CN112463119B - Software development method based on V-process work decomposition structure - Google Patents

Software development method based on V-process work decomposition structure Download PDF

Info

Publication number
CN112463119B
CN112463119B CN202011402554.6A CN202011402554A CN112463119B CN 112463119 B CN112463119 B CN 112463119B CN 202011402554 A CN202011402554 A CN 202011402554A CN 112463119 B CN112463119 B CN 112463119B
Authority
CN
China
Prior art keywords
software
development
work
research
project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202011402554.6A
Other languages
Chinese (zh)
Other versions
CN112463119A (en
Inventor
侯亚文
翟奇凡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Asia Vision Information Technology Co ltd
Original Assignee
Shanghai Asia Vision Information Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Asia Vision Information Technology Co ltd filed Critical Shanghai Asia Vision Information Technology Co ltd
Priority to CN202011402554.6A priority Critical patent/CN112463119B/en
Publication of CN112463119A publication Critical patent/CN112463119A/en
Application granted granted Critical
Publication of CN112463119B publication Critical patent/CN112463119B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F8/00Arrangements for software engineering
    • G06F8/10Requirements analysis; Specification techniques
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F11/00Error detection; Error correction; Monitoring
    • G06F11/36Preventing errors by testing or debugging software
    • G06F11/3668Software testing
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F8/00Arrangements for software engineering
    • G06F8/20Software design
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

The invention is suitable for the research and development field and the work decomposition structure of the embedded software research and development project. An infrastructure for development project management is provided. A range baseline is provided for the development project. Automobile SPICE is an internationally known quality management standard developed by embedded software in the Automotive industry, which provides 32 process reference models. The V-flow work decomposition structure accords with the quality standard of an automatic SPICE research and development project, adopts a system engineering process group (SYS) and a software engineering process group (SWE) in an automatic SPICE process reference model, adopts an iteration increment project life cycle according to the basic characteristics of progressive and clear requirements of the research and development project, invents a work decomposition structure which can be repeatedly defined in an iteration research and development stage environment, and develops a V-flow work decomposition structure tool based on a VBA technology under an EXCEL platform.

Description

Software development method based on V-process work decomposition structure
Technical Field
The invention is suitable for the research and development field and the work decomposition structure of the embedded software research and development project. An infrastructure for development project management is provided. A range baseline is provided for the development project.
Background
Automobile SPICE is an internationally known quality management standard developed by embedded software in the Automotive industry, which provides 32 process reference models. Among them, 16 processes are the basic choice for quality certification of the automatic SPICE project. They are distributed in the provisioning process group (ACQ) system engineering process group (SYS), software engineering process group (SWE), support process group (SUP), management process group (MAN).
The system engineering process set (SYS) and the software engineering process Set (SWE) belong to the engineering lifecycle of the automatic SPICE, starting from the system demand analysis (sys.2), in the following order: system architecture design (sys.3), software requirement analysis (compliance swe.1), software architecture design (swe.2), software detailed design and cell construction (swe.3), software cell verification (compliance swe.4), software integration and testing (swe.5), software qualification testing (swe.6), software system integration and testing (sys.4), system qualification testing (sys.5), and development flows are established.
Meanwhile, five groups of traceability relations are built between the processes of system demand analysis (SYS.2) and system qualification test (SYS.5), system architecture design (SYS.3) and system integration and test (SYS.4), software demand analysis (SWE.1) and software qualification test (SWE.6), software architecture design (SWE.2) and software integration and test (SWE.5), software detailed design and unit construction (SWE.3) and software unit verification (SWE.4) and the like, and the workflow lines and traceability relation lines jointly form V-shaped appearance of connection between the ten processes.
The V-process work decomposition structure employs a standard architecture process developed in advance, which is compatible with the V-feature process of the automatic SPICE, which is the meaning of the V-process, see fig. 1.
Disclosure of Invention
The invention provides a software development method based on a V-flow work decomposition structure, which accords with the quality standard of an automatic SPICE research and development project, adopts a system engineering process group and a software engineering process group in an automatic SPICE process reference model, adopts an iteration increment project life cycle according to the basic characteristics of progressive clarity of research and development project requirements, provides a work decomposition structure which can be repeatedly defined in an iteration research and development stage environment, and is developed into a VPWBS tool based on a VBA technology under an EXCEL platform, and specifically comprises the following steps:
(1) The top layer is the project: defining project products, acceptance criteria and product decomposition structures of the research and development project, and further comprising iterative research and development stages and project management work formulated according to the progress of customer demands;
(2) The first layer is an iterative development stage: the method comprises the following tasks: project product work, front-end development work, software development tasks and rear-end development work;
(3) Project tasks of the second layer: in the whole project life cycle, continuously maintaining project product definition, acceptance criteria and product decomposition structures through output files of the V flow until the project product is completely realized and accepted;
(4) Leading research and development work of the second layer: the method belongs to iterative research and development life cycles, and comprises system demand analysis work, system architecture design work, software demand analysis work and software architecture design work, wherein the output file of each iterative cycle comprises: new system architecture elements, a number of new software components;
(5) Software development tasks of the second layer: the method belongs to an iterative research and development life cycle, and defines a plurality of new software component development tasks according to an output file of a front-end research and development work; further comprising performing software integration work on the completed software component product: software integration and test, and software qualification test;
(6) Post-development work of the second layer: belongs to the iterative research and development life cycle, and comprises the system integration work: the integration work is to integrate the existing integrated software and system architecture of the project with newly added software components and new system architecture elements delivered by the software development task to generate updated integrated software and system architecture and system qualification test work;
(7) The third layer is a software component development task, and the upper layer task is a software development task; the method comprises the following steps of: defining a plurality of software units;
(8) The fourth layer is a software unit construction task, and the upper layer task is a software component development task; the method comprises a software unit construction work and a software unit verification work, and aims to realize a software unit product;
(9) The activities performed at each unit of work in the VPWBS originate from standard practices defined within established standard process hierarchy files;
(10) The output file of each unit of work in the VPWBS is derived from the standard output file defined within the established standard process hierarchy file;
(11) The VPWBS (virtual private space service) number realized in the EXCEL electronic watch is automatically generated, and the WBS number is not changed due to the addition of a new iteration stage, a new software component and a new software unit into the WBS number in the whole project implementation process, so that the uniqueness of the WBS number is ensured;
the standard process system files are eleven standard process system files corresponding to a system engineering process group and a software engineering process group which are defined according to an AutomotiveSPICE process reference model;
and developing a new iterative research and development stage according to the progress of the client demands, and executing the following research and development steps in each iterative research and development period:
step 1, leading research and development work; executing a V flow, comprising: a system demand analysis process, a system architecture design process, a software demand analysis process, and a software architecture design process; identifying a plurality of software component items, and generating a plurality of software component tasks under a software development task by using the software component items as drivers;
step 2, developing a software component to work; executing a V flow, comprising: the software detailed design process is used for identifying a plurality of software unit items and generating a plurality of software unit tasks by taking the software unit items as drivers;
step 3, developing a software unit to work; executing a V flow, comprising: a software unit construction process and a software unit verification process, so as to obtain a software unit product conforming to the software detailed design;
step 4, integrating software unit products; executing a V flow, comprising: the software integration and test process is carried out to obtain a software component product conforming to the software architecture design;
step 5, the whole confirmation of the software product is performed; executing a V flow, comprising: a software qualification testing process for confirming the overall qualification of the software increment submitted to the project product by the software development task;
step 6, integrating the system; and executing post-research and development work of the V flow: executing system integration and test processes to obtain an integrated system which accords with the system architecture design of the existing system architecture elements and increment elements;
step 7, integrating system confirmation work, and executing post-research and development work of the V flow: and executing a system qualification test process to confirm the overall qualification of the system increment of the project product submitted by iterative research and development.
Drawings
Fig. 1: v flow chart
Fig. 2: v-process work decomposition structure diagram
Fig. 3: software demand analysis standard process summary chart
Fig. 4: software architecture design standard process outline chart
Fig. 5: software detailed design and unit construction standard process outline chart
Fig. 6: software unit verification standard process outline chart
Fig. 7: software integration and test standard process summary chart
Fig. 8: software qualification test standard process outline chart
Fig. 9: project example chart
Detailed Description
And developing a new iterative research and development stage according to the progress of the client demands, executing the following seven research and development steps in each iterative research and development period, wherein the progress of the project demands is clear, and the project products are realized gradually.
(1) The first step of research and development is the pre-research and development work; executing a V flow, comprising: a system demand analysis process (compliance sys.2), a system architecture design process (compliance sys.3), a software demand analysis process (compliance swe.1), a software architecture design process (compliance swe.2); a plurality of software component items are identified, and are used as drivers to generate a plurality of software component tasks under the software development task.
(2) The second step of development is to develop software components; executing a V flow, comprising: the software detailed design process (compliance swe.3) identifies several software element items and creates several software element tasks for driving the generation.
(3) The third step of development is to develop a software unit; executing a V flow, comprising: a software cell build process (compliance swe.3) and a software cell verification process (compliance swe.4) to obtain a software cell product that conforms to the software detailed design.
(4) The fourth step of research and development is the integration work of the software unit products; executing a V flow, comprising: the software integration and testing process (compliance swe.5) results in a software component product that conforms to the design of the software architecture.
(5) The fifth step of research and development is the whole validation work of the software product; executing a V flow, comprising: the software qualification test process (compliance SWE.5) validates the overall qualification of the software delta submitted to the project product by the software development task.
(6) The sixth step of research and development is the system integration work; and executing post-research and development work of the V flow: and (3) executing a system integration and test process (compliance SYS.4) to obtain the integrated system which accords with the system architecture design of the existing system architecture elements and the increment elements.
(7) The seventh step of research and development is to confirm the work of the integrated system and execute the post research and development work of the V flow: a system qualification test process (compliance sys.5) is performed to confirm the overall qualification of the system increments of the project product submitted by the iterative development.

Claims (1)

1. A software development method based on a V-flow work decomposition structure accords with the quality standard of an automatic SPICE research and development project, adopts a system engineering process group and a software engineering process group in an automatic SPICE process reference model, adopts an iteration increment project life cycle according to the basic characteristics of progressive clarity of research and development project requirements, provides a work decomposition structure which can be repeatedly defined in an iteration research and development stage environment, and is developed into a VPWBS tool based on a VBA technology under an EXCEL platform, and is characterized in that:
(1) The top layer is the project: defining project products, acceptance criteria and product decomposition structures of the research and development project, and further comprising iterative research and development stages and project management work formulated according to the progress of customer demands;
(2) The first layer is an iterative development stage: the method comprises the following tasks: project product work, front-end development work, software development tasks and rear-end development work;
(3) Project tasks of the second layer: in the whole project life cycle, continuously maintaining project product definition, acceptance criteria and product decomposition structures through output files of the V flow until the project product is completely realized and accepted;
(4) Leading research and development work of the second layer: the method belongs to iterative research and development life cycles, and comprises system demand analysis work, system architecture design work, software demand analysis work and software architecture design work, wherein the output file of each iterative cycle comprises: new system architecture elements, a number of new software components;
(5) Software development tasks of the second layer: the method belongs to an iterative research and development life cycle, and defines a plurality of new software component development tasks according to an output file of a front-end research and development work; further comprising performing software integration work on the completed software component product: software integration and test, and software qualification test;
(6) Post-development work of the second layer: belongs to the iterative research and development life cycle, and comprises the system integration work: the integration work is to integrate the existing integrated software and system architecture of the project with newly added software components and new system architecture elements delivered by the software development task to generate updated integrated software and system architecture and system qualification test work;
(7) The third layer is a software component development task, and the upper layer task is a software development task; the method comprises the following steps of: defining a plurality of software units;
(8) The fourth layer is a software unit construction task, and the upper layer task is a software component development task; the method comprises a software unit construction work and a software unit verification work, and aims to realize a software unit product;
(9) The activities performed at each unit of work in the VPWBS originate from standard practices defined within established standard process hierarchy files;
(10) The output file of each unit of work in the VPWBS is derived from the standard output file defined within the established standard process hierarchy file;
(11) The VPWBS (virtual private space service) number realized in the EXCEL electronic watch is automatically generated, and the WBS number is not changed due to the addition of a new iteration stage, a new software component and a new software unit into the WBS number in the whole project implementation process, so that the uniqueness of the WBS number is ensured;
the standard process system files are eleven standard process system files corresponding to a system engineering process group and a software engineering process group which are defined according to an AutomotiveSPICE process reference model;
and developing a new iterative research and development stage according to the progress of the client demands, and executing the following research and development steps in each iterative research and development period:
step 1, leading research and development work; executing a V flow, comprising: a system demand analysis process, a system architecture design process, a software demand analysis process, and a software architecture design process; identifying a plurality of software component items, and generating a plurality of software component tasks under a software development task by using the software component items as drivers;
step 2, developing a software component to work; executing a V flow, comprising: the software detailed design process is used for identifying a plurality of software unit items and generating a plurality of software unit tasks by taking the software unit items as drivers;
step 3, developing a software unit to work; executing a V flow, comprising: a software unit construction process and a software unit verification process, so as to obtain a software unit product conforming to the software detailed design;
step 4, integrating software unit products; executing a V flow, comprising: the software integration and test process is carried out to obtain a software component product conforming to the software architecture design;
step 5, the whole confirmation of the software product is performed; executing a V flow, comprising: a software qualification testing process for confirming the overall qualification of the software increment submitted to the project product by the software development task;
step 6, integrating the system; and executing post-research and development work of the V flow: executing system integration and test processes to obtain an integrated system which accords with the system architecture design of the existing system architecture elements and increment elements;
step 7, integrating system confirmation work, and executing post-research and development work of the V flow: and executing a system qualification test process to confirm the overall qualification of the system increment of the project product submitted by iterative research and development.
CN202011402554.6A 2020-12-02 2020-12-02 Software development method based on V-process work decomposition structure Active CN112463119B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011402554.6A CN112463119B (en) 2020-12-02 2020-12-02 Software development method based on V-process work decomposition structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011402554.6A CN112463119B (en) 2020-12-02 2020-12-02 Software development method based on V-process work decomposition structure

Publications (2)

Publication Number Publication Date
CN112463119A CN112463119A (en) 2021-03-09
CN112463119B true CN112463119B (en) 2023-11-17

Family

ID=74805383

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011402554.6A Active CN112463119B (en) 2020-12-02 2020-12-02 Software development method based on V-process work decomposition structure

Country Status (1)

Country Link
CN (1) CN112463119B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115600997B (en) * 2022-12-12 2023-05-09 厦门盈趣科技股份有限公司 Digital research and development project management system and method for normative content management

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011031328A2 (en) * 2009-09-14 2011-03-17 Ldra Technology, Inc. Systems and methods for management of projects for development of embedded systems
CN105868115A (en) * 2016-04-05 2016-08-17 工业和信息化部电子第五研究所 Building method and system for software test model of software intensive system
CN107678738A (en) * 2017-10-17 2018-02-09 广州慧睿思通信息科技有限公司 A kind of method of software quality management
CN110321152A (en) * 2019-07-04 2019-10-11 青岛华正信息技术股份有限公司 A kind of Software Development Platform
CN110796342A (en) * 2019-10-09 2020-02-14 武汉光庭信息技术股份有限公司 Automatic management method and device based on typical maintenance project
CN111475905A (en) * 2019-01-22 2020-07-31 上海汽车集团股份有限公司 Method and device for establishing road vehicle function safety development process
CN111858298A (en) * 2020-05-29 2020-10-30 卡斯柯信号有限公司 Software testing method based on 3V model

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040093584A1 (en) * 2002-10-31 2004-05-13 Bearingpoint, Inc., A Delaware Corporation Facilitating software engineering and management in connection with a software development project according to a process that is compliant with a qualitatively measurable standard
US7603653B2 (en) * 2004-03-15 2009-10-13 Ramco Systems Limited System for measuring, controlling, and validating software development projects
US20080034347A1 (en) * 2006-07-31 2008-02-07 Subramanyam V System and method for software lifecycle management
US8744821B2 (en) * 2011-07-07 2014-06-03 Xldyn, Llc Spreadsheet-based templates for supporting the systems engineering process
WO2015179705A1 (en) * 2014-05-21 2015-11-26 Quantum Fuel Systems Technologies Worldwide, Inc. Enhanced compliance verification system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011031328A2 (en) * 2009-09-14 2011-03-17 Ldra Technology, Inc. Systems and methods for management of projects for development of embedded systems
CN105868115A (en) * 2016-04-05 2016-08-17 工业和信息化部电子第五研究所 Building method and system for software test model of software intensive system
CN107678738A (en) * 2017-10-17 2018-02-09 广州慧睿思通信息科技有限公司 A kind of method of software quality management
CN111475905A (en) * 2019-01-22 2020-07-31 上海汽车集团股份有限公司 Method and device for establishing road vehicle function safety development process
CN110321152A (en) * 2019-07-04 2019-10-11 青岛华正信息技术股份有限公司 A kind of Software Development Platform
CN110796342A (en) * 2019-10-09 2020-02-14 武汉光庭信息技术股份有限公司 Automatic management method and device based on typical maintenance project
CN111858298A (en) * 2020-05-29 2020-10-30 卡斯柯信号有限公司 Software testing method based on 3V model

Non-Patent Citations (9)

* Cited by examiner, † Cited by third party
Title
K公司PEPS汽车电子新产品研发项目风险管理研究;李岩武;《中国优秀硕士学位论文全文数据库 经济与管理科学辑》;J150-853 *
Sergiu Stefan Nicolaescud等.A new project management approach for R&D software projects in the automotive industry - continuous V-model.《international Journal of Web Engineering and Technology》.2017,120-142. *
VBA推进工具在项目开发中的应用;张仁德;2019中国汽车工程学会年会论文集;第2318-2322页 *
上海大众在电动汽车车载网络及车载网关开发方面的探索及实践;朱国章;《上海汽车》(第01期);39-43 *
基于A-SPICE的汽车软件项目管理的应用和优化;袁东阳;汽车与驾驶维修(维修版)(第07期);50-53 *
基于CMMI三级的银行项目管理方法探讨与实践;江峰;金融科技时代(第02期);17-22 *
基于VBA技术提升GJB5000A软件测试效率的方法;孙龑等;《电子技术与软件工程》;48-50 *
基于模型设计的电动汽车整车控制器开发与技术研究;阙同亮;《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》;C035-267 *
软件项目管理与质量管理流程整合研究;雷大力;《中国优秀硕士学位论文全文数据库 经济与管理科学辑》;J152-85 *

Also Published As

Publication number Publication date
CN112463119A (en) 2021-03-09

Similar Documents

Publication Publication Date Title
CN109376378B (en) Front-back processing method for rapidly extracting rigidity result of white car body mounting point
CN103049620B (en) Ship simulating system and ship simulating method used during shipbuilding
CN101017457A (en) Automatically testing method of computer software
CN112463119B (en) Software development method based on V-process work decomposition structure
Corallo et al. Enhancing product development through knowledge‐based engineering (KBE) A case study in the aerospace industry
CN112115611B (en) Collaborative simulation management system
Freedman An overview of fully integrated digital manufacturing technology
CN109977459A (en) A method of it is improved using CAE technology and strengthens loading spectrum precision
CA2528779A1 (en) White body modeling and virtual evaluation system for mechanical assemblies
CN111539066A (en) Method for parametric integrated design of automobile door cover
CN109902936A (en) A kind of maintenance personal's concocting method based on equipment repair process
Chang et al. Concurrent design and manufacturing for mechanical systems
CN109657376B (en) Full-vehicle automatic modeling method for CAE simulation
CN110321596B (en) Locomotive vehicle structure simulation method based on finite element analysis
CN1760903A (en) Flow verification system and method
CN116541929A (en) Construction method of parameterized BIM model of outdoor storage yard civil engineering standardization unit
CN105957138A (en) Assembly-based furniture product three-dimensional modeling method and system
CN115342971A (en) Satellite three-dimensional model-based quality characteristic simulation system
CN109086522B (en) Structure hierarchy modeling method for bridge management and maintenance process based on INVENTOR
CN106354913A (en) Parametric design platform for helical gear drive system and application method thereof
CN113946988A (en) Mechanical product collaborative simulation system based on simulation template and process driving
Koch et al. Facing Future Challenges in Crash Simulation Engineering–Model Organization, Quality and Management at Porsche
Dolgov et al. Evaluation of the effectiveness of the use of additive wax printing technologies for obtaining wax models for lost-wax casting in custom production based on simulation modeling
Andersson Modular simulation models as a key enabler for a question-answer driven verification process
CN115730373A (en) BIM-based assembly type building component design method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant