CN112550599A - Ship integral segmented embedded installation method - Google Patents

Ship integral segmented embedded installation method Download PDF

Info

Publication number
CN112550599A
CN112550599A CN202011339783.8A CN202011339783A CN112550599A CN 112550599 A CN112550599 A CN 112550599A CN 202011339783 A CN202011339783 A CN 202011339783A CN 112550599 A CN112550599 A CN 112550599A
Authority
CN
China
Prior art keywords
trolley
subsection
hoisting
new
track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011339783.8A
Other languages
Chinese (zh)
Inventor
王前进
龚容
刘渊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hudong Zhonghua Shipbuilding Group Co Ltd
Original Assignee
Hudong Zhonghua Shipbuilding Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hudong Zhonghua Shipbuilding Group Co Ltd filed Critical Hudong Zhonghua Shipbuilding Group Co Ltd
Priority to CN202011339783.8A priority Critical patent/CN112550599A/en
Publication of CN112550599A publication Critical patent/CN112550599A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B73/00Building or assembling vessels or marine structures, e.g. hulls or offshore platforms
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B73/00Building or assembling vessels or marine structures, e.g. hulls or offshore platforms
    • B63B73/10Building or assembling vessels from prefabricated hull blocks, i.e. complete hull cross-sections

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Butt Welding And Welding Of Specific Article (AREA)

Abstract

The invention discloses a ship integral subsection embedded installation method, which comprises the following steps: rebuilding a new subsection, and pre-embedding equipment needing to be modified or additionally installed into the newly built subsection; cutting an opening with the same size as the new section in the area to be modified or additionally installed; preparing a plurality of self-made hoisting trolleys which can be lifted, walked and adjusted left and right; paving a track on the ground for the trolley to walk, arranging the trolley on the track, and hoisting the finished new subsection use crane to the trolley; a power point is arranged in front of the track, the hoisting trolley is slowly dragged to the position right below the installation point through a winch and a chain block and is embedded into the main hull, and the subsection is completely embedded into the main hull by using the fine adjustment function of the cross-sliding bedplate of the hoisting trolley; synchronously starting up and down adjustment functions of the multiple trolleys to jack the new sections to the installation positions; assembling and welding the new sections.

Description

Ship integral segmented embedded installation method
Technical Field
The invention belongs to the technical field of ship construction, and particularly relates to a ship integral segmented embedded installation method.
Background
After the ship is finished and delivered, the ship needs to be modified or additionally provided with equipment for various reasons, and particularly the additional installation work amount of large-scale equipment is huge. The method is characterized in that a ship needs to enter a dock platform to destroy an outer plate and an internal structure of an original ship, a traditional hoisting process combining a crane and a chain block is adopted, a main ship body needs to be welded with a hoisting ring as a bearing point, so that the ship body deforms due to stress, then modified or additionally installed equipment is installed at a needed position, and then the internal structure and the outer plate of the ship are repaired. However, the method has the disadvantages of narrow construction space, high operation difficulty, influence on working efficiency and certain negative influence on installation precision, and meanwhile, a large amount of cutting, polishing, electric welding, painting and other work exists in subsequent work, so that great potential safety hazards exist in construction in the narrow space; on the other hand, the construction time in the dock is longer, the dock period is influenced, and the construction cost is increased.
Disclosure of Invention
Aiming at the problems in the prior art, the invention provides a ship integral subsection embedded installation method.
In order to achieve the purpose, the invention adopts the following technical scheme:
a ship integral subsection embedded installation method comprises the following steps: rebuilding a new subsection, and pre-embedding equipment needing to be modified or additionally installed into the newly built subsection; cutting an opening with the same size as the new section in the area to be modified or additionally installed; preparing a plurality of self-made hoisting trolleys which can be lifted, walked and adjusted left and right; paving a track on the ground for the trolley to walk, arranging the trolley on the track, and hoisting the finished new subsection use crane to the trolley; a power point is arranged in front of the track, the hoisting trolley is slowly dragged to the position right below the installation point through a winch and a chain block and is embedded into the main hull, and the subsection is completely embedded into the main hull by using the fine adjustment function of the cross-sliding bedplate of the hoisting trolley; synchronously starting up and down adjustment functions of the multiple trolleys to jack the new sections to the installation positions; assembling and welding the new sections.
Preferably one end of the track extends into the opening and the other end of the track extends outside the hull.
Preferably, the trolley comprises a moving groove, the traverse table is arranged in the moving groove, the traverse table can move in the moving groove, and the moving direction of the traverse table is in the horizontal plane and perpendicular to the track.
Preferably, the trolley is provided with a base, the bottom of the base is provided with steel wheels, the steel wheels are matched with the rails, the upper portion of the base is provided with an oil pressure driven lifting structure in the vertical direction, and the lifting end of the lifting structure is fixedly connected with the moving groove.
Compared with the prior art, the invention has the beneficial effects that: when the ship structure is reconstructed and installed, the main ship body is free from any force, so that the main ship body is free from any deformation; the method has the advantages of simple operation, safety, high efficiency, no deformation of the ship body, perfect joint control, node lifting, loss reduction and labor intensity reduction.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
FIG. 1 is a schematic flow chart of the installation method of the present invention.
Fig. 2 is a schematic view of the overall structure of the trolley of the present invention.
1-transversely moving the bedplate; 2-moving the trough; 3-a lifting structure; 4-a base; 5-orbit.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be obtained by a person skilled in the art without inventive effort based on the embodiments of the present invention, are within the scope of the present invention.
In the description of the present invention, it is to be understood that the terms "longitudinal", "lateral", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", and the like, indicate orientations or positional relationships based on those shown in the drawings, and are used merely for convenience of description and for simplicity of description, and do not indicate or imply that the referenced devices or elements must have a particular orientation, be constructed in a particular orientation, and be operated, and thus, are not to be construed as limiting the present invention.
As shown in fig. 1-2, the present embodiment provides a ship integral segment embedded installation method. The self-made steel wheel type crane trolley and the steel rail are adopted, the friction force is small, the self-made crane trolley has the functions of moving back and forth, left and right and up and down, and the main hull is not touched to finish the hoisting process. The invention relates to a novel hoisting process suitable for installing and hoisting large-scale equipment under special working conditions by embedding a main hull in sections.
Step one, a new subsection is built again, and equipment needing to be modified or additionally installed is embedded into the newly built subsection;
step two, cutting an opening with the same size as the new section in the area needing to be additionally installed;
step three, preparing three self-made hoisting trolleys which can be lifted, walked and adjusted left and right, laying segmented bracket tools, cranes, windlasses, chain blocks and other conventional hoisting tools;
fourthly, paving a track on the ground and an upper track of the trolley, and hoisting the finished new subsection crane onto the trolley;
step five, starting a power point, a winch and a chain block arranged at the front end, slowly dragging the self-made hoisting trolley to the position right below a mounting point, embedding the self-made hoisting trolley into the main hull, and completely embedding the segments into the main hull by using a transverse bedplate fine adjustment function of the hoisting trolley; (ii) a
Step six, synchronously starting up the vertical adjustment function of the three self-made hoisting trolleys to jack the new subsection to the installation position;
and step seven, assembling and welding to complete all installation.
Although the present invention has been described in detail with respect to the above embodiments, it will be understood by those skilled in the art that modifications or improvements based on the disclosure of the present invention may be made without departing from the spirit and scope of the invention, and these modifications and improvements are within the spirit and scope of the invention.

Claims (4)

1. A ship integral subsection embedded installation method is characterized by comprising the following steps: rebuilding a new subsection, and pre-embedding equipment needing to be modified or additionally installed into the newly built subsection; cutting an opening with the same size as the new section in the area to be modified or additionally installed;
preparing a plurality of self-made hoisting trolleys which can be lifted, walked and adjusted left and right;
paving a track on the ground for the trolley to walk, arranging the trolley on the track, and hoisting the finished new subsection use crane to the trolley;
a power point is arranged in front of the track, the hoisting trolley is slowly dragged to the position right below the installation point through a winch and a chain block and is embedded into the main hull, and the subsection is completely embedded into the main hull by using the fine adjustment function of the cross-sliding bedplate of the hoisting trolley;
synchronously starting up and down adjustment functions of the multiple trolleys to jack the new sections to the installation positions;
assembling and welding the new sections.
2. The marine vessel integral section embedment mounting method as claimed in claim 1, wherein one end of said rail extends into said opening and the other end of said rail extends outside of the hull.
3. The ship integral segment embedded installation method of claim 2, wherein the crane trolley comprises a moving groove, the traverse table is arranged in the moving groove, the traverse table can move in the moving groove, and the moving direction of the traverse table is in a horizontal plane and perpendicular to the rail.
4. The ship integral segment embedded installation method according to claim 3, wherein the trolley is provided with a base, steel wheels are arranged at the bottom of the base and are matched with the rail, an oil pressure driven vertical lifting structure is arranged at the upper part of the base, and a lifting end of the lifting structure is fixedly connected with the moving groove.
CN202011339783.8A 2020-11-25 2020-11-25 Ship integral segmented embedded installation method Pending CN112550599A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011339783.8A CN112550599A (en) 2020-11-25 2020-11-25 Ship integral segmented embedded installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011339783.8A CN112550599A (en) 2020-11-25 2020-11-25 Ship integral segmented embedded installation method

Publications (1)

Publication Number Publication Date
CN112550599A true CN112550599A (en) 2021-03-26

Family

ID=75043684

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011339783.8A Pending CN112550599A (en) 2020-11-25 2020-11-25 Ship integral segmented embedded installation method

Country Status (1)

Country Link
CN (1) CN112550599A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES338762A1 (en) * 1966-03-16 1968-04-16 Mitsubishi Heavy Ind Ltd Method for rebuilding the hull of a ship to increase its tonnage
CN204053355U (en) * 2014-09-25 2014-12-31 浙江海洋学院 A kind of boat segmental always organizes positioner
CN103029807B (en) * 2011-10-10 2015-05-20 上海船厂船舶有限公司 Device and method for translating jumbo ship block
CN106828771A (en) * 2017-02-09 2017-06-13 大连中远船务工程有限公司 Container ship bulb bow block renews installation method
CN111017152A (en) * 2019-11-15 2020-04-17 上海江南长兴造船有限责任公司 Ship repairing method for replacing bottom subsection
CN210416930U (en) * 2019-06-06 2020-04-28 舟山市龙山船厂有限公司 Device for replacing bottom plate of ship body
CN210942180U (en) * 2019-12-11 2020-07-07 蓬莱中柏京鲁船业有限公司 Device convenient for ship segmentation folding
CN111661274A (en) * 2020-05-25 2020-09-15 广州文冲船舶修造有限公司 Large container ship lashing bridge refitting process

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES338762A1 (en) * 1966-03-16 1968-04-16 Mitsubishi Heavy Ind Ltd Method for rebuilding the hull of a ship to increase its tonnage
CN103029807B (en) * 2011-10-10 2015-05-20 上海船厂船舶有限公司 Device and method for translating jumbo ship block
CN204053355U (en) * 2014-09-25 2014-12-31 浙江海洋学院 A kind of boat segmental always organizes positioner
CN106828771A (en) * 2017-02-09 2017-06-13 大连中远船务工程有限公司 Container ship bulb bow block renews installation method
CN210416930U (en) * 2019-06-06 2020-04-28 舟山市龙山船厂有限公司 Device for replacing bottom plate of ship body
CN111017152A (en) * 2019-11-15 2020-04-17 上海江南长兴造船有限责任公司 Ship repairing method for replacing bottom subsection
CN210942180U (en) * 2019-12-11 2020-07-07 蓬莱中柏京鲁船业有限公司 Device convenient for ship segmentation folding
CN111661274A (en) * 2020-05-25 2020-09-15 广州文冲船舶修造有限公司 Large container ship lashing bridge refitting process

Similar Documents

Publication Publication Date Title
CN104695984A (en) Multifunctional tunnel construction trolley
CN110552703B (en) Duct piece mounting system applied to shaft construction
CN109826631B (en) Telescopic adjustable tunnel trolley and working method thereof
CN205577896U (en) Novel high -efficient mechatronic workover machine
CN103982200B (en) Slide rail Mobile steel mould trolley in tunneling boring
CN112319731A (en) Installation method of large-scale marine equipment
CN105569692A (en) Trolley for welding tunnel waterproof board hanging cloth
CN204627622U (en) The multi-functional construction trolley in a kind of tunnel
CN201874475U (en) Low-position installation sleeve-type derrick
CN207332911U (en) A kind of operation tunnel Disease Treatment steel arch-shelf fitting machine
CN210563610U (en) Welding application multifunctional integrated mobile workshop
CN112550599A (en) Ship integral segmented embedded installation method
CN204778464U (en) Shield constructs gantry crane for subway
CN204002842U (en) In full section, slide rail moves steel form carrier
CN110921506A (en) Rotary lifting beam of coal mine transportation system
CN204000636U (en) Walking-type bridge anti-collision wall formwork hoisting device
CN207499886U (en) A kind of large cross-section tunnel moves adjustable waterproof construction trolley
CN219117019U (en) Auxiliary tool for replacing bin grate
CN107288354B (en) Construction method for overall displacement of gantry crane
CN218028885U (en) Coal conveying trestle maintenance operation platform of thermal power factory
CN210288079U (en) Trestle bridge template dragging device
CN216737275U (en) Be used for municipal concrete well lid movable hoisting accessory
CN220976225U (en) A installation hoist for rectangle push bench
CN214145494U (en) Novel shield constructs quick-witted station-crossing device
CN109626208A (en) A kind of encircling type single-beam operation trolley and application method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210326