CN112541528A - Power transmission and transformation project cost prediction index optimization method based on fuzzy clustering - Google Patents
Power transmission and transformation project cost prediction index optimization method based on fuzzy clustering Download PDFInfo
- Publication number
- CN112541528A CN112541528A CN202011398768.0A CN202011398768A CN112541528A CN 112541528 A CN112541528 A CN 112541528A CN 202011398768 A CN202011398768 A CN 202011398768A CN 112541528 A CN112541528 A CN 112541528A
- Authority
- CN
- China
- Prior art keywords
- index
- clustering
- foundation
- fuzzy clustering
- power transmission
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 31
- 230000005540 biological transmission Effects 0.000 title claims abstract description 28
- 230000009466 transformation Effects 0.000 title claims abstract description 25
- 238000005457 optimization Methods 0.000 title claims abstract description 16
- 238000011156 evaluation Methods 0.000 claims abstract description 14
- 238000004364 calculation method Methods 0.000 claims abstract description 13
- 229910000831 Steel Inorganic materials 0.000 claims description 21
- 239000010959 steel Substances 0.000 claims description 21
- 239000013598 vector Substances 0.000 claims description 18
- 239000012212 insulator Substances 0.000 claims description 6
- 239000011435 rock Substances 0.000 claims description 6
- 238000005491 wire drawing Methods 0.000 claims description 6
- 239000011159 matrix material Substances 0.000 claims description 5
- 238000013016 damping Methods 0.000 claims description 4
- 230000001681 protective effect Effects 0.000 claims description 4
- 239000004020 conductor Substances 0.000 claims description 3
- 230000002265 prevention Effects 0.000 claims description 3
- 125000006850 spacer group Chemical group 0.000 claims description 3
- 238000013461 design Methods 0.000 abstract description 2
- 230000000694 effects Effects 0.000 description 6
- 238000012545 processing Methods 0.000 description 4
- 239000004576 sand Substances 0.000 description 4
- 239000002689 soil Substances 0.000 description 4
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 4
- 238000010276 construction Methods 0.000 description 3
- 238000013459 approach Methods 0.000 description 2
- 238000013480 data collection Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000011248 coating agent Substances 0.000 description 1
- 238000000576 coating method Methods 0.000 description 1
- 238000007728 cost analysis Methods 0.000 description 1
- 238000002790 cross-validation Methods 0.000 description 1
- 238000013277 forecasting method Methods 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 238000012706 support-vector machine Methods 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/04—Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F18/00—Pattern recognition
- G06F18/20—Analysing
- G06F18/23—Clustering techniques
- G06F18/232—Non-hierarchical techniques
- G06F18/2321—Non-hierarchical techniques using statistics or function optimisation, e.g. modelling of probability density functions
- G06F18/23213—Non-hierarchical techniques using statistics or function optimisation, e.g. modelling of probability density functions with fixed number of clusters, e.g. K-means clustering
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0639—Performance analysis of employees; Performance analysis of enterprise or organisation operations
- G06Q10/06393—Score-carding, benchmarking or key performance indicator [KPI] analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E40/00—Technologies for an efficient electrical power generation, transmission or distribution
- Y02E40/70—Smart grids as climate change mitigation technology in the energy generation sector
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Economics (AREA)
- Physics & Mathematics (AREA)
- Strategic Management (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Tourism & Hospitality (AREA)
- Marketing (AREA)
- Entrepreneurship & Innovation (AREA)
- Development Economics (AREA)
- General Business, Economics & Management (AREA)
- Data Mining & Analysis (AREA)
- Health & Medical Sciences (AREA)
- Game Theory and Decision Science (AREA)
- Educational Administration (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- General Health & Medical Sciences (AREA)
- General Engineering & Computer Science (AREA)
- Bioinformatics & Cheminformatics (AREA)
- Primary Health Care (AREA)
- Bioinformatics & Computational Biology (AREA)
- Probability & Statistics with Applications (AREA)
- Computer Vision & Pattern Recognition (AREA)
- Life Sciences & Earth Sciences (AREA)
- Evolutionary Biology (AREA)
- Evolutionary Computation (AREA)
- Water Supply & Treatment (AREA)
- Public Health (AREA)
- Artificial Intelligence (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
A power transmission and transformation project cost prediction index optimization method based on fuzzy clustering is characterized in that n indexes are extracted from a technical-warp calculation system, the initial number of clustering centers is set to be 2, all indexes are classified by adopting a fuzzy clustering algorithm, a membership degree evaluation index K is calculated according to a fuzzy clustering result, then the number of the clustering centers is increased by one, the fuzzy clustering algorithm is adopted for continuous iteration until the calculated K value reaches the maximum value, and the clustering center corresponding to the K value at the moment is used as the optimized index. The design not only can effectively reduce the calculation difficulty of prediction, but also can improve the prediction precision.
Description
Technical Field
The invention belongs to the field of power transmission and transformation engineering design, and particularly relates to a power transmission and transformation engineering cost prediction index optimization method based on fuzzy clustering.
Background
The cost of the power transmission and transformation project is an important component of the investment of power grid enterprises, and accurate and reasonable estimation of the power transmission and transformation project is needed to make the best investment strategy. The existing cost compiling depends on manual work, the automation degree of the 'calculation amount' step which consumes most time, wastes most labor and is most prone to error in the compiling process is low, the engineering amount calculation mainly depends on manual work, the efficiency is low, the accuracy is poor, and the balance rate level of the engineering is always high. Meanwhile, the current power grid engineering cost data are stored in various different application systems in a scattered manner, a uniform service data collection platform is lacked, data association is not tight, a data island phenomenon is serious, a large amount of time and energy of basic engineering cost professionals are consumed for collection, filling and checking of the basic engineering data, the basic engineering data are influenced by factors such as professional quality and responsibility of the data collection and filling professionals, and authenticity and quality of the basic engineering data are lacked in cost analysis.
In order to solve the problems, intelligent algorithms appear in succession and show wide application value in the field of cost prediction. The traditional prediction methods are divided into qualitative prediction methods and quantitative prediction methods. The qualitative prediction method mainly comprises the following steps: the qualitative forecasting method is characterized in that the opinions and expectations of experts on projects are collected, the process is complicated, and the forecasting result inevitably introduces subjective factors of the experts. The quantitative prediction method comprises the following steps: the quantitative prediction method is not influenced by subjective factors and is widely applied to prediction of actual engineering, however, for complex construction projects, original data are complex and diverse, data regularity is poor, and the method has poor processing capability on interaction effects and nonlinear relations among data.
Disclosure of Invention
The invention aims to solve the problems in the prior art and provide a fuzzy clustering-based power transmission and transformation project cost prediction index optimization method which can effectively reduce the prediction calculation difficulty and improve the prediction precision.
In order to achieve the above purpose, the technical scheme of the invention is as follows:
a power transmission and transformation project cost prediction index optimization method based on fuzzy clustering sequentially comprises the following steps:
step A, extracting n indexes from a technical and economic quantity system to form a vector X of each index1,X2,…Xn;
Step B, setting the initial number of the clustering centers to be 2, classifying each index by adopting a fuzzy clustering algorithm, and calculating a membership degree evaluation index K according to a fuzzy clustering result;
step C, adding one to the number of the clustering centers, classifying each index again by adopting a fuzzy clustering algorithm, and recalculating a membership degree evaluation index K;
and D, circularly repeating the step C until the calculated K value reaches the maximum value, and taking the clustering center corresponding to the K value at the moment as an optimized index.
In the step B, the membership degree evaluation index K is calculated by adopting the following formula:
in the above formula, c is the number of cluster centers, uijAnd the membership degree of the ith index to the jth clustering center.
In the step B, the step of classifying the indexes by adopting the fuzzy clustering algorithm sequentially comprises the following steps:
b1, randomly dividing a membership matrix U in the range of 0-1, and initializing 2 clustering centers;
b2, determining the membership u of each index according to the following formulaij:
In the above formula, dijThe distortion degree of the ith index belonging to the jth cluster center, j being 1, 2 … c;
b3, updating the membership clustering center according to the calculated membership degree:
in the above formula, XiIs a vector of the i-th index, pjA vector for the jth cluster center;
b4, repeating the steps B2 and B3 circularly until pjThe updated distance satisfies the following condition:
in the above formula, pj m-1And epsilon is an allowable error constant for the vector of the jth cluster center after the m-1 th update.
In step B2, d isijThe calculation formula of (2) is as follows:
dij=‖Xi-pj‖=(Xi-pj)T(Xi-pj)。
in the step A, the n indexes comprise a peak, a base plane, a chassis, a sleeve, a chuck, a wire drawing disc, a concrete assembled foundation, a foundation cushion layer, a cast-in-place foundation, a foundation connecting beam, a protective cap, a rock anchor rod foundation, a cast-in-place pile foundation, a tree root pile foundation, a prefabricated pile foundation, a steel pipe pile foundation, a hole digging pile foundation, a flood discharge ditch, a retaining wall, a slope protection, a grounding body, a grounding electrode, a grounding module, a foundation permanent cofferdam, a foundation bolt, a plug-in angle steel or steel pipe, a steel ring, a concrete rod, a steel pipe rod, a tower, a wire drawing, a falling prevention device, a lightning conductor, an OPGW, an insulator string, a shockproof hammer, a spacer, a damping wire, an ice resistance ring, a.
Compared with the prior art, the invention has the beneficial effects that:
the invention relates to a power transmission and transformation project cost prediction index optimization method based on fuzzy clustering, which comprises the steps of firstly extracting n indexes from a technical computation system, then setting the initial number of clustering centers as 2, classifying the indexes by adopting a fuzzy clustering algorithm, then calculating a membership evaluation index K according to a fuzzy clustering result, then adding one to the number of clustering centers, continuously iterating by adopting the fuzzy clustering algorithm until the calculated K value reaches the maximum value, and taking the clustering center corresponding to the K value at the moment as an optimized index, wherein the membership evaluation index K is introduced to represent the clustering effect on the basis of the conventional fuzzy clustering, so that the optimal clustering effect can be finally obtained, the calculation difficulty of subsequent project cost prediction can be effectively reduced, and the project cost prediction error based on the clustering result is smaller, with higher accuracy. Therefore, the invention not only can effectively reduce the calculation difficulty of prediction, but also can improve the prediction precision.
Drawings
FIG. 1 is a flow chart of the present invention.
FIG. 2 is a K-value curve obtained by continuous iterative calculation in example 1.
Detailed Description
The present invention will be described in further detail with reference to the following detailed description and accompanying drawings.
Referring to fig. 1, a power transmission and transformation project cost prediction index optimization method based on fuzzy clustering sequentially comprises the following steps:
step A, extracting n indexes from a technical and economic quantity system to form a vector X of each index1,X2,…Xn;
Step B, setting the initial number of the clustering centers to be 2, classifying each index by adopting a fuzzy clustering algorithm, and calculating a membership degree evaluation index K according to a fuzzy clustering result;
step C, adding one to the number of the clustering centers, classifying each index again by adopting a fuzzy clustering algorithm, and recalculating a membership degree evaluation index K;
and D, circularly repeating the step C until the calculated K value reaches the maximum value, and taking the clustering center corresponding to the K value at the moment as an optimized index.
In the step B, the membership degree evaluation index K is calculated by adopting the following formula:
in the above formula, c is the number of cluster centers, uijAnd the membership degree of the ith index to the jth clustering center.
In the step B, the step of classifying the indexes by adopting the fuzzy clustering algorithm sequentially comprises the following steps:
b1, randomly dividing a membership matrix U in the range of 0-1, and initializing 2 clustering centers;
b2, determining the membership u of each index according to the following formulaij:
In the above formula, dijThe distortion degree of the ith index belonging to the jth cluster center, j being 1, 2 … c;
b3, updating the membership clustering center according to the calculated membership degree:
in the above formula, XiIs a vector of the i-th index, pjA vector for the jth cluster center;
b4, repeating the steps B2 and B3 circularly until pjThe updated distance satisfies the following condition:
in the above formula, pj m-1And epsilon is an allowable error constant for the vector of the jth cluster center after the m-1 th update.
In step B2, d isijThe calculation formula of (2) is as follows:
dij=‖Xi-pj‖=(Xi-pj)T(Xi-pj)。
in the step A, the n indexes comprise a peak, a base plane, a chassis, a sleeve, a chuck, a wire drawing disc, a concrete assembled foundation, a foundation cushion layer, a cast-in-place foundation, a foundation connecting beam, a protective cap, a rock anchor rod foundation, a cast-in-place pile foundation, a tree root pile foundation, a prefabricated pile foundation, a steel pipe pile foundation, a hole digging pile foundation, a flood discharge ditch, a retaining wall, a slope protection, a grounding body, a grounding electrode, a grounding module, a foundation permanent cofferdam, a foundation bolt, a plug-in angle steel or steel pipe, a steel ring, a concrete rod, a steel pipe rod, a tower, a wire drawing, a falling prevention device, a lightning conductor, an OPGW, an insulator string, a shockproof hammer, a spacer, a damping wire, an ice resistance ring, a.
The principle of the invention is illustrated as follows:
the invention provides a power transmission and transformation project cost prediction index optimization method based on fuzzy clustering, which adopts a membership degree evaluation index K in the process of fuzzy clustering. Because the sum of the membership degrees in the fuzzy clustering is 1, the greater the maximum value in the known membership degrees is, the better the clustering effect is, so that the K value can be increased along with the improvement of the clustering effect, and the c value corresponding to the K value reaching the maximum value is taken as the final clustering center number, so that the best clustering effect can be achieved.
Example 1:
referring to fig. 1, a power transmission and transformation project cost prediction index optimization method based on fuzzy clustering is sequentially performed according to the following steps:
1. extracting 43 indexes from the technical calculation system to form a vector X of each index1,X2,…X43The indexes comprise peaks, base planes, chassis, sleeves, chucks, anchor plates, concrete assembled foundations, foundation cushions, cast-in-place foundations, foundation connecting beams, protective caps, rock bolt foundations, cast-in-place pile foundations, tree root pile foundations, prefabricated pile foundations, steel pipe pile foundations, bored pile foundations, flood discharge ditches, retaining walls, slope protection, grounding bodies, grounding electrodes, grounding modules, foundation permanent cofferdams, foundation bolts, inserted angle steel or steel pipes, steel rings, concrete poles, steel pipe poles, towers, pull lines, anti-falling devices, lightning protection lines, leads, OPGWs, insulator chains, vibration dampers, spacing bars, heavy hammers, damping lines, ice resistance rings, jumper wires and spans;
2. firstly, setting the initial number of the clustering centers to be 2, then randomly dividing a membership matrix U with the range of 0-1, and initializing 2 clustering centers;
3. determining the membership degree u of each index according to the following formulaij:
dij=‖Xi-pj‖=(Xi-pj)T(Xi-pj)
In the above formula, dijFor the distortion degree of the ith index belonging to the jth cluster center, the distance between two vectors is used for representing j is 1, 2 … c, and dikThe same process is carried out;
4. updating the membership clustering center according to the calculated membership:
in the above formula, XiIs a vector of the i-th index, pjA vector for the jth cluster center;
5. repeating the steps 3 and 4 circularly until pjThe updated distance satisfies the following condition:
in the above formula, pj m-1The vector is the vector of the jth clustering center after the m-1 th update, epsilon is an allowable error constant, and the value of epsilon is 0.05;
6. calculating a membership degree evaluation index K to be 0.824 by adopting the following formula;
in the above formula, c is the number of cluster centers, and n isTotal number of indices, uijThe membership degree of the ith index to the jth clustering center;
7. adding one to the number of the clustering centers, and repeating the steps 3-6;
8. and (3) repeating the step (7) in a circulating manner until the calculated K value reaches the maximum value (see fig. 2), wherein the clustering center c corresponding to the K value is 18, and indexes (respectively: loop number, lead unit price, tower material unit price, terrain, geology, wind speed, ice coating, lead section, strain proportion, earthwork amount, basic concrete amount, basic steel amount, tower material amount, lead amount, synthetic insulator amount, disc insulator amount, hardware amount and tower amount) corresponding to the 18 clustering centers are used as optimized indexes.
In order to verify the effectiveness of the method, the clustering results of c 17, c 18 and c 19 are respectively selected to predict the construction cost of different power transmission and transformation projects, and the specific prediction steps are as follows:
the method comprises the following steps of taking optimized indexes as input, taking power transmission and transformation project cost as output, and solving a regression equation of a function by using a support vector machine to obtain a prediction model, wherein the method specifically comprises the following steps:
(1) three descriptive factors of loop number, terrain and geology are quantized:
the single loop, the double loop, the three loop and the four loops of the loop number of the power transmission line are respectively expressed by 1, 2, 3 and 4, if a section of line contains various loop numbers, the contained loop numbers are required to be subjected to weighted average processing according to the proportion of the length of the line with different loop numbers in the length of the total line;
the power transmission line approach terrain comprises flat ground, hills, a river network, a mud and marsh, mountain land, mountains and deserts, the flat ground is divided into 5 grades, the flat ground is a first grade, the hills are a second grade, the river network, the mud and marsh are combined into a third grade, the mountain land and the deserts are respectively a fourth grade and a fifth grade, the 5 terrain grades are respectively represented by 1, 2, 3, 4 and 5, and if one section of line comprises multiple terrains, weighted average processing needs to be carried out on the contained terrains according to the proportion of the different terrains.
The power transmission line approach geology comprises a common soil pit, a hard soil pit, loose sand stones, dry sand, a water pit, a muddy water pit, quicksand and a rock pit, wherein the common soil pit is of a first grade, the hard soil pit is of a second grade, the loose sand stones and the dry sand are of a third grade, the water pit, the muddy water pit, the quicksand and the rock pit are respectively of a fourth grade, a fifth grade, a sixth grade and a seventh grade, the geological grades are represented by 1-7, and if the geological conditions of a section of line are complex and various, the contained geology is subjected to weighted average treatment according to the proportion occupied by different geology;
(2) determining a sample matrix according to the sample data of each index value, and processing the sample data;
(3) determining a kernel function K (x)i,x)=exp(-||xi-x||/(2σ2))dSetting an error limit epsilon to 0.05, and obtaining optimized parameters (C, sigma) through cross validation, specifically, respectively substituting different parameters (C, sigma) into the prediction modelVerifying the model, and taking the (C, sigma) corresponding to the predicted value of the power transmission and transformation project cost obtained by calculating the model as an optimized (C, sigma) value;
(4) obtaining a power transmission and transformation project cost prediction model:
and secondly, predicting the construction cost of the power transmission and transformation project according to the obtained prediction model.
The prediction error calculation was performed on the obtained prediction data, and the results are shown in table 1:
TABLE 1 prediction error analysis Table
According to the results shown in table 1, when c is 18, that is, when the K value reaches the maximum, the cost of the power transmission and transformation project has the minimum error, that is, the method of the present invention can optimize the cost prediction index of the power transmission and transformation project, and improve the final prediction accuracy.
Claims (5)
1. A power transmission and transformation project cost prediction index optimization method based on fuzzy clustering is characterized by comprising the following steps:
the optimization method sequentially comprises the following steps:
step A, extracting n indexes from a technical and economic quantity system to form a vector X of each index1,X2,…Xn;
Step B, setting the initial number of the clustering centers to be 2, classifying each index by adopting a fuzzy clustering algorithm, and calculating a membership degree evaluation index K according to a fuzzy clustering result;
step C, adding one to the number of the clustering centers, classifying each index again by adopting a fuzzy clustering algorithm, and recalculating a membership degree evaluation index K;
and D, circularly repeating the step C until the calculated K value reaches the maximum value, and taking the clustering center corresponding to the K value at the moment as an optimized index.
2. The power transmission and transformation project cost prediction index optimization method based on fuzzy clustering of claim 1, characterized in that:
in the step B, the membership degree evaluation index K is calculated by adopting the following formula:
in the above formula, c is the number of cluster centers, uijAnd the membership degree of the ith index to the jth clustering center.
3. The power transmission and transformation project cost prediction index optimization method based on fuzzy clustering according to claim 1 or 2, characterized in that:
in the step B, the step of classifying the indexes by adopting the fuzzy clustering algorithm sequentially comprises the following steps:
b1, randomly dividing a membership matrix U in the range of 0-1, and initializing 2 clustering centers;
b2, determining the membership u of each index according to the following formulaij:
In the above formula, dijThe distortion degree of the ith index belonging to the jth cluster center, j being 1, 2 … c;
b3, updating the membership clustering center according to the calculated membership degree:
in the above formula, XiIs a vector of the i-th index, pjA vector for the jth cluster center;
b4, repeating the steps B2 and B3 circularly until pjThe updated distance satisfies the following condition:
in the above formula, pj m-1And epsilon is an allowable error constant for the vector of the jth cluster center after the m-1 th update.
4. The power transmission and transformation project cost prediction index optimization method based on fuzzy clustering of claim 3, wherein:
in step B2, d isijThe calculation formula of (2) is as follows:
dij=‖Xi-pj‖=(Xi-pj)T(Xi-pj)。
5. the power transmission and transformation project cost prediction index optimization method based on fuzzy clustering according to claim 1 or 2, characterized in that: in the step A, the n indexes comprise a peak, a base plane, a chassis, a sleeve, a chuck, a wire drawing disc, a concrete assembled foundation, a foundation cushion layer, a cast-in-place foundation, a foundation connecting beam, a protective cap, a rock anchor rod foundation, a cast-in-place pile foundation, a tree root pile foundation, a prefabricated pile foundation, a steel pipe pile foundation, a hole digging pile foundation, a flood discharge ditch, a retaining wall, a slope protection, a grounding body, a grounding electrode, a grounding module, a foundation permanent cofferdam, a foundation bolt, a plug-in angle steel or steel pipe, a steel ring, a concrete rod, a steel pipe rod, a tower, a wire drawing, a falling prevention device, a lightning conductor, an OPGW, an insulator string, a shockproof hammer, a spacer, a damping wire, an ice resistance ring, a.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011398768.0A CN112541528A (en) | 2020-12-02 | 2020-12-02 | Power transmission and transformation project cost prediction index optimization method based on fuzzy clustering |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011398768.0A CN112541528A (en) | 2020-12-02 | 2020-12-02 | Power transmission and transformation project cost prediction index optimization method based on fuzzy clustering |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112541528A true CN112541528A (en) | 2021-03-23 |
Family
ID=75015652
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011398768.0A Pending CN112541528A (en) | 2020-12-02 | 2020-12-02 | Power transmission and transformation project cost prediction index optimization method based on fuzzy clustering |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112541528A (en) |
Citations (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103646354A (en) * | 2013-11-28 | 2014-03-19 | 国家电网公司 | Effective index FCM and RBF neural network-based substation load characteristic categorization method |
CN105243255A (en) * | 2015-08-11 | 2016-01-13 | 北华航天工业学院 | Evaluation method for soft foundation treatment scheme |
CN106682416A (en) * | 2016-12-24 | 2017-05-17 | 合肥城市云数据中心股份有限公司 | Sewage enterprise water pollution source assessment method based on multi-index evaluation algorithm |
CN106845457A (en) * | 2017-03-02 | 2017-06-13 | 西安电子科技大学 | Method for detecting infrared puniness target based on spectrum residual error with fuzzy clustering |
CN107220977A (en) * | 2017-06-06 | 2017-09-29 | 合肥工业大学 | The image partition method of Validity Index based on fuzzy clustering |
CN107330458A (en) * | 2017-06-27 | 2017-11-07 | 常州信息职业技术学院 | A kind of fuzzy C-means clustering method of minimum variance clustering of optimizing initial centers |
CN108428236A (en) * | 2018-03-28 | 2018-08-21 | 西安电子科技大学 | The integrated multiple target SAR image segmentation method of feature based justice |
CN108879708A (en) * | 2018-08-28 | 2018-11-23 | 东北大学 | A kind of the reactive voltage partition method and system of active distribution network |
CN108898322A (en) * | 2018-07-11 | 2018-11-27 | 国网浙江省电力有限公司经济技术研究院 | A kind of electric grid investment strategy benefit integrated evaluating method based on FCM algorithm |
CN109508867A (en) * | 2018-10-22 | 2019-03-22 | 南京航空航天大学 | Air traffic region partitioning method based on fuzzy C-means clustering |
CN110211126A (en) * | 2019-06-12 | 2019-09-06 | 西安邮电大学 | Image partition method based on intuitionistic fuzzy C mean cluster |
CN110929777A (en) * | 2019-11-18 | 2020-03-27 | 济南大学 | Data kernel clustering method based on transfer learning |
CN111444949A (en) * | 2020-03-23 | 2020-07-24 | 中国人民解放军国防科技大学 | Rule optimization-based data-driven granularity modeling method |
-
2020
- 2020-12-02 CN CN202011398768.0A patent/CN112541528A/en active Pending
Patent Citations (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103646354A (en) * | 2013-11-28 | 2014-03-19 | 国家电网公司 | Effective index FCM and RBF neural network-based substation load characteristic categorization method |
CN105243255A (en) * | 2015-08-11 | 2016-01-13 | 北华航天工业学院 | Evaluation method for soft foundation treatment scheme |
CN106682416A (en) * | 2016-12-24 | 2017-05-17 | 合肥城市云数据中心股份有限公司 | Sewage enterprise water pollution source assessment method based on multi-index evaluation algorithm |
CN106845457A (en) * | 2017-03-02 | 2017-06-13 | 西安电子科技大学 | Method for detecting infrared puniness target based on spectrum residual error with fuzzy clustering |
CN107220977A (en) * | 2017-06-06 | 2017-09-29 | 合肥工业大学 | The image partition method of Validity Index based on fuzzy clustering |
CN107330458A (en) * | 2017-06-27 | 2017-11-07 | 常州信息职业技术学院 | A kind of fuzzy C-means clustering method of minimum variance clustering of optimizing initial centers |
CN108428236A (en) * | 2018-03-28 | 2018-08-21 | 西安电子科技大学 | The integrated multiple target SAR image segmentation method of feature based justice |
CN108898322A (en) * | 2018-07-11 | 2018-11-27 | 国网浙江省电力有限公司经济技术研究院 | A kind of electric grid investment strategy benefit integrated evaluating method based on FCM algorithm |
CN108879708A (en) * | 2018-08-28 | 2018-11-23 | 东北大学 | A kind of the reactive voltage partition method and system of active distribution network |
CN109508867A (en) * | 2018-10-22 | 2019-03-22 | 南京航空航天大学 | Air traffic region partitioning method based on fuzzy C-means clustering |
CN110211126A (en) * | 2019-06-12 | 2019-09-06 | 西安邮电大学 | Image partition method based on intuitionistic fuzzy C mean cluster |
CN110929777A (en) * | 2019-11-18 | 2020-03-27 | 济南大学 | Data kernel clustering method based on transfer learning |
CN111444949A (en) * | 2020-03-23 | 2020-07-24 | 中国人民解放军国防科技大学 | Rule optimization-based data-driven granularity modeling method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109543237B (en) | Foundation pit displacement prediction method based on GA-BP neural network | |
CN112100927A (en) | Prediction method for slope deformation and soft soil foundation settlement based on GA-BP neural network | |
CN101344389A (en) | Method for estimating tunnel surrounding rock displacement by neural network | |
CN111365051B (en) | Method for estimating stress of carbonaceous rock tunnel anchor rod based on transfer function of feedback algorithm | |
CN113221434A (en) | Foundation pit deformation prediction method | |
Xue et al. | PREDICTION OF SLOPE STABILITY BASED ON GA-BP HYBRID ALGORITHM. | |
Li et al. | Non-hydraulic factors analysis of pipe burst in water distribution systems | |
CN109389310B (en) | Electric vehicle charging facility maturity evaluation method based on Monte Carlo simulation | |
CN112541528A (en) | Power transmission and transformation project cost prediction index optimization method based on fuzzy clustering | |
Khalaf et al. | Multi-objective groundwater management using genetic algorithms in Kerbala desert area, Iraq | |
CN115511543A (en) | Power transmission and transformation project cost measuring and calculating method | |
CN115526671A (en) | New energy power station site selection method based on improved analytic hierarchy process | |
CN115829206A (en) | Risk assessment method for ground collapse caused by water supply and drainage pipeline | |
CN112711916B (en) | Power transmission line engineering construction equipment model selection method based on improved genetic algorithm | |
CN111612307B (en) | Method for quantitatively evaluating construction necessity degree of ecological regulating dam | |
CN111597696A (en) | Method for evaluating water delivery quantity of oasis in arid region based on ecological hydrological simulation and optimization | |
He et al. | Inverse analysis of geotechnical parameters using an improved version of non-dominated sorting genetic algorithm II | |
CN111539153A (en) | Water and sand combined optimization scheduling method based on pre-constructed sediment information base | |
Moghadam et al. | Reliability-based Operation of Reservoirs Using Combined Monte Carlo Simulation Model and a Novel Nature-inspired Algorithm | |
Noorzad et al. | Prediction of Crest Settlement of Concrete-Faced Rockfill Dams Using a New Approach | |
Xue et al. | A predictive model for determination of sand liquefaction potential based on energy method | |
Fang et al. | Application of the GA-BP neural network in earthwork calculation | |
Erpicum et al. | Optimisation of hydroelectric power stations operations with WOLF package | |
CN114186856A (en) | Identification method for key technical factors of power grid engineering construction | |
CN113128125B (en) | Method and device for predicting quantity of power transmission and transformation engineering material |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |