned active power value. The calculation process of P w-acc is shown in formula (1):

Figure BDA0002798735300000021
Figure BDA0002798735300000021

其中,UPk表示该计划断面第k个内网发电机设备的计划有功值;ULk表示该计划断面第k个内网发电机设备的潮流有功值;n表示该计划断面中所有内网发电机设备的数量;内网发电机设备是指由该调控中心直接管控的发电机组;Among them, UP k represents the planned active power value of the k-th internal grid generator equipment in the planned section; UL k represents the tidal active power value of the k-th internal grid generator equipment in the planned section; n represents all internal grid power generation in the planned section The number of generators and equipment; the internal network generator equipment refers to the generator set directly controlled by the control center;

S3:计算该计划断面中每个外网机组出力的有功功率修正值ΔPnet-i,ΔPnet-i如式(2)所示:S3: Calculate the active power correction value ΔP net-i of the output of each external grid unit in the planned section, ΔP net-i is shown in formula (2):

Figure BDA0002798735300000031
Figure BDA0002798735300000031

其中,SPi表示该计划断面第i个外网发电机设备的机组容量值;m表示该计划断面中所有外网发电机设备的数量,SPt表示该计划断面第t个外网发电机设备的机组容量值;外网发电机设备是指该调控中心非直接管控的发电机组或等值机组模型。Among them, SP i represents the unit capacity value of the ith external grid generator equipment in the planned section; m represents the number of all external grid generator equipment in the planned section, SP t represents the t external grid generator equipment in the planned section The generator capacity value of the external grid refers to the generator set or equivalent unit model that is not directly controlled by the control center.

S4:设置该计划断面的每个外网发电机的有功出力增加ΔPnet-i;将所有内网机组设置为不可调节,所有的外网机组设置为可调节;再次调用潮流计算程序完成该时刻计划断面的潮流计算;潮流计算完成后,将所有内网机组设置为可调节;通过上述步骤,实现电网发电有功计划和负荷预测之间的偏差修正,获得该时刻精确的潮流结果;S4: Set the active power output of each external grid generator in the planned section to increase ΔP net-i ; set all internal grid units to be non-adjustable, and all external grid units to be adjustable; call the power flow calculation program again to complete the moment The power flow calculation of the planned section; after the power flow calculation is completed, all the internal grid units are set to be adjustable; through the above steps, the deviation correction between the grid generation active power plan and the load forecast is realized, and the accurate power flow result at the moment is obtained;

S5将该时刻的潮流计算结果中的机组潮流值写入对应时刻的电网仿真机组出力表,将负荷潮流值写入对应时刻的电网仿真负荷潮流表。S5 writes the unit power flow value in the power flow calculation result at the moment into the power grid simulation unit output table at the corresponding moment, and writes the load flow value into the power grid simulation load flow table at the corresponding moment.

进一步地,检修操作事件表的获取方法为:根据检修计划中开关刀闸动作的时间计划,设置仿真断面中的开关刀闸变位事件,将该变位事件写入电网仿真检修操作事件表中;所述开关刀闸变位事件包括分合信息及变位时间。Further, the acquisition method of the maintenance operation event table is: according to the time plan of the switch knife switch action in the maintenance plan, the switch knife switch displacement event in the simulation section is set, and the displacement event is written in the power grid simulation maintenance operation event table. ; The switch knife switch displacement event includes opening and closing information and displacement time.

进一步地,所述开关刀闸变位事件包括分合信息及变位时间。Further, the switch knife switch displacement event includes opening and closing information and displacement time.

进一步地,步骤1)中,将96点电网仿真机组出力表、96点电网仿真负荷潮流表、电网仿真检修操作事件表和电网仿真预想故障事件表保存为日前计划电网仿真教案。Further, in step 1), the 96-point power grid simulation unit output table, the 96-point power grid simulation load flow table, the power grid simulation maintenance operation event table and the power grid simulation expected fault event table are saved as the previously planned power grid simulation lesson plan.

进一步地,步骤3)中包括以下步骤:Further, step 3) comprises the following steps:

3-1)通过电网潮流计算给出每个仿真潮流断面的过载设备和重载设备;统计所有仿真预演断面中过载设备和重载设备,按照设备统计次数给出排序结果;统计次数越多的设备表示设备重过载风险越大;3-1) Calculate the overloaded equipment and heavy-duty equipment of each simulated power flow section through the power flow calculation; count the overloaded equipment and heavy-loaded equipment in all simulated pre-review sections, and give the sorting results according to the number of equipment statistics; The device indicates that the risk of heavy overloading of the device is greater;

3-2)通过电网N-1扫描功能给出每个仿真预演断面的N-1过载设备和重载设备;统计所有仿真潮流断面中N-1计算的过载设备和重载设备,按照设备统计次数给出排序结果;统计次数越多的设备表示设备N-1计算的重过载风险越大。3-2) Through the power grid N-1 scanning function, the N-1 overloaded equipment and heavy-duty equipment of each simulation preview section are given; the overloaded equipment and heavy-loaded equipment calculated by N-1 in all simulated power flow sections are counted, according to the equipment statistics The number of times gives the sorting result; the device with more counts means the greater the risk of heavy overload calculated by device N-1.

本发明积极效果如下:The positive effects of the present invention are as follows:

1、本发明充分利用电网调度日前发电计划、检修计划和负荷预测数据生成电网仿真教案,提升了日前计划仿真潮流计算的精度。1. The present invention makes full use of the power grid dispatching day-ahead power generation plan, maintenance plan and load forecast data to generate a power grid simulation teaching plan, which improves the accuracy of the day-ahead planning simulation power flow calculation.

2、本发明方法通过对电网日前计划和预想故障的模拟,准确模拟了预想故障下的电网潮流分布情况,进一步明确电网计划执行的薄弱环节,提高了调度运行的安全性。2. The method of the present invention accurately simulates the power flow distribution of the power grid under the expected fault by simulating the power grid plan ahead of the day and the predicted fault, further clarifies the weak link of the power grid plan execution, and improves the security of dispatching operation.

附图说明Description of drawings

图1是本发明的流程图。Figure 1 is a flow chart of the present invention.

具体实施方式Detailed ways

下面将结合附图所示,对本申请实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本申请一部分实施例,而不是全部的实施例。以下对至少一个示例性实施例的描述实际上仅仅是说明性的,决不作为对本申请及其应用或使用的任何限制。基于本申请中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本申请保护的范围。其包括以下步骤,The technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of the present application, but not all of the embodiments. The following description of at least one exemplary embodiment is merely illustrative in nature and is in no way intended to limit the application, its application, or uses. Based on the embodiments in the present application, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present application. It includes the following steps,

1)生成用于电网仿真的发电曲线、负荷曲线及检修操作事件表;生成电网仿真预想故障事件表;生成日前计划仿真教案。1) Generate power generation curve, load curve and maintenance operation event table for power grid simulation; generate power grid simulation expected fault event table;

步骤1)中,根据初始电网运行断面,按照电网调度日前发电计划、检修计划和负荷预测数据,生成用于电网仿真的发电曲线、负荷曲线及检修操作事件表;根据用户设定的预想事故,设定电网仿真的预想故障类型及时间,生成电网仿真预想故障事件表。In step 1), according to the initial power grid operation section, according to the power generation plan, maintenance plan and load forecast data before the grid dispatching, the generation curve, load curve and maintenance operation event table for power grid simulation are generated; according to the expected accident set by the user, Set the expected fault type and time of power grid simulation, and generate a grid simulation expected fault event table.

步骤1)中,所述电网调度日前发电计划、检修计划和负荷预测数据的获取方式为:从电网调度自动化系统中获取电网调度日前发电计划、检修计划和负荷预测数据;In step 1), the method of obtaining the power generation plan, maintenance plan and load forecast data before the grid dispatching day is: obtaining the power grid dispatching day power generation plan, the maintenance plan and the load forecast data from the grid dispatching automation system;

所述日前发电计划包括电网中所有发电机组的96点有功计划;The day-ahead power generation plan includes a 96-point active power plan for all generating units in the power grid;

所述检修计划包括开关刀闸动作的时间计划;The maintenance plan includes the time plan of the switch knife action;

所述负荷预测数据包括电网中所有母线负荷的96点有功预测数据。The load forecast data includes 96-point active power forecast data of all busbar loads in the power grid.

步骤1)中,通过生成某时刻的电网仿真断面生成所述发电曲线和负荷曲线。In step 1), the power generation curve and the load curve are generated by generating a power grid simulation section at a certain time.

某时刻的电网仿真断面的生成方式为根据初始电网运行断面,逐个获取以15分钟为周期的计划数据,生成该时刻的电网仿真潮流断面。The generation method of the power grid simulation section at a certain moment is to obtain the planned data with a period of 15 minutes one by one according to the initial power grid operation section, and generate the power grid simulation power flow section at that moment.

某时刻的电网仿真断面的生成包括以下步骤,The generation of the power grid simulation section at a certain time includes the following steps:

S1:以在初始电网运行断面为基础,将所有机组有功设置为该时刻的计划有功值,将所有负荷有功设置为该时刻的有功预测值;调用潮流计算程序完成该时刻计划断面的潮流计算,从而得到出力潮流有功值;S1: Based on the initial power grid operation section, set the active power of all units to the planned active power value at this moment, and set the active power of all loads to the active power prediction value of this moment; call the power flow calculation program to complete the power flow calculation of the planned section at this moment, Thereby, the active value of the output current can be obtained;

S2:计算该计划断面内网机组出力潮流有功值与计划有功值的偏差Pw-acc,Pw-acc的计算过程如式(1)所示:S2: Calculate the deviation P w-acc between the output power flow active power value of the internal grid unit in the planned section and the planned active power value. The calculation process of P w-acc is shown in formula (1):

Figure BDA0002798735300000051
Figure BDA0002798735300000051

其中,UPk表示该计划断面第k个内网发电机设备的计划有功值;ULk表示该计划断面第k个内网发电机设备的潮流有功值;n表示该计划断面中所有内网发电机设备的数量;内网发电机设备是指由该调控中心直接管控的发电机组;Among them, UP k represents the planned active power value of the k-th internal grid generator equipment in the planned section; UL k represents the tidal active power value of the k-th internal grid generator equipment in the planned section; n represents all internal grid power generation in the planned section The number of generators and equipment; the internal network generator equipment refers to the generator set directly controlled by the control center;

S3:计算该计划断面中每个外网机组出力的有功功率修正值ΔPnet-i,ΔPnet-i如式(2)所示:S3: Calculate the active power correction value ΔP net-i of the output of each external grid unit in the planned section, ΔP net-i is shown in formula (2):

Figure BDA0002798735300000052
Figure BDA0002798735300000052

其中,SPi表示该计划断面第i个外网发电机设备的机组容量值;m表示该计划断面中所有外网发电机设备的数量,SPt表示该计划断面第t个外网发电机设备的机组容量值;外网发电机设备是指该调控中心非直接管控的发电机组或等值机组模型。Among them, SP i represents the unit capacity value of the ith external grid generator equipment in the planned section; m represents the number of all external grid generator equipment in the planned section, SP t represents the t external grid generator equipment in the planned section The generator capacity value of the external grid refers to the generator set or equivalent unit model that is not directly controlled by the control center.

S4:设置该计划断面的每个外网发电机的有功出力增加ΔPnet-i;将所有内网机组设置为不可调节,所有的外网机组设置为可调节;再次调用潮流计算程序完成该时刻计划断面的潮流计算;潮流计算完成后,将所有内网机组设置为可调节;通过上述步骤,实现电网发电有功计划和负荷预测之间的偏差修正,获得该时刻精确的潮流结果;S4: Set the active power output of each external grid generator in the planned section to increase ΔP net-i ; set all internal grid units to be non-adjustable, and all external grid units to be adjustable; call the power flow calculation program again to complete the moment The power flow calculation of the planned section; after the power flow calculation is completed, all the internal grid units are set to be adjustable; through the above steps, the deviation correction between the grid generation active power plan and the load forecast is realized, and the accurate power flow result at the moment is obtained;

S5将该时刻的潮流计算结果中的机组潮流值写入对应时刻的电网仿真机组出力表,将负荷潮流值写入对应时刻的电网仿真负荷潮流表。S5 writes the unit power flow value in the power flow calculation result at the moment into the power grid simulation unit output table at the corresponding moment, and writes the load flow value into the power grid simulation load flow table at the corresponding moment.

检修操作事件表的获取方法为:根据检修计划中开关刀闸动作的时间计划,设置仿真断面中的开关刀闸变位事件,将该变位事件写入电网仿真检修操作事件表中;所述开关刀闸变位事件包括分合信息及变位时间。The acquisition method of the maintenance operation event table is: according to the time plan of the switch knife switch action in the maintenance plan, set the switch knife switch displacement event in the simulation section, and write the displacement event into the power grid simulation maintenance operation event table; The switch knife switch displacement event includes the opening and closing information and the displacement time.

所述开关刀闸变位事件包括分合信息及变位时间。The switch knife switch displacement event includes opening and closing information and displacement time.

步骤1)中,将96点电网仿真机组出力表、96点电网仿真负荷潮流表、电网仿真检修操作事件表和电网仿真预想故障事件表保存为日前计划电网仿真教案。In step 1), the 96-point power grid simulation unit output table, the 96-point power grid simulation load flow table, the power grid simulation maintenance operation event table and the power grid simulation expected fault event table are saved as the previously planned power grid simulation lesson plan.

电网仿真机组出力表结构如下表表1所示:The structure of the power grid simulation unit output table is shown in Table 1 below:

表1Table 1

字段名称Field Name 字段说明Field Description 发电机组名称Genset name 设备名称,64字节字符串device name, 64-byte string 所属发电厂名称The name of the power plant 厂站名称,64字节字符串Factory station name, 64-byte string 96点机组有功96-point unit active 机组有功出力,96点浮点数数组The active power output of the unit, an array of 96-point floating-point numbers 96点机组无功96 point unit reactive power 机组无功出力,96点浮点数数组Unit reactive power output, 96-point floating point array 96点机组机端电压96-point generator terminal voltage 机组机端电压标幺值,96点浮点数数组Unit terminal voltage per unit value, 96-point floating point number array

电网仿真负荷潮流表结构如下表表2所示:The structure of the power grid simulation load flow table is shown in Table 2 below:

表2Table 2

字段名称Field Name 字段说明Field Description 负荷设备名称Load equipment name 设备名称,64字节字符串device name, 64-byte string 所属变电站名称Substation name 厂站名称,64字节字符串Factory station name, 64-byte string 96点负荷有功96 load active power 负荷有功值,96点浮点数数组Load active value, array of 96-point floating point numbers 96点负荷无功96 load reactive power 负荷无功值,96点浮点数数组Load reactive power value, array of 96-point floating point numbers

电网仿真检修操作事件表结构如下表表3所示:The structure of the power grid simulation maintenance operation event table is shown in Table 3 below:

表3table 3

Figure BDA0002798735300000061
Figure BDA0002798735300000061

Figure BDA0002798735300000071
Figure BDA0002798735300000071

电网仿真预想故障事件表结构如下表表4所示:The structure of the power grid simulation expected fault event table is shown in Table 4 below:

表4Table 4

字段名称Field Name 字段说明Field Description 设备名称device name 设备名称,64字节字符串device name, 64-byte string 所属厂站名称Factory name 厂站名称,64字节字符串Factory station name, 64-byte string 故障类型Fault type 整数,设备操作类型枚举值Integer, device operation type enumeration value 故障整数数据fault integer data 故障数据数值,32点整数数组Fault data value, 32-point integer array 故障浮点数据fault floating point data 故障数据数值,32点浮点数数组Fault data value, 32-point float array 故障时间downtime 时间标签,设备预想故障时间Time stamp, equipment expected failure time

2)根据所述日前计划仿真教案启动电网培训仿真系统,根据电网仿真检修操作事件表设置电网运行方式变化,按照电网仿真机组出力表和电网仿真负荷潮流表设置的电网发电、负荷数值完成仿真潮流计算;按照电网仿真预想故障事件表触发仿真故障,模拟电网故障情况,完成故障设置后的仿真潮流计算;2) Start the power grid training simulation system according to the previously planned simulation teaching plan, set the power grid operation mode change according to the power grid simulation maintenance operation event table, and complete the simulated power flow according to the power grid generation and load values set by the power grid simulation unit output table and the power grid simulation load flow table. Calculation; trigger simulation faults according to the power grid simulation expected fault event table, simulate power grid fault conditions, and complete the simulation power flow calculation after fault setting;

3)按照设定周期保存仿真潮流断面,调用电网潮流计算和N-1扫描功能给出每个仿真潮流断面的电网运行风险。3) Save the simulated power flow section according to the set period, and call the power flow calculation and N-1 scanning functions to give the power grid operation risk of each simulated power flow section.

步骤3)中包括以下步骤:Step 3) includes the following steps:

3-1)通过电网潮流计算给出每个仿真潮流断面的过载设备和重载设备;统计所有仿真预演断面中过载设备和重载设备,按照设备统计次数给出排序结果;统计次数越多的设备表示设备重过载风险越大;3-1) Calculate the overloaded equipment and heavy-loaded equipment of each simulated power flow section through the power flow calculation; count the overloaded equipment and heavy-loaded equipment in all simulation preview sections, and give the sorting results according to the number of equipment statistics; The device indicates that the risk of heavy overloading of the device is greater;

3-2)通过电网N-1扫描功能给出每个仿真预演断面的N-1过载设备和重载设备;统计所有仿真潮流断面中N-1计算的过载设备和重载设备,按照设备统计次数给出排序结果;统计次数越多的设备表示设备N-1计算的重过载风险越大。3-2) Through the power grid N-1 scanning function, the N-1 overloaded equipment and heavy-duty equipment of each simulation preview section are given; the overloaded equipment and heavy-loaded equipment calculated by N-1 in all simulated power flow sections are counted, according to the equipment statistics The number of times gives the sorting result; the device with more counts means the greater the risk of heavy overload calculated by device N-1.

本发明根据初始电网运行断面,按照电网调度日前发电计划、检修计划和负荷预测数据,生成电网仿真所需要的发电曲线、负荷曲线及检修操作事件表;根据用户设定的预想事故,设定电网仿真的预想故障类型及时间,生成电网仿真预想故障事件表;将96点电网仿真机组出力表、96点电网仿真负荷潮流表、电网仿真检修操作事件表和电网仿真预想故障事件表保存为日前计划电网仿真教案。以日前计划仿真教案启动电网培训仿真系统,根据电网仿真检修操作事件表设置电网运行方式变化,按照电网仿真机组出力表和电网仿真负荷潮流表设置的电网发电、负荷数值完成仿真潮流计算;按照电网仿真预想故障事件表触发仿真故障,模拟电网故障情况,完成故障设置后的仿真潮流计算。按照设定周期保存仿真潮流断面,调用电网潮流计算和N-1扫描功能给出每个仿真预演断面的电网运行风险。本发明充分利用电网调度日前发电计划、检修计划和负荷预测数据生成电网仿真教案,提升了日前计划仿真潮流计算的精度;通过对电网日前计划和预想故障的模拟,准确模拟了预想故障下的电网潮流分布情况,进一步明确电网计划执行的薄弱环节,提升了调度运行的安全水平。According to the initial power grid operation section, according to the power generation plan, maintenance plan and load forecast data before the grid dispatching day, the invention generates the power generation curve, load curve and maintenance operation event table required for power grid simulation; according to the expected accident set by the user, the power grid is set The predicted fault type and time of the simulation are generated, and the power grid simulation predicted fault event table is generated; the 96-point power grid simulation unit output table, the 96-point power grid simulation load flow table, the power grid simulation maintenance operation event table and the power grid simulation expected fault event table are saved as the plan for the day before Power grid simulation lesson plan. Start the power grid training simulation system with the previously planned simulation lesson plan, set the power grid operation mode change according to the power grid simulation maintenance operation event table, and complete the simulation power flow calculation according to the power generation and load values set by the power grid simulation unit output table and the power grid simulation load flow table; The simulation expected fault event table triggers the simulation fault, simulates the grid fault condition, and completes the simulation power flow calculation after the fault setting. The simulation power flow section is saved according to the set period, and the power flow calculation and N-1 scanning functions are called to give the power grid operation risk of each simulation preview section. The invention makes full use of the power grid dispatching day-ahead power generation plan, maintenance plan and load forecast data to generate a power grid simulation teaching plan, which improves the accuracy of the day-ahead planning simulation power flow calculation; and accurately simulates the power grid under the expected fault by simulating the power grid's day-ahead plan and expected faults The distribution of power flow further clarifies the weak links in the implementation of the power grid plan, and improves the safety level of dispatching operation.

本发明提出一种电网调度日前计划仿真预演方法。该方法实现了对电网日前调度计划的仿真预演,精确模拟了日前计划执行的电网运行状态,提升了大规模互联电网的风险预判和辨识能力,增强了电网安全经济运行的水平。The present invention proposes a simulation preview method for grid dispatching day-ahead planning. The method realizes the simulation rehearsal of the day-ahead dispatching plan of the power grid, accurately simulates the operation state of the power grid that is executed by the day-ahead plan, improves the risk prediction and identification ability of large-scale interconnected power grids, and enhances the level of safe and economic operation of the power grid.

通过对本发明步骤概括、节选出关键词,来辅助说明本发明的过程,具体如图1所示,首先获取初始运行断面和日前计划数据,然后根据计划数据生成仿真教案,驱动仿真系统运行,自动执行事件表,周期保存仿真电网事件执行后的仿真断面,最后进行N-1扫描明确仿真断面运行风险。The process of the present invention is explained by summarizing the steps of the present invention and selecting keywords to assist in explaining the process of the present invention. Specifically, as shown in FIG. 1 , firstly obtain the initial operation section and the previous plan data, then generate a simulation teaching plan according to the plan data, and drive the simulation system to run, Automatically execute the event table, periodically save the simulation section after the simulation power grid event is executed, and finally perform an N-1 scan to clarify the operation risk of the simulation section.

本发明提出一种电网调度日前计划仿真预演方法,其优点如下:The present invention proposes a simulation preview method for grid dispatching day-ahead plan, which has the following advantages:

1、本发明提出的一种电网调度日前计划仿真预演方法,充分利用电网调度日前发电计划、检修计划和负荷预测数据生成电网仿真教案,提升了日前计划仿真潮流计算的精度。1. The present invention proposes a power grid scheduling simulation preview method, which makes full use of the power grid scheduling day-ahead power generation plan, maintenance plan and load forecast data to generate a power grid simulation lesson plan, which improves the accuracy of the day-ahead planning simulation power flow calculation.

2、本发明方法通过对电网日前计划和预想故障的模拟,准确模拟了预想故障下的电网潮流分布情况,进一步明确电网计划执行的薄弱环节,提高了调度运行的安全性。2. The method of the present invention accurately simulates the power flow distribution of the power grid under the expected fault by simulating the power grid plan ahead of the day and the predicted fault, further clarifies the weak link of the power grid plan execution, and improves the security of dispatching operation.

需要注意的是,这里所使用的术语仅是为了描述具体实施方式,而非意图限制根据本申请的示例性实施方式。如在这里所使用的,除非上下文另外明确指出,否则单数形式也意图包括复数形式,此外,还应当理解的是,当在本说明书中使用术语“包含”和/或“包括”时,其指明存在特征、步骤、操作、器件、组件和/或它们的组合。It should be noted that the terminology used herein is for the purpose of describing specific embodiments only, and is not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly dictates otherwise, the singular is intended to include the plural as well, furthermore, it is to be understood that when the terms "comprising" and/or "including" are used in this specification, it indicates that There are features, steps, operations, devices, components and/or combinations thereof.

除非另外具体说明,否则在这些实施例中阐述的部件和步骤的相对布置、数字表达式和数值不限制本申请的范围。同时,应当明白,为了便于描述,附图中所示出的各个部分的尺寸并不是按照实际的比例关系绘制的。对于相关领域普通技术人员已知的技术、方法和设备可能不作详细讨论,但在适当情况下,所述技术、方法和设备应当被视为授权说明书的一部分。在这里示出和讨论的所有示例中,任何具体值应被解释为仅仅是示例性的,而不是作为限制。因此,示例性实施例的其它示例可以具有不同的值。应注意到:相似的标号和字母在下面的附图中表示类似项,因此,一旦某一项在一个附图中被定义,则在随后的附图中不需要对其进行进一步讨论。The relative arrangement of the components and steps, the numerical expressions and numerical values set forth in these embodiments do not limit the scope of the present application unless specifically stated otherwise. Meanwhile, it should be understood that, for the convenience of description, the dimensions of various parts shown in the accompanying drawings are not drawn in an actual proportional relationship. Techniques, methods, and devices known to those of ordinary skill in the relevant art may not be discussed in detail, but where appropriate, such techniques, methods, and devices should be considered part of the authorized description. In all examples shown and discussed herein, any specific value should be construed as illustrative only and not as limiting. Accordingly, other examples of exemplary embodiments may have different values. It should be noted that like numerals and letters refer to like items in the following figures, so once an item is defined in one figure, it does not require further discussion in subsequent figures.

对所公开的实施例的上述说明,使本领域专业技术人员能够实现或使用本发明。对这些实施例的多种修改对本领域的专业技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本发明的精神或范围的情况下,在其他实施例中实现。因此,本发明将不会被限制于本文所示的这些实施例,而是要符合与本文所公开的原理和新颖特点相一致的最宽的范围。The above description of the disclosed embodiments enables any person skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein, but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (6)

1. A power grid dispatching day-ahead plan simulation rehearsal method is characterized in that: which comprises the following steps of,
1) generating a power generation curve, a load curve and a maintenance operation event table for power grid simulation; generating a power grid simulation expected fault event table; generating a day-ahead plan simulation teaching plan;
2) starting a power grid training simulation system according to the day-ahead plan simulation teaching plan, setting power grid operation mode changes according to a power grid simulation overhaul operation event table, and completing simulation load flow calculation according to power grid power generation and load values set by a power grid simulation unit output table and a power grid simulation load tidal current table; triggering a simulation fault according to a power grid simulation expected fault event table, simulating a power grid fault condition, and completing simulation load flow calculation after fault setting;
3) saving the simulation power flow sections according to a set period, and calling a power grid power flow calculation and N-1 scanning function to give a power grid operation risk of each simulation power flow section;
in the step 1), generating a power generation curve, a load curve and a maintenance operation event table for power grid simulation according to an initial power grid operation section and power grid dispatching day-ahead power generation plan, maintenance plan and load prediction data; setting the expected fault type and time of power grid simulation according to the expected accident set by a user, and generating a power grid simulation expected fault event table;
in the step 1), generating the power generation curve and the load curve by generating a power grid simulation section at a certain moment;
the generation mode of the power grid simulation section at a certain moment is to acquire plan data with a period of 15 minutes one by one according to the initial power grid operation section and generate the power grid simulation tide section at the moment;
the generation of the simulation section of the power grid at a certain moment comprises the following steps,
s1: on the basis of the initial power grid operation section, setting the active power of all the units as a planned active power value at the moment, and setting the active power of all the loads as an active power predicted value at the moment; calling a power flow calculation program to complete power flow calculation of the planned section at the moment so as to obtain an output power flow active value;
s2: calculating the deviation P between the output power flow active value and the planned active value of the intranet unit in the planned sectionw-acc,Pw-accThe calculation process of (2) is shown in formula (1):
Figure FDA0003635423100000011
wherein, UPkA planned active value representing the kth intranet generator equipment of the planned section; UL (UL)kThe current active value of the kth intranet generator equipment of the planned section is represented; n represents the number of all internal network generator devices in the planned section; the intranet generator equipment is a generator set directly controlled by a control center;
s3: calculating the active power correction value delta P of the output of each external network unit in the planned sectionnet-i,ΔPnet-iAs shown in formula (2):
Figure FDA0003635423100000021
wherein, SPiShowing the planned cross sectionThe unit capacity values of the i external network generator devices; m represents the number of all external network generator devices in the planned section, SPtThe unit capacity value of the t-th external network generator equipment of the planned section is represented; the external network generator equipment refers to a generator set or an equivalent generator set model which is not directly controlled by a control center;
s4: the active power output increase delta P of each external network generator for setting the planned sectionnet-i(ii) a All internal network units are set to be unadjustable, and all external network units are set to be adjustable; calling a load flow calculation program again to complete the load flow calculation of the planned section at the moment; after the load flow calculation is completed, setting all the intranet units to be adjustable; through the steps, the deviation correction between the power generation active plan of the power grid and the load prediction is realized, and the accurate tidal current result at the moment is obtained;
and S5, writing the unit load flow value in the current calculation result at the moment into the power grid simulation unit output table at the corresponding moment, and writing the load flow value into the power grid simulation load current table at the corresponding moment.
2. The power grid dispatching day-ahead plan simulation rehearsal method according to claim 1, characterized in that: in the step 1), the power generation plan, the overhaul plan and the load prediction data before the power grid dispatching day are obtained in the following modes: acquiring a power generation plan, a maintenance plan and load prediction data of a power grid dispatching day ahead from a power grid dispatching automation system;
the day-ahead power generation plan comprises 96 active plans of all generator sets in the power grid;
the maintenance plan comprises a time plan for switching on and off the disconnecting link;
the load prediction data comprises 96-point active prediction data of all bus loads in the power grid.
3. The power grid dispatching day-ahead plan simulation rehearsal method according to claim 1, characterized in that: the method for acquiring the maintenance operation event list comprises the following steps: setting a switch disconnecting link displacement event in the simulation section according to a time plan of switch disconnecting link action in the maintenance plan, and writing the displacement event into a power grid simulation maintenance operation event table; the switch disconnecting link displacement event comprises switching-on and switching-off information and displacement time.
4. The power grid dispatching day-ahead plan simulation rehearsal method according to claim 3, characterized in that: the switch disconnecting link displacement event comprises switching-on and switching-off information and displacement time.
5. The power grid dispatching day-ahead plan simulation rehearsal method according to claim 1, characterized in that: in the step 1), a 96-point power grid simulation unit output table, a 96-point power grid simulation load tidal current table, a power grid simulation overhaul operation event table and a power grid simulation expected fault event table are stored as a planned power grid simulation teaching plan in the day-ahead.
6. The power grid dispatching day-ahead plan simulation rehearsal method according to claim 1, characterized in that: the step 3) comprises the following steps:
3-1) calculating and providing overload equipment and overload equipment of each simulation load flow section through the power grid load flow; counting overload devices and heavy-load devices in all simulation preview sections, and giving a sequencing result according to the device counting times; the more the statistics times, the larger the equipment overload risk;
3-2) providing N-1 overload equipment and heavy-load equipment of each simulation preview section through the power grid N-1 scanning function; counting overload devices and overload devices calculated by N-1 in all simulation power flow sections, and giving a sequencing result according to the counting times of the devices; a device with a higher number of statistics indicates a higher risk of heavy overload calculated by the device N-1.
CN202011341454.7A 2020-11-25 2020-11-25 A method for simulation preview of power grid dispatching day-ahead planning Active CN112560227B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011341454.7A CN112560227B (en) 2020-11-25 2020-11-25 A method for simulation preview of power grid dispatching day-ahead planning

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011341454.7A CN112560227B (en) 2020-11-25 2020-11-25 A method for simulation preview of power grid dispatching day-ahead planning

Publications (2)

Publication Number Publication Date
CN112560227A CN112560227A (en) 2021-03-26
CN112560227B true CN112560227B (en) 2022-06-14

Family

ID=75043738

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011341454.7A Active CN112560227B (en) 2020-11-25 2020-11-25 A method for simulation preview of power grid dispatching day-ahead planning

Country Status (1)

Country Link
CN (1) CN112560227B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113703649A (en) * 2021-08-12 2021-11-26 深圳供电局有限公司 Method and tool for adjusting tidal current output and load of simulation power grid
CN113783188B (en) * 2021-08-31 2024-03-26 国网江苏省电力有限公司技能培训中心 Power grid automatic power generation control simulation method considering new energy

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103280797A (en) * 2013-04-27 2013-09-04 国家电网公司 Day-ahead static security correction method
CN103617760A (en) * 2013-09-29 2014-03-05 江苏省电力公司 Power distribution network DTS (Dispatcher Training Simulation) simulation system and simulation method thereof
CN103633649A (en) * 2013-12-19 2014-03-12 国家电网公司 Generation method for future-state alternating-current flow of power grid
CN103901778A (en) * 2014-03-18 2014-07-02 国网四川省电力公司宜宾供电公司 On-line simulation method for power grid reactive voltage control system
CN104537484A (en) * 2014-12-22 2015-04-22 国家电网公司 Power grid load loss risk assessment method based on PSASP model and emergency power supply automatic throw-in strategy
CN104835376A (en) * 2015-04-14 2015-08-12 国网上海市电力公司 Dispatcher training simulation system with automatic switching device of standby power supply automatic safety device operation simulating function
CN105046395A (en) * 2015-05-15 2015-11-11 华南理工大学 Intraday rolling scheduling method of electric power system including multiple types of new energy
CN105913148A (en) * 2016-04-11 2016-08-31 国家电网公司 On-line platform-based power grid accident pre-arranged plan automatic realization method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103136975A (en) * 2011-12-02 2013-06-05 北京清大高科系统控制有限公司 Statistic marking method of power grid interconnection training simulation system
CN104809931B (en) * 2015-04-08 2017-05-03 中国南方电网有限责任公司电网技术研究中心 Power grid training case system combined hybrid simulation handling displaying method
CN104900109A (en) * 2015-07-02 2015-09-09 国家电网公司 Power grid anti-accident maneuver process graphic presentation method
CN107516895B (en) * 2017-08-25 2019-09-27 南方电网科学研究院有限责任公司 Power distribution network rapid simulation method and device, storage medium and computer equipment thereof
CN110635519B (en) * 2018-06-22 2020-11-20 国网江苏省电力有限公司扬州供电分公司 Active power distribution network distributed new energy day-ahead active power dispatching plan generation method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103280797A (en) * 2013-04-27 2013-09-04 国家电网公司 Day-ahead static security correction method
CN103617760A (en) * 2013-09-29 2014-03-05 江苏省电力公司 Power distribution network DTS (Dispatcher Training Simulation) simulation system and simulation method thereof
CN103633649A (en) * 2013-12-19 2014-03-12 国家电网公司 Generation method for future-state alternating-current flow of power grid
CN103901778A (en) * 2014-03-18 2014-07-02 国网四川省电力公司宜宾供电公司 On-line simulation method for power grid reactive voltage control system
CN104537484A (en) * 2014-12-22 2015-04-22 国家电网公司 Power grid load loss risk assessment method based on PSASP model and emergency power supply automatic throw-in strategy
CN104835376A (en) * 2015-04-14 2015-08-12 国网上海市电力公司 Dispatcher training simulation system with automatic switching device of standby power supply automatic safety device operation simulating function
CN105046395A (en) * 2015-05-15 2015-11-11 华南理工大学 Intraday rolling scheduling method of electric power system including multiple types of new energy
CN105913148A (en) * 2016-04-11 2016-08-31 国家电网公司 On-line platform-based power grid accident pre-arranged plan automatic realization method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘健,等..电网调控仿真培训系统设计与实现.《电力系统自动化》.2013,第37卷(第13期), *
林毅,等..日前计划安全校核中计划潮流自动生成技术.《电力系统自动化》.2012,第36卷(第20期), *
王大龙,等..计及风险的微电网日前优化调度分析.《重庆理工大学学报(自然科学)》.2020,第34卷(第4期), *

Also Published As

Publication number Publication date
CN112560227A (en) 2021-03-26

Similar Documents

Publication Publication Date Title
CN101236575B (en) Black start auxiliary decision support/training system and method thereof
CN108631306B (en) Method for evaluating recovery capability of power system after disaster
CN103679282B (en) The Forecasting Methodology of wind power climbing
CN103904682B (en) A kind of power forecasting method based on scene mixed model
CN112560227B (en) A method for simulation preview of power grid dispatching day-ahead planning
CN104835376B (en) There is the dispatcher training system system of prepared auto restart automatic safety device action simulation
CN202110440U (en) Direct-drive wind-driven generator frequency-variable controller closed loop test system
Podmore et al. An advanced dispatcher training simulator
CN108053149A (en) A kind of photovoltaic electric station grid connection methods of risk assessment for considering meteorologic factor
CN104835077B (en) The static security analysis system of function is supported with dispatcher's prediction failure
CN104835078B (en) Consider that the trend of prepared auto restart action determines method in static security analysis system
CN112185221B (en) Hybrid wind-solar hybrid power generation operation and maintenance simulation method and device
CN104809659B (en) Intelligent advanced application system suitable for districted dispatch system
Hiskens et al. Bounding uncertainty in power system dynamic simulations
CN104424510A (en) Power transmission grid frame recovering method based on plurality of intelligent bodies and cluster simulation of thermal power generating unit
CN103971293B (en) A kind of wind energy turbine set Reliability Modeling considering weather
CN111475915A (en) Successive fault online evaluation method based on fault probability and time domain simulation quasi-steady state
CN104836329B (en) Local-level dispatch supporting system capable of improving analyzing and processing capability of dispatcher during accident generation
CN104898460A (en) Online static safety analysis system suitable for local dispatch system
CN104332974B (en) Cascading failure simulation method for considering the actual operation characteristics of power system dispatcher
CN105514983A (en) Load model construction method based on statistical synthesis method and fault simulation method
CN104914813B (en) The multi-platform synchronous method of prepared auto restart model in static security analysis system
CN116683434A (en) Energy storage calling method considering grid connection requirement of photovoltaic power station and energy storage charge state
CN112085336B (en) Method and system for comprehensive capability evaluation of thermal power units in the process of clean energy transition
CN114792200A (en) Scheduling accident plan generating and checking method based on expert knowledge base

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant