CN112483731A - Temporary fixing method for fire-fighting stand pipe - Google Patents

Temporary fixing method for fire-fighting stand pipe Download PDF

Info

Publication number
CN112483731A
CN112483731A CN202011248521.0A CN202011248521A CN112483731A CN 112483731 A CN112483731 A CN 112483731A CN 202011248521 A CN202011248521 A CN 202011248521A CN 112483731 A CN112483731 A CN 112483731A
Authority
CN
China
Prior art keywords
fire
fighting
shaped clamp
shaped
riser
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011248521.0A
Other languages
Chinese (zh)
Inventor
张福财
李占魁
王国勤
张辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Shougang Construction Group Co Ltd
Original Assignee
Beijing Shougang Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Shougang Construction Group Co Ltd filed Critical Beijing Shougang Construction Group Co Ltd
Priority to CN202011248521.0A priority Critical patent/CN112483731A/en
Publication of CN112483731A publication Critical patent/CN112483731A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L3/00Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
    • F16L3/08Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing
    • F16L3/10Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing divided, i.e. with two or more members engaging the pipe, cable or protective tubing
    • F16L3/1091Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing divided, i.e. with two or more members engaging the pipe, cable or protective tubing with two members, the two members being fixed to each other with fastening members on each side

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

A temporary fixing method of a fire-fighting stand pipe belongs to the technical field of construction of frame structure temporary fire-fighting pipes. The positioning of the C-shaped clamp is adjusted up and down by utilizing the looseness of the C-shaped clamp screw, and meanwhile, the left and right adjustment of the fire-fighting vertical pipe is met by utilizing 5 round holes on the shoulder pole. The advantage lies in, simple easy operation, utilizes the not hard up location of adjusting C shape card from top to bottom of C shape card screw, utilizes 5 round holes on the shoulder pole to satisfy the regulation about the fire control riser simultaneously. The use of the fire-fighting riser is more flexible, the C-shaped clamp, the U-shaped bolt and the fire-fighting riser after being detached can be reused, manpower and material resources are saved, and the construction cost is greatly reduced.

Description

Temporary fixing method for fire-fighting stand pipe
Technical Field
The invention belongs to the technical field of construction of temporary fire fighting pipes of frame structures, and particularly provides a temporary fixing method of a fire fighting stand pipe.
Background
When the frame structure is constructed, the temporary fire fighting vertical pipe is generally welded and fixed by the stay bars and the frame steel columns, and the method has two defects, namely, the left and the right of the fixed fire fighting vertical pipe cannot be adjusted, and the use of the fire fighting pipe is limited; secondly, the supporting rods of the disassembled fire-fighting vertical pipe need to be cut by gas welding, so that the vertical pipe is easy to cause local damage and can not be reused, and the construction cost is increased.
Disclosure of Invention
The invention aims to provide a temporary fixing method of a fire fighting riser, which solves the problems that the left and right sides of the fixed fire fighting riser can not be adjusted, and the fire fighting pipe has limitation in use; the supporting rods of the disassembled fire-fighting stand pipe need to be subjected to gas welding cutting, so that the stand pipe is easy to cause local damage and cannot be reused, and the problems of construction cost increase and the like are caused.
The positioning of the C-shaped clamp is adjusted up and down by utilizing the looseness of the C-shaped clamp screw, and meanwhile, the left and right adjustment of the fire-fighting stand pipe is met by utilizing 5 round holes in the shoulder pole. The use of the fire-fighting riser is more flexible. The specific process steps are as follows:
firstly, processing a C-shaped card 1 and a carrying pole 4, wherein the C-shaped card 1 is processed by a 6mm steel plate, the carrying pole 4 is processed by 60mm equilateral angle steel, and 5 circular holes with equal intervals are formed in one surface of the angle steel; then fixing the C-shaped clamp 1 with a flange plate of a steel column 3 through a screw 2, and adjusting the positioning of the C-shaped clamp 1 up and down through loosening the screw 2 (figure 1);
secondly, welding and fixing the carrying pole 4 and the C-shaped clamp 1, enabling the carrying pole 4 to be tightly attached to the temporary fire-fighting vertical pipe 6, then clamping the fire-fighting vertical pipe 6 by utilizing a U-shaped bolt 5, and penetrating through two round holes in the carrying pole 4 for fixing (shown in figures 2, 3 and 4);
thirdly, when the fire-fighting vertical pipe 6 needs to be adjusted left and right, the U-shaped bolt 5 is loosened, and then the U-shaped bolt 5 is inserted into the other two round holes of the carrying pole 4. When the fire fighting riser 6 is not used any longer, the nuts of the bolt 2 and the U-bolt 5 of the C-shaped clamp 1 are loosened, and then the fire fighting riser 6 is protectively removed without being damaged. The removed C-clamp 1, U-bolt 5 and fire riser 6 can be reused (fig. 5, 6).
The method is simple and easy to operate, the C-shaped clamp is vertically adjusted by loosening the C-shaped clamp screw, and meanwhile, the left and right adjustment of the fire-fighting stand pipe is met by using 5 round holes in the shoulder pole. The use of the fire-fighting stand pipe is more flexible, the disassembled C-shaped clamp, U-shaped bolt and the fire-fighting stand pipe can be reused, manpower and material resources are saved, construction cost is greatly reduced, and good economic benefits are obtained for companies.
Drawings
FIG. 1 is a top view of a C-shaped clip fixing steel column flange plate
FIG. 2 is a top view of the shoulder pole welded to the C-shaped clip
FIG. 3 is a front view of the shoulder pole welded to the C-shaped clip
FIG. 4 is a top view of a U-bolt fastened fire riser
FIG. 5 is a top view of the U-bolt with the hole on the shoulder pole adjusted left and right
FIG. 6 is a front view of a U-bolt fastened fire riser
In the figure, a C-shaped clamp 1, a screw 2, a steel column 3, a carrying pole 4, a U-shaped bolt 5 and a fire fighting riser 6.
Detailed Description
Fig. 1-6 illustrate an embodiment of the present invention. The specific implementation mode is as follows:
firstly, a C-shaped clamp 1 and a carrying pole 4 are machined, the C-shaped clamp 1 is machined by a 6mm steel plate, the carrying pole 4 is machined by 60mm equilateral angle steel, and 5 circular holes with equal intervals are formed in one surface of the angle steel. Then fixing the C-shaped clamp 1 with a flange plate of a steel column 3 through a screw 2, and adjusting the positioning of the C-shaped clamp 1 up and down through loosening the screw 2;
secondly, welding and fixing the carrying pole 4 and the C-shaped clamp 1, enabling the carrying pole 4 to be tightly attached to the temporary fire-fighting vertical pipe 6, then clamping the fire-fighting vertical pipe 6 by utilizing a U-shaped bolt 5, and penetrating through two round holes in the carrying pole 4 for fixing;
thirdly, when the fire-fighting vertical pipe 6 needs to be adjusted left and right, the U-shaped bolt 5 is loosened, and then the U-shaped bolt 5 is inserted into the other two round holes of the carrying pole 4. When the fire fighting riser 6 is not used any longer, the nuts of the bolt 2 and the U-bolt 5 of the C-shaped clamp 1 are loosened, and then the fire fighting riser 6 is protectively removed without being damaged. The removed C-clamp 1, U-bolt 5 and fire riser 6 can be reused.
When the frame structure of the sintering main factory building is constructed, a temporary fixing method is adopted for the temporary fire-fighting stand pipe, and a good effect is achieved. The C-shaped clamp and the carrying pole rod are machined firstly, the carrying pole rod is formed by machining angle steel, 5 circular holes are formed in one surface of the angle steel at equal intervals, the C-shaped clamp is fixed with the steel column flange plate through screws, and the positioning of the C-shaped clamp is adjusted up and down through loosening the screws. The carrying pole is welded and fixed with the C-shaped clamp, the carrying pole is tightly attached to the temporary fire-fighting vertical pipe, then the fire-fighting vertical pipe is clamped by the U-shaped bolt and passes through two round holes of the carrying pole to be fixed, when the fire-fighting vertical pipe needs to be adjusted left and right, the U-shaped bolt is loosened, and then the U-shaped bolt is inserted into the other two round holes of the carrying pole. When the fire-fighting stand pipe is not used any more, the C-shaped clamping screw and the nut of the U-shaped bolt are loosened, and then the fire-fighting stand pipe is protectively dismounted without being damaged. The removed C-shaped clamp, U-shaped bolt and fire-fighting riser can be reused. The method is simple and easy to operate, the C-shaped clamp is vertically adjusted by loosening the C-shaped clamp screw, and meanwhile, the left and right adjustment of the fire-fighting stand pipe is met by using 5 round holes in the shoulder pole. The use of the fire-fighting stand pipe is more flexible, the disassembled C-shaped clamp, U-shaped bolt and the fire-fighting stand pipe can be reused, manpower and material resources are saved, construction cost is greatly reduced, and precious experience is accumulated for later similar construction.

Claims (1)

1. A temporary fixing method of a fire-fighting riser is characterized by comprising the following specific process steps:
firstly, processing a C-shaped clamp (1) and a carrying pole (4), wherein the C-shaped clamp (1) is processed by a 6mm steel plate, the carrying pole (4) is processed by 60mm equilateral angle steel, and one surface of the angle steel is provided with 5 round holes with equal intervals; then fixing the C-shaped clamp (1) with a flange plate of the steel column (3) through a screw (2), and adjusting the positioning of the C-shaped clamp (1) up and down through loosening the screw (2);
secondly, welding and fixing the carrying pole (4) and the C-shaped clamp (1), enabling the carrying pole (4) to be tightly attached to the temporary fire-fighting vertical pipe (6), then clamping the fire-fighting vertical pipe (6) by utilizing a U-shaped bolt (5), and penetrating through two round holes of the carrying pole (4) for fixing;
and thirdly, when the fire-fighting vertical pipe (6) needs to be adjusted left and right, loosening the U-shaped bolt (5), and then inserting the U-shaped bolt (5) into the other two round holes of the shoulder pole (4). When the fire-fighting stand pipe (6) is not used any more, the screw (2) of the C-shaped clamp (1) and the nut of the U-shaped bolt (5) are loosened, and the fire-fighting stand pipe (6) is protectively dismounted without being damaged. The disassembled C-shaped clamp (1), the U-shaped bolt (5) and the fire-fighting riser (6) can be reused.
CN202011248521.0A 2020-11-10 2020-11-10 Temporary fixing method for fire-fighting stand pipe Pending CN112483731A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011248521.0A CN112483731A (en) 2020-11-10 2020-11-10 Temporary fixing method for fire-fighting stand pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011248521.0A CN112483731A (en) 2020-11-10 2020-11-10 Temporary fixing method for fire-fighting stand pipe

Publications (1)

Publication Number Publication Date
CN112483731A true CN112483731A (en) 2021-03-12

Family

ID=74929772

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011248521.0A Pending CN112483731A (en) 2020-11-10 2020-11-10 Temporary fixing method for fire-fighting stand pipe

Country Status (1)

Country Link
CN (1) CN112483731A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201801268U (en) * 2010-09-28 2011-04-20 四川奥尔铂电梯有限公司 Elevator balance compensating chain suspension device
CN202181614U (en) * 2011-06-28 2012-04-04 中国二十冶集团有限公司 Steel pipe fixing device for joist steel
CN105065785A (en) * 2015-07-14 2015-11-18 苏州柏德纳科技有限公司 Pipeline supporting component
CN204903078U (en) * 2015-09-21 2015-12-23 山东电力建设第一工程公司 Instrument mounting bracket on spot
CN206269329U (en) * 2016-12-01 2017-06-20 中国电力工程顾问集团中南电力设计院有限公司 A kind of back-to-back valve Room air conditioning wind pipe mounting seat of flexible direct current
CN208628022U (en) * 2018-07-16 2019-03-22 北京金圣奥能源技术有限公司 The bracket of the air drill of Hand scarf oil pipe and environmentally friendly Hand scarf oil pipe device
CN210947818U (en) * 2019-08-30 2020-07-07 北京首钢建设集团有限公司 Safety rope fixing device used during steel frame installation
CN211175658U (en) * 2019-11-13 2020-08-04 广西中源机械有限公司 Steel pipe fixing pipe clamp
CN211548877U (en) * 2019-11-13 2020-09-22 北京首钢建设集团有限公司 Safety device on box frame beam

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201801268U (en) * 2010-09-28 2011-04-20 四川奥尔铂电梯有限公司 Elevator balance compensating chain suspension device
CN202181614U (en) * 2011-06-28 2012-04-04 中国二十冶集团有限公司 Steel pipe fixing device for joist steel
CN105065785A (en) * 2015-07-14 2015-11-18 苏州柏德纳科技有限公司 Pipeline supporting component
CN204903078U (en) * 2015-09-21 2015-12-23 山东电力建设第一工程公司 Instrument mounting bracket on spot
CN206269329U (en) * 2016-12-01 2017-06-20 中国电力工程顾问集团中南电力设计院有限公司 A kind of back-to-back valve Room air conditioning wind pipe mounting seat of flexible direct current
CN208628022U (en) * 2018-07-16 2019-03-22 北京金圣奥能源技术有限公司 The bracket of the air drill of Hand scarf oil pipe and environmentally friendly Hand scarf oil pipe device
CN210947818U (en) * 2019-08-30 2020-07-07 北京首钢建设集团有限公司 Safety rope fixing device used during steel frame installation
CN211175658U (en) * 2019-11-13 2020-08-04 广西中源机械有限公司 Steel pipe fixing pipe clamp
CN211548877U (en) * 2019-11-13 2020-09-22 北京首钢建设集团有限公司 Safety device on box frame beam

Similar Documents

Publication Publication Date Title
CN110748194B (en) Building supporting device and construction method
CN209817385U (en) Cantilever beam for cantilever scaffold
CN112483731A (en) Temporary fixing method for fire-fighting stand pipe
CN210947818U (en) Safety rope fixing device used during steel frame installation
CN203856226U (en) Fixture-type stairway protecting fence
CN214995260U (en) Positioning steel bar position controller
CN204201288U (en) Support of pipelines on a kind of steel grating
CN211548877U (en) Safety device on box frame beam
CN110106810B (en) Positioning device for mounting corrugated plate on guardrail upright post and construction method thereof
CN209798767U (en) Can have enough to meet need double pin 609 steel pipe tie beam staple bolts of roll adjustment
CN210059892U (en) Drilling auxiliary device of chassis girder
CN209799433U (en) Building engineering protection network
CN210164052U (en) Steel construction supporting framework convenient to dismouting
CN201803085U (en) Steel wire frame used for adjusting and detecting devices
CN104631849B (en) A kind of stair face limit construction protection railing and installation method
CN202559714U (en) Steel pipe butt-joint locating device
CN204456937U (en) A kind of stair face limit construction protection railing
CN215368849U (en) Guard rail saddle joint subassembly
CN208734077U (en) A kind of building template branch stake tool
CN220247183U (en) I-steel stand electromechanical device and pipeline installing support
CN217480547U (en) L-shaped embedded part adaptor integrated part
CN205206368U (en) Instrument formula floor protector
JP6689073B2 (en) Scaffolding board fixing device
CN216306932U (en) Interim fire hose fixed gallows on roof
CN214169596U (en) Adjustable installation device for special-shaped curtain wall framework

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20210312